CN106875159A - 现浇结构城市综合管廊施工综合管理*** - Google Patents

现浇结构城市综合管廊施工综合管理*** Download PDF

Info

Publication number
CN106875159A
CN106875159A CN201710085131.8A CN201710085131A CN106875159A CN 106875159 A CN106875159 A CN 106875159A CN 201710085131 A CN201710085131 A CN 201710085131A CN 106875159 A CN106875159 A CN 106875159A
Authority
CN
China
Prior art keywords
construction
typing
resource
duration
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710085131.8A
Other languages
English (en)
Inventor
吴建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710085131.8A priority Critical patent/CN106875159A/zh
Publication of CN106875159A publication Critical patent/CN106875159A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:1)、综合管廊结构分解;2)、工期计划录入;3)、所需资源数量分析、录入;4)、发布施工计划;5)、每日施工情况跟踪、录入;6)、工期预警;7)、资源调整、节点工期调整;8)、闭环、总结。本发明的优点是有效提高现场进度、质量、安全管理效率,降低施工成本。

Description

现浇结构城市综合管廊施工综合管理***
技术领域
本发明涉及城市地下综合管廊施工技术领域,尤其涉及现浇结构城市综合管廊施工综合管理***,适用于城市现浇综合管廊及类似长距离地下工程的施工过程管理。
背景技术
城市地下综合管廊项目在我国发展已有一定时间,但目前已有研究主要针对管廊的规划、设计、运营、移交阶段,对于城市综合管廊的施工过程,目前仍处于开始阶段。在现有的综合管廊建设中,管理人员主要为原从事市政、建筑工程的管理人员,对于综合管廊的施工,依旧沿用市政、建筑工程的管理办法,并不适用于地下管廊的施工,特别是在工期较紧,作业人员、施工机械、材料投入量巨大的情况下,常规进度、质量、安全、材料管理办法无法满足现场管理的需求。在此情况下,需要提出一种新的管理流程,建立一套新的管理体系,以适应城市地下综合管廊的施工,降低管理成本,提高管理质量。
发明内容
本发明的目的就是针对现有技术存在的问题,提供现浇结构城市综合管廊施工综合管理***,通过明确流程化、规范化的管理方法,克服在综合管廊施工过程中的进度、质量、安全管理工作粗放的缺点,高效简洁的完成管廊施工过程管理工作。
本发明的目的是这样实现的:现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
与现有技术相比,本发明的优点是:有效提高现场进度、质量、安全管理效率,降低施工成本。
附图说明
图1:现浇结构城市综合管廊施工综合管理***流程图
图中流程根据任务分解、进度要求、操作步骤制成。
具体实施方式
为进一步描述本发明,下面结合实施例和附图对本发明作进一步描述。
如图所述,现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
兰州新区地下综合管廊项目,采用本发明的管理流程,利用计算机软件协助,实现了较少管理人员管理大型管廊工程。采用本发明,可有效提高现场进度、质量、安全管理效率,有利于降低施工成本,具有良好的经济效益和社会效益。

Claims (1)

1.现浇结构城市综合管廊施工综合管理***,包括综合管廊结构分解,工期计划录入,所需资源数量分析、录入,发布施工计划,每日施工情况跟踪、录入,工期预警,资源调整、节点工期调整和闭环、总结,其特征在于,按以下步骤进行:
1)、综合管廊结构分解
对综合管廊主体结构施工进行三级划分,首先进行管廊工程单位工程划分;第二步进行单位工程的结构划分,按管廊平面图坐标,将标准段与节点部分进行划分;第三步,按每段的施工工序进行细化;
2)、工期计划录入
项目结构分解后,制定每项工序的工期节点,明确开始时间和结束时间,设置未完成提前预警时间;
3)、所需资源数量分析、录入
制定每项工序的工期节点后,计算每项工序所需的资源数量,包括各工种作业人员,所需施工机具,并录入倒推材料进场时间,录入材料进场时间计划;
4)、发布施工计划
根据分解的项目结构及制定的节点要求、资源需求,发布工作计划,主要包括进度管理、质量管理、安全管理、经营管理的职能部门,同时包括各协作队伍;
5)、每日施工情况跟踪、录入
施工开始后,由管理人员每日跟踪对比施工计划,并将实际资源、完成时间录入***;
6)、工期预警
实际施工资源与计划资源误差存在误差的,工期进度延误的,按日发布预警信息;
7)、资源调整、节点工期调整
对于所需资源与现场实际存在较大误差的,及时调整所需资源情况,在资源调整无效的情况下,调整工序工期;
8)、闭环、总结
各分段施工完成后,及时进行所需资源总结,对后续的分段工期及时进行调整。
CN201710085131.8A 2017-02-17 2017-02-17 现浇结构城市综合管廊施工综合管理*** Pending CN106875159A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710085131.8A CN106875159A (zh) 2017-02-17 2017-02-17 现浇结构城市综合管廊施工综合管理***

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710085131.8A CN106875159A (zh) 2017-02-17 2017-02-17 现浇结构城市综合管廊施工综合管理***

Publications (1)

Publication Number Publication Date
CN106875159A true CN106875159A (zh) 2017-06-20

Family

ID=59166117

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710085131.8A Pending CN106875159A (zh) 2017-02-17 2017-02-17 现浇结构城市综合管廊施工综合管理***

Country Status (1)

Country Link
CN (1) CN106875159A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755757A (zh) * 2018-06-29 2018-11-06 上海二十冶建设有限公司 基于预制装配叠合式地下综合管廊的快速混合施工方法
CN109299924A (zh) * 2018-10-19 2019-02-01 杭州数建科技有限公司 基于多级管控的精细化和智能化项目管理方法
CN109636675A (zh) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 一种基于人工智能的建筑施工现场的管理方法及***
CN109741090A (zh) * 2018-12-18 2019-05-10 刘雨昆 一种基于多因素的配网工程物资需求预测方法
CN110443480A (zh) * 2019-07-26 2019-11-12 中铁四局集团第一工程有限公司 一种施工进度监控预警方法及***
CN110766292A (zh) * 2019-09-29 2020-02-07 广船国际有限公司 一种船舶分段资源的调度方法、装置、设备及存储介质
CN110930044A (zh) * 2019-11-29 2020-03-27 伍知行 一种施工组织资源快速配置方法及***
CN111027803A (zh) * 2019-11-01 2020-04-17 国艺天成建设工程技术有限公司 施工管理方法及施工管理***
CN112541742A (zh) * 2020-12-21 2021-03-23 宁良武 一种建筑施工进度管理方法
CN113935853A (zh) * 2021-10-29 2022-01-14 广东三扬网络科技有限公司 一种生产进度跟踪管理方法、模块、***和存储介质
CN116128273A (zh) * 2023-04-17 2023-05-16 清云小筑(北京)创新技术有限公司 考虑可变工期与动态资源约束的工序自动排程方法及装置
CN117196161A (zh) * 2022-01-05 2023-12-08 陕西克林维尔信息科技有限公司 市政工程管理方法、装置、计算机可读存储介质及服务器

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (zh) * 2014-12-09 2015-04-01 张家驰 一种基于bim仿真模型与现场施工交互的方法和***
CN104766182A (zh) * 2015-04-30 2015-07-08 北京宁晖兴业科技有限公司 一种基于bim的建筑设计施工智能监管***
CN105512822A (zh) * 2015-12-14 2016-04-20 国家电网公司 基于可视化技术的施工进度管理方法
CN106339490A (zh) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 基于3dgis和工程三维模型的铁路桥梁施工进度管理***和管理方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484524A (zh) * 2014-12-09 2015-04-01 张家驰 一种基于bim仿真模型与现场施工交互的方法和***
CN104766182A (zh) * 2015-04-30 2015-07-08 北京宁晖兴业科技有限公司 一种基于bim的建筑设计施工智能监管***
CN105512822A (zh) * 2015-12-14 2016-04-20 国家电网公司 基于可视化技术的施工进度管理方法
CN106339490A (zh) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 基于3dgis和工程三维模型的铁路桥梁施工进度管理***和管理方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨峰: "城市地下市政综合管廊施工方法初步探讨与分析", 《安徽建筑》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755757A (zh) * 2018-06-29 2018-11-06 上海二十冶建设有限公司 基于预制装配叠合式地下综合管廊的快速混合施工方法
CN109299924A (zh) * 2018-10-19 2019-02-01 杭州数建科技有限公司 基于多级管控的精细化和智能化项目管理方法
CN109636675A (zh) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 一种基于人工智能的建筑施工现场的管理方法及***
CN109741090A (zh) * 2018-12-18 2019-05-10 刘雨昆 一种基于多因素的配网工程物资需求预测方法
CN110443480B (zh) * 2019-07-26 2023-10-27 中铁四局集团第一工程有限公司 一种施工进度监控预警方法及***
CN110443480A (zh) * 2019-07-26 2019-11-12 中铁四局集团第一工程有限公司 一种施工进度监控预警方法及***
CN110766292A (zh) * 2019-09-29 2020-02-07 广船国际有限公司 一种船舶分段资源的调度方法、装置、设备及存储介质
CN111027803A (zh) * 2019-11-01 2020-04-17 国艺天成建设工程技术有限公司 施工管理方法及施工管理***
CN110930044A (zh) * 2019-11-29 2020-03-27 伍知行 一种施工组织资源快速配置方法及***
CN112541742A (zh) * 2020-12-21 2021-03-23 宁良武 一种建筑施工进度管理方法
CN113935853A (zh) * 2021-10-29 2022-01-14 广东三扬网络科技有限公司 一种生产进度跟踪管理方法、模块、***和存储介质
CN117196161A (zh) * 2022-01-05 2023-12-08 陕西克林维尔信息科技有限公司 市政工程管理方法、装置、计算机可读存储介质及服务器
CN116128273A (zh) * 2023-04-17 2023-05-16 清云小筑(北京)创新技术有限公司 考虑可变工期与动态资源约束的工序自动排程方法及装置

Similar Documents

Publication Publication Date Title
CN106875159A (zh) 现浇结构城市综合管廊施工综合管理***
CN109710990B (zh) 基于bim技术的碾压混凝土坝施工进度-成本协同控制方法
CN104573892A (zh) 一种工程建设全过程可视化项目管理***
CN100561542C (zh) 一种Petri网的链式航班延误预警装置及其处理方法
CN114580752A (zh) 一种基于bim技术的工程施工进度智能管理***
CN104331779A (zh) 一种开发区建设项目管理***及方法
Belyakova et al. Management strategy for regional labor market (case of the Krasnoyarsk krai)
CN116562802A (zh) 一种基于bim的轨道交通智能化施工应用平台
CN110083989B (zh) 一种基于bim技术在管廊暗挖工程中安全数据监测方法
CN106681703A (zh) 一种可重用的界面组件构建***及方法
CN111476697A (zh) 一种智慧路网综合管理平台
Kenley et al. Location Breakdown Structure (LBS): a solution for construction project management data redundancy
CN110232469A (zh) 一种统筹法各类项目组织计划资源最少优化方法
Jia et al. Setting scheduled trip time based on AVL data
CN110232466A (zh) 一种统筹法各类项目组织计划资源均衡优化方法
Qiaolan et al. Civil engineering construction management based on BIM technology
Shivasami et al. Early implementation of BIM in large infrastructure projects to manage complex interfaces in a dense urban environment
Novikova et al. New technologies for utilization of associated petroleum gas in mature fields with no transport infrastructure
Trépanier et al. Democratized smartcard data for transit operator
Cameron et al. An environmental impact assessment for hydropower development in China
Liu et al. Application practice of code mapping technology in hydropower project construction management system
CN111985833B (zh) 一种页岩气压裂工程智能调度方法及***
Sander et al. CEVP-RIAAT Process-Application of an Integrated Cost and Schedule Analysis
Shevchenko et al. Challenges and threats for Ukraine airports caused by the global pandemic
Dara et al. Complexities in Metrorail Project-A Case Study of Hyderabad Metro Rail

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170620

RJ01 Rejection of invention patent application after publication