CN107067220A - The full-automatic lateral road figure technical method of project management progress - Google Patents

The full-automatic lateral road figure technical method of project management progress Download PDF

Info

Publication number
CN107067220A
CN107067220A CN201610439799.3A CN201610439799A CN107067220A CN 107067220 A CN107067220 A CN 107067220A CN 201610439799 A CN201610439799 A CN 201610439799A CN 107067220 A CN107067220 A CN 107067220A
Authority
CN
China
Prior art keywords
progress
engineering
project
software
engineering project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610439799.3A
Other languages
Chinese (zh)
Inventor
杨玉海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Haixing Integrated System Co Ltd
Original Assignee
Shenzhen Haixing Integrated System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Haixing Integrated System Co Ltd filed Critical Shenzhen Haixing Integrated System Co Ltd
Priority to CN201610439799.3A priority Critical patent/CN107067220A/en
Publication of CN107067220A publication Critical patent/CN107067220A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)

Abstract

Technical field:Management of engineering schedule graphic software techniques, the full-automatic generation technique of innovation engineering project progress figure, it is automatic calculate engineering project progress go into operation, the duration of completing, quantities, fund number.The orderly ever-changing progress msg data of Engineering Oriented project, correspondence automatically generates Protean engineering project progress lateral road linked, diagram.Realize three progress charts (three items) lateral road linked, diagram.Realize two grades of engineering project progress, three-level, level Four, Pyatyi, six grades of progress chart applications.Realize figure multi-format paging generation printing.Accurately reflect duration extension or lead, each progress associated connection.Duration compares with quantities or fund completion rate.Analysis of Policy Making is carried out, strengthens project management.Meet the multistage progress figure application demand of large and small engineering project.Extensive use can be obtained in terms of investment project progress control, budget items progress control and other progress controls.Whole thoughts, design method and software engineering all belong to source discover for the first time it is bright.Several seconds are operated every time with regard to that can be automatically performed.

Description

The full-automatic lateral road figure technical method of project management progress
1st, technical field
Management of engineering schedule graphics software
2nd, background technology
China advances now into fast-developing process to modernization of the country!Modernization of the country needs to carry out on a large scale Modernization construction, every year all engineering constructions of input many trillion member.It is face to do construction project well with how accomplishing many, fast, good, province Face development construction major issue.Modernization of the country needs building-up work to modernize.How engineering construction is planned!How engineering is carried out Build!How to do engineering construction management well is the important topic for being badly in need of solving.Chinese annual many trillion member construction investment, just there is number Thousand, tens thousand of construction projects.The planned planning project management of science, science engineering construction of being done step by step is built If.Each several hundred million members, the engineering construction project of billions of members, do construction well, shorten the engineering construction duration, reduce and build work Journey loss and waste, the duration, which shifts to an earlier date half a year, can just save the tens million of members of loan interest, the millions of members of operating expenses.The whole nation, which is saved, throws Enter tens billion of members, Qian Yiyuan!
3rd, the content of the invention
General introduction:Most of construction enterprises of present China also rest on original artificial management phase.Larger construction collection Enterprise of group also simply carries out enterprise's local messageization management, and technical merit is low.Construction project business management software is not comprehensive, interior Hold less, technical merit is low.External most notable gas large software company SAP, Oracle do not meet engineering corporation group yet The comprehensive handy integrated ERP system software engineering of management, wherein just without the advanced full-automatic graphics software of engineering project progress Technology.Engineering corporation group information system management overall application is the integrated ERP system software of enterprise, wherein, it is most important that work Journey project integrated management system software engineering, the full-automatic graphic software techniques of engineering of integrating project process.Chinese starfish is soft Part researches and develops engineering of integrating project management system software in the integrated ERP system software of innovation research and development engineering corporation, wherein being The system property technical requirements very high full-automatic graphics software of engineering project progress.This technology country is done there is presently no other people Arrive.
Project management is very complicated work.It is various construction project mansions, each towards many different the object of building Plant bridge road, railway subway etc..Each engineering project has temporary project, earth work, foundation engineering, major project, finishing Engineering, decorative engineering.There is presently no accomplish the scientific management technique that becomes more meticulous.In each construction stage up to several years, each How construction procedure, accurately calculate quantitiesHow counter fund, manpower, equipment investment carried out according to accurate quantities.Need Accurate schedule is wanted to be constructed, it is necessary to which the construction speed optimized realizes the science connection of front and rear progress.Also need to engineering Mesh management progress graph technology realizes progress construction plan and the management of performance graphic representation.The network connection of front and rear progress. Chinese starfish software Innovation project project management progress generation model realizes that progress msg is managed, and creates progress software digital figure Software engineering, creates progress figure Progress Project network connection model technology, realizes schedule duration, completion date, completion Quantities, the completion full-automatic graphic software techniques of most advanced most comprehensive one, two, three progress of fund input.
Innovation engineering project progress Auto, automatically generates engineering project progress control information record, builds Vertical project progress order and information, automatically generate the link of progress item, it is automatic calculate engineering project progress go into operation, the duration of completing, Quantities, fund.Engineering project object is, innovation all engineering projects orderly progress Protean according to actual conditions Ever-changing information data correspondence automatically generates Protean engineering project progress gunter drawing linked, diagram, realizes three progress charts (duration, quantities, fund) lateral road linked, diagram.Two grades of engineering project progress control, three-level progress chart network linking are realized, is combined Level Four, Pyatyi, six grades of progress chart applications.Realize many progress chart paging generation printings (A4, A3 form, other format widths).It is accurate True figure reflection actual construction time and extension or the lead of plan time, actual progress duration and quantities or fund completion rate pair According to.Meet the multistage progress figure of Larger Engineering Projects, middle or small engineering item number thousand, hundreds of, dozens of engineering project progress Application demand.Whole invention ways of thinking, design method and technology, software programming technique and source wound source program all belong to source wound Invention.It is that current function is most powerful, technology most meets the last word innovative technology that engineering project progress is automatically applied comprehensively.
With artificial picture, the artificial semi-automatic picture of computer software, the difference, starfish engineering project progress such as low-level progress chart Full-automatic graphics software Auto-generation Model technology can realize any different engineering projects all ever-changing progress figures, also Can realize automatically relevant progress network linking.With three progresses, multistage progress, the methods of multi-format and pattern Form, each graphic operation, several seconds of full-automatic generation progress figure is with regard to that can be automatically performed.Due to realizing integration ERP systems System data sharing application, enterprise group cura generalis person can realize empowerment management application, as long as using progress graphic operation, it is several Full-automatic graphics management second be can be achieved with using there is provided engineering project progress supervision, decision-making.Implement to construction plan and construction There is provided and instruct, be conducive to the scientific and efficient completion of engineering project.
Technical principle:Engineering project progress control information model is designed, design schedule graphic hotsopt prototype software carries out work Journey project progress message is managed and progress lateral road linked graphics software design and development, automatically generates engineering project progress lateral road chain Map interlinking shape.Data message is become into technology figure.
Inventive technique content:
3.1 engineering project progress control information models
Engineering project progress generation model technology:
Engineering project decomposition is carried out according to the designing technique of engineering project, engineering project progress generation model is designed.
Engineering project progress control information model technology:
Set up engineering project progress msg management mode:
Any architectural engineering, bridge road engineering, railway and subway engineering etc. can be decomposed into correspondence partitioned project, subitem Engineering, component engineering etc., continue to be decomposed into subordinate's progress item.Progress connection method above and below correspondence progress differentiated control, foundation, Including advance of working cycle connection method.Exploitation design engineering project progress automatic generating software modelling technique, generation engineering project is entered Spend table.
Set up engineering project progress link model:
Corresponding engineering project management program, calculates, writes various types of quantities, fund, manpower, number of devices Amount, work norm planned time.
Corresponding engineering project management program, the progress of automatically generating is vertically connected with, and selects special progress connection.
The commencement of works time is set, it is automatic to calculate all-work project process starting date, completion date, quantities, money Gold.Gone into operation including special progress and completion date.
Engineering project progress graph technology:
Set up engineering project progress graphical model:
Three progress graph models (plan time, actual construction time, quantities or fund)
Three-level progress chart administrative model (the progress figure that next stage is constituted)
Three-level progress chart administrative model (the progress figure of lower two grades of compositions)
Level Four progress chart administrative model (the progress figure combination of next and lower two grades of compositions)
Pyatyi progress chart administrative model (the progress figure combination of two lower two grades of compositions)
Six grades of progress chart administrative models (the progress figure combination of next stage and two lower two grades of compositions)
Corresponding engineering project management program, realizes all grades of progress data statistics, passes through digital figure software engineering Model, automatically generates corresponding Protean progress figure.
Set up engineering project progress figure link model:
Connection association can be realized by setting up the multistage progress chart of satisfaction in the whole connection progresses of engineering project program.
Set up engineering project scheduling network linked graphics model:
Two grades of progress web link graph shape models are the whole subordinate's progress charts and its associated connection progress chart of upper progress Network connection.
Three-level scheduling network linked graphics model is the lower two grades of progress charts of whole and its associated connection progress chart of upper progress Item network connection.
Progress link model realizes all progress figure connections of engineering project program, and particularly special progress is connected, It will realize that scheduling network figure is connected.
3.2 the full-automatic graphic software techniques of engineering project progress
3.2.1 engineering project sets up management software
Engineering project decomposes item and sets up management software
Engineering project progress Auto-generation Model software
Corresponding engineering Project decomposition layout automatically generates the whole progresses of engineering project.Automatically generate and build within the several seconds Thousands of progress records are found, tens thousand of, hundreds thousand of engineering progress datas are write.
3.2.2 engineering project progress control information software
Engineering project progress item plan information and correspondence actual information (plan time, actual construction time, quantities or money Gold) manage with calculating.Engineering project progress layout, whole progresses links and plan go into operation, the duration of completing, quantities and money The calculating etc. automatically of golden completion rate.Realize that progress figure administrative model correspondence statistics at different levels are calculated, meet correspondence progress figure application Demand.
3.2.3 engineering project progress graphics software
3.2.3.1 engineering project progress figure
Progress figure description:Figure (rectangle, circle, lines, round spot, polygon etc.)
Graphics shape change changes with coordinate data, and progress chart color changes according to design method.
Engineering project progress figure:The combination of all progress figures of engineering project, the relevant progress graphic network of institute Lines are linked.
Association progress graphic network is linked:The relevant progress figure of institute realizes that network lines are linked automatically, one-to-one chain Connect, a pair of multi-links.
Three progress charts:Three items (plan time, actual construction time and works of one progress are described using three rectangles Journey amount or fund), on-stream time is left side starting point, and completion date is terminal on the right of figure, shape face color filling, during progress Between fill.Progress figure is left and right, top indicates the content of progress item with text.
Three progresses represent three concerns of same progress, reflect the situation of change of each item, the change of divergence, Facilitate management engineering construction progress situation, decisioning solutions.
3.2.3.2 full-automatic graphic software techniques of engineering project progress
The up to thousands of progresses of whole progresses item after Larger Engineering Projects decomposition, it is aobvious using one-level progress graph technology It is so bad to use, it is impossible to meet the management work demand of different managers.If progress is very little, equally can not subtly it expire Sufficient management work demand.Each engineering project is also to be constructed stage by stage.Only innovate classification progress graph technology, ability The figure application of all progresses of all progress levels is realized, needs are applied in the manager's management that could meet different stage.
Software systems figure application point engineering project, engineering branch, engineering subitem, engineering component level Four application, Dou Nengshi Six grades of progress graph technology applications are realized in now two grades, lower three-level progress graph technology application, combination.All all progress levels are schemed Shape realizes that A4 longitudinally, laterally apply and A3 form applications by form, moreover it is possible to realize paging figure shows and print application.As desired Realize engineering drawing progress form application technology.
Software systems figure application function can realize lower two grades, lower three-level progress graph technology application demand.
3.2.3.2.1 the full-automatic lateral road graphic software techniques of engineering project progress
Engineering project, engineering branch, engineering subitem, engineering component level Four application of function all realize that following software engineerings should With:
Three two grades of progress charts full-automatic progress lateral road graphic network link software (A4 forms, A3 forms, other width lattice Formula)
The full-automatic progress lateral road graphic network link software of three progress chart three-levels (A4 forms, A3 forms, other width lattice Formula)
All progresses of all each progress levels three progress charts of whole progresses automatically generate combination according to progress order Progress chart, progress can be automatically generated progress constitutional diagram and printed by page beyond type face line number.
Single progress figure is automatically scaled when long, beautifies figure shows effect.
All whole progress items of each progress level realize the strand network link of upper and lower, forward and backward association progress.
Plan time, actual construction time, quantities or the respectively different color of fund progress bar are shown.Quantities and fund fail When being synchronously completed by the actual construction time, there is provided manager's decision-making management for progress bar color change color.
Each progress the left and right of figure, the main contents of the additional display progress in top.
Progress figure technology model realizes that the progress data change of all progress levels automatically generates Protean correspondence and entered Spend graphical format and the link of corresponding progress.All grades of progress graphic operations show for full-automatic several seconds with regard to that can complete graphic hotsopt Show.
Engineering project progress graphics software hierarchical statistics and figure shows are all automatically finished, each graphing capability operation Only need to can be achieved with several seconds completing.Manual amendment's figure, picture shape are not needed.The combination of progress figure, which is automatically generated, presses in the number of degrees It is ever-changing according to difference, it is the graphics software core technology that software model is realized this change and changed.
3.2.3.2.2 the full-automatic lateral road network connection graphic software technology of engineering project fund progress
The full-automatic lateral road network connection chart of project management fund progress is another type progress graph technology, is realized Partitioned project and subdivisional work fund progress chart.According to engineering project fund progress generation correspondence progress chart.
3.3. Innovation System application technology:
Multidisciplinary differentiated control application.
Operate user's foundation, grouping management, user authorization management, user department empowerment management application.
Realize standalone version and network system version application.
Adapt to all kinds of large data library management applications:Sybase, Oracle, SQLserver etc..
A local system application in integrated ERP system software, data sharing can be used as.
Chinese starfish duration of a project, quantities and the full-automatic graph technology of fund progress join integrated system by Shenzhen starfish The independent research of Co., Ltd poplar the bladder senior engineer whole, innovation.Whole systems approaches, design method, systemic-function Technology, Software for Design programming technique etc. constitute self-innovative system.It is systemic multi-functional technology, original software source program.Not yet There is the software engineering of any other people.The Chinese full-automatic graphic software techniques of starfish progress can be most leading constructed with the world Match in excellence or beauty also advanced, be in the integrated ERP system software of Chinese starfish and engineering of integrating project management system software in office Portion's system application, innovates oneself unique full-automatic graph technology methods and techniques model of progress, advanced handy.
The Chinese full-automatic graphic software techniques of starfish engineering project progress since 2008, enter first by Innovation project project one Full-automatic graphic software techniques application is spent, two progress graphic software techniques applications is developed into, realizes project management three today The full-automatic graphic software techniques application of progress:
Plan time, actual construction time, quantities, the comprehensive progress graphic software techniques application of fund, work can be more realized comprehensively Journey project management progress is monitored in real time comprehensively, is raised the management level!Certainly a progress chart, two progress chart patent of invention skills are included Art, project management construction plan duration progress chart is exactly a progress diagram technology application.Core technology is essentially identical, three progresses Figure core technology is more comprehensive, and content is more, and Engineering Project Management Effect is more preferable!According to circumstances determine to declare a progress chart, two Progress chart patent of invention technology.
4th, illustrate
Figure of description subsystem software Operation interface diagram and progress figure.
System software operation interface totally 5:
Fig. 1:System user Operation interface diagram
Fig. 2:System menu feature operation surface chart
Fig. 3:The progress chart A4 forms of engineering project three longitudinal direction Operation interface diagram
Fig. 4:The progress chart A3 form lateral operation surface charts of engineering project three
Fig. 5:Engineering project fund progress cross channel intersection chart table handling surface chart
First, two, three progress lateral road shapes and fund network totally 17:
Fig. 6:The progress gunter drawing of engineering project one (A4 forms longitudinal direction)
Fig. 7:The progress gunter drawing of engineering project partitioned project one (A4 forms longitudinal direction)
Fig. 8:The progress gunter drawing of engineering project one (A4 forms longitudinal direction)
Fig. 9:The progress gunter drawing of engineering project two (A4 forms are horizontal)
Figure 10:The progress gunter drawing of engineering project partitioned project two (A4 forms are horizontal)
Figure 11:The progress gunter drawing of engineering project two (A3 forms are laterally left)
Figure 12:The progress gunter drawing of engineering project two (A3 forms are laterally right)
Figure 13:The progress gunter drawing of engineering project three (A4 forms are horizontal)
Figure 14:The progress gunter drawing of engineering project partitioned project three (A4 forms are horizontal)
Figure 15:The progress gunter drawing of engineering project three (A3 forms are laterally left)
Figure 16:The progress gunter drawing of engineering project three (A3 forms are laterally right)
Figure 17:Engineering project fund scheduling network lateral road chart (A3 forms are laterally left)
Figure 18:Engineering project fund scheduling network lateral road chart (A3 forms are laterally right)
Figure 19:Project management network (A3 forms are left)
Figure 20:Project management network (A3 forms are right)
Figure 21:Project management partitioned project network (A3 forms are left)
Figure 22:Project management partitioned project network (A3 forms are right)
Figure model is engineering project and the representative example of partitioned project level, and China sea star graphics software can be with Automatically generate the different engineering project progress figures of any types.
Progress DBMS belonging to subdivisional work is corresponding with component engineering grade progress model graph technology automatically generates thousand changes ten thousand Change corresponding progress figure.
5th, embodiment
This project technological invention is innovated, and Chinese engineering project progress control graph technology application is reached international most leading skill Art level, it was demonstrated that Chinese also can original core technology leading in the world.
The 5.1 Chinese full-automatic graphic software techniques of starfish engineering project progress are Chinese starfish engineering of integrating project managements In local software system, therefore implement system in the Chinese starfish engineering of integrating project management system software application of offer Change overall application and implement systemic application in the Chinese starfish enterprise integration ERP system software application of offer.
The 5.2 Chinese full-automatic graphic software techniques of starfish engineering project progress, which constitute autonomous system software and provided, to be implemented to answer With.
Standalone version and network edition system application.
The 5.3 Chinese full-automatic graphic software techniques of starfish engineering project progress are systematization software engineerings, can decompose and carry For following embodiments:
Progress item:Plan time, actual construction time, quantities etc. combine three progress items
Plan time, actual construction time, actual funds etc. combine three progress items
The systems software technology applications such as engineering project, engineering branch, engineering subitem, engineering component:
Three two grades of progress charts full-automatic progress lateral road graphic network link software (A4 forms, A3 forms, other width lattice Formula)
The full-automatic progress lateral road graphic network link software of three progress chart three-levels (A4 forms, A3 forms, other width lattice Formula).

Claims (4)

1. the full-automatic lateral road figure technical method of project management progress
Most of construction enterprises of present China also rest on original artificial management phase.Larger construction conglomerate also only It is to carry out enterprise's local messageization management, technical merit is low.Construction project business management software is not comprehensive, and content is few, technology Level is low.It is comprehensively good that external most notable gas large software company SAP, Oracle do not meet engineering corporation group management yet With integrated ERP system software engineering, wherein just without the advanced full-automatic graphic software techniques of engineering project progress.Engineering is looked forward to Industry group information system management overall application is the integrated ERP system software of enterprise, wherein, it is most important that engineering project integration Management system software technology, the full-automatic graphic software techniques of engineering of integrating project process.Chinese starfish software is researched and developed in innovation Engineering of integrating project management system software is researched and developed in engineering corporation integration ERP system software, wherein systemic technical requirements The very high full-automatic graphics software of engineering project progress.Accomplish there is presently no other people this technology country.
Project management is very complicated work.Towards many different the object of building, various construction project mansions, various bridges Beam road, railway subway etc..Each engineering project have temporary project, earth work, foundation engineering, major project, fitting-out work, Decorative engineering.There is presently no accomplish the scientific management technique that becomes more meticulous.In each construction stage up to several years, each construction step Suddenly, how quantities is accurately calculatedHow counter fund, manpower, equipment investment carried out according to accurate quantities.Need precisely Schedule is constructed, it is necessary to which the construction speed optimized realizes the science connection of front and rear progress.Also need to project management Progress graph technology realizes progress construction plan and the management of performance graphic representation.The network connection of front and rear progress.China sea Star software Innovation project project management progress generation model realizes that progress msg is managed, and creates progress software digital graphics software skill Art, create progress figure Progress Project network connection model technology, realize the schedule duration, completion date, completed amount, Complete the full-automatic graphic software techniques of most advanced most comprehensive one, two, three progress of fund input.
Innovation engineering project progress Auto, engineering project progress control information record is automatically generated, work is set up Cheng Jindu orders and information, automatically generate the link of progress item, it is automatic calculate engineering project progress go into operation, the duration of completing, engineering Amount, fund.Engineering project object is Protean according to actual conditions, and the orderly progress thousand of all engineering projects of innovation becomes Ten thousand change information data correspondences automatically generate Protean engineering project progress gunter drawing linked, diagram, realize three progress chart (works Phase, quantities, fund) lateral road linked, diagram.Realize two grades of engineering project progress control, three-level progress chart network linking, combination four Level, Pyatyi, six grades of progress chart applications.Realize many progress chart paging generation printings (A4, A3 form, other format widths).Accurately Figure reflects extension or the lead of actual construction time and plan time, actual progress duration and quantities or fund completion rate pair According to.Meet the multistage progress figure of Larger Engineering Projects, middle or small engineering item number thousand, hundreds of, dozens of engineering project progress Application demand.Whole invention ways of thinking, design method and technology, software programming technique and source wound source program all belong to source wound Invention.It is that current function is most powerful, technology most meets the last word innovative technology that engineering project progress is automatically applied comprehensively.
With artificial picture, the artificial semi-automatic picture of computer software, the difference such as low-level progress chart, starfish engineering project progress it is complete from Dynamic graphics software Auto-generation Model technology can realize any different engineering projects all ever-changing progress figures, moreover it is possible to from The dynamic network linking for realizing the relevant progress item of institute.With three progresses, multistage progress, the methods of multi-format and pattern lattice Formula, each graphic operation, several seconds of full-automatic generation progress figure is with regard to that can be automatically performed.Due to realizing integrated ERP system Data sharing application, enterprise group cura generalis person can realize empowerment management application, as long as using progress graphic operation, several seconds Clock can be achieved with full-automatic graphics management using there is provided engineering project progress supervision, decision-making.Carried to construction plan and construction implementation For instructing, be conducive to the scientific and efficient completion of engineering project.
Technical principle:Engineering project progress control information model is designed, design schedule graphic hotsopt prototype software carries out engineering Mesh progress msg is managed and progress lateral road linked graphics software design and development, automatically generates engineering project progress lateral road linked, diagram Shape.Data message is become into technology figure.
2. engineering project progress control information model
Engineering project progress generation model technology:
Engineering project decomposition is carried out according to the designing technique of engineering project, engineering project progress generation model is designed.
Engineering project progress control information model technology:
Set up engineering project progress msg management mode:
Any architectural engineering, bridge road engineering, railway and subway engineering etc. can be decomposed into correspondence partitioned project, subitem work Journey, component engineering etc., continue to be decomposed into subordinate's progress item.Progress connection method above and below correspondence progress differentiated control, foundation, bag Include advance of working cycle connection method.Exploitation design engineering project progress automatic generating software modelling technique, generates engineering project progress Table.
Set up engineering project progress link model:
Corresponding engineering project management program, calculates, writes various types of quantities, fund, manpower, number of devices, labor Dynamic quota planned time.
Corresponding engineering project management program, the progress of automatically generating is vertically connected with, and selects special progress connection.
The commencement of works time is set, it is automatic to calculate all-work project process starting date, completion date, quantities, fund.Bag Special progress is included to go into operation and completion date.
Engineering project progress graph technology:
Set up engineering project progress graphical model:
Three progress graph models (plan time, actual construction time, quantities or fund)
Three-level progress chart administrative model (the progress figure that next stage is constituted)
Three-level progress chart administrative model (the progress figure of lower two grades of compositions)
Level Four progress chart administrative model (the progress figure combination of next and lower two grades of compositions)
Pyatyi progress chart administrative model (the progress figure combination of two lower two grades of compositions)
Six grades of progress chart administrative models (the progress figure combination of next stage and two lower two grades of compositions)
Corresponding engineering project management program, realizes all grades of progress data statistics, by digital figure software engineering model, Automatically generate corresponding Protean progress figure.
Set up engineering project progress figure link model:
Connection association can be realized by setting up the multistage progress chart of satisfaction in the whole connection progresses of engineering project program.
Set up engineering project scheduling network linked graphics model:
Two grades of progress web link graph shape models are the whole subordinate's progress charts and its associated connection progress chart network of upper progress Connection.
Three-level scheduling network linked graphics model is the lower two grades of progress charts of whole and its associated connection progress chart net of upper progress Network is connected.
Progress link model realizes all progress figure connections of engineering project program, and particularly special progress connection will Realize that scheduling network figure is connected.
3. the full-automatic graphic software techniques of engineering project progress
3.1 engineering projects set up management software
Engineering project decomposes item and sets up management software
Engineering project progress Auto-generation Model software
Corresponding engineering Project decomposition layout automatically generates the whole progresses of engineering project.Automatically generated within the several seconds and set up number Thousand progress records, write tens thousand of, hundreds thousand of engineering progress datas.
3.2 engineering project progress control information softwares
Engineering project progress item plan information and correspondence actual information (plan time, actual construction time, quantities or fund) pipe Reason is with calculating.
Engineering project progress layout, whole progresses links and plan go into operation, the duration of complete, quantities and fund completion rate oneself Dynamic calculating etc..
Realize that progress figure administrative model correspondence statistics at different levels are calculated, meet correspondence progress figure application demand.
3.3 engineering project progress graphics softwares
3.3.1 engineering project progress figure
Progress figure description:Figure (rectangle, circle, lines, round spot, polygon etc.)
Graphics shape change changes with coordinate data, and progress chart color changes according to design method.
Engineering project progress figure:The combination of all progress figures of engineering project, the relevant progress graphic network lines of institute Link.
Association progress graphic network is linked:The relevant progress figure of institute realizes that network lines are linked automatically, one-to-one link, one To multi-link.
Three progress charts:Three items (plan time, actual construction time and quantities of one progress are described using three rectangles Or fund), on-stream time is left side starting point, and completion date is terminal on the right of figure, and shape face color filling, progression time is filled out Fill.Progress figure is left and right, top indicates the content of progress item with text.
Three progresses represent three concerns of same progress, reflect the situation of change of each item, and the change of divergence is convenient Management engineering construction progress situation, decisioning solutions.
3.3.2. full-automatic graphic software techniques of engineering project progress
The up to thousands of progresses of whole progresses item after Larger Engineering Projects decomposition, it is obvious not using one-level progress graph technology Use well, it is impossible to meet the management work demand of different managers.If progress is very little, pipe equally can not be subtly met Manage work requirements.Each engineering project is also to be constructed stage by stage.Classification progress graph technology is only innovated, could be realized Needs are applied in the figure application of all progresses of all progress levels, the manager's management that could meet different stage.
Software systems figure application point engineering project, engineering branch, engineering subitem, engineering component level Four application, can be realized down Six grades of progress graph technology applications are realized in two grades, lower three-level progress graph technology application, combination.All all progress level figures are real Existing A4 longitudinally, laterally apply and A3 form applications by form, moreover it is possible to realizes paging figure shows and print application.Realize as desired Engineering drawing progress form application technology.
Software systems figure application function can realize lower two grades, lower three-level progress graph technology application demand.
3.3.2.1 the full-automatic lateral road graphic software techniques of engineering project progress
Engineering project, engineering branch, engineering subitem, engineering component level Four application of function all realize following software engineering applications:
The full-automatic progress lateral road graphic network link software of three two grades of progress charts (A4 forms, A3 forms, other format widths)
The full-automatic progress lateral road graphic network link software of three progress chart three-levels (A4 forms, A3 forms, other format widths)
All progresses of all each progress levels three progress charts of whole progresses automatically generate combination progress according to progress order Figure, progress can be automatically generated progress constitutional diagram and printed by page beyond type face line number.
Single progress figure is automatically scaled when long, beautifies figure shows effect.
All whole progress items of each progress level realize the strand network link of upper and lower, forward and backward association progress.
Plan time, actual construction time, quantities or the respectively different color of fund progress bar are shown.Quantities and fund fail by reality When the border duration synchronously completes, there is provided manager's decision-making management for progress bar color change color.
Each progress the left and right of figure, the main contents of the additional display progress in top.
Progress figure technology model realizes that the progress data change of all progress levels automatically generates Protean correspondence progress chart Shape form and the link of corresponding progress.All grades of progress graphic operations are automatically shown for several seconds with regard to that can complete graphic hotsopt.
Engineering project progress graphics software hierarchical statistics and figure shows are all automatically finished, and each graphing capability operation is only needed It can be achieved with several seconds completing.Manual amendment's figure, picture shape are not needed.The combination of progress figure is automatically generated by progress data not It is the graphics software core technology that software model is realized this change and changed with ever-changing.
3.3.2.2 the full-automatic lateral road network connection graphic software technology of engineering project fund progress
The full-automatic lateral road network connection chart of project management fund progress is another type progress graph technology, realizes branch Engineering and subdivisional work fund progress chart.According to engineering project fund progress generation correspondence progress chart.
4. Innovation System application technology:
Multidisciplinary differentiated control application.
Operate user's foundation, grouping management, user authorization management, user department empowerment management application.
Realize standalone version and network system version application
Adapt to all kinds of large data library management applications:Sybase, Oracle, SQLserver etc.
A local system application in integrated ERP system software, data sharing can be used as.
It is limited that Chinese starfish duration of a project, quantities and the full-automatic graph technology of fund progress join integrated system by Shenzhen starfish The independent research of company Yang Yuhai senior engineers whole, innovation.Whole systems approaches, design method, systemic-function technology, Software for Design programming technique etc. constitutes self-innovative system.It is systemic multi-functional technology, original software source program.It is not any Other people software engineering.The Chinese full-automatic graphic software techniques of starfish progress can be gone back with international most leading constructed match in excellence or beauty It is advanced, be in the integrated ERP system software of Chinese starfish and engineering of integrating project management system software in local system Using, oneself unique full-automatic graph technology methods and techniques model of progress is innovated, it is advanced handy.
The progress of Innovation project project one was complete first since 2008 for the Chinese full-automatic graphic software techniques of starfish engineering project progress Automatic pattern software engineering application, develops into two progress graphic software techniques applications, realizes the progress of project management three today Full-automatic graphic software techniques application:
Plan time, actual construction time, quantities, the comprehensive progress graphic software techniques application of fund, engineering can be more realized comprehensively Mesh management progress is monitored in real time comprehensively, is raised the management level!Certainly a progress chart, two progress chart patent of invention technologies, work are included Journey project management construction plan duration progress chart is exactly a progress diagram technology application.Core technology is essentially identical, the three progress kernel of graphs Heart technology is more comprehensive, and content is more, and Engineering Project Management Effect is more preferable!According to circumstances determine to declare a progress chart, two progresses Figure patent of invention technology.
CN201610439799.3A 2016-06-20 2016-06-20 The full-automatic lateral road figure technical method of project management progress Pending CN107067220A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610439799.3A CN107067220A (en) 2016-06-20 2016-06-20 The full-automatic lateral road figure technical method of project management progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610439799.3A CN107067220A (en) 2016-06-20 2016-06-20 The full-automatic lateral road figure technical method of project management progress

Publications (1)

Publication Number Publication Date
CN107067220A true CN107067220A (en) 2017-08-18

Family

ID=59617142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610439799.3A Pending CN107067220A (en) 2016-06-20 2016-06-20 The full-automatic lateral road figure technical method of project management progress

Country Status (1)

Country Link
CN (1) CN107067220A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108062612A (en) * 2017-09-20 2018-05-22 杨玉海 Capital items manage the full-automatic graphical diagrams technical method of progress
CN108280621A (en) * 2017-09-20 2018-07-13 杨玉海 Capital items manage the full-automatic lateral road figure technical method of progress
CN108470049A (en) * 2018-03-09 2018-08-31 国网上海市电力公司 A kind of construction project management system based on instrument board
CN108537511A (en) * 2018-04-10 2018-09-14 万翼科技有限公司 The method, apparatus and computer readable storage medium of project process displaying
CN109636616A (en) * 2018-11-21 2019-04-16 周剑毅 A method of realizing project cluster progress and investment master control management
CN109754145A (en) * 2018-03-30 2019-05-14 比亚迪股份有限公司 Project management method, device, system and the storage medium of task based access control
CN110309940A (en) * 2019-04-14 2019-10-08 济南森坤企业管理咨询有限公司 A kind of all kinds of project organization plan main resource plan management methods of critical path method
CN110309999A (en) * 2019-04-14 2019-10-08 济南森坤企业管理咨询有限公司 A kind of each intermediate item any combination main resource plan management method of critical path method
CN110580267A (en) * 2019-09-23 2019-12-17 重庆渝高科技产业(集团)股份有限公司 engineering information display control method for urban engineering management
CN113961281A (en) * 2021-08-13 2022-01-21 叮联信息技术有限公司 Internet-based task progress display method and device

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11305826A (en) * 1998-04-24 1999-11-05 Yokogawa Electric Corp Scheduling system
US20080103870A1 (en) * 2006-10-27 2008-05-01 Purdue Pharma L.P. Cycle planning tool for territory management
CN101246423A (en) * 2008-03-12 2008-08-20 浪潮集团山东通用软件有限公司 Method for pattern exhibition of task progress in management software
CN102236680A (en) * 2010-04-27 2011-11-09 杭州德昌隆信息技术有限公司 Gantt chart generation method and Gantt chart generation device based on browser
CN102541880A (en) * 2010-12-17 2012-07-04 金蝶软件(中国)有限公司 Gantt chart generating method and system
KR20120075556A (en) * 2010-11-23 2012-07-09 현대중공업 주식회사 Vessel mastering schedule management system
CN102981842A (en) * 2012-11-08 2013-03-20 北京空间飞行器总体设计部 Method of generating interactive Gantt chart
CN103295100A (en) * 2013-05-28 2013-09-11 机械工业第六设计研究院有限公司 Project management progress arranging method and project management progress arranging system
CN104751274A (en) * 2015-03-11 2015-07-01 中铁上海工程局集团有限公司 Method for scheduling rail construction progress of urban rail transit project
CN105117866A (en) * 2015-09-30 2015-12-02 北京恒华伟业科技股份有限公司 Progress state data processing method and apparatus
CN105512099A (en) * 2015-12-09 2016-04-20 金蝶软件(中国)有限公司 Gantt chart generation method and device

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11305826A (en) * 1998-04-24 1999-11-05 Yokogawa Electric Corp Scheduling system
US20080103870A1 (en) * 2006-10-27 2008-05-01 Purdue Pharma L.P. Cycle planning tool for territory management
CN101246423A (en) * 2008-03-12 2008-08-20 浪潮集团山东通用软件有限公司 Method for pattern exhibition of task progress in management software
CN102236680A (en) * 2010-04-27 2011-11-09 杭州德昌隆信息技术有限公司 Gantt chart generation method and Gantt chart generation device based on browser
KR20120075556A (en) * 2010-11-23 2012-07-09 현대중공업 주식회사 Vessel mastering schedule management system
CN102541880A (en) * 2010-12-17 2012-07-04 金蝶软件(中国)有限公司 Gantt chart generating method and system
CN102981842A (en) * 2012-11-08 2013-03-20 北京空间飞行器总体设计部 Method of generating interactive Gantt chart
CN103295100A (en) * 2013-05-28 2013-09-11 机械工业第六设计研究院有限公司 Project management progress arranging method and project management progress arranging system
CN104751274A (en) * 2015-03-11 2015-07-01 中铁上海工程局集团有限公司 Method for scheduling rail construction progress of urban rail transit project
CN105117866A (en) * 2015-09-30 2015-12-02 北京恒华伟业科技股份有限公司 Progress state data processing method and apparatus
CN105512099A (en) * 2015-12-09 2016-04-20 金蝶软件(中国)有限公司 Gantt chart generation method and device

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
全国建筑企业项目经理培训教材编写委员会: "《施工项目信息管理》", 31 January 2002 *
刘伊生: "《建设项目信息管理》", 31 May 1999 *
刘欣: "《项目管理基础》", 30 April 2015 *
刘津明: "工程项目进度与成本辅助控制横道图", 《烟台大学学报 (自然科学与工程版 )》 *
陈文斐: "P3软件在电力工程项目中的运用", 《上海电力》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108062612A (en) * 2017-09-20 2018-05-22 杨玉海 Capital items manage the full-automatic graphical diagrams technical method of progress
CN108280621A (en) * 2017-09-20 2018-07-13 杨玉海 Capital items manage the full-automatic lateral road figure technical method of progress
CN108470049A (en) * 2018-03-09 2018-08-31 国网上海市电力公司 A kind of construction project management system based on instrument board
CN109754145A (en) * 2018-03-30 2019-05-14 比亚迪股份有限公司 Project management method, device, system and the storage medium of task based access control
CN109754145B (en) * 2018-03-30 2020-08-07 比亚迪股份有限公司 Task-based project management method, device, system and storage medium
CN108537511A (en) * 2018-04-10 2018-09-14 万翼科技有限公司 The method, apparatus and computer readable storage medium of project process displaying
CN109636616A (en) * 2018-11-21 2019-04-16 周剑毅 A method of realizing project cluster progress and investment master control management
CN109636616B (en) * 2018-11-21 2021-09-14 周剑毅 Method for realizing project group progress master control management
CN110309940A (en) * 2019-04-14 2019-10-08 济南森坤企业管理咨询有限公司 A kind of all kinds of project organization plan main resource plan management methods of critical path method
CN110309999A (en) * 2019-04-14 2019-10-08 济南森坤企业管理咨询有限公司 A kind of each intermediate item any combination main resource plan management method of critical path method
CN110580267A (en) * 2019-09-23 2019-12-17 重庆渝高科技产业(集团)股份有限公司 engineering information display control method for urban engineering management
CN113961281A (en) * 2021-08-13 2022-01-21 叮联信息技术有限公司 Internet-based task progress display method and device

Similar Documents

Publication Publication Date Title
CN107067220A (en) The full-automatic lateral road figure technical method of project management progress
CN108280621A (en) Capital items manage the full-automatic lateral road figure technical method of progress
CN114741769A (en) Bridge engineering construction task planning method based on functional graphic object
CN106169114A (en) BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track
CN108062612A (en) Capital items manage the full-automatic graphical diagrams technical method of progress
CN106408171A (en) Heuristic activity-on-arrow diagram automatic drawing method
CN107368657A (en) A kind of resources of production quickly configuration method based on process simulation
CN106952024A (en) It is a kind of to strengthen the workflow engine method and system of net O&M scenarios suitable for ground
Rischmoller et al. 4D planning and scheduling (4D-PS): Grounding construction IT research in industry practice
JP2021021983A (en) Building construction management device
Danilovic Bring your suppliers into your projects—Managing the design of work packages in product development
Lucarelli et al. BEP & mapping process for the restoration building site
KR102439119B1 (en) 4D CAD system and its implemention method based on liner schedule chart with schedule and location information of each construction activity
Christmann et al. 8 Digital urban planning and urban planners’ mediatized construction of spaces
Fischer et al. Cost-loaded production model for planning and control
CN108876287A (en) data management system based on BIM
KR20110109710A (en) Three dimensional system and method for monitoring process
CN110222457B (en) Construction method of existing structure and newly-built primary support structure with existing structure closely attached
CN107515979A (en) A kind of processing method and processing system to high-volume part model data
KR100580125B1 (en) Process And Graphic Simulation Method for Planning and Construction Processes
Tirunagari et al. Simulation of construction sequence using BIM 4D techniques
CN112184134B (en) Network plan rationality evaluation dimension design method, evaluation method, system and device
Williams et al. The use of project post-mortems
CN110298629A (en) A kind of BIM implementation integration method
Broekmaat et al. Implementation scenarios for 4D CAD in practice

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination