CN107069632A - Ultra-high-tension power transmission line Snowremoval device and system - Google Patents

Ultra-high-tension power transmission line Snowremoval device and system Download PDF

Info

Publication number
CN107069632A
CN107069632A CN201710259684.0A CN201710259684A CN107069632A CN 107069632 A CN107069632 A CN 107069632A CN 201710259684 A CN201710259684 A CN 201710259684A CN 107069632 A CN107069632 A CN 107069632A
Authority
CN
China
Prior art keywords
power transmission
transmission line
ultra
telescopic bar
tension power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710259684.0A
Other languages
Chinese (zh)
Other versions
CN107069632B (en
Inventor
赵恒�
关东亮
冯永彬
崔晓华
刘志勇
祝树华
张志宝
李娜
曹振
孙晓月
崔明军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Linyi Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710259684.0A priority Critical patent/CN107069632B/en
Publication of CN107069632A publication Critical patent/CN107069632A/en
Application granted granted Critical
Publication of CN107069632B publication Critical patent/CN107069632B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/16Devices for removing snow or ice from lines or cables

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The invention provides a kind of ultra-high-tension power transmission line Snowremoval device and system, belong to high-tension apparatus Snowremoval technical field.Described device includes:Insulating telescopic bar and the knocker for being connected to described insulating telescopic bar one end, the other end of insulating telescopic bar are provided with the connecting portion being detachably connected with the unmanned plane;Control chip and signal transceiver are provided with insulating telescopic bar, control chip is connected by signal transceiver with the processor of the unmanned plane, control signal for receiving ground by the processor, according to the control signal, insulating telescopic bar and knocker action are controlled, to remove the accumulated snow on ultra-high-tension power transmission line.Ultra-high-tension power transmission line Snowremoval device and system provided in an embodiment of the present invention, the accumulated snow on ultra-high-tension power transmission line can be removed automatically, it is safe, ultra-high-tension power transmission line is avoided to damage operation maintenance personnel, the effect that removes the snow is good, it is ensured that the stability of ultra-high-tension power transmission line power Transmission under low temperature adverse circumstances.

Description

Ultra-high-tension power transmission line Snowremoval device and system
Technical field
The present invention relates to high-tension apparatus Snowremoval technical field, in particular to a kind of ultra-high-tension power transmission line accumulated snow Remove device and system.
Background technology
When snowfall occurs for northern China winter, easily accumulated snow is formed on the outdoor ultra-high-tension power transmission line of transformer station.Surface area The phenomenons such as electric discharge, flashover seriously easily occur for snow, icing, and grid equipment is possible to bring harm and causes consequence need timely The precautionary measures are taken, therefore operation maintenance personnel can be according to the cleaning dredging work that snowfall situation carries out ice and snow, ice is slipped.Need not timing Facilities for observation accumulated snow and snow melt situation, in time remove ice slip, it is ice-covering-proof wave, anti-accumulated snow dissolves and causes equipment short circuit accident and set The accidents such as standby flashover.
At present, operation maintenance personnel is insulated tension pole to common tool when accumulated snow ice slips removing on ultra-high-tension power transmission line, using exhausted The cephalomenia of edge pull bar is rapped dozen ice and slipped, or the head of insulated tension pole is bound into broom cleaning ice and snow.Due to close to high voltage power transmission Circuit homework belongs to dangerous operation, just in case operation maintenance personnel touches ultra-high-tension power transmission line by mistake, then security incident is likely to result in, seriously It can even cause casualties.
The content of the invention
For above-mentioned problems of the prior art, the invention provides a kind of ultra-high-tension power transmission line Snowremoval device And system, it is dynamic by UAV system, the accumulated snow on ultra-high-tension power transmission line can be removed automatically, it is to avoid ultra-high-tension power transmission line is to fortune Dimension personnel damage.
In a first aspect, the embodiments of the invention provide a kind of ultra-high-tension power transmission line Snowremoval device, for installed in nothing On man-machine, described device includes:Insulating telescopic bar and the knocker for being connected to described insulating telescopic bar one end, the insulating telescopic The other end of bar is provided with the connecting portion being detachably connected with the unmanned plane;
Control chip and signal transceiver are provided with the insulating telescopic bar, the control chip passes through signal transceiver It is connected with the processor of the unmanned plane, the control signal for receiving ground by the processor is believed according to the control Number, control insulating telescopic bar and knocker action, to remove the accumulated snow on ultra-high-tension power transmission line;
The motor being connected with the control chip is additionally provided with the insulating telescopic bar, in the control core Under the control of piece, the expansion link is driven to stretch out or retract;
The knocker includes swing mechanism and the stamp that is connected with the swing mechanism, the swing mechanism with it is described Control chip is connected, and under the control of the control chip, driving the stamp to swing, taps ultra-high-tension power transmission line, To shake off the accumulated snow on ultra-high-tension power transmission line.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the first of first aspect, wherein, institute Connecting portion is stated for engaging lug, the engaging lug is connected with the connecting seat set on the inside of unmanned plane upper wall in articulated manner.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of second of first aspect, wherein, institute State connecting portion and be formed with external screw thread, be connected in the female mounting hole of tool set on the inside of unmanned plane upper wall.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the third of first aspect, wherein, institute State the braking motor for being additionally provided with and being connected with control chip in insulating telescopic bar;The braking motor is outer with the motor The tailing axle connection of dew, for when the motor stops, reverse active force to be applied to the tailing axle of the motor, with The motor is set accurately to brake.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 4th of first aspect kind, wherein, institute Stamp is stated to be made of elastomeric material.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 5th of first aspect kind, wherein, institute State control chip and the signal transceiver is arranged on control panel, the control panel is plugged in the insulating telescopic bar In slot on wall, the slot is connected with for the power module that described device is powered.
With reference to the 5th kind of possible embodiment of first aspect, the embodiments of the invention provide the 6th of first aspect kind Possible embodiment, wherein, it is provided with hatch door to be opened/closed on the insulating telescopic bar perisporium relative with the slot.
With reference to the 6th kind of possible embodiment of first aspect, the embodiments of the invention provide the 7th of first aspect kind Possible embodiment, wherein, the swing mechanism is the oscillating cylinder being connected with the control chip, the stamp connection On the output shaft of the oscillating cylinder.
Second aspect, the embodiment of the present invention additionally provides a kind of ultra-high-tension power transmission line Snowremoval system, including main control computer, Unmanned plane and the ultra-high-tension power transmission line Snowremoval device being arranged on the unmanned plane, the unmanned plane include processor and logical Part is interrogated, the processor is connected by the communication component with the main control computer on ground, data are transmitted simultaneously to the main control computer Receive the control signal that the main control computer is returned.
With reference to second aspect, the embodiments of the invention provide the possible embodiment of the first of second aspect, wherein, institute Stating unmanned plane also includes alarm and the electric field induction device being arranged on rotor, and the electric field induction device connects with the processor Connect, the electric field intensity value for sensing surrounding transmits the electric field intensity value to processor;
The processor is used to the electric field intensity value received being compared with default alarm threshold value, if the electric field Intensity level is higher than the alarm threshold value, then sends alarm signal to the alarm.
The embodiment of the present invention brings following beneficial effect:
Ultra-high-tension power transmission line Snowremoval device and system provided in an embodiment of the present invention, high voltage power transmission can be removed automatically Accumulated snow on circuit, safe, it is to avoid ultra-high-tension power transmission line is damaged to operation maintenance personnel, snow removing effect is good, it is ensured that The stability of ultra-high-tension power transmission line power Transmission under low temperature adverse circumstances.
Other features and advantages of the present invention will be illustrated in the following description, also, partly be become from specification Obtain it is clear that or being understood by implementing the present invention.The purpose of the present invention and other advantages are in specification, claims And specifically noted structure is realized and obtained in accompanying drawing.
To enable the above objects, features and advantages of the present invention to become apparent, preferred embodiment cited below particularly, and coordinate Appended accompanying drawing, is described in detail below.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The accompanying drawing used required in embodiment or description of the prior art is briefly described, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
The structural representation for the ultra-high-tension power transmission line Snowremoval device that Fig. 1 is provided by one embodiment of the invention;
The structural representation for the ultra-high-tension power transmission line Snowremoval device that Fig. 2 is provided by another embodiment of the present invention;
The use state figure for the ultra-high-tension power transmission line Snowremoval device that Fig. 3 is provided by another embodiment of the present invention;
The structured flowchart for the ultra-high-tension power transmission line Snowremoval system that Fig. 4 is provided by one embodiment of the invention.
Icon:
1- ultra-high-tension power transmission line Snowremoval devices;11- control chips;12- signal transceivers;13- motors;14- Braking motor;15- oscillating cylinders;110- insulating telescopic bars;120- knockers;111- telescopic sections;112- changeover portions;113- drives Section;114- hatch doors;121- oscillating cylinders;122- stamps;130- connecting portions;2- unmanned planes;21- processors;22- communication sections Part;23- electric field induction devices;24- alarms;200- fuselages;210- rotors;3- main control computers.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with accompanying drawing to the present invention Technical scheme be clearly and completely described, it is clear that described embodiment is a part of embodiment of the invention, rather than Whole embodiments.The component of embodiments of the present invention, which are generally described and illustrated herein in the accompanying drawings can be matched somebody with somebody with a variety of Put to arrange and design.Therefore, the detailed description of embodiments of the invention below to providing in the accompanying drawings is not intended to limit The scope of claimed invention, but it is merely representative of the selected embodiment of the present invention.Based on the embodiment in the present invention, sheet The every other embodiment that field those of ordinary skill is obtained under the premise of creative work is not made, belongs to the present invention The scope of protection.
The problem of easily causing security incident for the accumulated snow on existing manual cleaning ultra-high-tension power transmission line, the present invention is real Example is applied there is provided a kind of ultra-high-tension power transmission line Snowremoval device and system, the ultra-high-tension power transmission line of the present invention is accumulated first below Snow remove device describes in detail.
Embodiment one
This embodiment offers a kind of ultra-high-tension power transmission line Snowremoval device, for installed in unmanned plane.Such as Fig. 1 and Shown in Fig. 2, the ultra-high-tension power transmission line Snowremoval device includes insulating telescopic bar 110 and is connected to the one end of insulating telescopic bar 110 Knocker 120, the other end of the insulating telescopic bar 110 is provided with the connecting portion 130 being detachably connected with unmanned plane.
As shown in fig. 1, connecting portion 130 is engaging lug, and engaging lug on the inside of unmanned plane upper wall in articulated manner with setting Connecting seat connection.It is formed with the engaging lug of connecting portion 130 on hole, the connecting seat of unmanned plane and is formed with hole, connecting shaft Hole through on the hole and engaging lug on connecting seat, so that the two be linked together.
It is appreciated that above-mentioned connecting portion can also be connected using other manner with unmanned plane.For example, connecting portion is formed with outside The female mounting hole of tool is formed with screw thread, unmanned plane, the mode that connecting portion is connected through a screw thread is connected on unmanned plane In the mounting hole set on the inside of wall.
It should be noted that the connection of connecting portion and unmanned plane is not limited to above two connected mode.
Control chip and signal transceiver are provided with insulating telescopic bar 110, the control chip passes through signal transceiver It is connected with the processor of the unmanned plane, the control signal for receiving ground by the processor is believed according to the control Number, control insulating telescopic bar and knocker action, to remove the accumulated snow on ultra-high-tension power transmission line.
The ultra-high-tension power transmission line Snowremoval device that the embodiment is provided, the product on ultra-high-tension power transmission line can be removed automatically Snow, safe, it is to avoid ultra-high-tension power transmission line is damaged to operation maintenance personnel, snow removing effect is good, it is ensured that high voltage transmission line The stability of road power Transmission under low temperature adverse circumstances.
The motor being connected with the control chip is additionally provided with insulating telescopic bar 110, in the control core Under the control of piece, the expansion link is driven to stretch out or retract.
As shown in figure 1, a kind of specific implementation of insulating telescopic bar 110 can be:Insulating telescopic bar includes telescopic section 111 and drive section 113, telescopic section 111 and drive section 113 are all hollow tubular elements.The telescopic section 111 and drive section Connected in the middle of 113 by changeover portion 112.Certainly, telescopic section 111 and drive section 113 can also be directly connected to, i.e. drive section 113 It is directly connected to following hollow expansion links.
Telescopic section 111 is internally provided with hollow expansion link, and hollow expansion link has a screw rod, hollow expansion link with Can relative motion in the axial direction between screw rod.Furthermore, one end of expansion link is provided with nut, nut and screw rod coupling Close, by the rotation of screw rod, expansion link can be moved back and forth along the axially any of screw rod.
The head end of expansion link is provided with guide screw cap, and guide screw cap is slidably connected with the madial wall of telescopic section shell, screw rod Head end also has a sliding block, and sliding block is connected to the madial wall of expansion link with slidable relation, when screw rod is in the band of motor During dynamic lower rotation, it is possible to move expansion link using guide screw hatband reciprocating along the axial direction of screw rod.
Drive section 113 is internally provided with motor, and motor is used to drive screw rod to rotate.Or, motor leads to Crossing reducing gear drives screw rod to rotate.The afterbody of motor has an exposed tailing axle, be additionally provided with inside drive section 113 with The braking motor of control chip connection, the exposed tailing axle connection of the braking motor and motor, for working as motor During stopping, reverse active force is applied to the tailing axle of motor, to suppress the inertia force that motor and screw rod are produced, makes drive Dynamic motor is accurately braked.
Changeover portion 112 is a kind of hollow pipe fitting, be respectively arranged with the axial two ends of changeover portion the first threaded portion and Second threaded portion.One end of the shell of telescopic section 111 is connected with the first threaded portion, the other end and the connecting portion screw thread of telescopic section 111 Connection.The shell of the hollow tubular of drive section 113 encapsulates motor, reducing gear and following braking motors wherein.
Knocker 120 includes swing mechanism and the stamp 122 being connected with swing mechanism, and swing mechanism connects with control chip Connect, under the control of control chip, driving stamp 122 to be swung, and ultra-high-tension power transmission line is tapped, to shake off high voltage transmission line Accumulated snow on road.Stamp 122 is made of elastomeric material, and quality is soft, will not damage electric wire.
Control chip and signal transceiver are arranged on control panel, and control panel is plugged on insulating telescopic bar inwall In slot, slot is connected with for the power module that described device is powered.The power module can be provided in described device Battery pack or the power supply that is external on unmanned plane.
As shown in Fig. 2 hatch door to be opened/closed is provided with the insulating telescopic bar perisporium relative with slot, convenient plug control Plate, maintenance etc. is taken out by control panel.The side of hatch door is with the perisporium of insulating telescopic bar by gemel connection, and opposite side, which is provided with, to be closed Locking device, when hatch door is closed, latches automatically.A handle is provided with the outside of hatch door, hatch door is easy to open.
Swing mechanism is the oscillating cylinder 121 being connected with control chip, and stamp is connected to the output shaft of oscillating cylinder 121 On, in the drive lower swing of oscillating cylinder 121, to tap ultra-high-tension power transmission line, shake off accumulated snow thereon.
Fig. 3 is the working state figure for the ultra-high-tension power transmission line Snowremoval device that the embodiment of the present invention is provided.Such as Fig. 3 institutes Show, the ultra-high-tension power transmission line Snowremoval device is arranged in the cabin of unmanned plane.The unmanned plane includes fuselage 200 and position In the rotor 210 of body upper.Ultra-high-tension power transmission line Snowremoval device 1 is under the control of ground main control computer, under fuselage Side is stretched out, and underlying stamp is swung, and ultra-high-tension power transmission line is tapped, to shake off accumulated snow thereon.
Embodiment two
This embodiment offers a kind of ultra-high-tension power transmission line Snowremoval system, as shown in figure 4, the system includes main control computer 3rd, unmanned plane 2 and the ultra-high-tension power transmission line Snowremoval device 1 being arranged on unmanned plane 2.Processor 21 is provided with unmanned plane 2 With communication component 22, processor 21 is connected by communication component 22 with the main control computer 3 on ground, and data are transmitted simultaneously to main control computer 3 Receive the control signal that main control computer 3 is returned.
Unmanned plane 2 also includes alarm 24 and the electric field induction device 23 being arranged on rotor, electric field induction device 23 and processing Device 21 is connected, the electric field intensity value for sensing surrounding, and electric field intensity value is transmitted to processor 21.
Processor 21 is used to the electric field intensity value received being compared with default alarm threshold value, if electric field intensity value Higher than alarm threshold value, then alarm signal is sent to alarm 24, prevent the rotor of unmanned plane 2 from touching ultra-high-tension power transmission line.
Control chip 11, the letter being connected respectively with control chip 11 are provided with ultra-high-tension power transmission line Snowremoval device 1 Number transceiver 12, motor 13, braking motor 14 and oscillating cylinder 15.
What main control computer 3 can be understood as resting on the ground includes the remote control in the device of remote control, or staff's hand. During work, main control computer 3 sends control signal to unmanned plane 2, controls flying height and the direction of unmanned plane, and high voltage transmission line Stretching, retraction and the action of oscillating cylinder of the insulating telescopic bar of road Snowremoval device 1.The processor 21 of unmanned plane 2 passes through Communication component 22 receives the control signal from main control computer 3, and control signal is forwarded into high voltage power transmission by communication component 22 Circuit Snowremoval device 1.The control chip 11 of ultra-high-tension power transmission line Snowremoval device is received by signal transceiver 12 and controlled Signal processed, and control the action of motor 13, braking motor 14 and oscillating cylinder 15.
Specifically the course of work is:When unmanned plane 2 is located at the top of ultra-high-tension power transmission line, believed according to the control of main control computer Number, motor 13 starts, the insulating telescopic bar elongation of Snowremoval device, is stretched out from fuselage lower section.When insulating telescopic bar is stretched Grow to behind suitable position, under stop signal effect, motor 13 stops, and insulating telescopic bar stops elongation.Oscillating cylinder 15 actions, stamp carries out snow removing operation.
Ultra-high-tension power transmission line Snowremoval device and system provided in an embodiment of the present invention have identical technical characteristic, institute Can also solve identical technical problem, identical technique effect is reached.
, can it should be noted that in embodiment provided by the present invention, it should be understood that disclosed system and method To realize by another way.Device embodiment described above is only schematical, for example, stroke of the unit Point, only a kind of division of logic function can have other dividing mode when actually realizing, in another example, multiple units or group Part can combine or be desirably integrated into another system, or some features can be ignored, or not perform.It is described to be used as separation unit The unit that part illustrates can be or may not be physically separate, and the part shown as unit can be or also may be used Not to be physical location, you can with positioned at a place, or it can also be distributed on multiple NEs.Can be according to reality The need for select some or all of unit therein to realize the purpose of this embodiment scheme.
In addition, each functional unit in the embodiment that the present invention is provided can be integrated in a processing unit, also may be used To be that unit is individually physically present, can also two or more units it is integrated in a unit.
If the function is realized using in the form of SFU software functional unit and is used as independent production marketing or in use, can be with It is stored in a computer read/write memory medium.Understood based on such, technical scheme is substantially in other words The part contributed to prior art or the part of the technical scheme can be embodied in the form of software product, the meter Calculation machine software product is stored in a storage medium, including some instructions are to cause a computer equipment (can be individual People's computer, server, or network equipment etc.) perform all or part of step of each of the invention embodiment methods described. And foregoing storage medium includes:USB flash disk, mobile hard disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), magnetic disc or CD etc. are various can be with the medium of store program codes.
In addition, term " first ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that indicating or implying phase To importance.
Finally it should be noted that:Embodiment described above, is only the embodiment of the present invention, to illustrate the present invention Technical scheme, rather than its limitations, protection scope of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, it will be understood by those within the art that:Any one skilled in the art The invention discloses technical scope in, it can still modify to the technical scheme described in previous embodiment or can be light Change is readily conceivable that, or equivalent substitution is carried out to which part technical characteristic;And these modifications, change or replacement, do not make The essence of appropriate technical solution departs from the spirit and scope of technical scheme of the embodiment of the present invention, should all cover the protection in the present invention Within the scope of.Therefore, protection scope of the present invention described should be defined by scope of the claims.

Claims (10)

1. a kind of ultra-high-tension power transmission line Snowremoval device, it is characterised in that for installed in unmanned plane, described device bag Include:Insulating telescopic bar and the knocker for being connected to described insulating telescopic bar one end, the other end of the insulating telescopic bar are provided with The connecting portion being detachably connected with the unmanned plane;
Control chip and signal transceiver are provided with the insulating telescopic bar, the control chip passes through signal transceiver and institute State the processor connection of unmanned plane, the control signal for receiving ground by the processor, according to the control signal, control Insulating telescopic bar and knocker action processed, to remove the accumulated snow on ultra-high-tension power transmission line;
The motor being connected with the control chip is additionally provided with the insulating telescopic bar, in the control chip Under control, the expansion link is driven to stretch out or retract;
The knocker includes swing mechanism and the stamp being connected with the swing mechanism, the swing mechanism and the control Chip is connected, and under the control of the control chip, driving the stamp to swing, taps ultra-high-tension power transmission line, to shake Accumulated snow on drop height pressure transmission line.
2. device according to claim 1, it is characterised in that the connecting portion is engaging lug, and the engaging lug is to be hinged Mode and unmanned plane upper wall on the inside of the connecting seat that sets be connected.
3. device according to claim 1, it is characterised in that the connecting portion is formed with external screw thread, is connected to unmanned plane In the female mounting hole of tool set on the inside of upper wall.
4. device according to claim 1, it is characterised in that be additionally provided with and connect with control chip in the insulating telescopic bar The braking motor connect;The braking motor is connected with the exposed tailing axle of the motor, for stopping when the motor When only, apply reverse active force to the tailing axle of the motor, so that the motor is accurately braked.
5. device according to claim 1, it is characterised in that the stamp is made of elastomeric material.
6. device according to claim 1, it is characterised in that the control chip and the signal transceiver are arranged on control In making sheet, the control panel is plugged in the slot on the insulating telescopic bar inwall, and the slot is with being described device The power module connection of power supply.
7. device according to claim 6, it is characterised in that on the insulating telescopic bar perisporium relative with the slot It is provided with hatch door to be opened/closed.
8. device according to claim 1, it is characterised in that the swing mechanism is the pendulum being connected with the control chip Take offence cylinder, the stamp is connected on the output shaft of the oscillating cylinder.
9. a kind of ultra-high-tension power transmission line Snowremoval system, it is characterised in that including main control computer, unmanned plane and be arranged on the nothing On man-machine such as ultra-high-tension power transmission line Snowremoval device according to any one of claims 1 to 8, the unmanned plane includes place Device and communication component are managed, the processor is connected by the communication component with the main control computer on ground, passed to the main control computer Transmission of data simultaneously receives the control signal that the main control computer is returned.
10. system according to claim 9, it is characterised in that the unmanned plane also includes alarm and is arranged on rotor On electric field induction device, the electric field induction device is connected with the processor, for sensing around electric field intensity value, will be described Electric field intensity value is transmitted to processor;
The processor is used to the electric field intensity value received being compared with default alarm threshold value, if the electric-field intensity Value is higher than the alarm threshold value, then sends alarm signal to the alarm.
CN201710259684.0A 2017-04-19 2017-04-19 Ultra-high-tension power transmission line Snowremoval device and system Expired - Fee Related CN107069632B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710259684.0A CN107069632B (en) 2017-04-19 2017-04-19 Ultra-high-tension power transmission line Snowremoval device and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710259684.0A CN107069632B (en) 2017-04-19 2017-04-19 Ultra-high-tension power transmission line Snowremoval device and system

Publications (2)

Publication Number Publication Date
CN107069632A true CN107069632A (en) 2017-08-18
CN107069632B CN107069632B (en) 2018-09-21

Family

ID=59599888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710259684.0A Expired - Fee Related CN107069632B (en) 2017-04-19 2017-04-19 Ultra-high-tension power transmission line Snowremoval device and system

Country Status (1)

Country Link
CN (1) CN107069632B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4135221A (en) * 1976-12-16 1979-01-16 Lvovsky Politekhnichesky Institut Ice melting circuit arrangement for a high-voltage transmission network
CN201975744U (en) * 2010-12-27 2011-09-14 王彬 Electric-power deicing tool
CN204538623U (en) * 2015-03-09 2015-08-05 国家电网公司 The artificial deicing tool of a kind of Multifunctional safe type electric power
CN105244833A (en) * 2015-11-22 2016-01-13 无锡同春新能源科技有限公司 De-icing unmanned aerial vehicle with photothermal device
CN105305356A (en) * 2015-12-09 2016-02-03 国网四川省电力公司广元供电公司 Power transmission line ground wire defroster
CN106025983A (en) * 2016-06-23 2016-10-12 陈晨 Overhead wire cable deicing unmanned plane

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4135221A (en) * 1976-12-16 1979-01-16 Lvovsky Politekhnichesky Institut Ice melting circuit arrangement for a high-voltage transmission network
CN201975744U (en) * 2010-12-27 2011-09-14 王彬 Electric-power deicing tool
CN204538623U (en) * 2015-03-09 2015-08-05 国家电网公司 The artificial deicing tool of a kind of Multifunctional safe type electric power
CN105244833A (en) * 2015-11-22 2016-01-13 无锡同春新能源科技有限公司 De-icing unmanned aerial vehicle with photothermal device
CN105305356A (en) * 2015-12-09 2016-02-03 国网四川省电力公司广元供电公司 Power transmission line ground wire defroster
CN106025983A (en) * 2016-06-23 2016-10-12 陈晨 Overhead wire cable deicing unmanned plane

Also Published As

Publication number Publication date
CN107069632B (en) 2018-09-21

Similar Documents

Publication Publication Date Title
CN109473932B (en) Short-range cable deicer
CN106072685B (en) A kind of pinion and-rack nut is efficiently caught broken device
CN106129890B (en) A kind of mountain area high-voltage electric power circuit upkeep operation unmanned plane
CN202395381U (en) Eliminator for winding substances of overhead conductor
CN109212383B (en) High-voltage line inspection device based on GPS
CN107069632A (en) Ultra-high-tension power transmission line Snowremoval device and system
CN109212382B (en) GPS inspection device for high-voltage line
CN203396826U (en) Portable induced-electricity electricity-testing device
CN205882549U (en) Electrified clearing device of overhead line foreign matter based on many rotors unmanned vehicles
CN108528241A (en) A kind of automobile-used charging pile that can be extracted automatically of electric firefighting
DE112020005287T5 (en) cable reel
CN109212380B (en) High-voltage line cycle inspection device based on GPS
CN218040468U (en) Device for preventing falling objects in high altitude during live working
CN106019508A (en) Device capable of scraping optical cable factice effectively
CN103143518A (en) Live cleaning tool for contact terminal and contact finger of 110kV disconnecting switch
CN205863867U (en) A kind of voltage wire ice removing device
CN207095600U (en) A kind of transmission line faultlocating device with dedusting and deicing function
CN203372290U (en) Chassis for aerial work platform
CN209943901U (en) Device convenient for moving computer host
CN204045249U (en) Cable sheath protective device in a kind of power construction process of convenient disassembly
CN208241183U (en) A kind of novel high-voltage line foreign matter cleaning equipment
CN203373093U (en) Aerial work platform
CN109193463B (en) Intelligent inspection device for high-voltage line
CN103382008A (en) Aerial work platform
CN206135294U (en) Pole is clear away to transformer substation's overhead line foreign matter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180921

Termination date: 20190419

CF01 Termination of patent right due to non-payment of annual fee