CN205977243U - A platform truck for tunnel water proofing board is laid and reinforcement - Google Patents

A platform truck for tunnel water proofing board is laid and reinforcement Download PDF

Info

Publication number
CN205977243U
CN205977243U CN201620832055.3U CN201620832055U CN205977243U CN 205977243 U CN205977243 U CN 205977243U CN 201620832055 U CN201620832055 U CN 201620832055U CN 205977243 U CN205977243 U CN 205977243U
Authority
CN
China
Prior art keywords
reinforcing bar
stand
door frame
platform
chassis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620832055.3U
Other languages
Chinese (zh)
Inventor
王祥军
龚俊
曾勇
熊幸
宋祖源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Wuxin Tunnel Intelligent Equipment Co Ltd
Original Assignee
Hunan Wuxin Tunnel Intelligent Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Wuxin Tunnel Intelligent Equipment Co Ltd filed Critical Hunan Wuxin Tunnel Intelligent Equipment Co Ltd
Priority to CN201620832055.3U priority Critical patent/CN205977243U/en
Application granted granted Critical
Publication of CN205977243U publication Critical patent/CN205977243U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a platform truck for tunnel water proofing board is laid and reinforcement, it includes rack, operating system, platform assembly, the system of lifting by crane, running gear, the rack includes portal stand, portal crossbeam group and longitudinal tie roof beam group, be equipped with a plurality of mounting holes on the portal stand, the portal crossbeam includes a plurality of side direction standard festival and a plurality of ministerial standard festivals. The utility model discloses a standardizing the design theory, can coming adjustment rack's height and width according to different highway tunnel and railway tunnel's section specification, the practicality is strong, the system of lifting by crane of scalable, every single move, rotation type cantilever crane and the operating system that can walk make things convenient for the lifting by crane of waterproof board and reinforcing bar, material loading, lay, the ligature operation, the platform assembly is convenient for constructor and is passed through, and maneuverability is strong. Use the utility model discloses a platform truck, the construction is swift, convenient, the cycle is short.

Description

Chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding
Technical field
This utility model is related to engineering machinery field and in particular to a kind of lay and reinforcing bar binding for anchor bar of waterproof plate in tunnels Chassis.
Background technology
Lining cutting refers to, for preventing surrouding rock deformation or caving in, build along materials such as tunnel trunk periphery armored concrete Permanent supporting construction.Concrete lining trolley is to have to use for special equipment in constructing tunnel process secondary lining, is used for Construction of concrete lining to tunnel inner wall.Before carrying out concrete lining every time, splash guard need to be completed in inside concrete position Laying and bar-mat reinforcement colligation.
At present, what domestic anchor bar of waterproof plate in tunnels laying and reinforcing bar binding adopted is easy stand mostly, and horse structure is no Method is adjusted, and the splash guard that can only be used in specific tunnel cross-section is laid with reinforcing bar binding it is impossible to be used for multiple difference tunnels The use of road section, this infrastructure cost high it is impossible to secondary utilization;And the lifting of splash guard and reinforcing bar uses Simple pulley and leads to Cross artificial pulling and carrying to complete the feeding of reinforcing bar, time-consuming take a lot of work, the labor intensity of workman is very big;The tunnel of China is because applying The differences such as work environment, construction requirement lead to its cross section profile often also different, so the current splash guard laying using, reinforcing bar are tied up Pricking chassis needs to be redesigned according to different section of outline and process, thus considerably increasing design cycle and processing Cycle.
Utility model content
This utility model provides a kind of chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding, can be according to tunnel cross-section chi Very little difference enters the adjustment of line height and width to the stand of chassis, and splash guard lifting and laying are convenient, and reinforcing bar lifts by crane and colligation Convenient, short construction period.Concrete scheme is as follows:
A kind of for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding chassis, including the passive stand of arch door shape, It is movably arranged on stand and for being transported to the jacking system of construction location, being arranged on stand and use splash guard and reinforcing bar In the platform assembly for workmen's offer construction space, it is arranged in platform assembly and is used for splash guard and reinforcing bar from ground The tackling system that is hoisted on jacking system, located at stand bottom and the walking mechanism that stand can freely walk can be made;
Described stand includes door frame column and the door frame crossbeam group being separately positioned on described door frame column and longitudinally connects Connect beam group, described door frame column is provided with multiple installing holes for adjusting the height in above-below direction for the door frame crossbeam group;Described Door frame crossbeam group includes at least two groups door frame crossbeams, and described door frame crossbeam includes two groups of lateral standard knots and one group of top standard Section, two groups of lateral standard knots are in up-narrow and down-wide splayed setting;Described top standard knot is horizontally disposed with, and its two ends connects respectively Connect the top of two groups of lateral standard knots.
In above technical scheme preferably, described tackling system includes being fixedly installed on described stand and including revolution Turning arm that the base of device, first end are movably arranged on described base and described turning arm is arranged on by steel wire rope The hook at two ends.
In above technical scheme preferably, described platform assembly includes many group platforms of the setting in step, described door frame Many group platforms are all provided with column and described door frame crossbeam, the longitudinal length of described platform and stand are longitudinally effectively along the vertical direction Working length is identical.
In above technical scheme preferably, described platform is provided with the guard rail playing protective action;Two neighboring platform Between be provided with the working stand passing through for workmen.
In above technical scheme preferably, described jacking system includes being movably arranged on the platform upper surface positioned at top Support base, it is arranged on described support base by power cylinder and for lifting the elevator of splash guard and reinforcing bar and being located at described The top of elevator and for accommodate by lifting splash guard and reinforcing bar mold.
In above technical scheme preferably, it is provided with track along the longitudinal direction on the upper surface of the platform at top, described Support base is provided with the road wheel matching with described track.
In above technical scheme preferably, described walking mechanism include being arranged at four of stand bottom can move freely and The roller of brake device.
In above technical scheme preferably, described longitudinally connected beam group includes many longitudinally connected beams, adjacent two longitudinal directions It has been provided with the brace of booster action between tie-beam.
The technical scheme that this utility model provides has the advantages that:
1st, the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding that this utility model provides, is arranged on door frame column There is multiple rows of installing hole, this installing hole is used for being bolted with door frame crossbeam, such that it is able to adjust door frame in the vertical direction Horizontal depth of beam, have adjusted the height of the platform located at door frame cross rail top, such that it is able to the constructor on platform simultaneously Member can construct at various height, meets the needs of different size tunnel-liner colligation;Door frame crossbeam is by multiple lateral standards Section and multiple tops standard knot are constituted, and adjacent standard knot can be dismantled, such that it is able to arrange difference according to actual needs Number, you can the lateral dimension (also including vertical dimension) realizing door frame crossbeam changes in different range, compares traditional The fixing stand of size, can achieve the adjustable of whole bed size, meets highway, the laying of railway tunnel splash guard of different section With reinforcing bar binding operation.
2nd, in this utility model, tackling system includes base, turning arm and hook, base be provided with slewing equipment it is ensured that The efficient transmission of power is (such as:Need to lift by crane splash guard and during reinforcing bar need to by bottom screw rodb base with rail top face stretching it is ensured that the having of power Effect transmission;By bottom screw rodb base cycle during chassis walking, it is allowed to depart from rail top face);Turning arm is scalable, pitching, rotation, Facilitate splash guard and reinforcing bar lifting, feeding, colligation operation.
3rd, in this utility model, door frame crossbeam includes two groups of lateral standard knots and one group of top standard knot, total in conjunction with platform So that platform adopts the staircase structural model of human oriented design, chassis top periphery is covered with platform, upper and lower with longitudinally for the design becoming Two interlayers directly continuous walking can lead to last layer it is not necessary to pass through cat ladder, and larger platform area is arranged at top, and staff exists On whole platform during operation safely, conveniently.
4th, in this utility model, jacking system includes support base, elevator and mold, and structure is simplified, and passes through track and row Walk the design realization activity setting of wheel, practical;Booster action, integral trolley good stability are played in the design of brace.
5th, the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding that this utility model provides, first with tackling system The splash guard on ground and reinforcing bar are hoisted to the platform of the construction above door frame, then utilize jacking system by splash guard and reinforcing bar To the particular location needing construction, jacking, to desired location, compares traditional artificial traction Simple pulley and carrying to longitudinal driving again To complete the mode of splash guard and reinforcing bar feeding, time and labour saving, the labor intensity of workman is less, splash guard and reinforcing bar lift by crane, transport Defeated, jacking positioning is convenient.
6th, the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding that this utility model provides, even if tunnel is because of ring of constructing The differences such as border, construction requirement lead to its cross section profile different, without redesign and processing, and traditional splash guard laying platform Car and reinforcing bar binding chassis need to re-start design according to different section of outline and process, and considerably increase design and add In the work cycle, also extend construction period simultaneously, therefore follow-up construction period can be shortened using the technical program.
In addition to objects, features and advantages described above, this utility model also has other purposes, feature and excellent Point.Below with reference to accompanying drawings, this utility model is described in further detail.
Brief description
In order to be illustrated more clearly that the technical scheme in this utility model embodiment, below will be to required in embodiment description Accompanying drawing to be used be briefly described it should be apparent that, drawings discussed below be only of the present utility model some enforcement Example, for those of ordinary skill in the art, on the premise of not paying creative work, can also obtain according to these accompanying drawings Obtain other accompanying drawings, wherein:
The front view for anchor bar of waterproof plate in tunnels laying and the chassis of reinforcing bar binding that Fig. 1 provides for this utility model;
Fig. 2 is the left view (platform assembly not shown) of Fig. 1;
In figure:1st, stand, 11, door frame column, 12, door frame crossbeam group, 121, lateral standard knot, 122, top standard knot, 13rd, longitudinally connected beam group, 14, brace, 2, jacking system, 21, support base, 22, elevator, 23, mold, 24, power cylinder, 3, Platform assembly, 31, platform, 32, guard rail, 33, working stand, 4, tackling system, 41, base, 42, turning arm, 43, hook, 44, Steel wire rope, 5, travel structure, 6, workmen.
Specific embodiment
With reference to accompanying drawing of the present utility model, the technical scheme in this utility model embodiment is carried out clear, complete Description it is clear that described embodiment is only a part of embodiment of the present utility model, rather than whole embodiment.
Embodiment 1:
Refer to Fig. 1~Fig. 2, a kind of chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding, rising including arch door shape The stand 1 of supporting role, it is movably arranged on stand 1 and for splash guard and reinforcing bar being transported to the jacking system of construction location 2nd, it is arranged on stand 1 and for providing the platform assembly 3 of construction space for workmen, being arranged in platform assembly 3 and use In the tackling system 4 being hoisted to jacking system 2 splash guard and reinforcing bar from ground, located at stand 1 bottom and can make the stand 1 can The walking mechanism 5 freely walked.
Described stand 1 includes door frame column 11, and (door frame column can be according to conventional set-up mode in prior art, such as According to front left, front right, rear left, rear right bit, four root posts are set) and it is separately positioned on the door frame on described door frame column 11 (when using four root posts, the two ends of one group of door frame crossbeam group connect front left respectively for crossbeam group 12 and longitudinally connected beam group 13 Column and front right column on, the two ends of another group of door frame crossbeam group connect respectively after the column of left and rear right vertical On post;The two ends of one group of longitudinally connected beam group connect on the column of front left and the column of rear left respectively, and another group longitudinally connects The two ends connecing beam group connect on the column of front right and the column of rear right respectively), on described door frame column 11 along the vertical direction (quantity of installing hole can be according to reality to be provided with multiple installing holes for adjusting the height in above-below direction for the door frame crossbeam group 12 Demand selects, and the distance of two neighboring installing hole can also design according to practical situation, between two neighboring installing hole Away from for 10-50cm);Described door frame crossbeam group 12 includes two groups of door frame crossbeams, that is, before and after be set up in parallel two groups it is also possible to according to Practical situation selects other as three groups, the quantity such as four groups, and described door frame crossbeam includes two groups of lateral standard knots 121 and one group of top Standard knot 122, two groups of lateral standard knots 121 are in up-narrow and down-wide splayed setting;Described top standard knot 122 is horizontally disposed with, And its two ends connects the top of two groups of lateral standard knots 121 respectively.
(herein, described tackling system 4 includes being fixedly installed on described stand 1 and include the base 41 of slewing equipment Base can also be arranged on stand by bracing frame), first end is movably arranged on described base 41 and can complete to stretch, bow Face upward and the turning arm 42 of revolution action and the hook 43 being arranged on described turning arm 42 second end by steel wire rope 44.
Described platform assembly 3 includes many group platforms 31 (platform quantity determines according to the actual requirements) of the setting in step, Many group platforms 31, the longitudinal length of described platform 31 are all provided with along the vertical direction on described door frame column 11 and described door frame crossbeam Identical with stand longitudinal direction effective operation length.
Described platform 31 is provided with the guard rail 32 playing protective action;It is provided with for constructing between two neighboring platform 31 The working stand 33 that personnel pass through.
Described jacking system 2 includes being movably arranged on the support base 21 of platform 31 upper surface positioned at top, passes through power Cylinder 24 is arranged on described support base 21 and for lifting the elevator 22 of splash guard and reinforcing bar and being located at described elevator 22 Top and for accommodate by lifting splash guard and reinforcing bar mold 23.
Be provided with track on the upper surface of the platform 31 at top along the longitudinal direction, described support base 21 be provided with described The road wheel that track matches is so that jacking system 2 can back and forth be walked in orbit.
Described walking mechanism 5 include being arranged at four of stand 1 bottom can move freely and brake device roller.
Described longitudinally connected beam group 13 includes many longitudinally connected beams (particular number can determine), phase according to practical situation It has been provided with the brace 14 of booster action between adjacent two longitudinally connected beams.
The application chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding of the present utility model, will first with tackling system The splash guard on ground and reinforcing bar are hoisted to the platform of the construction above door frame, are then indulged splash guard and reinforcing bar using jacking system To travelling to needing, to desired location, compare traditional artificial traction Simple pulley and carrying come again by jacking for the particular location of construction Complete splash guard and the mode of reinforcing bar feeding, time and labour saving, the labor intensity of workman is less, splash guard and reinforcing bar lifting, transport, Jacking positioning is convenient.
The foregoing is only embodiment of the present utility model, not thereby limit scope of patent protection of the present utility model, Equivalent structure or equivalent flow conversion that every utilization this utility model description and accompanying drawing content are made, directly or indirectly use In other related technical fields, all include in the same manner in scope of patent protection of the present utility model.

Claims (8)

1. a kind of chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding is it is characterised in that the support that rises including arch door shape is made Stand (1), to be movably arranged on stand (1) upper and for splash guard and reinforcing bar are transported to the jacking system of construction location (2), it is arranged on stand (1) above and for providing the platform assembly (3) of construction space for workmen, being arranged on platform assembly (3) upper and for splash guard and reinforcing bar are hoisted to from ground jacking system (2) tackling system (4), located at stand (1) bottom The portion and walking mechanism (5) that stand (1) can freely walk can be made;
Described stand (1) includes door frame column (11) and is separately positioned on the door frame crossbeam group on described door frame column (11) (12) and longitudinally connected beam group (13), described door frame column (11) be provided with multiple for adjusting door frame crossbeam group (12) upper and lower The installing hole of the height in direction;Described door frame crossbeam group (12) includes at least two groups door frame crossbeams, and described door frame crossbeam includes two Organize lateral standard knot (121) and one group of top standard knot (122), two groups of lateral standard knots (121) are in up-narrow and down-wide splayed Setting;Described top standard knot (122) is horizontally disposed with, and its two ends connects the top of two groups of lateral standard knots (121) respectively.
2. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 1 is it is characterised in that described Crane system (4) includes being fixedly installed on described stand (1) above and including the base (41) of slewing equipment, first end activity setting Turning arm (42) on described base (41) and the extension being arranged on described turning arm (42) second end by steel wire rope (44) Hook (43).
3. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 1-2 any one, its feature It is, described platform assembly (3) includes many group platforms (31), described door frame column (11) and the described door frame of the setting in step Many group platforms (31) are all provided with crossbeam, the longitudinal length of described platform (31) is long with stand longitudinal direction effective operation along the vertical direction Degree is identical.
4. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 3 is it is characterised in that described put down Platform (31) is provided with the guard rail (32) playing protective action;It is provided between two neighboring platform (31) and pass through for workmen Working stand (33).
5. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 3 is it is characterised in that described liter Fall system (2) is included being movably arranged on the support base (21) of platform (31) upper surface positioned at top, is set by power cylinder (24) Put in described support base (21) above and for lifting the elevator (22) of splash guard and reinforcing bar and being located at described elevator (22) Top and for accommodate by lifting splash guard and reinforcing bar mold (23).
6. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 5 is it is characterised in that be located at top It is provided with track along the longitudinal direction, described support base (21) is provided with and is matched with described track on the upper surface of platform (31) in portion Road wheel.
7. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 3 is it is characterised in that described row Walk mechanism (5) include being arranged at four of stand (1) bottom can move freely and brake device roller.
8. the chassis for anchor bar of waterproof plate in tunnels laying and reinforcing bar binding according to claim 3 is it is characterised in that described indulge Include many longitudinally connected beams to tie-beam group (13), between adjacent two longitudinally connected beams, be provided with the brace of booster action (14).
CN201620832055.3U 2016-08-01 2016-08-01 A platform truck for tunnel water proofing board is laid and reinforcement Active CN205977243U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620832055.3U CN205977243U (en) 2016-08-01 2016-08-01 A platform truck for tunnel water proofing board is laid and reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620832055.3U CN205977243U (en) 2016-08-01 2016-08-01 A platform truck for tunnel water proofing board is laid and reinforcement

Publications (1)

Publication Number Publication Date
CN205977243U true CN205977243U (en) 2017-02-22

Family

ID=58028597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620832055.3U Active CN205977243U (en) 2016-08-01 2016-08-01 A platform truck for tunnel water proofing board is laid and reinforcement

Country Status (1)

Country Link
CN (1) CN205977243U (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100651A (en) * 2017-05-13 2017-08-29 山东佳信机械设备有限公司 A kind of tunnel-liner is seamlessly connected reinforcing bar positioning, splash guard laying chassis
CN107191195A (en) * 2017-07-25 2017-09-22 重庆交通大学 The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic
CN107559025A (en) * 2017-10-13 2018-01-09 湖南五新隧道智能装备股份有限公司 A kind of waterproof construction chassis
CN107620601A (en) * 2017-10-13 2018-01-23 湖南五新隧道智能装备股份有限公司 Waterproof construction chassis of the waterproof construction with rotary folding arm group and comprising this arm group
CN107956488A (en) * 2017-12-27 2018-04-24 中铁工程装备集团有限公司 A kind of splash guard reinforcing bar spreads hanging platform car
CN108331603A (en) * 2018-04-04 2018-07-27 湖南五新隧道智能装备股份有限公司 A kind of multi-functional trolley and its construction method
CN108561157A (en) * 2018-05-16 2018-09-21 湖南五新隧道智能装备股份有限公司 A kind of Mobile workbench being laid with for reinforcing bar conveying binding and waterproof cloth
CN108756934A (en) * 2018-06-01 2018-11-06 招商局重庆交通科研设计院有限公司 Run disease tunnel assembled treatment structures construction operation trolley
CN108756960A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN108798727A (en) * 2018-08-02 2018-11-13 甘肃路桥第三公路工程有限责任公司 A kind of tunnel self-propelled splash guard dossal reinforcing bar positioning integrally multi-functional trolley and application
CN109113766A (en) * 2018-08-30 2019-01-01 中铁局集团有限公司 A kind of Waterproof cloth laying trolley
CN110566244A (en) * 2019-10-22 2019-12-13 湖南五新隧道智能装备股份有限公司 Trolley
WO2021129084A1 (en) * 2019-12-26 2021-07-01 洛阳高飞桥隧机械有限公司 Modular assembly operation platform apparatus of portal frame-free lining trolley
CN113152411A (en) * 2021-03-25 2021-07-23 安徽省路港工程有限责任公司 Construction method of ship lock reinforcement cage binding platform
CN113339021A (en) * 2021-05-31 2021-09-03 中铁工程服务有限公司 Complete equipment for accurately assembling secondary lining steel bars in mountain tunnel
CN113944489A (en) * 2021-10-18 2022-01-18 中国建筑土木建设有限公司 Adjustable waterproof board trolley

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100651A (en) * 2017-05-13 2017-08-29 山东佳信机械设备有限公司 A kind of tunnel-liner is seamlessly connected reinforcing bar positioning, splash guard laying chassis
CN107191195A (en) * 2017-07-25 2017-09-22 重庆交通大学 The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic
CN107559025A (en) * 2017-10-13 2018-01-09 湖南五新隧道智能装备股份有限公司 A kind of waterproof construction chassis
CN107620601A (en) * 2017-10-13 2018-01-23 湖南五新隧道智能装备股份有限公司 Waterproof construction chassis of the waterproof construction with rotary folding arm group and comprising this arm group
CN107620601B (en) * 2017-10-13 2023-09-05 湖南五新隧道智能装备股份有限公司 Rotary folding arm set for waterproof construction and trolley comprising same for waterproof construction
CN107956488A (en) * 2017-12-27 2018-04-24 中铁工程装备集团有限公司 A kind of splash guard reinforcing bar spreads hanging platform car
CN108331603A (en) * 2018-04-04 2018-07-27 湖南五新隧道智能装备股份有限公司 A kind of multi-functional trolley and its construction method
CN108561157A (en) * 2018-05-16 2018-09-21 湖南五新隧道智能装备股份有限公司 A kind of Mobile workbench being laid with for reinforcing bar conveying binding and waterproof cloth
CN108561157B (en) * 2018-05-16 2020-07-24 湖南五新隧道智能装备股份有限公司 A operation platform truck that is used for reinforcement to carry ligature and waterproof cloth to lay
CN108756934A (en) * 2018-06-01 2018-11-06 招商局重庆交通科研设计院有限公司 Run disease tunnel assembled treatment structures construction operation trolley
CN108756934B (en) * 2018-06-01 2023-10-20 招商局重庆交通科研设计院有限公司 Operation disease tunnel assembly type treatment structure construction operation trolley
CN108756960A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN108798727A (en) * 2018-08-02 2018-11-13 甘肃路桥第三公路工程有限责任公司 A kind of tunnel self-propelled splash guard dossal reinforcing bar positioning integrally multi-functional trolley and application
CN108798727B (en) * 2018-08-02 2024-04-02 甘肃路桥第三公路工程有限责任公司 Tunnel self-propelled waterproof board cloth hanging steel bar positioning integrated multifunctional trolley and application
CN109113766A (en) * 2018-08-30 2019-01-01 中铁局集团有限公司 A kind of Waterproof cloth laying trolley
CN110566244A (en) * 2019-10-22 2019-12-13 湖南五新隧道智能装备股份有限公司 Trolley
WO2021129084A1 (en) * 2019-12-26 2021-07-01 洛阳高飞桥隧机械有限公司 Modular assembly operation platform apparatus of portal frame-free lining trolley
CN113152411A (en) * 2021-03-25 2021-07-23 安徽省路港工程有限责任公司 Construction method of ship lock reinforcement cage binding platform
CN113339021A (en) * 2021-05-31 2021-09-03 中铁工程服务有限公司 Complete equipment for accurately assembling secondary lining steel bars in mountain tunnel
CN113944489A (en) * 2021-10-18 2022-01-18 中国建筑土木建设有限公司 Adjustable waterproof board trolley
CN113944489B (en) * 2021-10-18 2024-03-12 中国建筑土木建设有限公司 Adjustable waterproof board trolley

Similar Documents

Publication Publication Date Title
CN205977243U (en) A platform truck for tunnel water proofing board is laid and reinforcement
CN104060844B (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
CN207498755U (en) A kind of traveling trolley adjusted with horizontal extension and vertical supporting
CN102337905B (en) Open type TBM (Tunnel Boring Machine) fullface synchronous lining trolley for hydraulictunnel
CN106437795A (en) Tunnel vehicle-mounted folding type multifunctional work rack
CN108798727A (en) A kind of tunnel self-propelled splash guard dossal reinforcing bar positioning integrally multi-functional trolley and application
CN207498754U (en) A kind of novel track-laying machine of city track traffic engineering
CN101476292A (en) Method and equipment for mounting precast beam
CN104695335A (en) Overall reinforcement binding and hoisting construction method and construction device adopting upstroke movable scaffolding
CN108643941B (en) Gantry type arch installs trolley
CN110158486A (en) It is a kind of to set up the Bridge Erector and construction method for spelling wide beam
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN211142832U (en) Suspension bridge catwalk system
CN105019357A (en) Method for mounting specially-shaped precast bridge decks on open lattice steel beams of arched bridge
CN208870611U (en) A kind of multi-functional trolley of tunnel self-propelled splash guard dossal reinforcing bar positioning one
CN205382425U (en) Railway T type bridge adds builds sound barrier beam mold plate girder unwheeling
CN108004930A (en) The construction method of vertical shift bowstring arch bridge
CN205839594U (en) Over-and-under type construction system that bridge superstructure construction used
CN111636914A (en) Construction method for integrating transportation and erection of straddle type monorail PC track beam in circular-section tunnel
CN207919265U (en) Suitable for covering rail plate-type ballastless track plate paver on steel truss girder bridge
CN108482519A (en) A kind of reinforced mesh transport trolley
CN106400696B (en) Mobile type combination Bailey bracket platform, packaged type combination Bailey bracket set up platform and the erection method of steel platform
CN205976546U (en) A rail transport device for sloping scope of operation
CN102431907B (en) Walking type tunnel carriageway plate crane
CN204729105U (en) A kind of sliding-mode trolley for the concreting of gateway opening type inclined shaft

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant