CN106787187A - A kind of current misdelivery proof method - Google Patents
A kind of current misdelivery proof method Download PDFInfo
- Publication number
- CN106787187A CN106787187A CN201611177357.2A CN201611177357A CN106787187A CN 106787187 A CN106787187 A CN 106787187A CN 201611177357 A CN201611177357 A CN 201611177357A CN 106787187 A CN106787187 A CN 106787187A
- Authority
- CN
- China
- Prior art keywords
- maintenance
- systems
- oms
- power system
- management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000012423 maintenance Methods 0.000 claims abstract description 68
- 230000005540 biological transmission Effects 0.000 claims abstract description 30
- 230000005611 electricity Effects 0.000 claims abstract description 20
- 238000006243 chemical reaction Methods 0.000 claims description 3
- 238000012544 monitoring process Methods 0.000 claims 1
- 238000007689 inspection Methods 0.000 description 4
- 241001269238 Data Species 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 210000004556 brain Anatomy 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- H02J13/0017—
Landscapes
- Stand-By Power Supply Arrangements (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of current misdelivery proof method, it is related to power Transmission technical field, be associated for management and running OMS and power system monitor D5000 systems by the present invention, when there is transmission line of electricity to need maintenance, the number for needing maintenance point according to circuit handles corresponding work ticket by management and running OMS, by in the information transmission of all maintenance points to power system monitor D5000 systems, power system monitor D5000 systems indicate corresponding maintenance board to management and running OMS according to the information of maintenance point in corresponding circuit;When certain maintenance point completes maintenance, work ticket corresponding with the maintenance point is cancelled by management and running OMS, then maintenance point completion service information is sent in power system monitor D5000 systems by management and running OMS, power system monitor D5000 systems cancel the maintenance board corresponding with work ticket automatically;When needed in power system monitor D5000 systems maintenance circuit there is no maintenance board when the circuit could be powered, by the design of this kind of method can prevent to misdeliver electricity the occurrence of.
Description
Technical field
The present invention relates to power Transmission technical field, more particularly to a kind of current misdelivery proof method.
Background technology
When transmission line of electricity needs maintenance, regulation and control person needs to carry out stopping power transmission operation, but usual circuit needs are more
Place needs maintenance, and each maintenance point is required to handle a work ticket, so that the circuit of same needs maintenance has many Zhang Gongs
Make the situation of ticket, to ensure safety, it is necessary to could carry out power transmission to circuit after the completion of all working ticket.
At present, handle work ticket be in management and running OMS, and power system monitor be use power system monitor D5000 systems.
One circuit handles multiple work tickets, and on power system monitor D5000 system interfaces, can only hang a maintenance warning sign, it is impossible to
Number with work ticket is corresponding, and is all manually to check work ticket and work one by one in OMS by regulation and control person before power transmission
Daily record, checks whether that all working ticket has all been completed;If after due to carelessness wherein a work ticket completion, having removed maintenance
Warning sign, will miss other work tickets being carrying out, and cause misdelivery electricity, be caused very to the person, power network and equipment safety
Big potential safety hazard.
The content of the invention
The technical problem to be solved in the present invention is directed to above-mentioned the deficiencies in the prior art, there is provided a kind of current misdelivery proof method,
Solve the problems, such as to cause misdelivery electricity because work ticket is not corresponding with maintenance board, corresponded with maintenance board with work ticket, prevent
The characteristics of misdelivering electric after maintenance.
In order to solve the above technical problems, the technical solution used in the present invention is:A kind of current misdelivery proof method, scheduling is managed
Reason OMS and power system monitor D5000 systems are associated, and specific works are comprised the following steps:
(1)When transmission line of electricity needs maintenance, the quantity overhauled on demand a little handles more than one work by management and running OMS
Make ticket;
(2)Management and running OMS is sent to multi-line power transmission information is overhauled in power system monitor D5000 systems, power system monitor
D5000 systems are indicated on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(3)When transmission line of electricity completes to overhaul, said one above work ticket is cancelled by management and running OMS;
(4)Be sent to line maintenance completion information in power system monitor D5000 systems by management and running OMS, power system monitor
D5000 systems are cancelled on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(5)When the system interface circuit in power system monitor D5000 systems does not overhaul board, this circuit can carry out power transmission.
Preferably, management and running OMS and power system monitor D5000 systems are arranged on same computer.
Preferably, management and running OMS data carry out real-time update according to the foundation of maintenance point and performance.
Preferably, power system monitor D5000 system datas are carried out in real time more according to management and running OMS data conversion
Newly.
Preferably, overhauled on the transmission line of electricity of system interface in power system monitor D5000 systems after board has all been cancelled and first sent out
Go out indicating alarm, then power transmission.
Preferably, indicating alarm includes that power system monitor D5000 system interfaces are pointed out and auditory tone cues.
It is using the beneficial effect produced by above-mentioned technical proposal:The present invention supervises management and running OMS and power network
Control D5000 systems are associated, and when there is transmission line of electricity to need maintenance, staff first powers off the circuit, then basis
The circuit needs the number of maintenance point to handle corresponding work ticket by management and running OMS, one inspection of each work ticket correspondence
Repair a little, in the information transmissions that management and running OMS puts all maintenance to power system monitor D5000 systems, power system monitor D5000
System indicates corresponding maintenance board, one maintenance board of each work ticket correspondence according to the information of maintenance point in corresponding circuit;When
When certain maintenance point completes maintenance, work ticket corresponding with the maintenance point is cancelled by management and running OMS, then managed by scheduling
Be sent to maintenance point completion service information in power system monitor D5000 systems by reason OMS, and power system monitor D5000 systems are certainly
The dynamic revocation maintenance board corresponding with work ticket;When the circuit for needing to overhaul in power system monitor D5000 systems is there is no maintenance board
Shi Caineng is powered to the circuit, by the design of this kind of method, overhauls point and work ticket one-to-one corresponding, work ticket and maintenance
Board is corresponded, clearly directly perceived, sets up line maintenance point correspondence sign maintenance board simultaneously, when maintenance point completes maintenance, revocation inspection
Board is repaiied, illustrates that all maintenance points of the circuit have completed maintenance when circuit does not overhaul board, then carry out normal power-up, it is this kind of
Method can prevent to misdeliver electricity the occurrence of.
Brief description of the drawings
Fig. 1 is flow chart of the invention.
Specific embodiment
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description.
As shown in figure 1, being a kind of flow chart of current misdelivery proof method of the invention, a kind of current misdelivery proof method manages scheduling
Reason OMS and power system monitor D5000 systems are associated, and specific works are comprised the following steps:
(1)When transmission line of electricity needs maintenance, the quantity overhauled on demand a little handles more than one work by management and running OMS
Make ticket;
(2)Management and running OMS is sent to multi-line power transmission information is overhauled in power system monitor D5000 systems, power system monitor
D5000 systems are indicated on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(3)When transmission line of electricity completes to overhaul, said one above work ticket is cancelled by management and running OMS;
(4)Be sent to line maintenance completion information in power system monitor D5000 systems by management and running OMS, power system monitor
D5000 systems are cancelled on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(5)When the system interface circuit in power system monitor D5000 systems does not overhaul board, this circuit can carry out power transmission.
The management and running OMS and power system monitor D5000 systems are arranged on same computer, installed in same electricity
Economized on resources on brain, while observation more intuitive and convenient.
The management and running OMS data carry out real-time update according to the foundation of maintenance point and performance.
The power system monitor D5000 system datas carry out real-time update according to management and running OMS data conversion.
Overhaul first to be sent after board has all been cancelled on the transmission line of electricity of system interface in the power system monitor D5000 systems and carry
Warn report, then power transmission.
The indicating alarm includes that power system monitor D5000 system interfaces are pointed out and auditory tone cues.
It is using the beneficial effect produced by above-mentioned technical proposal:The present invention supervises management and running OMS and power network
Control D5000 systems are associated, and when there is transmission line of electricity to need maintenance, staff first powers off the circuit, then basis
The circuit needs the number of maintenance point to handle corresponding work ticket by management and running OMS, one inspection of each work ticket correspondence
Repair a little, in the information transmissions that management and running OMS puts all maintenance to power system monitor D5000 systems, power system monitor D5000
System indicates corresponding maintenance board, one maintenance board of each work ticket correspondence according to the information of maintenance point in corresponding circuit;When
When certain maintenance point completes maintenance, work ticket corresponding with the maintenance point is cancelled by management and running OMS, then managed by scheduling
Be sent to maintenance point completion service information in power system monitor D5000 systems by reason OMS, and power system monitor D5000 systems are certainly
The dynamic revocation maintenance board corresponding with work ticket;When the circuit for needing to overhaul in power system monitor D5000 systems is there is no maintenance board
Shi Caineng is powered to the circuit, by the design of this kind of method, overhauls point and work ticket one-to-one corresponding, work ticket and maintenance
Board is corresponded, clearly directly perceived, sets up line maintenance point correspondence sign maintenance board simultaneously, when maintenance point completes maintenance, revocation inspection
Board is repaiied, illustrates that all maintenance points of the circuit have completed maintenance when circuit does not overhaul board, then carry out normal power-up, it is this kind of
Method can prevent to misdeliver electricity the occurrence of.
Presently preferred embodiments of the present invention is the foregoing is only, is not intended to limit the invention, it is all in essence of the invention
Any modification, equivalent and improvement made within god and principle etc., should be included within the scope of the present invention.
Claims (6)
1. a kind of current misdelivery proof method, it is characterised in that:Management and running OMS and power system monitor D5000 systems are closed
Connection, specific works are comprised the following steps:
(1)When transmission line of electricity needs maintenance, the quantity overhauled on demand a little handles more than one work by management and running OMS
Make ticket;
(2)Management and running OMS is sent to multi-line power transmission information is overhauled in power system monitor D5000 systems, power system monitor
D5000 systems are indicated on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(3)When transmission line of electricity completes to overhaul, said one above work ticket is cancelled by management and running OMS;
(4)Be sent to line maintenance completion information in power system monitor D5000 systems by management and running OMS, power system monitor
D5000 systems are cancelled on the corresponding circuit of system interface overhauls board correspondingly with said one above work ticket;
(5)When the system interface circuit in power system monitor D5000 systems does not overhaul board, this circuit can carry out power transmission.
2. a kind of current misdelivery proof method according to claim 1, it is characterised in that:The management and running OMS and electricity
Net monitoring D5000 systems are arranged on same computer.
3. a kind of current misdelivery proof method according to claim 1, it is characterised in that:The management and running OMS data
Foundation and performance according to maintenance point carry out real-time update.
4. a kind of current misdelivery proof method according to claim 1, it is characterised in that:The power system monitor D5000 system numbers
Real-time update is carried out according to according to management and running OMS data conversion.
5. a kind of current misdelivery proof method according to claim 1, it is characterised in that:In the power system monitor D5000 systems
Overhauled on the transmission line of electricity of system interface after board has all been cancelled and first send indicating alarm, then power transmission.
6. a kind of current misdelivery proof method according to claim 5, it is characterised in that:The indicating alarm includes power system monitor
D5000 system interfaces are pointed out and auditory tone cues.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611177357.2A CN106787187B (en) | 2016-12-19 | 2016-12-19 | A kind of current misdelivery proof method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611177357.2A CN106787187B (en) | 2016-12-19 | 2016-12-19 | A kind of current misdelivery proof method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106787187A true CN106787187A (en) | 2017-05-31 |
CN106787187B CN106787187B (en) | 2019-04-23 |
Family
ID=58889779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611177357.2A Active CN106787187B (en) | 2016-12-19 | 2016-12-19 | A kind of current misdelivery proof method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106787187B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008269023A (en) * | 2007-04-16 | 2008-11-06 | Chugoku Electric Power Co Inc:The | Operation target reporting system and operation target reporting server |
CN101697400A (en) * | 2009-10-26 | 2010-04-21 | 华北电网有限公司北京十三陵蓄能电厂 | Method for preventing accident of cross operation by five-prevention shutting system |
CN102065284A (en) * | 2010-12-29 | 2011-05-18 | 广东电网公司电力科学研究院 | Method and system for realizing visualized operation of power grid |
CN201937334U (en) * | 2010-12-01 | 2011-08-17 | 许继集团有限公司 | Centralized type protecting, overhauling and mistaken-operation-preventing system |
CN104851052A (en) * | 2015-04-02 | 2015-08-19 | 国网山东省电力公司青岛供电公司 | Intelligent error preventing method and system used for outputting dispatching operation ticket |
CN205160208U (en) * | 2015-11-11 | 2016-04-13 | 云南电网有限责任公司玉溪供电局 | Power dispatching prevents maloperation ticket system |
CN106059090A (en) * | 2016-07-20 | 2016-10-26 | 国网江苏省电力公司扬州供电公司 | Prompt system based on scheduling automation system and work method thereof |
-
2016
- 2016-12-19 CN CN201611177357.2A patent/CN106787187B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008269023A (en) * | 2007-04-16 | 2008-11-06 | Chugoku Electric Power Co Inc:The | Operation target reporting system and operation target reporting server |
CN101697400A (en) * | 2009-10-26 | 2010-04-21 | 华北电网有限公司北京十三陵蓄能电厂 | Method for preventing accident of cross operation by five-prevention shutting system |
CN201937334U (en) * | 2010-12-01 | 2011-08-17 | 许继集团有限公司 | Centralized type protecting, overhauling and mistaken-operation-preventing system |
CN102065284A (en) * | 2010-12-29 | 2011-05-18 | 广东电网公司电力科学研究院 | Method and system for realizing visualized operation of power grid |
CN104851052A (en) * | 2015-04-02 | 2015-08-19 | 国网山东省电力公司青岛供电公司 | Intelligent error preventing method and system used for outputting dispatching operation ticket |
CN205160208U (en) * | 2015-11-11 | 2016-04-13 | 云南电网有限责任公司玉溪供电局 | Power dispatching prevents maloperation ticket system |
CN106059090A (en) * | 2016-07-20 | 2016-10-26 | 国网江苏省电力公司扬州供电公司 | Prompt system based on scheduling automation system and work method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106787187B (en) | 2019-04-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202231491U (en) | Power distribution monitoring system | |
CN106655523A (en) | Smart electric service system | |
CN108898255A (en) | One kind is based on the twinborn intelligence community O&M supervisory control simulation cloud platform of digitlization | |
CN206584222U (en) | A kind of supercentral station's centralized monitoring system | |
CN107545519B (en) | Power grid enterprise operation and inspection management and control method | |
CN112508384B (en) | Visual automatic monitoring equipment and method for power dispatching operation ticket | |
CN205983124U (en) | Comprehensive supervision system | |
CN203466628U (en) | Intelligent electric power monitoring system having three-dimensional view | |
CN108596782A (en) | Large-area power failure data rapid intercommunication method | |
CN110018378B (en) | Fault studying and judging method for distributing different transformers of same overhead line by multiple repair work orders | |
CN107832857A (en) | A kind of low-voltage network system of smart city | |
CN205139686U (en) | Intelligent building equipment control system | |
CN106787187A (en) | A kind of current misdelivery proof method | |
Peng et al. | Design and development of intelligent operation and maintenance training system for substation based on augmented reality | |
CN107122834B (en) | Intelligent order dispatching system and method | |
CN206234966U (en) | The cloud control system of air-conditioning | |
CN204496268U (en) | A kind of digital integration remote training fault diagnosis system of production system | |
CN107301606A (en) | A kind of energy management monitoring system | |
CN107045315A (en) | A kind of Monitoring and Control System for Hydropower Station and method | |
CN108303956B (en) | Automatic on-duty centralized monitoring system for power grid dispatching | |
CN102437526A (en) | Rapid repairing and integral dispatching system of power grid | |
CN209046364U (en) | Power fault analysis and orientation management system based on NB-IoT | |
CN203038094U (en) | Chemical production safety monitoring device | |
CN202634080U (en) | Remote maintenance system for substation automation system | |
CN203149055U (en) | Substation integrated monitoring system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |