CN106638998A - Concrete vertical alternative bay construction method - Google Patents

Concrete vertical alternative bay construction method Download PDF

Info

Publication number
CN106638998A
CN106638998A CN201610899702.7A CN201610899702A CN106638998A CN 106638998 A CN106638998 A CN 106638998A CN 201610899702 A CN201610899702 A CN 201610899702A CN 106638998 A CN106638998 A CN 106638998A
Authority
CN
China
Prior art keywords
storehouse
vertical
seam
level
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610899702.7A
Other languages
Chinese (zh)
Inventor
王强
王桂玲
孙学锋
张德财
岳著文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610899702.7A priority Critical patent/CN106638998A/en
Publication of CN106638998A publication Critical patent/CN106638998A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a concrete vertical alternative bay construction method. The method includes the steps that horizontal alternative bay seams of a to-be-constructed structure are divided out in the horizontal direction, and multiple vertical alternative bay seams of the to-be-constructed structure are divided out in the vertical direction; a first section of vertical structure is constructed to the horizontal alternative bay seams and the first vertical alternative bay seams; a first layer of horizontal structure is horizontally constructed on the first section of vertical structure and at the horizontal alternative bay seams in an alternative bay mode; meanwhile, a second section of vertical structure is vertically constructed to the second vertical alternative bay seams and the horizontal alternative bay seams on the first section of vertical structure and at the horizontal alternative bay seams in an alternative bay mode; a second layer of horizontal structure is horizontally constructed on the second section of vertical structure in an alternative bay mode and at the horizontal alternative bay seams; the next section of vertical structure is vertically constructed on the second section of vertical structure to the next vertical alternative bay seam and the horizontal alternative bay seam in an alternative bay mode and at the second vertical alternative bay seams; construction is repeated till construction of the last section of horizontal vertical structure and the last layer of horizontal structure is completed. Construction time is greatly saved.

Description

A kind of concrete vertically jumps storehouse construction method
Technical field
The present invention relates to the realm of building construction, more particularly to a kind of the concrete for setting post-cast strip is not stayed vertically to jump storehouse construction party Method.
Background technology
In traditional high level (including podium) building construction process, due to structure overlength, need to stay in structure and set post-cast strip, The time that pours of post-cast strip takes lag structure and pours 60 days or so in itself.Because post-cast strip delays to close, some operations are just Can delay, can also there is certain risk hidden danger.In the recent period for skyscraper is using the method for cancel the late poured band, after original Pour band to be changed to jump storehouse construction joint, concrete interval in construction joint both sides pours for more than 7 days.But this method, applies in same layer structure In work, construction joint both sides have the time difference of 7 days, although shifted to an earlier date than the construction of post-cast strip method, but still had the delay of 7 days.
The content of the invention
The technical problem to be solved is to provide a kind of concrete for being capable of transverse and longitudinal synchronous construction and vertically jumps storehouse Construction method, can make full use of jump storehouse interval, improve efficiency, time-consuming.
To realize above-mentioned technique effect, the invention discloses a kind of concrete vertically jumps storehouse construction method, including:
The level of structure to be onstructed is marked off in the horizontal direction to storehouse seam is jumped, and knot to be onstructed is marked off in a vertical direction The multiple tracks of structure vertically jumps storehouse seam;
To the level, to jumping, storehouse seam is vertical with first to jump storehouse seam to construction first paragraph vertical structure;
Level jump storehouse construction ground floor horizontal structure on the first paragraph vertical structure is in the level to storehouse seam is jumped; Meanwhile, in first it is vertical jump storehouse seam and be on the first paragraph vertical structure vertical storehouse of jumping construct second segment vertical structure to the Vertically jump storehouse seam and the level and stitch to storehouse is jumped in two roads;
Level jump storehouse construction second layer horizontal structure on the second segment vertical structure is in the level to storehouse seam is jumped; Meanwhile, vertically jump storehouse seam and be on the second segment vertical structure vertical storehouse of jumping in second and construct next section of vertical structure under Vertically jump storehouse seam and the level together to stitch to storehouse is jumped;Repeat to construct, until completing final stage vertical structure and last layer The construction of horizontal structure.
The concrete is vertically jumped storehouse construction method and is further improved by, and is set forth in the level and is in storehouse seam is jumped The step of level jumps storehouse construction ground floor horizontal structure on the first paragraph vertical structure, including:
It is on reinforcing bar from first paragraph vertical structure to side colligation ground floor horizontal structure, installs to storehouse seam is jumped in level The template of first level structure;
After the level of the first paragraph vertical structure sows foot jump storehouse condition to jump storehouse, ground floor horizontal structure is poured Concrete, completes ground floor horizontal structure.
The concrete is vertically jumped storehouse construction method and is further improved by, and is set forth in first vertical storehouse seam of jumping and is in On the first paragraph vertical structure the step of vertical jump storehouse construction second segment vertical structure, including:
In first it is vertical jump storehouse seam be on first paragraph vertical structure upwards the reinforcing bar of colligation second segment vertical structure, If the template of second segment vertical structure;
After described first vertical jump storehouse sows foot jump storehouse condition, the concrete of second segment vertical structure is poured, completed Second segment vertical structure.
The concrete is vertically jumped storehouse construction method and is further improved by, it is described complete final stage vertical structure and The step of construction of last layer of horizontal structure, including:
Construction completes final stage vertical structure and that layer of horizontal structure below the final stage vertical structure;
Level is jumped storehouse and is constructed last layer of horizontal structure on the final stage vertical structure.
The present invention is as a result of above technical scheme so as to have the advantages that:Applying for storehouse is jumped using by plane The conversion of work method is used in vertical vertical structure, i.e., divide on the vertical plane and jump storehouse seam, from the method that basis is constructed successively upwards, Level is jumped into storehouse and vertical jump storehouse synchronous construction, accelerates efficiency of construction;And traditional construction is then to pour for 7 days after left side pours and finishes Right side body of wall is built, after waiting right side body of wall to conserve 3-4 days, assembling reinforcement upwards, supporting module, a floor pours on carrying out. And the inventive method, the time of the maintenance of right side body of wall, assembling reinforcement supporting module is all circulated when 7 days of storehouse are jumped vertically upward Between within, greatly save the time.
Description of the drawings
Fig. 1~7 are the construction process schematic diagram that concrete of the present invention vertically jumps storehouse construction method.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment the present invention is further detailed explanation.
A kind of concrete of the present invention is vertically jumped storehouse construction method and is mainly used using the construction method conversion that plane is jumped storehouse In vertical vertical structure, i.e., jump storehouse seam is divided on the vertical plane, from the method that basis is constructed successively upwards, level is jumped into storehouse and is erected To storehouse synchronous construction is jumped, accelerate efficiency of construction, save the engineering time.
Concrete of the present invention vertically jumps storehouse construction method mainly includes following construction procedure:
S001:The level of structure to be onstructed is marked off in the horizontal direction to storehouse seam is jumped, and marks off treat in a vertical direction The multiple tracks of constructing structure vertically jumps storehouse seam;
S002:To level, to jumping, storehouse seam is vertical with first to jump storehouse seam to construction first paragraph vertical structure;
S003:Level jump storehouse construction ground floor horizontal structure on first paragraph vertical structure is in level to storehouse seam is jumped;Together When, it is on first paragraph vertical structure that vertical to jump storehouse second segment vertical structure of constructing perpendicular to second in first vertical storehouse seam of jumping Stitch to storehouse is jumped to storehouse seam and level is jumped;
S004:Level jump storehouse construction second layer horizontal structure on second segment vertical structure is in level to storehouse seam is jumped;Together When, vertically jump storehouse seam and be on second segment vertical structure vertical storehouse of jumping in second and construct next section of vertical structure to lower perpendicular together Stitch to storehouse is jumped to storehouse seam and level is jumped;Repeat to construct, until completing final stage vertical structure and last layer of horizontal structure Construction.
Wherein, in step S003, level jump storehouse construction first on first paragraph vertical structure is in storehouse seam is jumped in level The step of layer horizontal structure, specifically include:
It is on reinforcing bar from first paragraph vertical structure to side colligation ground floor horizontal structure, installs to storehouse seam is jumped in level The template of first level structure;
After the level of first paragraph vertical structure sows foot jump storehouse condition to jump storehouse, the coagulation of ground floor horizontal structure is poured Soil, completes ground floor horizontal structure.
In step S003, vertical jump storehouse construction second segment is on first paragraph vertical structure in first vertical storehouse seam of jumping The step of vertical structure, specifically include:
In first it is vertical jump storehouse seam be on first paragraph vertical structure upwards the reinforcing bar of colligation second segment vertical structure, If the template of second segment vertical structure;
After first vertical jump storehouse sows foot jump storehouse condition, the concrete of second segment vertical structure is poured, complete second Section vertical structure.
In step S004, the step of complete the construction of final stage vertical structure and last layer of horizontal structure, including:
Construction completes final stage vertical structure and that layer of horizontal structure below final stage vertical structure;
Level is jumped storehouse and is constructed last layer of horizontal structure on final stage vertical structure.
Coordinate shown in Fig. 1~7, by one level to as a example by the left side body of wall and right side body of wall of jumping storehouse seam both sides, coordinate attached Figure, vertically jumps storehouse construction method and is described further to concrete of the present invention.
First, the level of structure to be onstructed is marked off in the horizontal direction to storehouse seam is jumped, and marks off treat in a vertical direction The multiple tracks of constructing structure vertically jumps storehouse seam.
Secondly, refering to shown in Fig. 1, jump storehouse construction with traditional level during one layer of construction the same, the body of wall time press level to Jump storehouse seam is stayed and set.Specially:Construction first paragraph vertical structure 11 stitches 21 and first vertical jump storehouse seam 31 to level to storehouse is jumped.
Then, coordinate shown in Fig. 2, next step construction is to be on first paragraph vertical structure 11 to adopt to jump storehouse seam 21 in level The reinforcing bar of the timely colligation ground floor horizontal structure of storehouse mode is jumped with level, the template of ground floor horizontal structure is installed;Meanwhile, in Together vertical jump storehouse seam 31 is on first paragraph vertical structure 11 and jumps storehouse mode (engineering method and level jump storehouse mode phase using vertical Together, only direction is from level to transforming to vertically upward) reinforcing bar of the second segment vertical structure of colligation in time, install second segment and vertically tie The template of structure.
The level for treating first paragraph vertical structure 11 is jumped storehouse condition and (is jumped to jump storehouse seam 21 and first satisfaction of vertical jump storehouse seam 31 Storehouse seam both sides concrete interval pours for more than 7 days) after, ground floor horizontal structure 111 is poured, meanwhile, pour second segment and vertically tie Structure 12 to second is vertically jumped at storehouse seam 32 and level is to storehouse seam 21 is jumped, as shown in Figure 3.It is now placed in the wall construction ratio on right side The stagnant later layer of wall construction positioned at left side, but operation it is synchronous (while assembling reinforcement, while supporting module, while pouring coagulation Soil).The method that floor between floor jumps storehouse seam according to level in the same manner is stayed and set.
Then, in the same manner, refering to shown in Fig. 4 and Fig. 5, level on second segment vertical structure 12 is in storehouse seam 21 is jumped in level Jump storehouse construction second layer horizontal structure 121;Meanwhile, vertically jump storehouse seam 32 in second and be on second segment vertical structure 12 vertically Next section of vertical structure 13 construct to lower storehouse seam 33 and the level of jumping vertical together to jump storehouse seam 21 in jump storehouse;So in the same manner, left side wall A body floor faster than right side body of wall, this ensures that theres one layer of schedule in 7 days, and traditional construction is poured in left side Right side body of wall is poured within 7 days after finishing, after waiting right side body of wall to conserve 3-4 days, assembling reinforcement upwards, supporting module, on carrying out Floor is poured.And this inventive method, the time of the maintenance of right side body of wall, assembling reinforcement supporting module is all circulated vertically upward Jump within the 7 day time in storehouse, greatly save the time.
Finally, refering to level jump storehouse and vertical jump storehouse synchronous construction shown in Fig. 6, is repeated, until it is vertical to complete final stage The construction of that layer of horizontal structure 131 of structure 14 and the lower section of final stage vertical structure 14;Then at final stage vertical structure Level is jumped storehouse and is constructed last layer of horizontal structure 141 on 14, as shown in fig. 7, completing integrally-built construction.
Concrete of the present invention is vertically jumped storehouse construction method and is used vertically vertically using the construction method conversion that plane is jumped storehouse In structure, i.e., jump storehouse is divided on the vertical plane and is stitched, from the method that basis is constructed successively upwards, level is jumped into storehouse and vertically jump storehouse is same Step construction, accelerates efficiency of construction;And traditional construction is then to pour within 7 days after left side pours and finishes right side body of wall, right side body of wall is waited After maintenance 3-4 days, assembling reinforcement upwards, supporting module, a floor pours on carrying out.And the inventive method, by right-side wall Body maintenance, the time of assembling reinforcement supporting module are all circulated within the 7 day time for jumping storehouse vertically upward, when greatling save Between.
The present invention is described in detail above in association with drawings and Examples, those skilled in the art can basis Described above makes many variations example to the present invention.Thus, some of embodiment details should not constitute limitation of the invention, The present invention is by the scope defined using appended claims as protection scope of the present invention.

Claims (4)

1. a kind of concrete vertically jumps storehouse construction method, it is characterised in that including step:
The level of structure to be onstructed is marked off in the horizontal direction to storehouse seam is jumped, and structure to be onstructed is marked off in a vertical direction Multiple tracks vertically jumps storehouse seam;
To the level, to jumping, storehouse seam is vertical with first to jump storehouse seam to construction first paragraph vertical structure;
Level jump storehouse construction ground floor horizontal structure on the first paragraph vertical structure is in the level to storehouse seam is jumped;Together When, storehouse seam is vertically jumped in first and is on the first paragraph vertical structure vertical storehouse construction second segment vertical structure of jumping to second Vertically jump storehouse seam and the level and stitch to storehouse is jumped in road;
Level jump storehouse construction second layer horizontal structure on the second segment vertical structure is in the level to storehouse seam is jumped;Together When, vertically jump storehouse seam and be on the second segment vertical structure vertical storehouse of jumping in second and construct next section of vertical structure to next Vertically jump storehouse seam and the level and stitch to storehouse is jumped in road;Repeat to construct, until completing final stage vertical structure and last layer of water The construction of flat structure.
2. concrete as claimed in claim 1 vertically jumps storehouse construction method, it is characterised in that be set forth in the level to jump storehouse The step of seam is in level jump storehouse construction ground floor horizontal structure on the first paragraph vertical structure, including:
It is on reinforcing bar from first paragraph vertical structure to side colligation ground floor horizontal structure, installs first to storehouse seam is jumped in level The template of horizontal structure;
After the level of the first paragraph vertical structure sows foot jump storehouse condition to jump storehouse, the coagulation of ground floor horizontal structure is poured Soil, completes ground floor horizontal structure.
3. concrete as claimed in claim 1 vertically jumps storehouse construction method, it is characterised in that be set forth in first vertical jump storehouse The step of seam is on the first paragraph vertical structure vertical jump storehouse construction second segment vertical structure, including:
In first it is vertical jump storehouse seam be on first paragraph vertical structure upwards the reinforcing bar of colligation second segment vertical structure, install the The template of two sections of vertical structures;
After described first vertical jump storehouse sows foot jump storehouse condition, the concrete of second segment vertical structure is poured, complete second Section vertical structure.
4. concrete as claimed in claim 1 vertically jumps storehouse construction method, it is characterised in that described to complete final stage vertical The step of construction of structure and last layer of horizontal structure, including:
Construction completes final stage vertical structure and that layer of horizontal structure below the final stage vertical structure;
Level is jumped storehouse and is constructed last layer of horizontal structure on the final stage vertical structure.
CN201610899702.7A 2016-10-17 2016-10-17 Concrete vertical alternative bay construction method Pending CN106638998A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610899702.7A CN106638998A (en) 2016-10-17 2016-10-17 Concrete vertical alternative bay construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610899702.7A CN106638998A (en) 2016-10-17 2016-10-17 Concrete vertical alternative bay construction method

Publications (1)

Publication Number Publication Date
CN106638998A true CN106638998A (en) 2017-05-10

Family

ID=58856961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610899702.7A Pending CN106638998A (en) 2016-10-17 2016-10-17 Concrete vertical alternative bay construction method

Country Status (1)

Country Link
CN (1) CN106638998A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111396077A (en) * 2020-03-10 2020-07-10 北京市政建设集团有限责任公司 Tunnel air duct secondary lining construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1455054A (en) * 2003-05-08 2003-11-12 中国第二十冶金建设公司 Ordinary concrete block bunker-jump casting crack control method
CN102116036A (en) * 2009-12-30 2011-07-06 中国京冶工程技术有限公司厦门分公司 Method for constructing underground large building by combining top-down construction method technology with sequence construction method technology
KR101078782B1 (en) * 2011-03-08 2011-11-02 이형훈 Expansion joint using truss base support member and construction method thereof
CN102677898A (en) * 2011-03-17 2012-09-19 中铁二局股份有限公司 Sequence construction method for large area reinforced concrete floors
CN104131706A (en) * 2014-07-28 2014-11-05 中建一局集团建设发展有限公司 Vertical steel bar two-layer connecting structure of concrete framework structure and construction method of vertical steel bar two-layer connecting structure
CN104963357A (en) * 2015-07-08 2015-10-07 中国十七冶集团有限公司 Large-area RC basement structure sequence construction method
CN105569339A (en) * 2015-12-31 2016-05-11 青建集团股份公司 Super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1455054A (en) * 2003-05-08 2003-11-12 中国第二十冶金建设公司 Ordinary concrete block bunker-jump casting crack control method
CN102116036A (en) * 2009-12-30 2011-07-06 中国京冶工程技术有限公司厦门分公司 Method for constructing underground large building by combining top-down construction method technology with sequence construction method technology
KR101078782B1 (en) * 2011-03-08 2011-11-02 이형훈 Expansion joint using truss base support member and construction method thereof
CN102677898A (en) * 2011-03-17 2012-09-19 中铁二局股份有限公司 Sequence construction method for large area reinforced concrete floors
CN104131706A (en) * 2014-07-28 2014-11-05 中建一局集团建设发展有限公司 Vertical steel bar two-layer connecting structure of concrete framework structure and construction method of vertical steel bar two-layer connecting structure
CN104963357A (en) * 2015-07-08 2015-10-07 中国十七冶集团有限公司 Large-area RC basement structure sequence construction method
CN105569339A (en) * 2015-12-31 2016-05-11 青建集团股份公司 Super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111396077A (en) * 2020-03-10 2020-07-10 北京市政建设集团有限责任公司 Tunnel air duct secondary lining construction method

Similar Documents

Publication Publication Date Title
CN108312291A (en) A kind of concrete 3D printing building structure and its method of construction
CN105350454A (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN106894587A (en) Precast stair connection method
CN107893529A (en) Suitable for deep basal pit outer wall of basement PC template systems and its construction method
CN106049754B (en) The assembled section of the standard of assembly concrete combined column and the combined column being made up of assembly section
CN104295003A (en) Structural column construction method
CN105201204B (en) A kind of method and structure of rotten when preventing pouring reinforcement concrete column suspension column
CN102605883A (en) Light steel joist partition connecting structure and construction method thereof
CN106638998A (en) Concrete vertical alternative bay construction method
CN106930458A (en) Assembling type steel structure floor and its construction method
CN103615007A (en) Construction method for pouring basement exterior wall and bottom plate simultaneously
CN103015723A (en) Secondary casting molding construction method of cast-in-situ concrete stand structure
CN103452328A (en) Device and method for decreasing columns and reinforcing girders of reinforced concrete members
CN106285001B (en) A kind of facet integration segment quickly intersects flowing water construction method
CN106894554A (en) The Sloping roof structure and its construction method of prefabricated board Cast-in-situ Beam
CN205558264U (en) Space reentrant corner system of clear water inclined wall switching clear water swash plate
CN105862669B (en) A kind of construction method of Hydraulic and Hydro-Power Engineering dam rectangle steel lining
CN105839786A (en) Air-supported membrane building concrete anchor bolt pre-buried structure and construction method thereof
CN109853790A (en) A kind of EPS module concrete frame filling wall construction technology
CN106968334A (en) A kind of construction method of cast-in-place concrete framework secondary structure constructional column
CN208830582U (en) A kind of secondary structure PCization construction masonry
CN102220808A (en) Beam lowering construction method of frame structure
CN206599994U (en) One kind is exempted to pierce formula form bracing system branch head part
CN207244960U (en) A kind of Prefabricated stacking floor with tool-typed formwork for being used to drop plate region
CN206722170U (en) assembling type steel structure floor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170510

WD01 Invention patent application deemed withdrawn after publication