CN106169114A - BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track - Google Patents

BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track Download PDF

Info

Publication number
CN106169114A
CN106169114A CN201610431025.6A CN201610431025A CN106169114A CN 106169114 A CN106169114 A CN 106169114A CN 201610431025 A CN201610431025 A CN 201610431025A CN 106169114 A CN106169114 A CN 106169114A
Authority
CN
China
Prior art keywords
construction
bim
module
model
management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610431025.6A
Other languages
Chinese (zh)
Inventor
王晖
王龙
马少雄
张学刚
杨宫印
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Railway Institute
Original Assignee
Shaanxi Railway Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Railway Institute filed Critical Shaanxi Railway Institute
Priority to CN201610431025.6A priority Critical patent/CN106169114A/en
Publication of CN106169114A publication Critical patent/CN106169114A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of BIM technology application platform based on high-speed railway CRTSIII plate-type Construction of Ballastless Track, creation module including BIM model information storehouse, BIM information model attributes is extracted and enquiry module, safety quality management module, material and progress module, system integration module and scientific and technological archive management module.During BIM technology is applied to high-speed railway plate type ballastless track construction management by the present invention first, it is achieved design optimization, construction simulation analysis, 3-D technology are told somebody what one's real intentions are, and improve work efficiency, have saved cost.

Description

BIM technology based on high-speed railway CRTSIII plate-type Construction of Ballastless Track is applied Platform
Technical field
The present invention relates to the realm of building construction, be specifically related to a kind of based on high-speed railway CRTSIII plate-type non-fragment orbit The BIM technology application platform of construction.
Background technology
At present, in China, ferrum each office debt ratio is averagely about 80%, and Project profit rate is relatively low, high ferro project loss situation The most serious.The reason of loss is a lot, wherein production technology fall behind and the production efficiency that causes be exactly lowly one important former Cause.
BIM technology is as a kind of datumization instrument being applied to engineering-built management, in the use of the developed regions such as North America Rate is more than 70%, and the utilization rate of building trade is about 6% at present at home.This technology integrates various item by parameter model Purpose relevant information, carries out sharing and transmitting in project planning, the lifecycle process running and safeguard, makes engineering Various architecture informations are made correct understanding and efficiently reply by personnel, provide the basis of collaborative work for each side's construction bodies, Improve production efficiency, cost-effective and reduction of erection time aspect plays a significant role.
BIM technology combines with the CRSTIII template construction technology of domestic independent property right, reaches to improve high ferro and executes Work efficiency rate, the cost-effective and purpose of reduction of erection time, realize " high standard, high-quality, high efficiency, zero mistake for high speed railway construction Difference " the project control objective that becomes more meticulous, it is provided that a kind of new management mode.Also successfully go abroad for China's high ferro technology and do Useful exploration and trial are gone out.At present, at home and abroad there is no precedent, be worth registration study.
Summary of the invention
It is an object of the invention to provide a kind of BIM skill based on high-speed railway CRTSIII plate-type Construction of Ballastless Track Art application platform, is achieved by BIM technology and improves high-speed rail construction efficiency, the cost-effective and purpose of reduction of erection time further, For promoting that high speed railway construction realizes the project control objective that becomes more meticulous of " high standard, high-quality, high efficiency, zero error ", it is provided that A kind of new management mode.
For achieving the above object, the technical scheme that the present invention takes is:
BIM technology application platform based on high-speed railway CRTSIII plate-type Construction of Ballastless Track, including
The creation module in BIM model information storehouse, for by full details such as the building of whole construction project, material, constructions It is fused in model database;
BIM information model attributes is extracted and enquiry module, is integrated with all behavioural informations relevant with management, and is used for leading to Cross information association, the mode such as call can truly simulate the agenda of whole process of construction, makes engineers and technicians build various The information of building makes correct understanding and efficiently reply, simultaneously engineers and technicians can to the curve element of engineering, space technology parameter, Most cun of section structure, coordinate and elevation information implement accurately inquiry;
Safety quality management module, for the safety in work progress, the closed-loop process of quality problems, Danger source And special type facilities management;
Material and progress module, for arbitrarily extracting engineering material requested amount according to site operation plan, simultaneously can be to work Journey construction speed is implemented to control, analyze;
System integration module, for being monitored key procedure, place;
Scientific and technological archive management module, for electronics builder's diary, electronic document and associated construction data is divided Class manages.
Wherein, described BIM model building module realizes this bid section CRSTIII template parametrization by CATIA Modeling Platform The foundation of model, based on the parameterized model set up, obtains the structure of section by measuring the cutting section at any mileage Dimension model, and extracting directly goes out coordinate, absolute altitude, control point range information.
Wherein, described BIM model and construction data incidence relation set up module can be additionally used in based on BIM construction information, Parameterized model, in conjunction with construction site management platform, adds up quantities according to the template specified, form, and classification is derived Statistical result, helps project management department to adjust quantities;
Wherein, described construction integrated management scheme output module Construction simulation based on DEL~MIA technology, make CRTSIII type construction technology animation, guide field is constructed.
The method have the advantages that
During first BIM technology being applied to high-speed railway plate type ballastless track construction management, it is achieved design optimization, execute Work process simulation, 3-D technology are told somebody what one's real intentions are, and improve work efficiency, have saved cost.To design, peace in BIM technology application process Entirely, quality, material, progress, cost have all carried out the management of science.Project is made tentatively to achieve from visualizing, become more meticulous, dynamically Management, to the modem management pattern of precision management.Simultaneously, it is possible to realize from local to overall three-dimensional, the four-dimension, five dimension Site operation is simulated, and effectively raises production efficiency, has saved production cost, shortens the construction period.
Accompanying drawing explanation
Fig. 1 is that a kind of BIM technology based on high-speed railway CRTSIII plate-type Construction of Ballastless Track of the embodiment of the present invention should With the Implementation Roadmap of platform.
Fig. 2 is the Modeling Routing schematic diagram of one specific embodiment of the present invention.
Detailed description of the invention
In order to make objects and advantages of the present invention clearer, below in conjunction with embodiment, the present invention is carried out further Describe in detail.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to limit this Bright.
As it is shown in figure 1, embodiments provide a kind of based on high-speed railway CRTSIII plate-type Construction of Ballastless Track BIM technology application platform, including
The creation module in BIM model information storehouse, for by full details such as the building of whole construction project, material, constructions It is fused in model database;
BIM information model attributes is extracted and enquiry module, is integrated with all behavioural informations relevant with management, and is used for leading to Cross information association, the mode such as call can truly simulate the agenda of whole process of construction, makes engineers and technicians build various The information of building makes correct understanding and efficiently reply, simultaneously engineers and technicians can to the curve element of engineering, space technology parameter, Most cun of section structure, coordinate and elevation information implement accurately inquiry;
Safety quality management module, for the safety in work progress, the closed-loop process of quality problems, Danger source And special type facilities management;
Material and progress module, for arbitrarily extracting engineering material requested amount according to site operation plan, simultaneously can be to work Journey construction speed is implemented to control, analyze;
System integration module, for being monitored key procedure, place;
Scientific and technological archive management module, for electronics builder's diary, electronic document and associated construction data is divided Class manages.
Described BIM model building module realizes this bid section CRSTIII template parameterized model by CATIA Modeling Platform Set up, based on the parameterized model set up, obtain the physical dimension mould of section by measuring the cutting section at any mileage Type, and extracting directly goes out coordinate, absolute altitude, control point range information.
Described BIM model and construction data incidence relation are set up module and be can be additionally used in based on BIM construction information, parametrization Model, in conjunction with construction site management platform, adds up quantities according to the template specified, form, and statistics knot is derived in classification Really, project management department is helped to adjust quantities;
Described construction integrated management scheme output module Construction simulation based on DELMIA technology, makes CRTSIII type and executes Work technique animation, guide field is constructed.
Embodiment
The program is successfully applied to visitor Xu Zheng specially engineering the 6th bid section high-speed railway CRTSIII plate-type Construction of Ballastless Track In project, including pier #154 to #215, wherein 154-207 is curve (directly delaying), and 207-215 is straightway.By by high ferro The two-dimensional signal (drawing information) of construction project is completely converted into three-dimensional entity model, and it is by the building of whole construction project, material The full details such as material, construction are fused in model database, and engineers and technicians can be to the curve needed for whole project construction Key element, pass space technology parameter, most cun of section structure, coordinate and elevation information are implemented accurately to inquire about, project Modeling Routing As shown in Figure 1.
This project, based on BIM construction model, utilizes 3DVIA Composer three-dimensional interactive browser technology, by project BIM construction model carries out light-weight technologg, in conjunction with necessary word summary, engineering document, drawing, video etc., and to important work Journey structure and construction member carry out parameter mark, form " drawing " and the engineering information electronic document of three dimensional stress.Site operation people Member can utilize information document that the document checks that three-dimensional BIM model, engineering are relevant and threedimensional model is measured acquisition Project data or utilize threedimensional model to be labeled a certain structure, carries out collaborative work with designer.
This project achieves 4D technology by the 3D+ time concept of BIM technology.To each position additional period in model Concept, it is achieved construction speed is simulated, and is analyzed by the contrast forming curves figure with target advance.Before construction, permissible Create different construction plans, such as construction general plan, daily planning of constructing, different construction plans and corresponding model can be entered Row association, sets up information management database.Meanwhile, so that general plan or daily planning are associated with corresponding construction model, Management personnel just can accurately know construction mileage and the associated construction information of every day, for later stage material, progress control, builds letter Breath platform.After construction plan and model interaction, construction speed can be shown by three-dimensional artificial, truly reflect process.Permissible Version is special, the work progress of complex process, show in detail by different colours, different visual angles.Site operation people Member accurately sees the internals of engineering construction, facilitates observer to see construction speed the most intuitively clearly.Also may be used The thing the most vivid, eyes be can't see can clearly be showed.By construction plan is right with what reality was planned Ratio, target advance and the analysis of actual progress, can carry out three-dimensional artificial contrast, for practice of construction progress control, reality simultaneously Case study provides effective and supports.By BIM technology application platform, it is achieved that the construction at project links is often to manage Reason, including construction safety daily record, construction quality daily record, construction technology daily record, the daily record of construction teams and groups, deposits in construction process Problem and can not implement completely to upload in time by platform, examine, rectify and improve, the closed loop management process such as examination.By profit BIM mould Type data, estimate investment project overall expenses, the cost management of finished item, simultaneously, it is possible to each in high ferro process of construction Link carries out capital budgeting.And by BIM platform whole project done and totally to run planning, and show that substantial amounts of visual data is made Support for program decisions.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For Yuan, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (4)

1. BIM technology application platform based on high-speed railway CRTSIII plate-type Construction of Ballastless Track, its characteristic is, including
The creation module in BIM model information storehouse, for merging full details such as the building of whole construction project, material, constructions In model database;
BIM information model attributes is extracted and enquiry module, is integrated with all behavioural informations relevant with management, and for by letter Breath associate, the mode such as call can truly simulate the agenda of whole process of construction, makes engineers and technicians believe various buildings Breath makes correct understanding and efficiently reply, and engineers and technicians can be to the curve element of engineering, space technology parameter, section simultaneously Most cun of structure, coordinate and elevation information implement accurately inquiry;
Safety quality management module, for the safety in work progress, the closed-loop process of quality problems, Danger source and spy Plant facilities management;
Material and progress module, for arbitrarily extracting engineering material requested amount according to site operation plan, can execute engineering simultaneously Work progress is implemented to control, analyze;
System integration module, for being monitored key procedure, place;
Scientific and technological archive management module, for electronics builder's diary, electronic document and the classification pipe to associated construction data Reason.
BIM technology based on high-speed railway CRTSIII plate-type Construction of Ballastless Track the most according to claim 1 application is flat Platform, its characteristic is, described BIM model building module realizes this bid section CRSTIII template parametrization by CATIA Modeling Platform The foundation of model, based on the parameterized model set up, obtains the structure of section by measuring the cutting section at any mileage Dimension model, and extracting directly goes out coordinate, absolute altitude, control point range information.
BIM technology based on high-speed railway CRTSIII plate-type Construction of Ballastless Track the most according to claim 1 application is flat Platform, its characteristic is, described BIM model and construction data incidence relation set up module can be additionally used in based on BIM construction information, Parameterized model, in conjunction with construction site management platform, adds up quantities according to the template specified, form, and classification is derived Statistical result, helps project management department to adjust quantities.
BIM technology based on high-speed railway CRTSIII plate-type Construction of Ballastless Track the most according to claim 1 application is flat Platform, its characteristic is, described construction integrated management scheme output module Construction simulation based on DELMIA technology, makes CRTSIII type construction technology animation, guide field is constructed.
CN201610431025.6A 2016-06-15 2016-06-15 BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track Pending CN106169114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610431025.6A CN106169114A (en) 2016-06-15 2016-06-15 BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610431025.6A CN106169114A (en) 2016-06-15 2016-06-15 BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track

Publications (1)

Publication Number Publication Date
CN106169114A true CN106169114A (en) 2016-11-30

Family

ID=58064413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610431025.6A Pending CN106169114A (en) 2016-06-15 2016-06-15 BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track

Country Status (1)

Country Link
CN (1) CN106169114A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106845841A (en) * 2017-01-18 2017-06-13 陕西铁路工程职业技术学院 A kind of Life cycle informatization management method of the type track plates of CRTS III based on BIM technology
CN106980705A (en) * 2017-02-22 2017-07-25 中国建筑第八工程局有限公司 Safety protection standard construction method based on BIM technology
CN107818198A (en) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 A kind of science of bridge building management platform based on BIM technology
CN109682303A (en) * 2019-01-31 2019-04-26 中铁四局集团第二工程有限公司 Curve PC track girder precision three-dimensional detection method based on BIM technology
CN112464330A (en) * 2020-10-19 2021-03-09 中铁第四勘察设计院集团有限公司 BIM design method of CRTS III plate type ballastless track
CN113011832A (en) * 2021-04-28 2021-06-22 阜阳市福颖网络技术开发有限公司 Engineering cost system based on BIM

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104657512A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing steel truss arch bridge engineering quantity statistics by employing BIM (building information modeling)
CN104657510A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing rapid steel truss arch bridge modeling by utilizing BIM

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104657512A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing steel truss arch bridge engineering quantity statistics by employing BIM (building information modeling)
CN104657510A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing rapid steel truss arch bridge modeling by utilizing BIM

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张为和: "基于BIM的夜郎河双线特大桥施工应用方案研究", 《铁道标准设计》 *
李昌宁等: "郑徐铁路专线CRTSIII型板式无砟轨道施工关键技术", 《轨道标准设计》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106845841A (en) * 2017-01-18 2017-06-13 陕西铁路工程职业技术学院 A kind of Life cycle informatization management method of the type track plates of CRTS III based on BIM technology
CN106980705A (en) * 2017-02-22 2017-07-25 中国建筑第八工程局有限公司 Safety protection standard construction method based on BIM technology
CN107818198A (en) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 A kind of science of bridge building management platform based on BIM technology
CN109682303A (en) * 2019-01-31 2019-04-26 中铁四局集团第二工程有限公司 Curve PC track girder precision three-dimensional detection method based on BIM technology
CN112464330A (en) * 2020-10-19 2021-03-09 中铁第四勘察设计院集团有限公司 BIM design method of CRTS III plate type ballastless track
CN113011832A (en) * 2021-04-28 2021-06-22 阜阳市福颖网络技术开发有限公司 Engineering cost system based on BIM

Similar Documents

Publication Publication Date Title
CN106096111A (en) BIM technology application in high-speed railway CRTSIII plate-type Construction of Ballastless Track
CN106169114A (en) BIM technology application platform based on high-speed railway CRTS III plate-type Construction of Ballastless Track
CN106988221B (en) Unit construction bridge beam construction method based on BIM
Ding et al. A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects
Chen et al. A BIM-based construction quality management model and its applications
CN101739478B (en) Spacecraft assembly simulation technique-based virtual assembly system and virtual assembly method
CN110826130A (en) Application method of BIM modeling in design and construction of special-shaped curved surface structure body
CN111950975A (en) BIM technology-based multi-organization coordination management cloud platform for construction engineering project
CN112232761B (en) Infrastructure application system and method
CN108537519A (en) A kind of architectural design method based on BIM
CN108121704A (en) A kind of three-dimensional final acceptance of construction system
Sampaio Project management in office: BIM implementation
CN110991882A (en) Project construction fine management method based on BIM5D
CN111191996A (en) BIM-based dynamic cost management method for whole process of power transmission and transformation project
CN115774893A (en) Railway full-life-cycle multi-source data integration correlation method, system and storage medium
CN108694260A (en) Application process of the BIM technology in Steel Bridge processing and manufacturing
Kellogg et al. Hierarchy model of construction productivity
CN117035700A (en) BIM-based hydraulic and hydroelectric engineering forward collaborative design method
Liu et al. Research on virtual construction in the construction phase and its 4D LOD analysis
Erzaij et al. Application of building information modeling (3D and 4D) in construction sector in Iraq
Jeong A Study on the Development of Standardization for Building Process based on BIM
Wang et al. Integration of GIS and BIM in Metro Construction
Cianci et al. Information modeling and landscape: intervention methodology for reading complex systems
Yakshina et al. Bim technology in the educational process
Zhao Refined node data mining platform in the construction phase of building installation engineering based on BIM technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161130

RJ01 Rejection of invention patent application after publication