CN110309940A - A kind of all kinds of project organization plan main resource plan management methods of critical path method - Google Patents

A kind of all kinds of project organization plan main resource plan management methods of critical path method Download PDF

Info

Publication number
CN110309940A
CN110309940A CN201910296761.9A CN201910296761A CN110309940A CN 110309940 A CN110309940 A CN 110309940A CN 201910296761 A CN201910296761 A CN 201910296761A CN 110309940 A CN110309940 A CN 110309940A
Authority
CN
China
Prior art keywords
resource
plan
target control
work
management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910296761.9A
Other languages
Chinese (zh)
Inventor
吴茜龄
吴开平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Senkun Enterprise Management Consulting Co Ltd
Original Assignee
Jinan Senkun Enterprise Management Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Senkun Enterprise Management Consulting Co Ltd filed Critical Jinan Senkun Enterprise Management Consulting Co Ltd
Priority to CN201910296761.9A priority Critical patent/CN110309940A/en
Publication of CN110309940A publication Critical patent/CN110309940A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Quality & Reliability (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides one kind: all kinds of project organic managements and target control plan, the method of various main resource planning management, this method comprises the following steps: (1) drawing Gantt chart or vivid progress gunter drawing according to project organic management and the target control time that work in every may start earliest in the works;(2) it identifies project respectively the unit time requirements of organization and administration and target control various main resources of work in every in the works;(3) Gantt chart or vivid progress chart according to project organic management and target control plan, the statistics of resource requirement dynamic table is carried out to various main resources needed for work in every respectively, as various main resource planning management according to (if a certain work does not need certain resource, zero) enabling the requirement of its this resource is.

Description

A kind of all kinds of project organization plan main resource plan management methods of critical path method
Technical field
The invention belongs to critical path method technical fields, are the main compositions of critical path method project organic management Yu target control technology Specifically a kind of realization: one of part according to project organic management and target control plan, carries out various main resources The method of planning management.
Background technique
Eighties of last century early fifties, in order to be applicable in the development of production and the scientific research and technological development of relationship complexity The managerial needs of job engineering, each advanced industrial country has all successively carried out the research of planning management new technology in the world, wherein Successfully CPM (critical path method) and PERT (programme evaluation and review technique) is studied in the U.S. first, is established due to such methods and is closed in work It is the formulation of plan, coordination, optimization and control organically to be combined, on the basis of network model so being referred to as in foreign countries For network planning technique.
The U.S. is applied to the development of establishment Polaris missile in the PERT (programme evaluation and review technique) of invention in 1956 at that time Plan, has coordinated 3,000 many enterprises, and making plan, two years ahead completes on schedule;It is applied to cost 400 again later More hundred million dollars, mobilize manpower more than 40 ten thousand Apollo space program management and control, obtain good result.
It is counted according to kremlin, the construction and erection enterprises of application network planning technique, the duration can shorten 20%, engineering Cost can reduce by 10% or so.
In March, 1978, civil engineering association, U.S. proceedings comment on that this method is current only planning management newly side Method, and in foreseeable future, it is not in the new method of one kind to substitute it, therefore, we should enjoy it, make With it, improve it.
Currently, each advanced industrial country, such as the United States, Russia, English, day, method, moral in the world, is all promoting and applying network planning skill Art.
The famous mathematician Hua Luogeng professor in China, from the national conditions in China, absorbing, external network planning technique is theoretical On the basis of, " critical path method " scientific system is established, and since eighties of last century early sixties, promote in production practice Using achieving huge economic benefit.
Since network planning technique is there are following many defects and deficiency, influences and restrict pushing away for network planning technique Row is promoted, popularization and application:
(1) restriction and planar network of project or taskings management and target control plannet model rule are established The restriction of model tormulation mode manages most projects or taskings and is unable to complete with target control person, especially compared with Big or more complex project;
(2) it is unfavorable for the restriction of computer technology application, the application of such technology depends on the support of computer technology, net Foundation, modification, the calculating of time parameter, the optimal control of constructing aims and optimal control of resource object of network model etc., only It is difficult to complete by manpower;
(3) restriction of application range, CPM are only applicable to type project or task certainly and are directly decomposed into a series of specific works Organization and administration and target control;PERT is only applicable to the evaluation of non-type project or task milestone target certainly;And with section Comprehensive fast development of technology, not only most projects or task have the feature of mixed type, and method for organizing also has There is the feature of mixed type;
(4) lack necessary function technology, major function technology only has: time-cost trade-off technology;Duration is constant, money Source demand balance optimizing technology;Resource is limited, duration most short optimisation technique;With non-type project or task milestone target certainly Evaluation technology;
(5) all there is apparent defect and deficiency in major function technology, such as:
1) it time-cost trade-off technology: needs to carry out time parameter meter by the route that key job forms to each respectively After calculation, critical circuits can be just judged, need to calculate the rate of each single item key job, just can be carried out the excellent of duration-cost Change, this be in practical work it is highly difficult, it is even impossible;
2) duration is constant, resources balance optimisation technique: its optimization method does not consider non-key work in part (or motor-driven) Resource requirement current intelligence in time difference range, hence it is evident that unreasonable;
3) resource is limited, duration shortest optimisation technique: the work started before the period will be optimized and come most important first place, Do not consider influence size of the optimization of the non-key work started before the optimization period to the duration;
4) Evaluation technology of non-type project or task milestone target certainly, when not considering non-key milestone target interval Between Lagi-jInfluence etc. to estimate variance.
Network planning technique belongs to critical path method, is one of application technology of critical path method, it may be said that network planning technique is system Method is raised, not vice versa.
Each intermediate item or taskings management with target control plan, resource comprehensive optimization method, be critical path method project or One of the target control of taskings management and target control technology, embodiment is that Hua Luogeng professor is pointed: application is planned as a whole Method, wants the time to key job, wants benefit to non-key work.
Traditional network planning technique does not have project organic management and target control plan, resource comprehensive optimization method.
Project or taskings' management and target control plan, without the duration is constant, resources balance optimization or duration not Become, the optimization that resource requirement is minimum or relatively minimal, can not judge project or taskings' management and target control plan, In the condition that the duration is constant, if can satisfy the limited requirement of resource;Project or taskings' management and target control meter It draws, after resource optimization of limiting the quantity, the requirement of limitation resource can only be met, but be not able to satisfy the requirement of resource requirement equilibrium.
Summary of the invention
The present invention is according to project or taskings' management and target control plan and its Gantt chart or vivid progress gunter drawing And resource requirement dynamic table, it as the case may be and requires, using different resource comprehensive optimization method, realizes project or task Organization and administration and target control plan, the resource requirement for meeting resource limitation are balanced.
For the present invention by project or task by organization and administration and target control requirement, the work decomposed is divided into type work certainly Type work two types are affirmed with non-:
(1) type work certainly: time t required for work is completediIt is affirmative;
(2) non-type work certainly: the time needed for completing work is non-affirmative, need to be completed using three point estimations The estimation of working time:
at、mt、bt, Dt=(at+4mt+bt) ÷ 6, σt 2=[(bt-at)÷6]2
atThe optimistic completion working time;
mtThe possible completion working time;
btThe pessimistic completion working time;
DtThe weighted average of working time is completed in estimation;
σt 2Complete the estimated bias of working time.
The present invention presses the type of project institute disintegration, and project is divided into type, non-type and three type of mixed type certainly certainly Type:
(1) affirmative type project: by organization and administration and target control requirement, the work decomposed all is the work of type certainly;
(2) non-type project certainly: by organization and administration and target control requirement, the work decomposed all is the work of non-type certainly Make;
(3) mixed type project: by organization and administration and target control requirement, the work of the existing type certainly of the work decomposed, There is the work of non-type certainly again.
Organizational form and organizer of the project of the present invention by organization and administration and target control requirement, between institute's disintegration Method has following seven kinds:
Project is by organization and administration and target control requirement, the organizational form and method for organizing between work decomposed, with i Work is with for j work, and i work is the preceding activity that j works or j work is next work of i work, i work and j work Between organizational form and method for organizing:
(1) FYS (LT): i work terminates LT days, and j work starts;
(2)STS(LTi): i work starts LTiIt, j work starts;
(3)FTF(LTj): i work terminates LTjIt, j work terminates;
(4)STF(LTi, LTj): i work starts LTiIt, use LT againjIt, j work terminates, i.e. j work will work in i and open Beginning LTiAfter it, LT is usedjIt terminates;
(5) STS and FTF (LTi, LTj): i work starts LTiIt, j work start, i work terminate LTjIt, j work knot Beam;
(6) STS and STF (LTi’LTi’, LTj): i work start LTi days, j work start, i work beginning LTi‘It, use again LTjIt, j work terminates, i.e. j work will work in i starts LTi’After it, LT is usedjIt terminates;
(7) FTS and STF (LT, LTi, LTj): i work terminate LT days, j work start, i work beginning LTiIt, use LT againj It, j work terminates, i.e. j work will work in i starts LTiAfter it, LT is usedjIt terminates.
Organization and administration between work are divided into type certainly and non-type two types certainly with target control mode by the present invention:
(1) type organizes and target control mode certainly: away from the organization and administration for being all affirmative when bonding relation and overlap joint With target control mode;
(2) the non-organization and administration of type certainly are with target control mode: bonding relation is affirmative;But away from being non-affirmative when overlapping , need to using three point estimations be overlapped when away from estimation:
1)LTa、LTm、LTb, DLT=(LTa+4LTm+LTb) ÷ 6, σLT 2=[(LTb-LTa)÷6]2
2)LTia、LTim、LTib, DiLT=(LTia+4LTim+LTib) ÷ 6, σiLT 2=[(LTib-LTia)÷6]2
3)LTja、LTjm、LTjb, DjLT=(LTja+4LTjm+LTjb) ÷ 6, σjLT 2=[(LTjb-LTja)÷6]2
4)LTI ' a、LTI ' m、LTI ' b, DI ' LT=(LTI ' a+4LTI ' m+LTI ' b) ÷ 6, σI ' LT 2=[(LTI ' b-LTI ' a)÷6]2
The present invention presses the difference of project organic management and target control mode, by project organic management and target control mode It is divided into type, non-type and mixed type three types certainly certainly with method:
(1) affirmative type project organic management and target control mode: organization and administration and mesh between project institute disintegration Control mode is marked, is all the organization and administration and target control mode of type certainly;
(2) non-type project organic management and target control mode certainly: organization and administration between project institute disintegration and Target control mode is all the organization and administration and target control mode of non-type certainly;
(3) mixed type project organic management and target control mode: organization and administration and mesh between project institute disintegration Control mode is marked, existing type certainly, also there are the organization and administration and target control mode of non-type certainly.
Project organic management of the present invention is divided into three classes with target control plan:
(1) type project organic management and target control plan certainly: type project certainly, using type organization and administration and mesh certainly Mark project organic management and the target control plan of control mode;
(2) non-type project organic management and target control plan certainly, include the following three types:
1) affirmative type project, project organic management and target control using the non-organization and administration of type certainly with target control mode System plan;
2) non-type project certainly, project organic management and target control using type organization and administration certainly with target control mode System plan;
3) non-type project certainly, using the project organic management and target of non-type certainly organization and administration and target control mode Control plan;
(3) mix mode project organic management and target control plan, including following five kinds:
1) mix mode project, project organic management and target control using type organization and administration certainly with target control mode Plan;
2) mixed type project, project organic management and target control using the non-organization and administration of type certainly with target control mode System plan;
3) mixed type project, project organic management and target control using mixed type organization and administration with target control mode Plan;
4) non-type project certainly, project organic management and target control using mixed type organization and administration with target control mode System plan;
5) affirmative type project, project organic management and target control using mixed type organization and administration with target control mode Plan.
Project organic management and target control plan, such as following table of the present invention by organization and administration with target control requirement formulation It is shown:
Wherein:
A. type work is affirmed:
at=mt=bt=Dt=t;σt 2=0;
B. affirm type overlap joint when away from:
a.LTa=LTm=LTb=DLT=LT, σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi, σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj, σjLT 2=0;
d.LTI ' a=LTI ' m=LTI ' b=DI ' LT=LTI ', σI ' LT 2=0.
According to the above project organic management and target control plan, by the organization and administration of following steps finished item and target The formulation of control plan:
(1) conversion of organizational logical relationship between being worked, such as by project organic management and target control plan What person determined: the preceding activity of B work is A work, is converted into next work of A work as B work;Or next work of A work It works as B, is converted into the preceding activity of B work as A work;
(2) arrangement of organizational logical relationship is carried out
(3) inspection and supplement of job engineering logical relation defect: work in every in groundwork list, in addition to ST, Preceding activity, including FIN are must determine;In addition to FIN, it must be determined that have next work, including ST;It is not any work The work of preceding activity is the preceding activity of FIN;It is not the work of next work of any work, is next work of ST; Determine preceding activity or (and) work that does not determine next work, as there is the work of tissue defects, should be by tissue Logical relation, supplement its preceding activity or (and) next work;
(4) in groundwork list job engineering sequence sequence: by ST successively are as follows: using ST as preceding activity Work;Using ordering work as the work of preceding activity;……;Until FIN;By FIN successively are as follows: with FIN be it is next The work of work;It take ordering work as the work of next work;……;Until ST;
(5) inspection and modification of job engineering logical relation defect and mistake: suitable by tight preceding tissue sequence and next tissue In sequence sequencer procedure, fails the work for completing sequence, as there is the work of organizational logical relationship defect or mistake, it should be by group Logical relation is knitted to be supplemented or modified.
Project organic management of the present invention and the time parameter calculation method of target control plan are as follows:
(1) time that work may start earliest
(2) time that work may terminate earliest
(3) interval time between work
(4) motor-driven (part) time difference to work: FFi=min (Lagi-j);
(5) total time difference to work: TFi=min (TFj+Lagi-j);
(6) it works the time that must start at the latest: LSi=ESi+TFi
(7) it works the time that must terminate at the latest: LFi=EFi+TFi
Project organic management of the present invention and the estimate variance calculation method of target control plan are as follows:
The present invention is complete by every groundwork after the completion of project organic management and target control planned time parameter calculate Influence at time Estimate deviation to next work implementation process carries out deviations2Adjustment after, carry out the meter of its estimate variance It calculates.
For the work (i.e. discontinuous work) of discontinuous completion, the adjustment for completing working time estimated bias is carried out;
The method of adjustment of every groundwork estimation work deadline deviation:
Note
(1)*σi 2- it is σ adjustedi 2
(2)σi 2The variance of-estimated time to completion the deviation for being groundwork i: σi 2=[(bit-ait)÷6]2, in which:
1)bitPessimism (longest) value of-estimated time to completion for being groundwork i;
2)aitOptimism (most short) value of-estimated time to completion for being groundwork i;
(3)DitThe weighted average of-the estimated time to completion for being groundwork i: Dit=(ait+4mit+bit) ÷ 6, in which:
1)mitMost probable (time) value of-estimated time to completion for being groundwork i;
(4)DitThe limit value of the estimated time to completion of '-be groundwork i.
By Parameters of Normal DistributionWork as λiWhen >=3.5, P (Dit') ≈ 100%, so
Project organic management and target control in the works, the estimated bias of groundwork deadline, to next work Influence, away from (EF when considering actually to overlapi-ESj) influence, i.e., by when practical overlap joint away from adjustment to the shadow of next work It rings;
Temporal duration estimate variance is overlapped between groundwork, to next work influence value υ2 j(LT)Calculation method, by following table institute Show:
Project organic management in the works, work item " work " organization arrangement (when overlap joint away from) estimate variance (υ2 rLT) take following calculating As a result maximum value
It works in organization and administration and the estimate variance of target control in the works, the influence to next work will consider work Between interval time (ESj-EFi) influence factor, be as follows:
Every groundwork adds up estimated time to completion deviation variance υ2 j(t)Calculation method:
Note:
(1)EFi'-for groundwork i is because estimation work deadline estimated bias influences, the time that can be completed at the latest, by Parameters of Normal Distribution λi=λiWhen >=3.5, P(iEF’)≈ 100%, so
(2) project organic management and target control in the works, the variance of every groundwork estimated time to completion deviation is by two Part forms: i.e. υ2 j(t)It (does not include * σj 2) and * σj 2;υ2 i(t)It also include two parts, i.e. υ2 i(t)With * σi 2For j's " work " It influences;υ2 j(t)It (does not include * σj 2The estimate variance of)-be j attack time;υ2 i(t)It (does not include * σi 2)-start for i work The estimate variance of time.
Project organic management of the present invention and target control plan, the calculating of time parameter and estimate variance:
(1) to the project organic management and target control plan, i.e. table one and table two of organizational logical relationship expression before tight, Calculate ESi、EFiAnd υi 2
(2) to the project organic management of next organizational logical relationship expression and target control plan, i.e. table one and table three, Calculate Lagi-jAfterwards, FF is determinedi, then calculate TFi、LSiAnd LFi
The present invention provides a kind of according to all kinds of project organic managements and target control plan, carries out various main resource plans The method of management, this method comprises the following steps: (1) according to project organic management and target control, work in every is most in the works The time that may early start draws Gantt chart or vivid progress gunter drawing;(2) by project organic management and target control plan, The statistics for carrying out resource requirement dynamic table to various main resources needed for work in every respectively, as various main resource meters Draw management foundation (if a certain work does not need certain resource, zero) enabling the requirement of its this resource is.
Each intermediate item or taskings' management and target control plan, the method for various main resource planning management are as follows Shown in table:
Gantt chart or vivid progress gunter drawing and resource planning control chart
According to all kinds of project organic managements and target control plan, main resource planning management is carried out, following steps are passed through It realizes:
(1) its gunter is drawn by project organic management and the target control time that work in every may start earliest in the works Figure or vivid progress gunter drawing:
It 1) is carried out with a kind of project organic management and target control work in every unit time main resource requirement in the works The optimal control of project organic management and the constructing aims and resource object of target control plan;To meet constructing aims and money The project organic management of source target call and the target control time that work in every may start earliest in the works draw its gunter Figure or vivid progress gunter drawing;
2) Gantt chart or vivid progress of the Gantt chart or vivid progress gunter drawing and non-key work that can be divided into key job are horizontal Road figure;
(2) organization and administration of determining respectively or valuation items and target control work in every unit time main resource in the works Requirement, be respectively filled in " resource needs " column of project organic management Yu target control plan;
1) its main resource refers to that the constructing aims for carrying out project organic management and target control plan and resource object optimization are controlled Main resource other than main resource used by making;
2) type of main resource, such as manpower, fund, capital equipment, main material;
(3) it according to project organic management and target control plan and its Gantt chart or vivid progress gunter drawing, carries out respectively The statistics of various main resource requirement dynamic tables needs dynamic table with various main resources, as main resource planning management Foundation.
It 1) include used by carrying out constructing aims and the resource object optimal control of project organic management and target control plan Main resource.
2) for not needing the work of certain resource, resource requirement is set as zero;
3) project organic management and target control plan can be provided respectively and each stage closes by the requirement of main resource planning management Key work needs dynamic table with the various main resources of non-key work;
4) project organic management and target control plan are provided respectively and each stage, various main resources need dynamic resource to need Want the resource requirement and average resource requirement of minimum, most periods;
5) project organic management and target control plan are provided respectively and each stage, various main resources need dynamic resource to need Want total amount.

Claims (10)

1. a kind of all kinds of project organization plan main resource plan management methods of critical path method, it is characterised in that: realize it is a kind of according to According to all kinds of project organic managements and target control plan, the complete scheme of main resource planning management is carried out, following steps are passed through It realizes:
Step (1) draws its gunter by project organic management and the target control time that work in every may start earliest in the works Figure or vivid progress gunter drawing;
Step (2) is determining respectively or valuation items organization and administration and target control work in every unit time main resource in the works Requirement, be respectively filled in " resource needs " column of project organic management Yu target control plan;
Step (3) carries out respectively according to project organic management and target control plan and its Gantt chart or vivid progress gunter drawing The statistics of various main resource requirement dynamic tables needs dynamic table with various main resources, as main resource planning management Foundation.
2. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (1) is described, draws its Gantt chart or vivid progress gunter drawing;It is with a kind of project organic management and target control Work in every unit time main resource requirement in the works carries out the constructing aims of project organic management and target control plan With the optimal control of resource object;To meet project organic management and the target control plan of constructing aims and resource object requirement The time that middle work in every may start earliest draws its Gantt chart or vivid progress gunter drawing.
3. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (1) is described, draws its Gantt chart or vivid progress gunter drawing;Can be divided into key job Gantt chart or image into Spend the Gantt chart or vivid progress gunter drawing of gunter drawing and non-key work.
4. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (2) is described, respectively the organization and administration of determining or valuation items and target control work in every unit time master in the works The requirement of resource is wanted, main resource refers to the constructing aims and resource for carrying out project organic management and target control plan Main resource other than main resource used by objective optimization controls.
5. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (2) is described, respectively the organization and administration of determining or valuation items and target control work in every unit time master in the works Want the requirement of resource;The type of main resource, such as manpower, fund, capital equipment, main material.
6. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (3) is described, carries out the statistics of various main resource requirement dynamic tables respectively, is needed with various main resources dynamic State table, as the foundation of main resource planning management, the constructing aims including carrying out project organic management and target control plan With main resource used by resource object optimal control.
7. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (3) is described, carries out the statistics of various main resource requirement dynamic tables respectively, is needed with various main resources dynamic State table, the foundation as main resource planning management;For not needing the work of certain resource, resource requirement is set as zero.
8. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (3) is described, carries out the statistics of various main resource requirement dynamic tables respectively, is needed with various main resources dynamic State table, the foundation as main resource planning management;Project organization pipe can be provided respectively by the requirement of main resource planning management Reason needs dynamic table with target control plan and each stage key job and the various main resources of non-key work.
9. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (3) is described, carries out the statistics of various main resource requirement dynamic tables respectively, is needed with various main resources dynamic State table, the foundation as main resource planning management;Project organic management and target control plan and each stage, each are provided respectively Plant resource requirement and average resource requirement that main resource needs dynamic resource to need minimum, most periods.
10. all kinds of project organization plan main resource plan management methods of a kind of critical path method according to claim 1, feature Be: step (3) is described, carries out the statistics of various main resource requirement dynamic tables respectively, is needed with various main resources dynamic State table, the foundation as main resource planning management;Project organic management and target control plan and each stage, each are provided respectively Kind main resource needs dynamic resource to need total amount.
CN201910296761.9A 2019-04-14 2019-04-14 A kind of all kinds of project organization plan main resource plan management methods of critical path method Pending CN110309940A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910296761.9A CN110309940A (en) 2019-04-14 2019-04-14 A kind of all kinds of project organization plan main resource plan management methods of critical path method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910296761.9A CN110309940A (en) 2019-04-14 2019-04-14 A kind of all kinds of project organization plan main resource plan management methods of critical path method

Publications (1)

Publication Number Publication Date
CN110309940A true CN110309940A (en) 2019-10-08

Family

ID=68074427

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910296761.9A Pending CN110309940A (en) 2019-04-14 2019-04-14 A kind of all kinds of project organization plan main resource plan management methods of critical path method

Country Status (1)

Country Link
CN (1) CN110309940A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120253869A1 (en) * 2009-12-14 2012-10-04 Rebecca Ansley System and Method for Process Improvement and Associated Products and Services
CN107067220A (en) * 2016-06-20 2017-08-18 杨玉海 The full-automatic lateral road figure technical method of project management progress

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120253869A1 (en) * 2009-12-14 2012-10-04 Rebecca Ansley System and Method for Process Improvement and Associated Products and Services
CN107067220A (en) * 2016-06-20 2017-08-18 杨玉海 The full-automatic lateral road figure technical method of project management progress

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴开平: "替代、且显著领先于具有国际先进水平的网络计划技术的统筹法-JQ、JH、(JQ-JH)搭接项目组织管理与目标控制技术" *

Similar Documents

Publication Publication Date Title
CN105069524B (en) Planned dispatching optimization method based on big data analysis
Zhang et al. Improved strategy for resource allocation in repetitive projects considering the learning effect
CN113032872B (en) BIM technology-based fabricated building progress plan comprehensive resource management and control method
CN110232466A (en) A kind of all kinds of project organization plan resources balance optimization methods of critical path method
CN110232469A (en) A kind of all kinds of minimum optimization methods of project organization plan resource of critical path method
CN110309942A (en) A kind of all kinds of project organization multistage plan main resource plan management methods of critical path method
CN110309940A (en) A kind of all kinds of project organization plan main resource plan management methods of critical path method
CN110232465A (en) A kind of all kinds of project organization multistage plans of critical path method resources balance optimization method step by step
CN110322043A (en) A kind of critical path method projects combo by project resource at least with relatively minimal optimization method
CN110334830A (en) A kind of qualitative Time-cost optimization application method of all kinds of project organization plans of critical path method
CN110309999A (en) A kind of each intermediate item any combination main resource plan management method of critical path method
CN110334834A (en) A kind of qualitative Time-cost optimization method of all kinds of project organization plans of critical path method
CN110322103A (en) A kind of all kinds of project organization plan resource limited optimization methods of critical path method
CN110232491A (en) A kind of critical path method project organization multistage plan afterbody resources balance optimization method
CN110310000A (en) A kind of all kinds of project organization plan resource comprehensive optimization methods of critical path method
CN110334829A (en) A kind of all kinds of project organization ways to draw up the plan of critical path method forms mode
CN110309998A (en) A kind of all kinds of project organization multistage system of planning reviewing methods of critical path method
CN110322102A (en) A kind of all kinds of project organization plan time resource dynamic reviewing methods of critical path method
CN110363324A (en) A kind of any projects combo multistage plan of the critical path method minimum optimization method of resource step by step
CN110232468A (en) A kind of critical path method combination project, which is fallen into a trap, draws a system most rear class resources balance optimization method
CN110322210A (en) A kind of all kinds of project organization plans inspection amending methods of critical path method forms mode
CN110322041A (en) A kind of any project combined resource limited optimization method of critical path method
CN110322211A (en) A kind of critical path method projects combo resource and duration dynamic reviewing method
CN110334836A (en) A kind of critical path method combination project is fallen into a trap the system of drawing resources balance optimization method step by step
CN110334831A (en) A kind of qualitative Time Optimization method of the gradual control project organization multistage system of planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant after: Jinan senkun Technology Co.,Ltd.

Address before: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant before: Jinan Senkun Enterprise Management Consulting Co.,Ltd.