CN106875159A - 现浇结构城市综合管廊施工综合管理*** - Google Patents
现浇结构城市综合管廊施工综合管理*** Download PDFInfo
- Publication number
- CN106875159A CN106875159A CN201710085131.8A CN201710085131A CN106875159A CN 106875159 A CN106875159 A CN 106875159A CN 201710085131 A CN201710085131 A CN 201710085131A CN 106875159 A CN106875159 A CN 106875159A
- Authority
- CN
- China
- Prior art keywords
- construction
- typing
- resource
- duration
- plan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 60
- 238000007726 management method Methods 0.000 claims abstract description 33
- 238000013439 planning Methods 0.000 claims abstract description 11
- 238000004458 analytical method Methods 0.000 claims abstract description 8
- 238000012986 modification Methods 0.000 claims abstract description 8
- 230000004048 modification Effects 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 7
- 230000015556 catabolic process Effects 0.000 claims description 3
- 238000009472 formulation Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 230000011218 segmentation Effects 0.000 claims description 3
- 230000008901 benefit Effects 0.000 abstract description 4
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 238000012384 transportation and delivery Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明公开了现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:1)、综合管廊结构分解;2)、工期计划录入;3)、所需资源数量分析、录入;4)、发布施工计划;5)、每日施工情况跟踪、录入;6)、工期预警;7)、资源调整、节点工期调整;8)、闭环、总结。本发明的优点是有效提高现场进度、质量、安全管理效率,降低施工成本。
Description
技术领域
本发明涉及城市地下综合管廊施工技术领域,尤其涉及现浇结构城市综合管廊施工综合管理***,适用于城市现浇综合管廊及类似长距离地下工程的施工过程管理。
背景技术
城市地下综合管廊项目在我国发展已有一定时间,但目前已有研究主要针对管廊的规划、设计、运营、移交阶段,对于城市综合管廊的施工过程,目前仍处于开始阶段。在现有的综合管廊建设中,管理人员主要为原从事市政、建筑工程的管理人员,对于综合管廊的施工,依旧沿用市政、建筑工程的管理办法,并不适用于地下管廊的施工,特别是在工期较紧,作业人员、施工机械、材料投入量巨大的情况下,常规进度、质量、安全、材料管理办法无法满足现场管理的需求。在此情况下,需要提出一种新的管理流程,建立一套新的管理体系,以适应城市地下综合管廊的施工,降低管理成本,提高管理质量。
发明内容
本发明的目的就是针对现有技术存在的问题,提供现浇结构城市综合管廊施工综合管理***,通过明确流程化、规范化的管理方法,克服在综合管廊施工过程中的进度、质量、安全管理工作粗放的缺点,高效简洁的完成管廊施工过程管理工作。
本发明的目的是这样实现的:现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
与现有技术相比,本发明的优点是:有效提高现场进度、质量、安全管理效率,降低施工成本。
附图说明
图1:现浇结构城市综合管廊施工综合管理***流程图
图中流程根据任务分解、进度要求、操作步骤制成。
具体实施方式
为进一步描述本发明,下面结合实施例和附图对本发明作进一步描述。
如图所述,现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
兰州新区地下综合管廊项目,采用本发明的管理流程,利用计算机软件协助,实现了较少管理人员管理大型管廊工程。采用本发明,可有效提高现场进度、质量、安全管理效率,有利于降低施工成本,具有良好的经济效益和社会效益。
Claims (1)
1.现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085131.8A CN106875159A (zh) | 2017-02-17 | 2017-02-17 | 现浇结构城市综合管廊施工综合管理*** |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085131.8A CN106875159A (zh) | 2017-02-17 | 2017-02-17 | 现浇结构城市综合管廊施工综合管理*** |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106875159A true CN106875159A (zh) | 2017-06-20 |
Family
ID=59166117
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710085131.8A Pending CN106875159A (zh) | 2017-02-17 | 2017-02-17 | 现浇结构城市综合管廊施工综合管理*** |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106875159A (zh) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755757A (zh) * | 2018-06-29 | 2018-11-06 | 上海二十冶建设有限公司 | 基于预制装配叠合式地下综合管廊的快速混合施工方法 |
CN109299924A (zh) * | 2018-10-19 | 2019-02-01 | 杭州数建科技有限公司 | 基于多级管控的精细化和智能化项目管理方法 |
CN109636675A (zh) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | 一种基于人工智能的建筑施工现场的管理方法及*** |
CN109741090A (zh) * | 2018-12-18 | 2019-05-10 | 刘雨昆 | 一种基于多因素的配网工程物资需求预测方法 |
CN110443480A (zh) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | 一种施工进度监控预警方法及*** |
CN110766292A (zh) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | 一种船舶分段资源的调度方法、装置、设备及存储介质 |
CN110930044A (zh) * | 2019-11-29 | 2020-03-27 | 伍知行 | 一种施工组织资源快速配置方法及*** |
CN111027803A (zh) * | 2019-11-01 | 2020-04-17 | 国艺天成建设工程技术有限公司 | 施工管理方法及施工管理*** |
CN112541742A (zh) * | 2020-12-21 | 2021-03-23 | 宁良武 | 一种建筑施工进度管理方法 |
CN113935853A (zh) * | 2021-10-29 | 2022-01-14 | 广东三扬网络科技有限公司 | 一种生产进度跟踪管理方法、模块、***和存储介质 |
CN116128273A (zh) * | 2023-04-17 | 2023-05-16 | 清云小筑(北京)创新技术有限公司 | 考虑可变工期与动态资源约束的工序自动排程方法及装置 |
CN117196161A (zh) * | 2022-01-05 | 2023-12-08 | 陕西克林维尔信息科技有限公司 | 市政工程管理方法、装置、计算机可读存储介质及服务器 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104484524A (zh) * | 2014-12-09 | 2015-04-01 | 张家驰 | 一种基于bim仿真模型与现场施工交互的方法和*** |
CN104766182A (zh) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | 一种基于bim的建筑设计施工智能监管*** |
CN105512822A (zh) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | 基于可视化技术的施工进度管理方法 |
CN106339490A (zh) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | 基于3dgis和工程三维模型的铁路桥梁施工进度管理***和管理方法 |
-
2017
- 2017-02-17 CN CN201710085131.8A patent/CN106875159A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104484524A (zh) * | 2014-12-09 | 2015-04-01 | 张家驰 | 一种基于bim仿真模型与现场施工交互的方法和*** |
CN104766182A (zh) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | 一种基于bim的建筑设计施工智能监管*** |
CN105512822A (zh) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | 基于可视化技术的施工进度管理方法 |
CN106339490A (zh) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | 基于3dgis和工程三维模型的铁路桥梁施工进度管理***和管理方法 |
Non-Patent Citations (1)
Title |
---|
杨峰: "城市地下市政综合管廊施工方法初步探讨与分析", 《安徽建筑》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755757A (zh) * | 2018-06-29 | 2018-11-06 | 上海二十冶建设有限公司 | 基于预制装配叠合式地下综合管廊的快速混合施工方法 |
CN109299924A (zh) * | 2018-10-19 | 2019-02-01 | 杭州数建科技有限公司 | 基于多级管控的精细化和智能化项目管理方法 |
CN109636675A (zh) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | 一种基于人工智能的建筑施工现场的管理方法及*** |
CN109741090A (zh) * | 2018-12-18 | 2019-05-10 | 刘雨昆 | 一种基于多因素的配网工程物资需求预测方法 |
CN110443480B (zh) * | 2019-07-26 | 2023-10-27 | 中铁四局集团第一工程有限公司 | 一种施工进度监控预警方法及*** |
CN110443480A (zh) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | 一种施工进度监控预警方法及*** |
CN110766292A (zh) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | 一种船舶分段资源的调度方法、装置、设备及存储介质 |
CN111027803A (zh) * | 2019-11-01 | 2020-04-17 | 国艺天成建设工程技术有限公司 | 施工管理方法及施工管理*** |
CN110930044A (zh) * | 2019-11-29 | 2020-03-27 | 伍知行 | 一种施工组织资源快速配置方法及*** |
CN112541742A (zh) * | 2020-12-21 | 2021-03-23 | 宁良武 | 一种建筑施工进度管理方法 |
CN113935853A (zh) * | 2021-10-29 | 2022-01-14 | 广东三扬网络科技有限公司 | 一种生产进度跟踪管理方法、模块、***和存储介质 |
CN117196161A (zh) * | 2022-01-05 | 2023-12-08 | 陕西克林维尔信息科技有限公司 | 市政工程管理方法、装置、计算机可读存储介质及服务器 |
CN116128273A (zh) * | 2023-04-17 | 2023-05-16 | 清云小筑(北京)创新技术有限公司 | 考虑可变工期与动态资源约束的工序自动排程方法及装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106875159A (zh) | 现浇结构城市综合管廊施工综合管理*** | |
CN109710990B (zh) | 基于bim技术的碾压混凝土坝施工进度-成本协同控制方法 | |
CN104573892A (zh) | 一种工程建设全过程可视化项目管理*** | |
CN100561542C (zh) | 一种Petri网的链式航班延误预警装置及其处理方法 | |
CN114580752A (zh) | 一种基于bim技术的工程施工进度智能管理*** | |
CN104331779A (zh) | 一种开发区建设项目管理***及方法 | |
Belyakova et al. | Management strategy for regional labor market (case of the Krasnoyarsk krai) | |
CN116562802A (zh) | 一种基于bim的轨道交通智能化施工应用平台 | |
CN110083989B (zh) | 一种基于bim技术在管廊暗挖工程中安全数据监测方法 | |
CN106681703A (zh) | 一种可重用的界面组件构建***及方法 | |
CN111476697A (zh) | 一种智慧路网综合管理平台 | |
Kenley et al. | Location Breakdown Structure (LBS): a solution for construction project management data redundancy | |
CN110232469A (zh) | 一种统筹法各类项目组织计划资源最少优化方法 | |
Jia et al. | Setting scheduled trip time based on AVL data | |
CN110232466A (zh) | 一种统筹法各类项目组织计划资源均衡优化方法 | |
Qiaolan et al. | Civil engineering construction management based on BIM technology | |
Shivasami et al. | Early implementation of BIM in large infrastructure projects to manage complex interfaces in a dense urban environment | |
Novikova et al. | New technologies for utilization of associated petroleum gas in mature fields with no transport infrastructure | |
Trépanier et al. | Democratized smartcard data for transit operator | |
Cameron et al. | An environmental impact assessment for hydropower development in China | |
Liu et al. | Application practice of code mapping technology in hydropower project construction management system | |
CN111985833B (zh) | 一种页岩气压裂工程智能调度方法及*** | |
Sander et al. | CEVP-RIAAT Process-Application of an Integrated Cost and Schedule Analysis | |
Shevchenko et al. | Challenges and threats for Ukraine airports caused by the global pandemic | |
Dara et al. | Complexities in Metrorail Project-A Case Study of Hyderabad Metro Rail |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170620 |
|
RJ01 | Rejection of invention patent application after publication |