CN106638509A - Tunnel structure capable of reducing side slope excavation and construction method thereof - Google Patents

Tunnel structure capable of reducing side slope excavation and construction method thereof Download PDF

Info

Publication number
CN106638509A
CN106638509A CN201710003852.XA CN201710003852A CN106638509A CN 106638509 A CN106638509 A CN 106638509A CN 201710003852 A CN201710003852 A CN 201710003852A CN 106638509 A CN106638509 A CN 106638509A
Authority
CN
China
Prior art keywords
tunnel
side slope
slope
concrete
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710003852.XA
Other languages
Chinese (zh)
Inventor
张涛
俞灵光
秦晓亮
彭继乐
赵继勇
余志超
刘淑芳
赵星
张毅驰
孙楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201710003852.XA priority Critical patent/CN106638509A/en
Publication of CN106638509A publication Critical patent/CN106638509A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel structure capable of reducing side slope excavation and a construction method thereof, wherein the tunnel structure comprises a tunnel body intersected with a side slope, a vertically arranged concrete retaining wall is arranged on the side wall, close to the side slope, of the tunnel body, and a reinforced concrete cover arch matched with the arch crown of the tunnel body is arranged at the top of the concrete retaining wall; the construction method comprises the steps of site investigation, construction preparation, construction of a semi-open tunnel, construction of a semi-hidden tunnel, support and the like. The invention adopts the semi-hidden and semi-exposed tunnel to solve the problem of environmental damage caused by large-scale side slope excavation, and compared with the traditional method, the method changes passive mode into active mode, shortens the construction period and improves the engineering benefit.

Description

A kind of tunnel structure and its construction method that can reduce slope excavating
Technical field
The present invention relates to tunnel and its technical field of construction, and in particular to a kind of tunnel structure that can reduce slope excavating and Its construction method.
Background technology
In Hydraulic and Hydro-Power Engineering construction and running, most of power stations are located at mountain area, in highway geometry, tunnel axle In the case of line adjustment difficulty, Shang Ba highways and Chang Nei highways during excavating or biasing serious tunnel mouth hanging, unavoidable shape Excavate into Slope with multi-step, then need to carry out dam public affairs in excavation formation in side slope position in the case of originally excavation circuit is unalterable Road Huo Changnei highways, when side slope position is excavated, traditional scheme is by all cubic meters of wholes of predetermined excavation position Excavate, form Shang Ba highway Huo Changnei highways builds space, then the slope after excavation is carried out into supporting, severe is excavated not only A large amount of original vegetation can be destroyed, high slope rockmass is also thus brought, construction fussy degree is increased, and has delayed the duration, together When also increase investment.For medium and small project, slope excavating is reduced, investment reduction and the problem of reduction of erection time increasingly cause How the attention of people, take maximally effective processing scheme both to have met requirement of engineering, and ring water guaranteed request can be met again, becomes One of passive problem actively, to be the consideration of designer's emphasis, but do not have corresponding technical scheme in prior art.
The content of the invention
The present invention is intended to provide a kind of tunnel structure and its construction method that can reduce slope excavating, to solve existing Li Shui Electrical engineering build in Slope with multi-step existing difficulty of construction is big when excavating, construction period length, construction investment are big, vegetation deterioration is tight The problems such as weight.
The present invention is achieved by following technical solution:
A kind of tunnel structure that can reduce slope excavating, including the tunnel body intersected with side slope, tunnel body is near side The side wall on slope is provided with the concrete guard wall of vertical arrangement, and concrete guard wall top is provided with the reinforcing bar matched with tunnel body vault Concrete jacket encircles.
The tunnel body vault is provided with horizontal and vertical side slope slip casting solidification anti-skid structure.
The tunnel inner body wall is provided with the reinforced concrete lining layer layer fitted with it.
The tunnel body outer wall is provided with the steelframe fitted with it and supports.
The concrete guard wall bottom is provided with some friction piles.
Insert concrete guard wall in the friction pile top.
The construction method of the above-mentioned tunnel structure that can reduce slope excavating is comprised the following steps:
A, the tunnel mouth hanging position big to High Side Slope of Highway section, bias in upper dam High Side Slope of Highway section, field are surveyed Examine, determine the construction location of side slope and formulate construction plan, be ready for construction equipment;
B, the side slope to construction location are cleared up, and are removed vegetation and are excavated out barricade casting space;
C, friction pile is set below barricade casting space, friction pile is poured in place concrete structure or precast concrete Structure;
D, lay above friction pile and backplate and pour out concrete guard wall, concrete guard wall inwall is vertically, outer wall inclines;
E, concrete guard wall lay reinforcing bar after meeting age at the top of it, then pour out and match with tunnel body vault Reinforced concrete soil suite arch;
F, the longitudinal grouting tube for being inserted into some longitudinal directions and being spaced apart in side slope, longitudinal grouting tube is according to tunnel sheet Body vault radian is arranged;
If G, the insertion dried layer horizontal grouting tube perpendicular with longitudinal grouting tube above longitudinal grouting tube;
H, respectively cement mortar injected into side slope by longitudinal grouting tube and horizontal grouting tube;
I, the concrete slurry of injection side slope and reinforced concrete soil suite arch meet tunnel excavation body after age, tunnel excavation Being supported using steelframe while body carries out first liner timbering;
In steelframe stayed surface pouring reinforcement concrete lining cutting after the completion of J, first liner timbering, reinforced concrete lining layer has been laid Into after.
The spacing of the friction pile is 3m.
The invention has the beneficial effects as follows:
Compared with prior art, what the present invention was provided can reduce the tunnel structure and its construction method of slope excavating, adopt Hazy tunnel structure form, in the case of Shang Ba highways, Chang Nei highways, tunnel mouth hanging equal-pitch contour difficulty, by upper The positions such as the dam highway inner side tunnel mouth hanging serious compared with high slope section, bias compared with high slope section, Chang Nei highways inner side, are arranged Hazy tunnel structure, reduces excavation and the supporting of side slope, and then guarantees the safety of highway communication or tunnel mouth hanging.Solve The environmental disruption problem that extensive excavation slope is brought, changes from passive to active compared with conventional method, shortens the construction period, Improve project benefit.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
In figure:1- friction piles, 2- concrete guard walls, 3- reinforced concretes soil suite arch, the horizontal grouting tubes of 4-, 5- steelframes Support, 6- reinforced concrete lining layer layers, 7- longitudinal directions grouting tube, 8- side slopes, 9- tunnel bodies.
Specific embodiment
Technical scheme is described further below in conjunction with drawings and Examples, but required protection domain It is not limited to described;
As shown in figure 1, the tunnel structure that can reduce slope excavating that the present invention is provided, including the tunnel intersected with side slope 8 Body 9, tunnel body 9 is provided with the concrete guard wall 2 of vertical arrangement near the side wall of side slope 8, the top of concrete guard wall 2 be provided with The reinforced concrete soil suite arch 3 that the vault of tunnel body 9 matches.
The vault of tunnel body 9 is provided with horizontal and vertical side slope slip casting solidification anti-skid structure.The tunnel body 9 Inwall is provided with the reinforced concrete lining layer layer 6 fitted with it.The outer wall of tunnel body 9 is provided with the steel fitted with it Frame supports 5.The bottom of the concrete guard wall 2 is provided with some friction piles 1.Insert concrete guard wall 2 in the top of the friction pile 1.
Embodiment:
The tunnel mouth hanging position big to High Side Slope of Highway section, bias in upper dam High Side Slope of Highway section, field is reconnoitred, Determine the construction location of side slope 8 and formulate construction plan, be ready for construction equipment;The side slope 8 of construction location is cleared up, Remove vegetation and excavate out barricade casting space;Friction pile 1 is set below barricade casting space, and the spacing of friction pile 1 is 3m, Friction pile 1 is poured in place concrete structure or precast concrete;Backplate is laid in the top of friction pile 1 and pour out coagulation Native barricade 2, concrete guard wall 2 is C20 concrete, and the inwall of concrete guard wall 2 is vertical, outer wall is inclined;Concrete guard wall 2 meets age Reinforcing bar is laid at the top of it after phase, the reinforced concrete soil suite arch 3 matched with the vault of tunnel body 9 is then poured out;In side slope 8 Some longitudinal directions and the longitudinal grouting tube 7 being spaced apart are inserted into, longitudinal grouting tube 7 is according to the vault radian cloth of tunnel body 9 Put;If in the horizontal grouting tube 4 that the top of longitudinal grouting tube 7 insertion dried layer is perpendicular with longitudinal grouting tube 7;Pass through respectively Longitudinal grouting tube 7 and horizontal grouting tube 4 inject concrete slurry into side slope 8;The concrete slurry and steel of injection side slope 8 Reinforced concrete set arch 3 meets tunnel excavation body 9 after age, supports 5 to carry out a phase using steelframe while tunnel excavation body 9 Supporting;5 surface pouring reinforcement concrete lining cutting 6 are supported in steelframe after the completion of first liner timbering, reinforced concrete lining layer 6 is C25 steel Reinforced concrete, after the completion of reinforced concrete lining layer 6 is laid.
Above-described embodiment is only a preferred embodiment of the present invention, and the protection domain being not intended to limit the present invention is all Done deformation, modification or equivalent etc., all should fall into the protection model of the present invention on the basis of technical scheme Enclose.

Claims (8)

1. a kind of tunnel structure that can reduce slope excavating, it is characterised in that:Including the tunnel body (9) intersected with side slope (8), Tunnel body (9) is provided with the concrete guard wall (2) of vertical arrangement near the side wall of side slope (8), and concrete guard wall (2) top is provided with Encircle (3) with the reinforced concrete soil suite that tunnel body (9) vault matches.
2. the tunnel structure that slope excavating can be reduced according to claim 1, it is characterised in that:The tunnel body (9) Vault is provided with horizontal and vertical side slope slip casting solidification anti-skid structure.
3. the tunnel structure that slope excavating can be reduced according to claim 1, it is characterised in that:The tunnel body (9) Inwall is provided with the reinforced concrete lining layer layer (6) fitted with it.
4. the tunnel structure that slope excavating can be reduced according to claim 1, it is characterised in that:The tunnel body (9) Outer wall is provided with the steelframe fitted with it and supports (5).
5. the tunnel structure that slope excavating can be reduced according to claim 1, it is characterised in that:The concrete guard wall (2) bottom is provided with some friction piles (1).
6. the tunnel structure that slope excavating can be reduced according to claim 5, it is characterised in that:Friction pile (1) top End insertion concrete guard wall (2).
7. a kind of construction method of the tunnel structure that can reduce slope excavating as described in any one of claim 1-6, its feature It is:The method is comprised the following steps:
A, the tunnel mouth hanging position big to High Side Slope of Highway section, bias in upper dam High Side Slope of Highway section, field are reconnoitred, really The construction location on deckle slope (8) simultaneously formulates construction plan, is ready for construction equipment;
B, the side slope (8) to construction location are cleared up, and are removed vegetation and are excavated out barricade casting space;
C, setting friction pile (1) below barricade casting space, friction pile (1) is poured in place concrete structure or concrete Soil structure;
D, backplate and pour out concrete guard wall (2) in the laying of friction pile (1) top, concrete guard wall (2) inwall vertically, outer wall Incline;
E, concrete guard wall (2) lay reinforcing bar after meeting age at the top of it, then pour out and tunnel body (9) vault phase Reinforced concrete soil suite arch (3) matched somebody with somebody;
F, the longitudinal grouting tube (7) for being inserted into some longitudinal directions and being spaced apart in side slope (8), longitudinal grouting tube (7) according to Tunnel body (9) vault radian is arranged;
G, in longitudinal grouting tube (7) if the top insertion dried layer horizontal grouting tube perpendicular with longitudinal grouting tube (7) (4);
H, respectively cement mortar injected into side slope (8) by longitudinal grouting tube (7) and horizontal grouting tube (4);
I, the concrete slurry of injection side slope (8) and reinforced concrete soil suite arch (3) meet tunnel excavation body (9) after age, open (5) are supported to carry out first liner timbering using steelframe while digging tunnel body (9);
The pouring reinforcement concrete lining cutting of (5) surface (6) are supported in steelframe after the completion of J, first liner timbering, reinforced concrete lining layer (6) After the completion of laying.
8. the construction method of the tunnel structure that can reduce slope excavating according to claim 7, it is characterised in that:It is described anti- The spacing of sliding pile (1) is 3m.
CN201710003852.XA 2017-01-04 2017-01-04 Tunnel structure capable of reducing side slope excavation and construction method thereof Pending CN106638509A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710003852.XA CN106638509A (en) 2017-01-04 2017-01-04 Tunnel structure capable of reducing side slope excavation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710003852.XA CN106638509A (en) 2017-01-04 2017-01-04 Tunnel structure capable of reducing side slope excavation and construction method thereof

Publications (1)

Publication Number Publication Date
CN106638509A true CN106638509A (en) 2017-05-10

Family

ID=58844092

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710003852.XA Pending CN106638509A (en) 2017-01-04 2017-01-04 Tunnel structure capable of reducing side slope excavation and construction method thereof

Country Status (1)

Country Link
CN (1) CN106638509A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110747904A (en) * 2019-11-26 2020-02-04 山西省交通规划勘察设计院有限公司 Highway tunnel bias open cut tunnel structural form and construction method thereof
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN112647536A (en) * 2020-12-04 2021-04-13 四川省交通勘察设计研究院有限公司 Open cut tunnel construction method without side slope disturbance

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201635745U (en) * 2010-04-08 2010-11-17 安徽省交通规划设计研究院 Ribbed-arch multi-arch tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN103206219A (en) * 2013-05-06 2013-07-17 浙江省宏途交通建设有限公司 Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method
CN203308470U (en) * 2013-05-28 2013-11-27 山西省交通科学研究院 Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN104806267A (en) * 2015-04-29 2015-07-29 中铁第一勘察设计院集团有限公司 Shield end socket reinforcing system of scree soil layer advance large pipe roof and construction method thereof
CN104989425A (en) * 2015-06-29 2015-10-21 上海市政工程设计研究总院(集团)有限公司 Underground excavation hole entering supporting structure and method
CN105133625A (en) * 2015-09-16 2015-12-09 中南大学 Reinforced structure of tunnel transversely penetrating through sliding slope and construction method
CN106223989A (en) * 2016-08-10 2016-12-14 兰州理工大学 Unsymmetrial loading tunnel hole excavation safeguard structure and construction method
CN206396732U (en) * 2017-01-04 2017-08-11 中国电建集团贵阳勘测设计研究院有限公司 Can reduce tunnel structure of side slope excavation

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201635745U (en) * 2010-04-08 2010-11-17 安徽省交通规划设计研究院 Ribbed-arch multi-arch tunnel
CN102518453A (en) * 2011-12-14 2012-06-27 中铁十二局集团有限公司 Quick tunnel-entrance construction method for bias-pressure shallow-buried or single-pressure tilting arenaceous loess tunnels
CN103206219A (en) * 2013-05-06 2013-07-17 浙江省宏途交通建设有限公司 Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method
CN203308470U (en) * 2013-05-28 2013-11-27 山西省交通科学研究院 Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section
CN204419195U (en) * 2014-12-29 2015-06-24 山西省交通科学研究院 A kind of supporting and protection structure pattern being applicable to tunnel portal section
CN104806267A (en) * 2015-04-29 2015-07-29 中铁第一勘察设计院集团有限公司 Shield end socket reinforcing system of scree soil layer advance large pipe roof and construction method thereof
CN104989425A (en) * 2015-06-29 2015-10-21 上海市政工程设计研究总院(集团)有限公司 Underground excavation hole entering supporting structure and method
CN105133625A (en) * 2015-09-16 2015-12-09 中南大学 Reinforced structure of tunnel transversely penetrating through sliding slope and construction method
CN106223989A (en) * 2016-08-10 2016-12-14 兰州理工大学 Unsymmetrial loading tunnel hole excavation safeguard structure and construction method
CN206396732U (en) * 2017-01-04 2017-08-11 中国电建集团贵阳勘测设计研究院有限公司 Can reduce tunnel structure of side slope excavation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN110985002B (en) * 2019-11-11 2021-03-23 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN110747904A (en) * 2019-11-26 2020-02-04 山西省交通规划勘察设计院有限公司 Highway tunnel bias open cut tunnel structural form and construction method thereof
CN112647536A (en) * 2020-12-04 2021-04-13 四川省交通勘察设计研究院有限公司 Open cut tunnel construction method without side slope disturbance

Similar Documents

Publication Publication Date Title
CN108035335A (en) A kind of construction freezing method well shaft type underground parking garage method
CN104452809A (en) Ultra-shallow buried tunnel cover-excavation construction method
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN101864960A (en) Carst region double-arch road tunnel construction method
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN106522989A (en) Air shaft structure and shield excavation parallel construction method
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN106638509A (en) Tunnel structure capable of reducing side slope excavation and construction method thereof
CN107905798A (en) The method that flat top wall boring construction is carried out using central drift method
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN108374663B (en) Twice-molding construction method for sandy gravel geological tunnel
CN111271066B (en) Bias-pressure hole-entering oblique crossing positive construction method
CN108343035A (en) River construction method is worn under shallow tunnel
CN106761771A (en) A kind of construction method for crossing native shallow tunnel on rock under the location of mountain valley
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN206396732U (en) Can reduce tunnel structure of side slope excavation
CN105840203A (en) Large section loess tunnel pre-cutting method construction method
CN206768831U (en) Support, anchor cable post-tensioning HU type building enclosures before a kind of steel pipe
CN205605215U (en) Big section loess tunnel is grooving method construction structures in advance
CN206768832U (en) Support, anchor cable post-tensioning H type component building enclosures before a kind of steel pipe
CN211950500U (en) Bias hole-entering structure
CN215292503U (en) Tunnel structure passing through karst cavity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510