CN106758837A - 一种结合拱上立柱的斜拉扣挂施工*** - Google Patents

一种结合拱上立柱的斜拉扣挂施工*** Download PDF

Info

Publication number
CN106758837A
CN106758837A CN201611211319.4A CN201611211319A CN106758837A CN 106758837 A CN106758837 A CN 106758837A CN 201611211319 A CN201611211319 A CN 201611211319A CN 106758837 A CN106758837 A CN 106758837A
Authority
CN
China
Prior art keywords
tower
arch
cable
bridge pier
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611211319.4A
Other languages
English (en)
Other versions
CN106758837B (zh
Inventor
黄欣
阎树欣
袁帅
郭琪
赵静波
周意咏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201611211319.4A priority Critical patent/CN106758837B/zh
Publication of CN106758837A publication Critical patent/CN106758837A/zh
Application granted granted Critical
Publication of CN106758837B publication Critical patent/CN106758837B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种结合拱上立柱的斜拉扣挂施工***,适合跨度大、杆件重量大和地形条件复杂情况下的钢桁架拱桥施工。所述的斜拉扣挂体系包括:扣索、锚索、锚碇、主扣塔、辅助扣塔、拱上立柱、交界桥墩、辅助桥墩、拱座和拱肋。本发明介绍的施工方法能高效的解决所要求条件下钢桁架拱桥的施工问题,有效的缩短了工期,显著节约了施工成本。

Description

一种结合拱上立柱的斜拉扣挂施工***
技术领域
本发明涉及一种结合拱上立柱的斜拉扣挂施工***,该***适用于跨度大、杆件重量大和地形条件复杂情况下的钢桁架拱桥施工。
背景技术
桥梁工程中传统的施工方法可分为:支架法、转体法和扣挂法。在跨度大、地形条件复杂(如:跨越河流等)情况下,支架法不再适用。在桥梁整体重量较大、地形上不具备装备的条件下,转体法也很难实现。在杆件重量很大的情况下,若采用传统的扣挂法,将临时提升的交界桥墩作为扣塔,其受力相对集中,承载力很难满足工程需要;由于桥墩布置情况和地形限制,通常也很难实现拱脚处几节拱肋的斜拉扣挂;并且传统的斜拉扣挂法且需在交界桥墩完工后才可进行主拱圈的悬臂拼装,会影响施工工期。因此,现有的传统施工方法无法高效的满足跨度大、杆件重量大和地形条件复杂情况下钢桁架拱桥的施工。
发明内容
本发明的目的在于提供一种结合拱上立柱的斜拉扣挂施工***,解决了在跨度大、杆件重量大和地形条件复杂情况下的钢桁架拱桥斜拉扣挂悬臂拼装和合拢问题,可以保证工程经济、高效、安全的施工,并且能较大程度地缩短工期。
为了实现上述目的,本发明通过以下的技术方案予以实现:
一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述斜拉扣挂***包含扣索***、扣塔***和锚索***,扣索***和锚索***均与扣塔***连接。扣塔***分为主扣塔***和辅助扣塔***。主扣塔为主扣塔***的拉伸结构,辅助扣塔***包括辅助扣塔和拱上立柱。
所述扣索***将扣索通过扣点与吊装的构件连接。
所述锚索***包括锚索、锚碇和拱座,用于平衡扣索的水平力。
所述主扣塔为安装在交界桥墩上的扣塔,承担该***主要的竖向力。其中,交界桥墩为距主拱最近的桥墩。
所述辅助扣塔为安装在辅助桥墩上的扣塔,辅助桥墩为距交界桥墩较近的桥墩。
所述拱上立柱为拱肋上设置的临时立柱。
本发明的有益效果是:
本发明涉及的斜拉扣挂施工方法对扣塔***做出了一定的改进,将其分为由主扣塔构成的主扣塔***与由辅助扣塔和拱上立柱组成的辅助扣塔***。主扣塔和辅助扣塔的结合,分摊了扣挂***较大的竖向力,改善了扣塔和扣索的受力情况,减小了悬臂的主体拱肋产生的拱脚的压力和弯矩。拱上立柱的设置克服了桥墩布置情况和地形限制,实现了前几节拱肋的斜拉扣挂,很大程度的降低了悬臂钢拱桁架拱脚处的弯矩,保证了拱脚和整体桥梁施工过程中拱脚的安全。主扣塔的施工和拱肋的安装可同步进行,有效的缩短了工期。根据有限元分析结果实时调整各施工阶段的索力,高质量的控制了拱桥线性。
本发明通过将既有的桥墩和架设的拱上立柱形成的扣塔***与扣索***、锚索***相结合,高效的解决了跨度大、杆件重量大和地形条件复杂情况下钢桁架拱桥的施工问题,显著节约了施工的经济成本和时间成本,降低了施工过程中的安全风险,在桥梁施工领域具有较广阔的应用前景。
附图说明
图1是本发明具体实施方式的结构示意图。
图中:1、扣索 2、锚索 3、锚碇 4、主扣塔 5、辅助扣塔6、拱上立柱 7、交界桥墩 8、辅助桥墩 9、拱座 10、拱肋。
具体实施方式
下面结合附图对本发明的具体实施方式作进一步的详细描述:
从附图1中可知,主扣塔4和辅助扣塔5分别通过扣索1、锚索2与拱肋10、锚碇3连接。主扣塔4和辅助扣塔5分别设在交界桥墩7和辅助桥墩8上。拱上立柱6则分别通过扣索1、锚索2与肋10、拱座9连接。
利用本发明实施桥梁拱肋的安装时,可将其分为拱脚处拱肋的安装和主体拱肋的安装。拱脚处拱肋施工和扣塔的施工可同时进行。
对于拱脚处拱肋的安装,首先利用缆索吊完前两节拱肋的悬臂拼装,然后架设拱上立柱6,之后将拱上立柱6作为临时扣塔,通过扣索1与拱肋10连接、锚索2与拱座9连接,索力张拉后即可将拱肋固定,完成前几节段拱肋的悬臂拼装。
在辅助桥墩8和交界桥墩7上分别完成辅助扣塔5和主扣塔4的施工后,可进行主体拱肋的安装。首先将锚碇3通过锚索2逐段连接至辅助扣塔5或主扣塔4,辅助扣塔5或主扣塔4通过扣索1与中间节段或跨中节段的拱肋连接,然后按照设计位置张拉和调整索力,完成该节段拱肋的安装,之后重复此步骤即可完成剩余部分主体拱肋的悬臂拼装。
整体拱圈合拢后,将扣索1、锚索2、主扣塔4、辅助扣塔5和拱上立柱6拆除即可。

Claims (8)

1.一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述斜拉扣挂***包含扣索***、扣塔***和锚索***,扣索***和锚索***均与扣塔***连接;扣塔***分为主扣塔***和辅助扣塔***;主扣塔为主扣塔***的拉伸结构,辅助扣塔***包括辅助扣塔和拱上立柱。
2.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述扣索***将扣索通过扣点与吊装的构件连接。
3.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述锚索***包括锚索、锚碇和拱座,用于平衡扣索的水平力。
4.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述主扣塔为安装在交界桥墩上的扣塔,承担该***主要的竖向力;其中,交界桥墩为距主拱最近的桥墩。
5.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述辅助扣塔为安装在辅助桥墩上的扣塔,辅助桥墩为距交界桥墩较近的桥墩;。
6.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:所述拱上立柱为拱肋上设置的临时立柱。
7.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:
主扣塔(4)和辅助扣塔(5)分别通过扣索(1)、锚索(2)与拱肋(10)、锚碇(3)连接;主扣塔(4)和辅助扣塔(5)分别设在交界桥墩(7)和辅助桥墩(8)上;拱上立柱(6)分别通过扣索(1)、锚索(2)与肋(10)、拱座(9)连接。
8.根据权利要求1所述的一种结合拱上立柱的斜拉扣挂施工***,其特征在于:桥梁拱肋的安装时,将其分为拱脚处拱肋的安装和主体拱肋的安装;拱脚处拱肋施工和扣塔的施工可同时进行;
对于拱脚处拱肋的安装,首先利用缆索吊完前两节拱肋的悬臂拼装,然后架设拱上立柱(6),之后将拱上立柱(6)作为临时扣塔,通过扣索(1)与拱肋(10)连接、锚索(2)与拱座(9)连接,索力张拉后即可将拱肋固定,完成前几节段拱肋的悬臂拼装;
在辅助桥墩(8)和交界桥墩(7)上分别完成辅助扣塔(5)和主扣塔(4)的施工后,进行主体拱肋的安装;首先将锚碇(3)通过锚索(2)逐段连接至辅助扣塔(5)或主扣塔(4),辅助扣塔(5)或主扣塔(4)通过扣索(1)与中间节段或跨中节段的拱肋连接,然后按照设计位置张拉和调整索力,完成该节段拱肋的安装,之后重复此步骤即可完成剩余部分主体拱肋的悬臂拼装;
整体拱圈合拢后,将扣索(1)、锚索(2)、主扣塔(4)、辅助扣塔(5)和拱上立柱(6)拆除即可。
CN201611211319.4A 2016-12-24 2016-12-24 一种结合拱上立柱的斜拉扣挂施工*** Active CN106758837B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611211319.4A CN106758837B (zh) 2016-12-24 2016-12-24 一种结合拱上立柱的斜拉扣挂施工***

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611211319.4A CN106758837B (zh) 2016-12-24 2016-12-24 一种结合拱上立柱的斜拉扣挂施工***

Publications (2)

Publication Number Publication Date
CN106758837A true CN106758837A (zh) 2017-05-31
CN106758837B CN106758837B (zh) 2020-06-02

Family

ID=58919330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611211319.4A Active CN106758837B (zh) 2016-12-24 2016-12-24 一种结合拱上立柱的斜拉扣挂施工***

Country Status (1)

Country Link
CN (1) CN106758837B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227692A (zh) * 2017-07-18 2017-10-03 广西路桥工程集团有限公司 一种斜拉扣挂安装***
CN108239937A (zh) * 2017-09-14 2018-07-03 贵州桥梁建设集团有限责任公司 拱桥塔架自平衡控制方法
CN111608693A (zh) * 2020-06-02 2020-09-01 仲恺农业工程学院 一种高强钢管混凝土拱
CN111764306A (zh) * 2020-07-20 2020-10-13 四川省公路规划勘察设计研究院有限公司 大跨主拱立柱上设扣索转向装置的悬臂浇筑成拱控制方法
CN113062231A (zh) * 2021-04-06 2021-07-02 招商局重庆交通科研设计院有限公司 悬臂浇筑拱圈施工装置及施工方法
CN114875769A (zh) * 2021-07-22 2022-08-09 长沙理工大学 预制装配化中空夹层钢管混凝土拱桥及其施工方法
CN115992490A (zh) * 2023-03-23 2023-04-21 中铁十七局集团第五工程有限公司 一种大跨度混凝土拱桥斜拉扣挂悬臂浇筑施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000240001A (ja) * 1999-02-19 2000-09-05 Hitachi Zosen Corp オーバーブリッジ
CN102418315A (zh) * 2011-09-30 2012-04-18 长沙理工大学 低扣塔架设桥宽较大的钢管混凝土拱桥的施工方法
CN202809498U (zh) * 2012-10-17 2013-03-20 张清标 一种新型缆索吊装***
CN105926444A (zh) * 2016-04-22 2016-09-07 中铁二院工程集团有限责任公司 一种混凝土拱桥成拱方法
CN205711696U (zh) * 2016-06-24 2016-11-23 河海大学 一种拉索与拱组合体系的人行天桥

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000240001A (ja) * 1999-02-19 2000-09-05 Hitachi Zosen Corp オーバーブリッジ
CN102418315A (zh) * 2011-09-30 2012-04-18 长沙理工大学 低扣塔架设桥宽较大的钢管混凝土拱桥的施工方法
CN202809498U (zh) * 2012-10-17 2013-03-20 张清标 一种新型缆索吊装***
CN105926444A (zh) * 2016-04-22 2016-09-07 中铁二院工程集团有限责任公司 一种混凝土拱桥成拱方法
CN205711696U (zh) * 2016-06-24 2016-11-23 河海大学 一种拉索与拱组合体系的人行天桥

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227692A (zh) * 2017-07-18 2017-10-03 广西路桥工程集团有限公司 一种斜拉扣挂安装***
CN107227692B (zh) * 2017-07-18 2023-01-24 广西路桥工程集团有限公司 一种斜拉扣挂安装***
CN108239937A (zh) * 2017-09-14 2018-07-03 贵州桥梁建设集团有限责任公司 拱桥塔架自平衡控制方法
CN111608693A (zh) * 2020-06-02 2020-09-01 仲恺农业工程学院 一种高强钢管混凝土拱
CN111764306A (zh) * 2020-07-20 2020-10-13 四川省公路规划勘察设计研究院有限公司 大跨主拱立柱上设扣索转向装置的悬臂浇筑成拱控制方法
CN111764306B (zh) * 2020-07-20 2022-03-15 四川省公路规划勘察设计研究院有限公司 大跨主拱立柱上设扣索转向装置的悬臂浇筑成拱控制方法
CN113062231A (zh) * 2021-04-06 2021-07-02 招商局重庆交通科研设计院有限公司 悬臂浇筑拱圈施工装置及施工方法
CN113062231B (zh) * 2021-04-06 2022-02-18 招商局重庆交通科研设计院有限公司 悬臂浇筑拱圈施工装置及施工方法
CN114875769A (zh) * 2021-07-22 2022-08-09 长沙理工大学 预制装配化中空夹层钢管混凝土拱桥及其施工方法
CN115992490A (zh) * 2023-03-23 2023-04-21 中铁十七局集团第五工程有限公司 一种大跨度混凝土拱桥斜拉扣挂悬臂浇筑施工方法

Also Published As

Publication number Publication date
CN106758837B (zh) 2020-06-02

Similar Documents

Publication Publication Date Title
CN106758837A (zh) 一种结合拱上立柱的斜拉扣挂施工***
CN100543235C (zh) 斜拉索辅助全悬臂架设钢桁梁的方法及***
CN103669224B (zh) 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工方法及钢管支架
CN102418315B (zh) 低扣塔架设桥宽较大的钢管混凝土拱桥的施工方法
CN108374347A (zh) 一种高速铁路大跨度提篮拱桥钢拱肋扣挂***施工方法
CN103741601B (zh) 一种塔、梁以及索同步成桥工艺
CN101418543B (zh) 一种自锚式悬索桥斜拉施工法
CN107190627B (zh) 部分地锚式悬索桥及其施工方法
CN206706584U (zh) 中墩不对称扣挂缆索***安装多跨拱桥中墩拱肋
CN103882812B (zh) 斜拉索桥中跨主梁的施工方法
CN105178200B (zh) 悬浇拱桥一号节段施工的斜拉组合支架施工方法
CN108086334B (zh) 一种可回收的快速预应力锚索及其施工方法
CN102535348B (zh) 一种铰塔斜拉桥斜拉索的张拉方法
CN104328740A (zh) 大跨径钢管拱桥竖转施工与线形控制方法
CN106087752A (zh) 多跨提篮拱桥施工方法
CN107012797B (zh) 一种支架法与斜拉扣挂法组合的施工***及方法
CN201106155Y (zh) 斜拉索辅助全悬臂架设钢桁梁装置
CN103938552A (zh) 大跨度钢桁拱桥自平衡悬拼施工方法及主墩限位支座
CN103243658A (zh) 斜拉桥牵索挂篮及其组拼方法
CN208088097U (zh) 一种三塔悬索桥主梁安装施工结构
CN105421236B (zh) 一种斜拉悬索协作体系桥梁的合拢方法
CN107476263A (zh) 一种预应力闸墩锚索的施工方法
CN106120573B (zh) 跨海多跨提篮拱桥自平衡扣挂施工方法
CN205557349U (zh) 一种吊杆更换装置
CN208379426U (zh) 桥梁抗拉结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Huang Xin

Inventor after: Yuan Shuai

Inventor after: Zhao Jingbo

Inventor after: Guo Qi

Inventor after: Yan Shuxin

Inventor after: Zhou Yiyong

Inventor before: Huang Xin

Inventor before: Yan Shuxin

Inventor before: Yuan Shuai

Inventor before: Guo Qi

Inventor before: Zhao Jingbo

Inventor before: Zhou Yiyong

GR01 Patent grant
GR01 Patent grant