CN106651125A - Material distribution system and processing method thereof - Google Patents
Material distribution system and processing method thereof Download PDFInfo
- Publication number
- CN106651125A CN106651125A CN201610983689.3A CN201610983689A CN106651125A CN 106651125 A CN106651125 A CN 106651125A CN 201610983689 A CN201610983689 A CN 201610983689A CN 106651125 A CN106651125 A CN 106651125A
- Authority
- CN
- China
- Prior art keywords
- module
- materials
- goods
- data
- material supply
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Marketing (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention discloses a material distribution system and a processing method thereof. The material distribution system comprises a resource planning module connected with a data source and used for obtaining the material supplying information, wherein the material supplying information at least comprises service data and the service data at least comprise material planning data, contract signing data, contract fulfillment data, storage management data and contract settlement data; and a database connected with the resource planning module and used for storing the material supplying information. According to the technical scheme of the invention, the technical problem in the prior art that a conventional material distribution system has business link barriers so as to cause the incomplete material supplying information can be solved.
Description
Technical field
The present invention relates to electrical network goods and materials allotment field, in particular to a kind of material Recombined System and its processing method.
Background technology
State Grid Corporation of China is just progressively perfecting material supply organizational framework, sets up the coordination system of actively honouring an agreement, preliminary shape
It is that more efficient, quick response goods and materials are needed into the Modern Logistics System framework of " centralized management, classification supply, Collaboration "
Ask, stablize, efficiently ensure material supply, and as requirement of the supply chain overall process to material supply is improved constantly, electrical network goods and materials
Supply allotment should possess more specification, comprehensive, flexible idea in management.
At present, the support system that Qinghai Electric Power Corporation's electrical network material supply allotment is related to includes ERP system (national grid
Enterprise resource planning, Enterprise Resource Plan's writes a Chinese character in simplified form) and e-commerce platform (ECP system,
Enterprise Cloud Platform's writes a Chinese character in simplified form), data supporting is provided for electrical network material supply allotment, by electronics business
The business platform information of link such as can honour an agreement to contract signing, contract is counted, analyzed;Can be to goods and materials by ERP system
Demand, storage information carry out report form statistics, coordinate to solve inside and outside portion's supply problem to a certain extent, it is ensured that emphasis thing
Money, emphasis event, the material supply of key project.
At present, Qinghai Electric Power Corporation's electrical network material supply allotment exist service link barrier, information data insertion it is smooth,
The problems such as response speed is slow, mainly including following several respects:
(1) there is barrier between each service link of Qinghai company material supply, goods and materials plan, contract signing, contract honour an agreement,
The service link information communication such as storage, Office Of Contract Settlements is not smooth.
(2) Qinghai company goods and materials allotment business lacks at present statistical analysis means, each for monthly, annual material supply
Class form can only be counted manually, increase the workload of employee, but data accuracy is not still high.
(3) it is weaker in terms of the tracking regulation and control monitoring and early warning of material supply full-service flow process, to material requirements, adopt
Purchase, contract signing, contract is honoured an agreement, stores in a warehouse, Office Of Contract Settlements material supply full-service flow process key node does not carry out early warning prompting, nothing
Method ensures that material supply is timely, reliable.
There is service link barrier for material Recombined System of the prior art, cause material supply information incomplete
Problem, not yet proposes at present effective solution.
The content of the invention
A kind of material Recombined System and its processing method are embodiments provided, it is of the prior art at least to solve
There is service link barrier in material Recombined System, cause the incomplete technical problem of material supply information.
A kind of one side according to embodiments of the present invention, there is provided material Recombined System, including:Resource plans as a whole module,
It is connected with data source, for obtaining material supply information, wherein, material supply information at least includes:Business datum, business datum
At least include:Goods and materials planning data, contract signing data, contract are honoured an agreement data, warehousing management data and Office Of Contract Settlements data;Number
According to storehouse, plan as a whole module with resource and be connected, for storing material supply information.
Further, database is additionally operable to store material supply information by structured way.
Further, resource pool module is additionally operable to receive report parameter, and generates corresponding form according to report parameter;
Said system also includes:Display module, plans as a whole module and is connected, for showing corresponding form with resource.
Further, said system also includes:Monitoring and early warning module, plans as a whole module and is connected, for obtaining key with resource
The early-warning conditions of service node, monitor the execution state of key business node, if execution state meets early-warning conditions, generate
Early warning information.
Further, said system also includes:Daily operation module, plans as a whole module and is connected, for receiving goods and materials with resource
Allotment request, according to material supply information goods and materials programs are determined, according to goods and materials programs goods and materials allotment instruction is generated;It is defeated
Go out module, be connected with daily operation module, for export allotment instruction to corresponding transaction processing system.
Further, daily operation module is additionally operable to first of return after reception goods and materials allotment instruction is performed and performs knot
Really.
Further, said system also includes:Response coordination module, plans as a whole module and is connected with resource, emergent for receiving
Goods and materials allotment request, according to material supply information emergency materials programs are determined, being generated according to emergency materials programs should
Anxious goods and materials allotment instruction;Output module, is connected with response coordination module, for exporting emergency materials allotment instruction to corresponding industry
Business processing system.
Further, daily operation module is additionally operable to receive the second execution returned after emergency materials allotment instruction is performed
As a result.
Further, said system also includes:Authority management module, for the authority information of receives input, believes authority
Cease and verified, be verified result;Display module, is connected with authority management module, for being shown accordingly according to the result
Use entrance.
Further, said system also includes:Input module, plans as a whole respectively module, monitoring and early warning module, daily with resource
The connection of operating module, response coordination module and authority management module, for being input into report parameter, early-warning conditions, goods and materials allotment please
Ask, emergency materials allotment is asked or authority information.
Another aspect according to embodiments of the present invention, additionally provides a kind of processing method of material Recombined System, including:Obtain
Material supply information is taken, wherein, material supply information at least includes:Business datum, business datum at least includes:Goods and materials quota
According to, contract signing data, contract honour an agreement data, warehousing management data and Office Of Contract Settlements data;By material supply information Store extremely
In database.
In embodiments of the present invention, material supply information is obtained, and by material supply information Store to database, so as to
The whole process for realizing material supply business represents, and for material supply management and control support is provided.Because material Recombined System can be with ERP
System and ECP system incorporate all service link data as data source, solve material Recombined System of the prior art
There is service link barrier, cause the incomplete technical problem of material supply information.Therefore, carried by the above embodiment of the present invention
For scheme, it is possible to achieve information sharing, it is ensured that whole material supply information communication is smooth, is fully meeting each business demand
Meanwhile, improve the cooperation degree between each business;Guarantee each service link advance to perfect order, realize the efficient of material supply.
Description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, this
Bright schematic description and description does not constitute inappropriate limitation of the present invention for explaining the present invention.In the accompanying drawings:
Fig. 1 is a kind of structural representation of material Recombined System according to embodiments of the present invention;
Fig. 2 is that a kind of optional material supply information according to embodiments of the present invention carries out structured storage according to system
Schematic diagram;
Fig. 3 is that a kind of optional material supply information according to embodiments of the present invention carries out structuring and deposits according to Business Nature
The schematic diagram of storage;
Fig. 4 is the schematic diagram of the business structure of a kind of optional material Recombined System according to embodiments of the present invention;
Fig. 5 is the schematic diagram of the Technical Architecture of a kind of optional material Recombined System according to embodiments of the present invention;And
Fig. 6 is a kind of flow chart of the processing method of material supply information according to embodiments of the present invention.
Specific embodiment
In order that those skilled in the art more fully understand the present invention program, below in conjunction with the embodiment of the present invention
Accompanying drawing, is clearly and completely described to the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only
The embodiment of a part of the invention, rather than the embodiment of whole.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment that member is obtained under the premise of creative work is not made, should all belong to the model of present invention protection
Enclose.
It should be noted that description and claims of this specification and the term " first " in above-mentioned accompanying drawing, "
Two " it is etc. the object for distinguishing similar, without for describing specific order or precedence.It should be appreciated that so using
Data can exchange in the appropriate case, so as to embodiments of the invention described herein can with except illustrating here or
Order beyond those of description is implemented.Additionally, term " comprising " and " having " and their any deformation, it is intended that cover
Lid is non-exclusive to be included, and for example, process, method, system, product or the equipment for containing series of steps or unit is not necessarily limited to
Those steps clearly listed or unit, but may include clearly not list or for these processes, method, product
Or intrinsic other steps of equipment or unit.
Embodiment 1
According to embodiments of the present invention, there is provided a kind of embodiment of material Recombined System.
Fig. 1 is a kind of structural representation of material Recombined System according to embodiments of the present invention, as shown in figure 1, the system
Including such as lower module:
Resource plans as a whole module 11, is connected with data source 13, for obtaining material supply information, wherein, material supply information
At least include:Business datum, business datum at least includes:Goods and materials planning data, contract signing data, contract are honoured an agreement data, storehouse
Storage management data and Office Of Contract Settlements data.
Specifically, above-mentioned data source can be ERP system and ECP system;Above-mentioned material supply information can include
Each service link such as goods and materials plan, bid and purchase, contract signing, quality surveillance, contract are honoured an agreement, warehousing management, Office Of Contract Settlements
Business datum, and the retired account information of equipment.
Database 15, plans as a whole module 11 and is connected, for storing material supply information with resource.
In a kind of optional scheme, goods and materials deployment platform (i.e. above-mentioned material Recombined System) can be with goods and materials Business Stream
Journey is served as theme, and to the business datum of goods and materials plan, contract signing, contract performance, warehousing management, Office Of Contract Settlements resource system is carried out
Raise, resource plans as a whole module can be with ERP system and ECP system as data source, and from goods and materials full supply chain management, acquisition runs through
The industry of the service links such as goods and materials plan, bid and purchase, contract signing, quality surveillance, contract are honoured an agreement, warehousing management, Office Of Contract Settlements
Business data, and the retired account information of equipment, store in local data base, so as to build the information centre of material supply.
By the above embodiment of the present invention, resource plans as a whole module and obtains material supply information, and material supply information is deposited
Store up into database, so as to the whole process for realizing material supply business represents, for material supply management and control support is provided.Due to goods and materials
Mixing system can incorporate all service link data using ERP system and ECP system as data source, solve existing skill
There is service link barrier in the material Recombined System in art, cause the incomplete technical problem of material supply information.Therefore, pass through
The scheme that the above embodiment of the present invention is provided, it is possible to achieve information sharing, it is ensured that whole material supply information communication is smooth, is filling
While point meeting each business demand, the cooperation degree between each business is improved;Guarantee each service link advance to perfect order, realize goods and materials
That what is supplied is efficient.
Optionally, in the above embodiment of the present invention, database is additionally operable to store material supply letter by structured way
Breath.
Specifically, above-mentioned structured storage can carry out material supply information according to Business Nature and system to draw
Point, material supply information can be divided into ERP, ECP and associated other application system according to system, as shown in Figure 2;
Can honour an agreement, store in a warehouse according to goods and materials plan, contract signing, contract, five modules of Office Of Contract Settlements, the structural data of system is entered
Row classification, as shown in Figure 3.
Optionally, in the above embodiment of the present invention, resource plans as a whole module and is additionally operable to receive report parameter, and according to form
Parameter generates corresponding form.
Specifically, above-mentioned report parameter can generate the condition that form needs, such as the timeline such as monthly, annual
Data qualification and the report form templates such as part, the material supply information for needing.
Said system also includes:Display module, plans as a whole module and is connected, for showing corresponding form with resource.
Herein it should be noted that goods and materials allotment business lacks at present statistical analysis means, for monthly, annual goods and materials
Supplying all kinds of forms can only manually count, and increase the workload of employee, but data accuracy is not still high.
In a kind of optional scheme, goods and materials deployment platform can adopt the SG-UAP that State Grid Corporation of China develops design to put down
Platform (application system unitized overall development platform, Unified Applicatoin Platform's writes a Chinese character in simplified form) is developed, with
FusionCharts (chart components of Flash, for making data animation chart) and Cognos (operation function solution)
It is integrated, abundant fixed form, multidimensional form are provided the user, in the form such as monthly or annual that user input needs to generate
After parameter, report form template corresponding with report parameter is called, and corresponding material supply information is read from database, passed through
Statistical analysis, obtains final form, and shows user, and user can see the form of final needs.
By such scheme, all kinds of statistical forms of material Recombined System customized development are covered goods and materials plan, are closed
With, each service link such as honour an agreement, it is possible to achieve business statistics is automated, while operating efficiency is improved, data accuracy
It is improved, so as to lift Consumer's Experience.
Optionally, in the above embodiment of the present invention, said system also includes:
Monitoring and early warning module, plans as a whole module and is connected with resource, and for obtaining the early-warning conditions of key business node, monitoring is closed
The execution state of key service node, if execution state meets early-warning conditions, generates early warning information.
Specifically, above-mentioned early-warning conditions can be the alert status of each service node, and such as overlong time, state are wrong
The early warning value of the business datum of mistake etc., or each service node, early warning value of such as storage information etc..
Herein it should be noted that tracking regulation and control of the business in material supply full-service flow process are allocated in existing material supply
Monitoring and early warning aspect is weaker, material requirements, buying, contract signing, contract is honoured an agreement, is stored in a warehouse, Office Of Contract Settlements material supply
Full-service flow process key node does not carry out early warning prompting, it is impossible to ensure that material supply is timely, reliable.
In a kind of optional scheme, material requirements, buying, contract signing, contract can be honoured an agreement, stored in a warehouse, contract knot
The goods and materials full supply chain key business nodes such as calculation arrange early-warning parameterses, monitor the implementation status of each business, and information is carried out
Collect and analysis, if meeting early-warning conditions, generate corresponding early warning information and be sent to corresponding personnel, so as to realize difference
Abnormal conditions are sent advanced warning by level early warning, are carried out and are coordinated, track work.
By such scheme, it is possible to reduce artificial problem occurs, it is easy to user to grasp material supply progress, realizes that goods and materials are supplied
Full-service flow monitoring early warning is answered, material supply service quality is lifted.
Optionally, in the above embodiment of the present invention, said system also includes:
Daily operation module, plans as a whole module and is connected with resource, for receiving goods and materials allotment request, according to material supply information
Determine goods and materials programs, according to goods and materials programs goods and materials allotment instruction is generated.
Output module, is connected with daily operation module, for export allotment instruction to corresponding transaction processing system.
Specifically, above-mentioned transaction processing system can be ERP system.
In a kind of optional scheme, in order to ensure the smooth development of goods and materials allotment center daily operation, daily operation mould
Block can pass through with reference to the Items Management Mode of goods and materials allotment center routine work, the goods and materials allotment request of receiving user's input
Inquiry database determines corresponding goods and materials programs, and according to goods and materials programs different materials measurement instructions are generated, and will
The materials measurement instruction output realizes that goods and materials are allocated to ERP system, is further perfect allotment mechanism provided auxiliary and support.
Optionally, in the above embodiment of the present invention, daily operation module is additionally operable to reception goods and materials allotment instruction and is performed
The first implementing result for returning afterwards.
In a kind of optional scheme, daily operation module can also receive the implementation status of goods and materials allotment instruction, feedback
Implementing result, and implementing result is carried out into display preservation, so as to user can allocate implementation status with real-time query to goods and materials.
Optionally, in the above embodiment of the present invention, said system also includes:
Response coordination module, plans as a whole module and is connected with resource, for receiving emergency materials allotment request, according to material supply
Information determines emergency materials programs, and according to emergency materials programs emergency materials allotment instruction is generated.
Output module, is connected with response coordination module, for exporting emergency materials allotment instruction to corresponding Business Processing
System.
In a kind of optional scheme, for the smooth development that the response coordination for ensureing goods and materials allotment center works, meet an urgent need
Coordination module can accept emergency materials demand (i.e. above-mentioned emergency materials allotment request), to material requirements, arrival, the knot of meeting an urgent need
Calculation situation is inquired about, counted, so that it is determined that the programs of emergency materials, and refer to according to the different dispensings of dispensing mode generation
Order, by materials measurement instruction output to ERP system, realizes that goods and materials are allocated, be further perfect allotment mechanism provided auxiliary and
Support.
Optionally, in the above embodiment of the present invention, response coordination module is additionally operable to receive emergency materials allotment instruction quilt
The second implementing result returned after execution.
In a kind of optional scheme, response coordination module can also receive the implementation status of emergency materials allotment instruction,
Execution result back, and implementing result is carried out into display preservation, so as to user can be performed with real-time query to emergency materials allotment
Situation.
Optionally, in the above embodiment of the present invention, said system also includes:
Authority management module, for the authority information of receives input, verifies to authority information, is verified result.
Display module, is connected with authority management module, use accordingly entrance for showing according to the result.
In a kind of optional scheme, goods and materials deployment platform can carry out integrated with unified rights, and authority management module can
With the authority information of receiving user's input, user right is verified, determine the module that user can use, and carried for user
For using entrance accordingly, so as to realize providing the user unified rights management and the purpose using entrance.
Optionally, in the above embodiment of the present invention, said system also includes:
Input module, respectively with resource plan as a whole module, monitoring and early warning module, daily operation module, response coordination module and
Authority management module connects, for being input into report parameter, early-warning conditions, goods and materials allotment request, emergency materials allotment request or weighing
Limit information.
In a kind of optional scheme, user can be defeated to goods and materials deployment platform by instruments such as external keyboard, mouses
Enter report parameter, early-warning conditions, goods and materials allotment request, emergency materials allotment request or authority information, so as to realize corresponding work(
Energy.
With reference to Fig. 4 to Fig. 5, a kind of preferred embodiment of the invention is described in detail.
As shown in figure 4, allocate system model according to the material supply of Qinghai electric power company requiring, the industry of goods and materials deployment platform
Business framework is as follows:1st, resource is planned as a whole:From goods and materials full supply chain management, through goods and materials plan, bid and purchase, contract signing,
The service links such as quality surveillance, contract are honoured an agreement, warehousing management, Office Of Contract Settlements, and the retired account information of equipment, build goods and materials and supply
The information centre answered.Guarantee that whole material supply information communication is smooth, while each business demand is fully met, improve each industry
Cooperation degree between business;Guarantee each service link advance to perfect order, realize the efficient of material supply;2nd, monitoring and early warning:Monitoring and early warning
Be material requirements, buying, contract signing, contract are honoured an agreement, are stored in a warehouse, the goods and materials full supply chain key business node such as Office Of Contract Settlements sets
Early-warning parameterses, monitoring business implementation status are put, and information is collected and analysis, realize different levels early warning, to abnormal feelings
Condition sends advanced warning, carries out and coordinates, tracks work;3rd, daily operation:With reference to the instrumentation tubes of goods and materials allotment center routine work
Reason pattern, is further perfect allotment mechanism provided auxiliary and support while material supply is ensured.With allotment center as pivot
Knob, strengthens Materials Company and each relevant unit/department, the communication and coordination of supplier, improves the ability for solving significant problem;4th, should
It is anxious to coordinate:Emergency materials demand is accepted, emergent material requirements, arrival, clearing situation are inquired about, counted;It is determined that emergent thing
The programs of money, according to dispensing mode different dispensing instructions are generated, and are fed back to allocating result implementation status.Goods and materials are adjusted
Served as theme with goods and materials operation flow with platform application architecture, to goods and materials plan, contract signing, contract performance, warehousing management, contract
The business datum of clearing carries out resource pool, monitoring and early warning, and the whole process for realizing material supply business represents, and ensures goods and materials allotment
Everything goes well with your work carries out for center daily operation and response coordination etc., and for material supply management and control support is provided.
The design of goods and materials deployment platform data framework follows SG-ERP data framework design principles, from goods and materials deployment platform entirety
The visual angle unification of business is organized to data and planned, improves data-storing and shared efficiency between cross-system;From enterprise's number
According to the angle of asset management, the plan in collection, storage, the mobile and access link of data in whole data life period is formulated
Summary, model, flow process.The data that perfect or what's new is related to belong in the 12 data subject areas concluded in SG-ERP
Individual subject area, distinguishes according to Business Nature, further refine out goods and materials plan, contract signing, contract honour an agreement, store in a warehouse, contract knot
Calculate five sub- subject areas.By structured way data storage in intranet environment, output data is supplied to ERP, Cognos, SG-
The systems such as UAP carry out work flow.
Require according to the management and control of SG-ERP frameworks, the Technical Architecture of Qinghai goods and materials deployment platform is as shown in figure 5, Qinghai goods and materials are adjusted
Developed using the SG-UAP platforms that state host pushes away with platform, it is integrated with FusionCharts and Cognos provide the user it is rich
Rich fixed form, multidimensional report form showing, finally carries out integrated providing the user unified rights management and making with unified rights
Use entrance.All data carry out data integration from data center using ERP and ECP as source data by interface interface.
By such scheme, goods and materials deployment platform covers all business modules of Qinghai electric power company material supply, is comprehensive
Property statistical analysis system.Goods and materials deployment platform follows SG-ERP data frameworks mentality of designing and principle the most advanced, from enterprise
The angle of data assets management, formulates the plan in collection, storage, the mobile and access link of data in whole data life period
Summary, model, flow process.Goods and materials deployment platform is developed using the SG-UAP platforms that State Grid Corporation of China develops design, with
FusionCharts and Cognos are integrated, provide the user abundant fixed form, multidimensional report form showing, lift Consumer's Experience.
Embodiment 2
According to embodiments of the present invention, there is provided a kind of embodiment of the method for the processing method of material supply information, need
It is bright, can hold in the such as computer system of one group of computer executable instructions the step of the flow process of accompanying drawing is illustrated
OK, and, although show logical order in flow charts, but in some cases, can be with different from order herein
Perform shown or described step.
Fig. 6 is a kind of flow chart of the processing method of material supply information according to embodiments of the present invention, as shown in fig. 6,
The method comprises the steps:
Step S602, obtains material supply information, wherein, material supply information at least includes:Business datum, business datum
At least include:Goods and materials planning data, contract signing data, contract are honoured an agreement data, warehousing management data and Office Of Contract Settlements data.
Specifically, above-mentioned data source can be ERP system and ECP system;Above-mentioned material supply information can include
Each service link such as goods and materials plan, bid and purchase, contract signing, quality surveillance, contract are honoured an agreement, warehousing management, Office Of Contract Settlements
Business datum, and the retired account information of equipment.
Step S604, by material supply information Store to database.
In a kind of optional scheme, goods and materials deployment platform (i.e. above-mentioned material Recombined System) can be with goods and materials Business Stream
Journey is served as theme, and to the business datum of goods and materials plan, contract signing, contract performance, warehousing management, Office Of Contract Settlements resource system is carried out
Raise, resource plans as a whole module can be with ERP system and ECP system as data source, and from goods and materials full supply chain management, acquisition runs through
The industry of the service links such as goods and materials plan, bid and purchase, contract signing, quality surveillance, contract are honoured an agreement, warehousing management, Office Of Contract Settlements
Business data, and the retired account information of equipment, store in local data base, so as to build the information centre of material supply.
By the above embodiment of the present invention, material supply information is obtained, and by material supply information Store to database,
So as to the whole process for realizing material supply business represents, for material supply management and control support is provided.Because material Recombined System can be with
Using ERP system and ECP system as data source, all service link data are incorporated, solve goods and materials of the prior art and adjust
There is service link barrier in match system, cause the incomplete technical problem of material supply information.Therefore, by above-mentioned reality of the invention
Apply the scheme of example offer, it is possible to achieve information sharing, it is ensured that whole material supply information communication is smooth, is fully meeting each business
While demand, the cooperation degree between each business is improved;Guarantee each service link advance to perfect order, realize the efficient of material supply.
The embodiments of the present invention are for illustration only, do not represent the quality of embodiment.
In the above embodiment of the present invention, the description to each embodiment all emphasizes particularly on different fields, and does not have in certain embodiment
The part of detailed description, may refer to the associated description of other embodiment.
In several embodiments provided herein, it should be understood that disclosed technology contents, can pass through other
Mode is realized.Wherein, device embodiment described above is only schematic, such as the division of described unit, Ke Yiwei
A kind of division of logic function, can there is an other dividing mode when actually realizing, such as multiple units or component can with reference to or
Person is desirably integrated into another system, or some features can be ignored, or does not perform.Another, shown or discussed is mutual
Between coupling or direct-coupling or communication connection can be INDIRECT COUPLING or communication link by some interfaces, unit or module
Connect, can be electrical or other forms.
The unit as separating component explanation can be or may not be it is physically separate, it is aobvious as unit
The part for showing can be or may not be physical location, you can with positioned at a place, or can also be distributed to multiple
On unit.Some or all of unit therein can according to the actual needs be selected to realize the purpose of this embodiment scheme.
In addition, each functional unit in each embodiment of the invention can be integrated in a processing unit, it is also possible to
It is that unit is individually physically present, it is also possible to which two or more units are integrated in a unit.Above-mentioned integrated list
Unit both can be realized in the form of hardware, it would however also be possible to employ the form of SFU software functional unit is realized.
If the integrated unit is realized using in the form of SFU software functional unit and as independent production marketing or used
When, during a computer read/write memory medium can be stored in.Based on such understanding, technical scheme is substantially
The part for contributing to prior art in other words or all or part of the technical scheme can be in the form of software products
Embody, the computer software product is stored in a storage medium, including some instructions are used so that a computer
Equipment (can be personal computer, server or network equipment etc.) perform the whole of each embodiment methods described of the invention or
Part steps.And aforesaid storage medium includes:USB flash disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited
Reservoir (RAM, Random Access Memory), portable hard drive, magnetic disc or CD etc. are various can be with store program codes
Medium.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (11)
1. a kind of material Recombined System, it is characterised in that include:
Resource plans as a whole module, is connected with data source, for obtaining material supply information, wherein, the material supply information is at least
Including:Business datum, the business datum at least includes:Goods and materials planning data, contract signing data, contract are honoured an agreement data, storehouse
Storage management data and Office Of Contract Settlements data;
Database, plans as a whole module and is connected, for storing the material supply information with the resource.
2. system according to claim 1, it is characterised in that the database is additionally operable to store institute by structured way
State material supply information.
3. system according to claim 1, it is characterised in that
The resource plans as a whole module and is additionally operable to receive report parameter, and generates corresponding form according to the report parameter;
The system also includes:Display module, plans as a whole module and is connected, for showing corresponding form with the resource.
4. system according to claim 1, it is characterised in that the system also includes:
Monitoring and early warning module, plans as a whole module and is connected with the resource, for obtaining the early-warning conditions of key business node, monitors institute
The execution state of key business node is stated, if the execution state meets the early-warning conditions, early warning information is generated.
5. system according to claim 1, it is characterised in that the system also includes:
Daily operation module, plans as a whole module and is connected with the resource, for receiving goods and materials allotment request, according to the material supply
Information determines goods and materials programs, and according to the goods and materials programs goods and materials allotment instruction is generated;
Output module, is connected with the daily operation module, for exporting the goods and materials allotment instruction to corresponding Business Processing
System.
6. system according to claim 5, it is characterised in that the daily operation module is additionally operable to receive the goods and materials to be adjusted
The first implementing result returned after being performed with instruction.
7. system according to claim 1, it is characterised in that the system also includes:
Response coordination module, plans as a whole module and is connected with the resource, for receiving emergency materials allotment request, according to the goods and materials
Information provision determines emergency materials programs, and according to the emergency materials programs emergency materials allotment instruction is generated;
Output module, is connected with the response coordination module, for exporting the emergency materials allotment instruction to corresponding business
Processing system.
8. system according to claim 7, it is characterised in that the response coordination module is additionally operable to receive the emergent thing
The second implementing result that money allotment instruction is returned after being performed.
9. system according to claim 1, it is characterised in that the system also includes:
Authority management module, for the authority information of receives input, verifies to the authority information, is verified result;
Display module, is connected with the authority management module, use accordingly entrance for showing according to the result.
10. the system according to any one in claim 3 to 9, it is characterised in that the system also includes:
Input module, respectively with the resource plan as a whole module, monitoring and early warning module, daily operation module, response coordination module and
Authority management module connects, for being input into report parameter, early-warning conditions, goods and materials allotment request, emergency materials allotment request or weighing
Limit information.
11. a kind of processing methods of material supply information, it is characterised in that include:
Material supply information is obtained, wherein, the material supply information at least includes:Business datum, the business datum is at least
Including:Goods and materials planning data, contract signing data, contract are honoured an agreement data, warehousing management data and Office Of Contract Settlements data;
By the material supply information Store into database.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610983689.3A CN106651125A (en) | 2016-11-08 | 2016-11-08 | Material distribution system and processing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610983689.3A CN106651125A (en) | 2016-11-08 | 2016-11-08 | Material distribution system and processing method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106651125A true CN106651125A (en) | 2017-05-10 |
Family
ID=58806805
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610983689.3A Pending CN106651125A (en) | 2016-11-08 | 2016-11-08 | Material distribution system and processing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106651125A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107146059A (en) * | 2017-05-19 | 2017-09-08 | 广东电网有限责任公司物流服务中心 | A kind of goods and materials contract is honoured an agreement information management-control method |
CN109146375A (en) * | 2018-08-15 | 2019-01-04 | 国网湖南省电力有限公司 | Power grid material Management System and method |
CN109614436A (en) * | 2018-11-21 | 2019-04-12 | 国网四川省电力公司眉山供电公司 | Power Material regulator control system and corresponding method |
CN109636173A (en) * | 2018-12-06 | 2019-04-16 | 平安科技(深圳)有限公司 | Computer room asset monitoring method, system, electronic device and storage medium |
CN111047377A (en) * | 2018-10-12 | 2020-04-21 | 北京国双科技有限公司 | Data processing method and device on product supply chain |
CN111124374A (en) * | 2019-12-26 | 2020-05-08 | 南方电网科学研究院有限责任公司 | Method for realizing special effect animation based on Electron and HTML5 |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
CN111584048A (en) * | 2020-04-22 | 2020-08-25 | 中国人民解放军总医院第八医学中心 | Emergency medical material financing management device and method |
CN111582719A (en) * | 2020-05-08 | 2020-08-25 | 闯志超 | Method and system for dispatching planning of power grid materials |
CN112418807A (en) * | 2020-11-30 | 2021-02-26 | 国网重庆市电力公司物资分公司 | Contract settlement method |
CN113095610A (en) * | 2019-12-23 | 2021-07-09 | 珠海格力电器股份有限公司 | Planning scheduling and allocating system, method and storage medium |
CN113329129A (en) * | 2021-05-28 | 2021-08-31 | 国网江苏省电力有限公司连云港供电分公司 | Material full-flow voice service automatic processing system and method |
CN114154836A (en) * | 2021-11-29 | 2022-03-08 | 中国邮电器材集团有限公司 | Method for monitoring contract execution and triggering early warning and electronic equipment |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105184488A (en) * | 2015-09-09 | 2015-12-23 | 晋亿实业股份有限公司 | Railway material management system and management method |
CN105303306A (en) * | 2015-10-15 | 2016-02-03 | 国家电网公司 | Electric power material dispatching platform system |
CN105913211A (en) * | 2016-04-29 | 2016-08-31 | 国家电网公司 | Material managing and controlling system and method |
-
2016
- 2016-11-08 CN CN201610983689.3A patent/CN106651125A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105184488A (en) * | 2015-09-09 | 2015-12-23 | 晋亿实业股份有限公司 | Railway material management system and management method |
CN105303306A (en) * | 2015-10-15 | 2016-02-03 | 国家电网公司 | Electric power material dispatching platform system |
CN105913211A (en) * | 2016-04-29 | 2016-08-31 | 国家电网公司 | Material managing and controlling system and method |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107146059A (en) * | 2017-05-19 | 2017-09-08 | 广东电网有限责任公司物流服务中心 | A kind of goods and materials contract is honoured an agreement information management-control method |
CN109146375A (en) * | 2018-08-15 | 2019-01-04 | 国网湖南省电力有限公司 | Power grid material Management System and method |
CN111047377B (en) * | 2018-10-12 | 2023-08-25 | 北京国双科技有限公司 | Method and device for processing data on product supply chain |
CN111047377A (en) * | 2018-10-12 | 2020-04-21 | 北京国双科技有限公司 | Data processing method and device on product supply chain |
CN109614436A (en) * | 2018-11-21 | 2019-04-12 | 国网四川省电力公司眉山供电公司 | Power Material regulator control system and corresponding method |
CN109636173A (en) * | 2018-12-06 | 2019-04-16 | 平安科技(深圳)有限公司 | Computer room asset monitoring method, system, electronic device and storage medium |
CN113095610A (en) * | 2019-12-23 | 2021-07-09 | 珠海格力电器股份有限公司 | Planning scheduling and allocating system, method and storage medium |
CN111124374A (en) * | 2019-12-26 | 2020-05-08 | 南方电网科学研究院有限责任公司 | Method for realizing special effect animation based on Electron and HTML5 |
CN111124374B (en) * | 2019-12-26 | 2023-09-12 | 南方电网科学研究院有限责任公司 | Method for realizing special effect animation based on Electron and HTML5 |
CN111584048A (en) * | 2020-04-22 | 2020-08-25 | 中国人民解放军总医院第八医学中心 | Emergency medical material financing management device and method |
CN111582719A (en) * | 2020-05-08 | 2020-08-25 | 闯志超 | Method and system for dispatching planning of power grid materials |
CN111553643A (en) * | 2020-05-18 | 2020-08-18 | 国网河北省电力有限公司物资分公司 | Material purchasing plan and supply chain management system |
CN112418807A (en) * | 2020-11-30 | 2021-02-26 | 国网重庆市电力公司物资分公司 | Contract settlement method |
CN113329129A (en) * | 2021-05-28 | 2021-08-31 | 国网江苏省电力有限公司连云港供电分公司 | Material full-flow voice service automatic processing system and method |
CN114154836A (en) * | 2021-11-29 | 2022-03-08 | 中国邮电器材集团有限公司 | Method for monitoring contract execution and triggering early warning and electronic equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106651125A (en) | Material distribution system and processing method thereof | |
JP2863347B2 (en) | Future planning and dynamic management method of flow process by visualization | |
Shafer et al. | The effects of worker learning, forgetting, and heterogeneity on assembly line productivity | |
Lin et al. | An innovative machine learning model for supply chain management | |
Wang et al. | Robot scheduling for mobile‐rack warehouses: Human–robot coordinated order picking systems | |
US20080103843A1 (en) | Integrating information for maintenance | |
US20030009410A1 (en) | Collaboration bill of material | |
Stefanovic et al. | Supply chain business intelligence: technologies, issues and trends | |
Winkler et al. | Trends in digitalization of intralogistics and the critical success factors of its implementation | |
Nounou et al. | A cyber-physical system architecture based on lean principles for managing industry 4.0 setups | |
Telukdarie et al. | Enterprise definition for Industry 4.0 | |
Yadav et al. | A fuzzy decision framework of lean-agile-green (LAG) practices for sustainable vaccine supply chain | |
Karunarathna et al. | A study of the implications of logistics 4.0 in future warehousing: a Sri Lankan perspective | |
Dadash Pour et al. | RETRACTED: the role of Industry 4.0 technologies in overcoming pandemic challenges for the manufacturing sector | |
CN113112107A (en) | Transfer planning method, device, server and storage medium | |
Pradhan et al. | A Novel IIoT Based ERP-PLM System for MSME of Indian Market | |
Pine et al. | Emerging insights on building infrastructure for data-driven transparency and accountability of organizations | |
Taghipour et al. | The impact of digitalization on supply chain management: a literature review | |
Sharma et al. | Cloud Computing for Supply Chain Management and Warehouse Automation: A Case Study of Azure Cloud | |
CN113592378A (en) | BOM construction method and management system of large complex equipment | |
CN111598500A (en) | Production material management system based on micro-service architecture | |
Dolz Ausina | Evaluation of different AI applications for operational logistic systems | |
Azevedo et al. | The role of supply chain 4.0 on supply chain collaboration-an exploratory case study in the automotive industry | |
Mon et al. | Evaluation of technological development for the definition of Industries 4.0 | |
Dulishkovych et al. | Business Process Management of Virtual Enterprise based on Augmented Reality. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170510 |
|
RJ01 | Rejection of invention patent application after publication |