CN106848938B - Cable testing bridge hangs installation method under a kind of High Altitude Platform - Google Patents

Cable testing bridge hangs installation method under a kind of High Altitude Platform Download PDF

Info

Publication number
CN106848938B
CN106848938B CN201710085878.3A CN201710085878A CN106848938B CN 106848938 B CN106848938 B CN 106848938B CN 201710085878 A CN201710085878 A CN 201710085878A CN 106848938 B CN106848938 B CN 106848938B
Authority
CN
China
Prior art keywords
bridge
springboard
installation
crane span
span structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710085878.3A
Other languages
Chinese (zh)
Other versions
CN106848938A (en
Inventor
王新成
倪淑梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710085878.3A priority Critical patent/CN106848938B/en
Publication of CN106848938A publication Critical patent/CN106848938A/en
Application granted granted Critical
Publication of CN106848938B publication Critical patent/CN106848938B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses cable testing bridges under a kind of High Altitude Platform to hang installation method, making including mobile platform and installation, the installation of crane span structure, springboard, the laying of safety rope, cable laying and subsequently dismounting and etc., mobile platform includes steel tube poles, crossbeam, springboard and right-angle coupler, steel tube poles include left upright bar, right upright bar, according to construction drawing field surveys crane span structure installation site, the left upright bar, right upright bar and the connection of cross bar are connected using steel pipe right angle fastener, and the lifting lug of left upright bar, right upright bar and upper end is connected by screw bolts, easy to demolition;Using the method for the present invention construction can safe efficient facility, guarantee the quality complete crane span structure installation and crane span structure inner cable laying construction task, save full hall scaffold rental charge;The method of the present invention solves the awkward situation of conventional installation methods long-time active channel, the advantages that having easy for installation, safe operation, reduce construction cost, and be not take up channel.

Description

Cable testing bridge hangs installation method under a kind of High Altitude Platform
Technical field
The invention belongs to architectural engineering construction technique fields, more particularly, to cable testing bridge hanging peace under a kind of High Altitude Platform Dress method.
Background technology
It is high to smelt engineering steelshop steel-structure factory building, technique platform level is more, and crane span structure installation difficulty is big, and especially first Layer converter platform, is usually 8~11 meters away from ground level, and the cable testing bridge hanging installation generally use under platform sets up landing steel Pin hand cradle sets up manual operation mounting platform, and standing time is long after scaffold building, waits until that crane span structure inner cable has been laid always And can be removed after installing bridge cover plate, scaffold leasing period is long, and occupancy construction channel time is long, makees to other constructions It is unfavorable that industry is brought, and increases construction cost.
Invention content
The technical problem to be solved by the present invention is to overcome the existing defects, provides cable testing bridge under a kind of High Altitude Platform and hangs Installation method, being capable of safe efficient facility, the guarantee the quality installation of completion crane span structure and the laying of crane span structure inner cable using the method for the present invention construction Construction task, save full hall scaffold rental charge;Steelshop ground construction space is narrow, and professional more, material is installed in workshop Material heap is put and engineering equipment temporary storage space is squeezed, and ground space seems especially precious in workshop, the method for the present invention It solves the awkward situation of conventional installation methods long-time active channel, there is easy for installation, safe operation, reduce construction cost, and The advantages that being not take up channel.
To achieve the above object, cable testing bridge hangs installation method under a kind of High Altitude Platform of present invention offer, including following Step:
A. according to steel smelting platform lower edge clear height from the ground, mobile platform is made;Mobile platform include steel tube poles, crossbeam, Springboard and right-angle coupler, steel tube poles include left upright bar, right upright bar, and foundation construction drawing field surveys crane span structure installation site is described Left upright bar, right upright bar and the connection of cross bar are connected using steel pipe right angle fastener, and the lifting lug of left upright bar, right upright bar and upper end uses spiral shell It tethers and connects, it is easy to demolition;
B. using mobile platform welded at one installation two steel tube poles, then with right-angle coupler cross bar respectively at two Steel tube poles connect, and form a U-typed frame;Along crane span structure installation direction a set of U-typed frame is filled at interval of 1.5 meter amperes;
C. it is laid with springboard for the first time, is being close to steel tube poles and cross bar connection place is laid side by side springboard, springboard and cross bar connect Contact portion position 10# iron wires bind secured;
D. tensioning side safety rope is tensioned 6 galvanized steel wire rope of ∮ on the inside of steel tube poles along crane span structure installation direction, Height is 1.2 meters from springboard;
E. it stands on mounted springboard, first distinguishes erection bridge column at the both ends of crane span structure, continue to pacify after tensioning chalk line Fill remaining bridge upright, then erection bridge trailing arm, stretch tight chalk line in bridge bracket arm mounting height, to the height of every place's bridge bracket arm into Row adjustment;
F. it is laid with springboard second, after installation is complete in all bridge bracket arms, removes springboard binding wire, move horizontally Springboard to the side of bridge bracket arm, springboard with beam contact at fastened with 10# iron wire plates solid, be easily installed cable testing bridge;It stands On springboard after movement, in the inside tensioning galvanized steel wire rope of steel tube poles, it is ready for safety installation cable testing bridge;
G. it after the completion of cable testing bridge is fixedly mounted, waits for that crane span structure inner cable has been laid, after bridge cover plate is installed, utilizes shifting Moving platform successively removes springboard, cross bar, finally removes steel tube poles with gas cutting.
As a preferred technical solution of the present invention, the width of U-typed frame calculates, B=crane span structure width+cable laying Walkway width+bridge upright weld job space length.
As a preferred technical solution of the present invention, cable laying walkway width is 600mm, bridge upright Weld job space length is 200mm.
As a preferred technical solution of the present invention, the clipping room of U-typed frame is away from being 1.5 meters, according to straightway crane span structure Column welding installation, every 1.5 meter ampere of code requirement fill column at one, here crane span structure jointing;U-typed frame and bridge upright At one, there are one supporting points when welding in the overhead position bridge upright by construction personnel.
As a preferred technical solution of the present invention, the left upright bar, right upright bar and cross bar are ∮ 48 × 3.5mm steel Pipe is made.
As a preferred technical solution of the present invention, the lifting lug is processed with 120 × 120mm square 12mm steel plates It forms, there is the drilling of a diameter of 14mm at center.
Compared with prior art, the beneficial effects of the invention are as follows:
It being capable of safe efficient facility, the guarantee the quality installation of completion crane span structure and the laying of crane span structure inner cable using the method for the present invention construction Construction task, save full hall scaffold rental charge it is hundreds thousand of;Steelshop ground construction space is narrow, and profession is installed in workshop More, placing of material and engineering equipment temporary storage space are squeezed, and ground space seems especially precious in workshop, the present invention Method solves the awkward situation of conventional installation methods long-time active channel.
Description of the drawings
Fig. 1 is mounting structure schematic diagram of the present invention.
In figure:1-1, left upright bar;1-2, right upright bar 2, cross bar;3, bridge upright;4, bridge bracket arm;5, cable testing bridge;6、 Springboard;7, galvanized steel wire rope;8, lifting lug;9, bolt.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution:11.5 meters of converter platforms of certain steel mill, construction drawing requirement The crane span structure of two layers of 600mm width of hanging installation, every converter 1 arrange under platform, total 3 row of 3 converters;Across charging across and converter Across 1 48 meters of row amount to 144 meters of length.It has been laid to crane span structure inner cable since being installed crane span structure, has about needed 5 months.
It is identical that crane span structure installation method is hung under the three row platform, it is specific as follows:
A. converter platform beam lower edge 11.25 meters of clear height from the ground make 9.6 meters of highly mobile platforms;It is existing according to construction drawing The field specific mounting coordinate of mapping crane span structure;Prepare the springboard 6 of 48 × 3.5 steel pipes of ∮, right-angle coupler and 200 × 3000 specifications;
B., mobile platform is installed, left upright bar 1-1, right upright bar 1-2 hanging at drilling and the lifting lug 8 of upper end use spiral shell respectively Bolt 9 is connected and fixed, and the connection of left upright bar 1-1, right upright bar 1-2 and cross bar 2 are connected using steel pipe right angle fastener, are installed along crane span structure Direction fills a set of U-typed frame at interval of 1.5 meter amperes, considers crane span structure width 600mm, crane span structure after installation is complete walkway width it is pre- 600mm is stayed, in addition the clipping room of left upright bar 1-1 and bridge upright 3 is away from terms of 200mm, such U-typed width of frame amounts to 1400mm;Height is considered with the average height 1700mm of people;
C. it is laid with springboard 6 for the first time, is being close to left upright bar 1-1 and 2 connection place of cross bar is laid side by side springboard 6, springboard 6 and cross 2 contact site of bar 10# iron wires are bound securely, and welding erection bridge column 3 and bolt 9 fasten bridge bracket arm 4 with this position Springboard 6;
D. tensioning side safety rope is tensioned 6 galvanized steel wire rope of ∮ on the inside of left upright bar 1-1 along crane span structure installation direction 7, highly for 1.2 meters with a distance from springboard 6, welding erection bridge column 3 and bolt 9 fasten bridge bracket arm 4, and construction personnel uses this Locate galvanized steel wire rope 7 and hangs safety belt;
E. it stands on mounted springboard 6, first continues after the both ends of crane span structure difference erection bridge column 3, tensioning chalk line Remaining bridge upright 3, then erection bridge trailing arm 4 are installed, in the taut chalk line of 4 mounting height of bridge bracket arm, to every place's bridge bracket arm 4 Height is adjusted;
F. it is laid with springboard 6 second, after installation is complete in all bridge bracket arms 4, removes 6 binding wire of springboard, it is horizontal Springboard 6 move right to the side of bridge bracket arm 4, springboard 6 is being fastened admittedly with 10# iron wire plates with 2 contact position of cross bar, is being easily installed Cable testing bridge 5, on the springboard 6 stood after movement, in the inside tensioning galvanized steel wire rope 7 of steel tube poles, for safety installation cable Crane span structure 5 is ready;
G. it after the completion of cable testing bridge 5 is fixedly mounted, waits for that crane span structure inner cable has been laid, after bridge cover plate is installed, utilizes Mobile platform successively removes springboard 6, cross bar 2, finally removes steel tube poles, that is, left upright bar 1-1 and right upright bar 1-2.
It being capable of safe efficient facility, the guarantee the quality installation of completion crane span structure and the laying of crane span structure inner cable using the method for the present invention construction Construction task, it is hundreds thousand of full hall scaffold rental charge can be saved according to above-described embodiment quantities;Steelshop ground Construction space is narrow, and professional more, placing of material is installed in workshop and engineering equipment temporary storage space is squeezed, in workshop Ground space seems especially precious, and the method for the present invention solves the awkward situation of conventional installation methods long-time active channel.Although Through the embodiment of the present invention has shown and described, for the ordinary skill in the art, it is possible to understand that do not departing from this Can these embodiments be carried out with a variety of change, modification, replacement and modification in the case of the principle and spirit of invention, it is of the invention Range is defined by the appended claims and the equivalents thereof.

Claims (3)

1. cable testing bridge hangs installation method under a kind of High Altitude Platform, it is characterised in that include the following steps:
A. according to steel smelting platform lower edge clear height from the ground, mobile platform is made;The mobile platform include steel tube poles, crossbeam, Springboard and right-angle coupler, the steel tube poles include left upright bar, right upright bar, according to construction drawing field surveys crane span structure installation site, The left upright bar, right upright bar and the connection of cross bar are connected using steel pipe right angle fastener, and the lifting lug of left upright bar, right upright bar and upper end is adopted It is connected with, it is easy to demolition;
B. using mobile platform welded at one installation two steel tube poles, then with right-angle coupler cross bar respectively at two steel pipes Upright bar connects, and forms a U-typed frame;Along crane span structure installation direction a set of U-typed frame is filled at interval of 1.5 meter amperes;U-typed frame Width calculates, B=crane span structure width+cable laying walkway width+bridge upright weld job space length;The cable applies If walkway width is 600mm, bridge upright weld job space length is 200mm;The clipping room of U-typed frame is away from being 1.5 Rice, according to the welding installation of straightway bridge upright, every 1.5 meter ampere of code requirement fills column at one, here crane span structure jointing; U-typed frame and bridge upright are at one, and there are one supporting points when welding in the overhead position bridge upright by construction personnel;
C. it is laid with springboard for the first time, is being close to steel tube poles and cross bar connection place is laid side by side springboard, springboard and beam contact portion Position is secured with the binding of 10# iron wires;
D. tensioning side safety rope is tensioned 6 galvanized steel wire rope of ∮, height on the inside of steel tube poles along crane span structure installation direction It is 1.2 meters from springboard;
E. it stands on mounted springboard, first distinguishes erection bridge column at the both ends of crane span structure, after tensioning chalk line continue that it is installed Remaining bridge upright, then erection bridge trailing arm adjust the height of every place's bridge bracket arm in the taut chalk line of bridge bracket arm mounting height It is whole;
F. it is laid with springboard second, after installation is complete in all bridge bracket arms, removes springboard binding wire, move horizontally springboard To the side of bridge bracket arm, springboard with beam contact at fastened with 10# iron wire plates solid, be easily installed cable testing bridge;It stands and is moving On springboard after dynamic, in the inside tensioning galvanized steel wire rope of steel tube poles, it is ready for safety installation cable testing bridge;
G. it after the completion of cable testing bridge is fixedly mounted, waits for that crane span structure inner cable has been laid, after bridge cover plate is installed, is put down using mobile Platform successively removes springboard, cross bar, finally removes steel tube poles with gas cutting.
2. hanging installation method according to cable testing bridge under a kind of High Altitude Platform described in claim 1, it is characterised in that:It is described left vertical Bar, right upright bar and cross bar are that ∮ 48 × 3.5mm steel pipe manufacturings form.
3. hanging installation method according to cable testing bridge under a kind of High Altitude Platform described in claim 1, it is characterised in that:The lifting lug is used 120 × 120mm square 12mm steel plates are process, and there is the drilling of a diameter of 14mm at center.
CN201710085878.3A 2017-02-17 2017-02-17 Cable testing bridge hangs installation method under a kind of High Altitude Platform Active CN106848938B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710085878.3A CN106848938B (en) 2017-02-17 2017-02-17 Cable testing bridge hangs installation method under a kind of High Altitude Platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710085878.3A CN106848938B (en) 2017-02-17 2017-02-17 Cable testing bridge hangs installation method under a kind of High Altitude Platform

Publications (2)

Publication Number Publication Date
CN106848938A CN106848938A (en) 2017-06-13
CN106848938B true CN106848938B (en) 2018-08-21

Family

ID=59128443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710085878.3A Active CN106848938B (en) 2017-02-17 2017-02-17 Cable testing bridge hangs installation method under a kind of High Altitude Platform

Country Status (1)

Country Link
CN (1) CN106848938B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109494625A (en) * 2018-10-24 2019-03-19 中国二十冶集团有限公司 The installation method of cable testing bridge
CN109650276A (en) * 2018-12-31 2019-04-19 宁波二十冶建设有限公司 A kind of multi-layer cable gantry more changing device and construction method
CN109888698A (en) * 2019-04-12 2019-06-14 枣庄矿业集团新安煤业有限公司 Inverted T shaped cable trough
CN111446663B (en) * 2020-04-29 2020-11-24 山东颐德电气设备工程有限公司 High altitude cable removes auxiliary device
CN112242678B (en) * 2020-09-23 2022-01-18 安徽华希电力科技有限公司 Fastening device for glass fiber reinforced plastic cable bridge cover plate
CN115864215B (en) * 2022-11-21 2023-08-15 国网湖北省电力有限公司荆州供电公司 Cable bridge hanging and installing equipment and method under high-altitude platform

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251679B (en) * 2011-05-10 2015-04-22 中广核工程有限公司 Construction method
CN203082364U (en) * 2012-12-14 2013-07-24 中国二十冶集团有限公司 Support for cabling of overhead bridge frame
CA2902633C (en) * 2013-04-05 2019-04-16 Rolando S. Garcia A cabled pipe rack
CN203411226U (en) * 2013-07-29 2014-01-29 沈阳市华域建筑设计有限公司 Common lifting device for cable bridge and vent pipeline
CN103628918B (en) * 2013-12-06 2015-12-09 中铁二十三局集团有限公司 Highway tunnel illumination engineering construction method
CN104065006A (en) * 2014-06-26 2014-09-24 镇江市江岛电器制造有限公司 Cable bridge installation method
CN104089090A (en) * 2014-07-08 2014-10-08 江苏海纬集团有限公司 Cable tray installation requirements
CN204609266U (en) * 2015-04-20 2015-09-02 中建安装工程有限公司 A kind of Mobile operating platform for the construction of piping lane comprehensive pipeline

Also Published As

Publication number Publication date
CN106848938A (en) 2017-06-13

Similar Documents

Publication Publication Date Title
CN106848938B (en) Cable testing bridge hangs installation method under a kind of High Altitude Platform
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN101435276B (en) Hydraulic lifting and positioning device for steel beam at top of silo structure and construction method thereof
CN100590277C (en) Overhead bridge type suspension scaffold
CN104088467B (en) A kind of large Steel Cantilever truss structure high-altitude construction Deformation monitoring method
CN103882813B (en) For calf support platform and the building method thereof of bridge pier and straining beam synchronous construction
CN105003090B (en) Temporary support frame for mounting assembly type steel structure
CN210066507U (en) Combined high pier capping beam construction support
CN103993735A (en) Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN106193098A (en) For reinforcing the base structure of lowering or hoisting gear
CN105317205B (en) The construction method and equipment therefor of a kind of elevator
CN104100090A (en) High-altitude comprehensive construction method of big-cantilever steel truss structure
CN114086771A (en) Steel column installation process
CN104481194A (en) Reversed assembling method of upright cylindrical equipment
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN103114754A (en) Alternative hoisting method for conjoined coal bunker top truss girder pre-placing
CN202214974U (en) 5.8 m ultrahigh external climbing frame
CN105951599B (en) High column mould bases integrated construction technique
CN109083395B (en) Large-span suspension cable operation platform and erecting method thereof
CN107217912B (en) A kind of superelevation physical isolation construction method for neighbouring high-speed rail Business Line construction
CN111236603A (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN106836949B (en) Large scale equipment rotary construction method
CN113738125B (en) Construction method for lifting limited-space large-span steel structure of station house under line
CN111608377B (en) Comprehensive construction method for building overhanging scaffold
CN209723570U (en) Steel column docking installation operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant