CN105569339A - Super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement - Google Patents

Super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement Download PDF

Info

Publication number
CN105569339A
CN105569339A CN201511029293.7A CN201511029293A CN105569339A CN 105569339 A CN105569339 A CN 105569339A CN 201511029293 A CN201511029293 A CN 201511029293A CN 105569339 A CN105569339 A CN 105569339A
Authority
CN
China
Prior art keywords
construction
construction section
section
combines
storehouse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201511029293.7A
Other languages
Chinese (zh)
Other versions
CN105569339B (en
Inventor
张同波
叶林
王宇飞
李翠翠
吴伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingjian Group Co Ltd
Original Assignee
Qingjian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingjian Group Co Ltd filed Critical Qingjian Group Co Ltd
Priority to CN201511029293.7A priority Critical patent/CN105569339B/en
Publication of CN105569339A publication Critical patent/CN105569339A/en
Application granted granted Critical
Publication of CN105569339B publication Critical patent/CN105569339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to the technical field of building construction, in particular to a super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement. The construction method comprises a construction organization technology combining sequence with skip and a construction organization technology combining intermittence with reinforcement. The super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement can be widely applied to the super-long concrete structure construction, can effectively control the concrete shrinkage crack, improve the engineering quality and accelerate the construction speed, and has relatively high economic and social benefits.

Description

The overlong jointless structural construction method that order combines with jumping storehouse, interval and reinforcement
Technical field
The present invention relates to technical field of building construction, particularly relate to the overlong jointless structural construction method that a kind of order combines with jumping storehouse, interval and reinforcement.
Background technology
Overlong Concrete Structure is constructed, much more existing adopt to arrange ater-casting method or carry out jumpings storehouse method constructs, but there is series of problems in ater-casting, and jump merely storehouse method and have larger limitation in practice of construction operating process.Adopt the method arranging ater-casting, in practice of construction operating process, often Yin Liu establishes ater-casting and causes a lot of construction quality problem.And jump storehouse fado for concrete in mass, and build and mostly be 7-10 days interval time, there is limitation.
Summary of the invention
In order to solve above-mentioned problems of the prior art, the invention provides the overlong jointless structural construction method that a kind of order combines with jumping storehouse, interval and reinforcement, this " order and jump storehouse, interval and strengthen " overlong jointless structural construction technology of combining can be widely used on Overlong Concrete Structure constructs, effectively can control Shrinkage Cracking of Concrete, improve workmanship, accelerate speed of application, there is higher economic and social benefit.
Technical scheme of the present invention is achieved in that
Order with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that: described construction method comprises order and jumps construction organization technology and interval that storehouse combines and strengthen the construction organization technology that combines;
Described order combines with jumping storehouse, interval combines with reinforcement and refers in concrete pouring construction the adjacent construction section meeting the shortest intermittent time, the construction method that employing order combines with jumping storehouse, to not meeting the shortest intermittent time, the adjacent construction section of jumping storehouse method can not being used again, adopt the construction method of intermittent reinforcing band;
The construction of described overlong jointless structural refers to that exceeding specification to length must arrange the building that ater-casting specify, does not arrange the method for the disposable sequence construction in any control temperature contraction ater-casting;
The shortest described intermittent time: by experiment and the concrete temperature that draws of theory analysis shrink, in controlled range, the shortest of adjacent concrete construction section builds interval time;
Described order can be divided into I and II great Qu, A/B/C/D/E/F/G/H eights' construction section with the operation side of jumping the construction organization technology that storehouse combines, and the construction organization technology that described order combines with jumping storehouse comprises order cross construction order, jumps storehouse sequence of construction;
Described interval is A/B/C/D/E/F construction section with the operation side of the construction organization technology that reinforcement combines, and arranges expansion reinforcing band between regional.
Further, described order cross construction order carries out cross construction respectively in I and II great Qu, and sequence of construction and A construction section proceed to B construction section, then proceed to C construction section, finally proceed to D construction section; E construction section proceeds to F construction section, then proceeds to G construction section, finally proceeds to H construction section.
Further, described jumping storehouse sequence of construction can be parallel construction or flowing water is constructed with parallel combination, and namely sequence of construction first carries out A construction section to C construction section, arrive E construction section again, finally arrive G construction section, then carry out B construction section to D construction section, arrive F construction section again, finally arrive H construction section.
Further, described interval is that A construction section proceeds to B construction section with the sequence of construction of the construction organization technology that reinforcement combines, then proceeds to C construction section; D construction section proceeds to E construction section, then proceeds to F construction section.
Further, described construction section is built simultaneously, described A construction section and D construction section, B construction section and E construction section, arranges expansion reinforcing band between C construction section and F construction section.
The invention has the beneficial effects as follows: this " order and jump storehouse, interval and strengthen " overlong jointless structural construction technology of combining can be widely used on Overlong Concrete Structure constructs, effectively can control Shrinkage Cracking of Concrete, improve workmanship, accelerate speed of application, there is higher economic and social benefit.Be directed to the condition of construction of different parts Overlong Concrete Structure, propose the overlong jointless structural construction method of " order combines with jumping storehouse, interval combines with reinforcement " of system, both the demand of anti-crack of Overlong Concrete Structure can have been met, combine with practice of construction hoc scenario again, under the prerequisite ensureing workmanship, accelerate the speed of construction, decrease the cost of construction.Meet the demand of anti-crack of Overlong Concrete Structure, improve workmanship; Building the shortest intermittent time combined with the sequence construction intermittent time, adapted to engineering practice of construction hoc scenario, accelerated speed of application, be widely used in, in Practical Project, having dissemination.
Accompanying drawing explanation
Fig. 1 is order cross construction sequential schematic;
Fig. 2 is for jumping storehouse method sequence of construction schematic diagram;
Fig. 3 is that body of wall and basement floor slab construction organize schematic diagram;
Fig. 4 is intermittent reinforcing band sequence of construction schematic diagram.
Reference numeral: 1, body of wall; 2, expansion reinforcing band.
Detailed description of the invention
Below in conjunction with specific embodiment, the present invention will be further described, but do not limit the present invention.
Order with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, construction method comprises order and jumps construction organization technology and interval that storehouse combines and strengthen the construction organization technology that combines;
Order combines with jumping storehouse, interval combines with reinforcement and refers in concrete pouring construction the adjacent construction section meeting the shortest intermittent time, the construction method that employing order combines with jumping storehouse, to not meeting the shortest intermittent time, the adjacent construction section of jumping storehouse method can not being used again, adopt the construction method of intermittent reinforcing band;
Overlong jointless structural construction refers to that exceeding specification to length must arrange the building that ater-casting specify, does not arrange the method for the disposable sequence construction in any control temperature contraction ater-casting;
The shortest intermittent time be by experiment and the concrete temperature that draws of theory analysis shrink, in controlled range, the shortest of adjacent concrete construction section builds interval time.
1, the construction organization technology sequentially combined with jumping storehouse
For ensureing the jointless construction of Overlong Concrete Structure, under different construction requirement, keeping jointless construction, mainly taking the mobilization that order combines with jumping storehouse.First choose a typical condition of construction to be described, the face of making even is 160 meters of * 60 meters of operation sides, is divided into Liang Ge great district: I and II; 8 construction sections, are numbered A/B/C/D/E/F/G/H.
(1) as shown in Figure 1, when order cross construction can meet the requirement of the shortest intermittent time, then subregional order cross construction is organized; Can be changed the intermittent time by the construction organization of adjustment critical process (reinforcing bar), to meet the requirement of the shortest intermittent time or duration.In I, II Liang Ge great district, carry out cross construction respectively, sequence of construction as shown in the figure, i.e. construction section A → B → C → D and construction section E → F → G → H.The duration is tight and when can meeting the requirement of the shortest intermittent time, can pass through the node extending forward critical process, make it form certain parallel construction, to accelerate speed of application, that is: parallel combination with flowing water is constructed.Critical process reinforcing bar binding carries out certain parallel construction, thus accelerates speed of application.
(2) as shown in Figure 2, the duration tight and can not meet the shortest intermittent time require time, can select the method for jumping storehouse construction, its construction organization should be parallel construction or flowing water are constructed with parallel combination.Namely construction section A, C, E, G section of first constructing is constructed construction section B, D, F, H section again.Be concrete in mass at main building, its shortest intermittent time is long and sequence construction can not meet the demands time, also can adopt and jump storehouse with order in conjunction with construction.
(3) body of wall 1 and basement floor slab construction tissue.One, consistent with base plate subregion; Its two, body of wall 1 can not meet the intermittent time require time, subregion can be increased to reduce the pinch confinement of base plate to body of wall 1.As shown in Figure 3, body of wall 1 has carried out corresponding subregion by base plate.
2, interval and the construction organization technology strengthening combining
As shown in Figure 4, when engineering adjacent area need be built for meeting construction period in 1-3 days, can not the shortest intermittent time be met, when can not carry out again the method construction of jumping storehouse, the construction method of selectively-expandable reinforcing band 2.Here select a typical project case, the method is described.
Operation side is A/B/C/D/E/F six construction sections, and sequence construction is construction section A → B → C and construction section D → E → F; As required, construction section is built simultaneously, can arrange expansion reinforcing band 2, reach the object of synchronous construction between A-D, B-E, C-F district, saves the duration.
Be only the preferred embodiment of invention described in upper, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (5)

1. order with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that: described construction method comprises order and jumps construction organization technology and interval that storehouse combines and strengthen the construction organization technology that combines;
Described order combines with jumping storehouse, interval combines with reinforcement and refers in concrete pouring construction the adjacent construction section meeting the shortest intermittent time, the construction method that employing order combines with jumping storehouse, to not meeting the shortest intermittent time, the adjacent construction section of jumping storehouse method can not being used again, adopt the construction method of intermittent reinforcing band;
The construction of described overlong jointless structural refers to that exceeding specification to length must arrange the building that ater-casting specify, does not arrange the method for the disposable sequence construction in any control temperature contraction ater-casting;
The shortest described intermittent time: by experiment and the concrete temperature that draws of theory analysis shrink, in controlled range, the shortest of adjacent concrete construction section builds interval time;
Described order can be divided into I and II great Qu, A/B/C/D/E/F/G/H eights' construction section with the operation side of jumping the construction organization technology that storehouse combines, and the construction organization technology that described order combines with jumping storehouse comprises order cross construction order, jumps storehouse sequence of construction;
Described interval is A/B/C/D/E/F construction section with the operation side of the construction organization technology that reinforcement combines, and arranges expansion reinforcing band between regional.
2. order according to claim 1 with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that, described order cross construction order carries out cross construction respectively in I and II great Qu, sequence of construction and A construction section proceed to B construction section, proceed to C construction section again, finally proceed to D construction section; E construction section proceeds to F construction section, then proceeds to G construction section, finally proceeds to H construction section.
3. order according to claim 2 with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that, described jumping storehouse sequence of construction can be parallel construction or flowing water is constructed with parallel combination, namely sequence of construction first carries out A construction section to C construction section, arrive E construction section again, finally arrive G construction section, then carry out B construction section to D construction section, arrive F construction section again, finally arrive H construction section.
4. order according to claim 1 with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that, described interval is that A construction section proceeds to B construction section with the sequence of construction of the construction organization technology that reinforcement combines, then proceeds to C construction section; D construction section proceeds to E construction section, then proceeds to F construction section.
5. order according to claim 4 with jump storehouse, interval and strengthen the overlong jointless structural construction method that combines, it is characterized in that, described construction section is built simultaneously, described A construction section and D construction section, B construction section and E construction section, arranges expansion reinforcing band between C construction section and F construction section.
CN201511029293.7A 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase Active CN105569339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511029293.7A CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511029293.7A CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Publications (2)

Publication Number Publication Date
CN105569339A true CN105569339A (en) 2016-05-11
CN105569339B CN105569339B (en) 2017-11-17

Family

ID=55879910

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511029293.7A Active CN105569339B (en) 2015-12-31 2015-12-31 Order and the overlong jointless structural construction method jumped storehouse, intermittently combined with strengthening phase

Country Status (1)

Country Link
CN (1) CN105569339B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638998A (en) * 2016-10-17 2017-05-10 中国建筑第八工程局有限公司 Concrete vertical alternative bay construction method
CN108396899A (en) * 2018-03-23 2018-08-14 中国十七冶集团有限公司 A kind of ground library concrete plate surface jumps block formula pouring structure and its construction method
CN112709261A (en) * 2020-12-22 2021-04-27 碧源建工有限公司 Construction method based on skip method and intermittent expansion reinforcing belt
CN113897909B (en) * 2021-09-07 2022-09-30 中建一局集团建设发展有限公司 Construction method of expansion reinforcing band connecting structure in complex arc-shaped water channel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06313305A (en) * 1993-04-28 1994-11-08 Kawasaki Steel Corp Jointless multiple span floor slab bridge
NL9300879A (en) * 1993-05-21 1994-12-16 Rudolf Van Der Woerdt Method for laying a suspended floor on a resilient underlayer
US5760106A (en) * 1995-07-05 1998-06-02 Board Of Trustees Operating Michigan State University Sealant method of epoxy resin-clay composites
CN102251674A (en) * 2011-06-05 2011-11-23 山东宁建建设集团有限公司 Bunker-skipping type seamless construction method of ultra-long concrete structure
CN102677899A (en) * 2012-03-09 2012-09-19 中石油东北炼化工程有限公司吉林设计院 Seamless structural method of overlong reinforced concrete pond

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06313305A (en) * 1993-04-28 1994-11-08 Kawasaki Steel Corp Jointless multiple span floor slab bridge
NL9300879A (en) * 1993-05-21 1994-12-16 Rudolf Van Der Woerdt Method for laying a suspended floor on a resilient underlayer
US5760106A (en) * 1995-07-05 1998-06-02 Board Of Trustees Operating Michigan State University Sealant method of epoxy resin-clay composites
CN102251674A (en) * 2011-06-05 2011-11-23 山东宁建建设集团有限公司 Bunker-skipping type seamless construction method of ultra-long concrete structure
CN102677899A (en) * 2012-03-09 2012-09-19 中石油东北炼化工程有限公司吉林设计院 Seamless structural method of overlong reinforced concrete pond

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638998A (en) * 2016-10-17 2017-05-10 中国建筑第八工程局有限公司 Concrete vertical alternative bay construction method
CN108396899A (en) * 2018-03-23 2018-08-14 中国十七冶集团有限公司 A kind of ground library concrete plate surface jumps block formula pouring structure and its construction method
CN112709261A (en) * 2020-12-22 2021-04-27 碧源建工有限公司 Construction method based on skip method and intermittent expansion reinforcing belt
CN113897909B (en) * 2021-09-07 2022-09-30 中建一局集团建设发展有限公司 Construction method of expansion reinforcing band connecting structure in complex arc-shaped water channel

Also Published As

Publication number Publication date
CN105569339B (en) 2017-11-17

Similar Documents

Publication Publication Date Title
CN105569339A (en) Super-long structure seamless construction method combining sequence with skip and combining intermittence with reinforcement
MY190080A (en) Composite structural wall and method of construction thereof
EP2567033A4 (en) A building structure
Song et al. Transfer length and splitting force calculation for pretensioned concrete girders with high-capacity strands
CN203639944U (en) Vault immersed tube tunnel
CN113898102A (en) Ribbed concrete laminated slab
CN207482772U (en) A kind of applied to precasting yard concrete transportation and the operation for moving beam vehicle
CN103061509A (en) Construction process for implementing post-cast strip casting by post-cast strip stiff steel pipe support system
CN103195200A (en) Steel bar truss buckle hanging type floor support plate
CN106285001B (en) A kind of facet integration segment quickly intersects flowing water construction method
CN107012973A (en) The masonry structure and its construction method of a kind of new ribs building block
CN106401016A (en) Non-bearing light cavity wall poured with main body at the same time and construction method thereof
CN104786368A (en) Reinforcement forming technology
CN203807954U (en) Box girder strengthening structure based on steel plate-concrete and unbonded pre-stressing tendons
CN201627360U (en) Turnover formwork construction device
CN103526877B (en) A kind of precast concrete
CN204282816U (en) A kind of girder template
CN203795262U (en) Construction site steel road
MX354071B (en) Roof on the basis of lightweight blocks and method for constructing same.
CN206917056U (en) A kind of construction wall insulation blocks
CN206233406U (en) A kind of non-bearing lightweight chamber wall poured simultaneously with main body
CN105317216A (en) Wall body reversed construction method and wall body and concrete framework casting structure
CN205444473U (en) Joint construction of concrete beam both sides supporting different grade type floor
CN103624871A (en) Novel concrete pouring and conveying system
CN203034675U (en) Steel bar composite truss composite board

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant