CN105672450A - Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure - Google Patents

Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure Download PDF

Info

Publication number
CN105672450A
CN105672450A CN201610086577.8A CN201610086577A CN105672450A CN 105672450 A CN105672450 A CN 105672450A CN 201610086577 A CN201610086577 A CN 201610086577A CN 105672450 A CN105672450 A CN 105672450A
Authority
CN
China
Prior art keywords
steel sheet
tunnel structure
sheet pile
laying method
larsen steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610086577.8A
Other languages
Chinese (zh)
Inventor
曹依雯
庄静
吴坚慧
邵建伟
熊艾玲
董瑶瑶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201610086577.8A priority Critical patent/CN105672450A/en
Publication of CN105672450A publication Critical patent/CN105672450A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a laying method for a large-aperture water draining pipeline parallel to the upper part of an existing metro tunnel structure. The method comprises the following steps: step 1, reinforcing the bottom of a groove with a hierarchical grouting process by adopting a mixture of cement and water glass; step 2, performing construction supporting by Larsen steel sheet piles: adopting the Larsen steel sheet piles as supporting piles; step 3, performing excavation and arranging steel supports and steel enclosing purlins, wherein the steel supports are fixedly connected with the Larsen steel sheet piles through section steel; step 4, excavating to the bottom of a foundation pit and ramming a pipeline foundation to be flat; step 5, laying a glass fiber reinforced plastic sand-included large-aperture pipeline on the pipeline foundation, constructing a main body structure, and after the main body structure reaches the design strength, performing backfill from bottom to top until the backfill height reaches a design ground elevation; and step 6, pulling out the Larsen steel sheet piles and filling a gap after pulling out the Larsen steel sheet piles or the steel enclosing purlins. The method is high in construction speed and can ensure that the displacement of the top of each supporting pile in the foundation pit excavation process and the settling volume of surrounding ground are within an acceptable range.

Description

It is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure
Technical field
The present invention relates to technical field of building construction, particularly relate to and a kind of be parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure.
Background technology
In order to improve the drainage waterlogging prevention ability in city, it is generally required to arrange bigbore drainage pipeline, laying large-caliber drainage pipeline becomes the important measures solving completed region of the city road hydrops. But, in completed region of the city, substantial amounts of subway tunnel structure has been carried out complete, if needing to arrange large-caliber drainage pipeline in drainage system, then can only implement above subway tunnel structure.
At present, be arranged at the large-caliber drainage pipeline above subway tunnel structure and generally adopt reinforced concrete pipiline, the time that in laid processes, foundation ditch opens wide need to meet in concrete reinforced pipe the curing time on basis, large diameter reinforced concrete pipe the lifting time, match concrete manhole formwork erection, build and curing time etc.; The space of excavation of foundation pit need to meet the work surface of armored concrete lifting and the installation requirement of supporting pipe pillow, base plate and bed course. It is said that in general, the time that foundation ditch opens wide is more of a specified duration, the space of excavation is more big, and the soil deformation amount bottom the foundation ditch brought is more big. Owing to the deadweight in large diameter reinforced concrete pipe road is heavier, the specification of required lifting machine equipment is big, and the additional load produced in lower pipe process is also bigger.
Additionally, the drainage pipeline laid at present is also frequently with line slab supporting or channel-section steel steel sheet pile enclosure, owing to the rigidity of the measure of going along with sb. to guard him is less, the surrounding ground sedimentation brought is relatively big, but also to match with on-site groundwater treatment scheme. When closing on structures place and laying drainage pipeline, the rotary churning pile fender post as drainage pipeline foundation ditch of double diameter 800mm is added frequently with the root pile of diameter 400mm, to reduce the impact closing on structures, but the vertical first horizontal support of this fender post need to adopt reinforced concrete fortifield village purlin, fender post and enclose purlin and be required for maintenance, the activity duration is also longer.
But, if adopting the laying of above-mentioned large diameter pipeline repeatedly, for parallel laid large diameter pipeline above existing subway tunnel structure, owing to subway tunnel structure is very sensitive for surrounding environment change, carrying out job execution particularly in tunnel upper can make tunnel structure be subjected to displacement and deform, even more so that tunnel structure cracking seepage. Therefore, the top laying large-caliber drainage pipeline being parallel to existing subway tunnel structure always is and brings great challenge to the design of city outdoor drainage in the forbidden zone of pipeline laying.
Therefore, those skilled in the art need badly and study that a kind of speed of application is fast, can ensure that the displacement on fender post top in Excavation Process and surrounding ground settling amount within the acceptable range be parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure.
Summary of the invention
Because the drawbacks described above of prior art, the invention provides that a kind of speed of application is fast, can ensure that the displacement on fender post top in Excavation Process and surrounding ground settling amount within the acceptable range be parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure.
For achieving the above object, the invention provides and a kind of be parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure, it is characterized in that, comprise the steps: step one, adopt the cement mixture with waterglass, by delamination pour slurry technique, channel bottom is carried out consolidation process; Step 2, construction supporting Larsen steel sheet pile; Adopting Larsen steel sheet pile as fender post, the edge of described Larsen steel sheet pile is provided with elongated waterproof fore shaft; Step 3, excavating and arrange bracing members and steel encloses purlin, described bracing members is fixed with described Larsen steel sheet pile by shaped steel and is connected; Step 4, dig to, at the bottom of foundation ditch, ramming flat pipeline foundation; Step 5, on described pipeline foundation, lay chamber for fibre-reinforced plastics sand inclusion large diameter pipeline, agent structure of constructing, reach, after design strength, to backfill from bottom to top until agent structure, until being backfilled to design ground elevation; Step 6, extracts described Larsen steel sheet pile, and fills described Larsen steel sheet pile or described steel encloses the space after purlin is extracted.
In some preferred implementations, the fresh Portland cement that described cement adopts intensity to be 42.5, described cement is as follows with the component of the mixture of waterglass: grouting volume ratio is more than or equal to 20%, the ratio of mud is 0.5, cement and waterglass volume ratio are 1:1, and modulus of water glass is 3.0~3.3.
In some preferred implementations, in described elongated waterproof fore shaft, it is filled with hermetic seal material.
In some preferred implementations, described hermetic seal material is butter or Colophonium.
In some preferred implementations, described Larsen steel sheet pile adopts screen-type to squeeze into method construction, and adopts the mode of static pressure pile-sinking.
In some preferred implementations, described steel is enclosed and is connected by welding manner between purlin with described bracing members, described Larsen steel sheet pile.
In some preferred implementations, described steel encloses the junction of purlin and described bracing members, described Larsen steel sheet pile and is provided with stiffener.
In some preferred implementations, adopting 25cm gravel sand basis when ramming flat pipeline foundation, 5cm yellow ground lining is flat, and compactness is 90%.
In some preferred implementations, in described step 5 during backfill, after being backfilled to the elevation place of described bracing members, remove bracing members again.
In some preferred implementations, excavation lays a length of tubing every time, adopts the mode gone along with sb. to guard him equally and excavate to lay next length of tubing after having backfilled again.Every length of tubing length is 3m or 4.5m.
In some preferred implementations, in step 6, the cement grout adopting the ratio of mud to be 0.8 fills steel sheet pile or steel encloses the space after purlin is extracted.
Beneficial effects of the present invention:
The above-mentioned paving mode of the present invention, adopt Larsen steel sheet pile as fender post, excavation of foundation pit space decreases about 20%, space occupation of land decreases about 50%, simultaneously because adopt bracing members and steel to enclose purlin, the unlimited time of foundation ditch about decreases 50%, accelerates speed of application, effectively reduces the impact on existing subway tunnel structure.
In the above-mentioned paving mode of the present invention; adopt Larsen steel sheet pile as fender post; the edge of Larsen steel sheet pile is provided with elongated waterproof fore shaft; it is filled with hermetic seal material in elongated waterproof fore shaft; so that be mutually twisted into the continuous retaining wall that can intercept water and mutually pin down between Larsen steel sheet pile; ensure that the rigidity of retaining design and intensity, it is ensured that in Excavation Process, the displacement on fender post top and surrounding ground settling amount are within the acceptable range.
In the above-mentioned paving mode of the present invention, adopt cement and waterglass delamination pour slurry mode that the soil body of channel bottom is reinforced, add the intensity of passive area inside foundation ditch, effectively reduce internal force and the deformation of retaining design, large diameter pipeline is provided reliable base support simultaneously.
Additionally, large diameter pipeline adopts chamber for fibre-reinforced plastics sand inclusion pipe, the deadweight of chamber for fibre-reinforced plastics sand inclusion pipe is relatively light, and required hanging device is less, remains basically stable with general vehicular load, reduces the impact on existing subway tunnel structure.
Excavation lays a length of tubing every time, adopts the mode gone along with sb. to guard him equally and excavate to lay next joint road after having backfilled again.
Every length of tubing length is 3m or 4.5m, it is possible to meet road traffic night block part track construction, daytime open to traffic requirement, reduce single excavation area ensure that the impact on subway tunnel is only small, be controlled.
Below with reference to accompanying drawing, the technique effect of the design of the present invention, concrete structure and generation is described further, to be fully understood from the purpose of the present invention, feature and effect.
Accompanying drawing explanation
Fig. 1 is the structural representation of one embodiment of the invention.
Detailed description of the invention
As described in Figure 1, the present embodiment proposes and a kind of is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure, and the method comprises the steps:
Step one, employing cement and the mixture 2 of waterglass, carry out consolidation process by delamination pour slurry technique to channel bottom. In the mixture of cement and waterglass, adopt the mixed liquor of fresh Portland cement (strength of cement class 4 2.5) and waterglass, cement mixing content and the ratio of mud should determine according to scene test. But the component of mixture should meet following condition simultaneously: grouting volume ratio is more than or equal to 20%, and the ratio of mud is 0.5, cement and waterglass volume ratio are 1:1, and modulus of water glass is 3.0~3.3.
The soil body of channel bottom is reinforced by cement and waterglass mixture delamination pour slurry, adds the intensity of passive area inside foundation ditch, effectively reduces internal force and the deformation of retaining design, large diameter pipeline provides reliable base support simultaneously.
Step 2, construction supporting Larsen steel sheet pile 1. Adopting Larsen steel sheet pile 1 as fender post, Larsen steel sheet pile 1 adopts screen-type to squeeze into method construction. The edge of Larsen steel sheet pile 1 is provided with elongated waterproof fore shaft, is filled with hermetic seal material in elongated waterproof fore shaft.Wherein, hermetic seal material preferably employs as the material such as butter, Colophonium. When specifically applying, adopt standard steel sheet pile as fore shaft reshaping clamping fixture, adopt low speed winch tractive adjustment to process, or knock mold propulsion method with oxy-acetylene flame baking the affected part after applying some drugs in conjunction with sledgehammer and carry out straightening process.
Owing to adopting Larsen steel sheet pile as fender post; the edge of Larsen steel sheet pile is provided with elongated waterproof fore shaft; so that be mutually twisted into the continuous retaining wall that can intercept water and mutually pin down between Larsen steel sheet pile; ensure that the rigidity of retaining design and intensity, it is ensured that in Excavation Process, the displacement on fender post top and surrounding ground settling amount are within the acceptable range.
Step 3, excavate and arrange bracing members and steel encloses purlin. Bracing members is connected by shaped steel is fixing with Larsen steel sheet pile 1. In the present embodiment, shaped steel adopts H type shaped steel 5, and bracing members is the both sides that horizontal support 6, H type shaped steel is arranged at horizontal support 6, and is attached by welding manner.
According to design size, after being excavated to 6 times 0.3m of horizontal support, construction level supports 6. Larsen steel sheet pile 1 and steel enclose purlin and should adopt welding connecting mode, and steel encloses purlin and should fit Larsen steel sheet pile 1, if steel encloses there is gap between purlin and Larsen steel sheet pile 1, then should fill pea gravel concreten in gap and tamp. Steel encloses purlin and bracing members junction and encloses the edge of a wing of purlin and support and web all should be welded with stiffener, and the thickness of stiffener is not less than 10mm. Welding adopts welded corner joint, and the fillet weld size of angle welding cannot be less than 1.5t0.5, and cannot be less than 8mm.
The above-mentioned paving mode of the present invention, adopt Larsen steel sheet pile as fender post, the space of excavation of foundation pit decreases about 20%, space occupation of land decreases about 50%, simultaneously because adopt bracing members and steel to enclose purlin, the unlimited time of foundation ditch about decreases 50%, thus accelerating speed of application, effectively reduces the impact on existing subway tunnel structure.
Step 4, dig to, at the bottom of foundation ditch, ramming flat pipeline foundation 3. Pipeline foundation 3 adopts 25cm gravel sand basis, and 5cm yellow ground lining is flat, and compactness is 90%.
Step 5, on pipeline foundation, lay chamber for fibre-reinforced plastics sand inclusion large diameter pipeline 4, agent structure of constructing, reach, after design strength, to backfill from bottom to top until agent structure, until being backfilled to design ground elevation.
Step 6, extracts Larsen steel sheet pile 1, and the cement grout adopting the ratio of mud to be 0.8 fills Larsen steel sheet pile or steel encloses the space after purlin is extracted. When specifically applying, along full stake depth bounds internal pore compaction grouting.
The preferred embodiment of the present invention described in detail above. Should be appreciated that those of ordinary skill in the art just can make many modifications and variations according to the design of the present invention without creative work. Therefore, all technical staff in the art, all should in the protection domain being defined in the patent claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.

Claims (10)

1. one kind is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure, it is characterised in that comprise the steps:
Step one, employing cement and the mixture of waterglass, carry out consolidation process by delamination pour slurry technique to channel bottom;
Step 2, construction supporting Larsen steel sheet pile; Adopting Larsen steel sheet pile as fender post, the edge of described Larsen steel sheet pile is provided with elongated waterproof fore shaft;
Step 3, excavating and arrange bracing members and steel encloses purlin, described bracing members is fixed with described Larsen steel sheet pile by shaped steel and is connected;
Step 4, dig to, at the bottom of foundation ditch, ramming flat pipeline foundation;
Step 5, on described pipeline foundation, lay chamber for fibre-reinforced plastics sand inclusion large diameter pipeline, agent structure of constructing, reach, after design strength, to backfill from bottom to top until agent structure, until being backfilled to design ground elevation;
Step 6, extracts described Larsen steel sheet pile, and fills described Larsen steel sheet pile or described steel encloses the space after purlin is extracted.
2. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 1, it is characterized in that, the fresh Portland cement that described cement adopts intensity to be 42.5, described cement is as follows with the component of the mixture of waterglass: grouting volume ratio is more than or equal to 20%, the ratio of mud is 0.5, cement and waterglass volume ratio are 1:1, and modulus of water glass is 3.0~3.3.
3. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 2, it is characterised in that in described elongated waterproof fore shaft, be filled with hermetic seal material.
4. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 3, it is characterised in that described hermetic seal material is butter or Colophonium.
5. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 3, it is characterised in that described Larsen steel sheet pile adopts screen-type to squeeze into method construction, and adopts the mode of static pressure pile-sinking.
6. as described in claim 4 or 5, it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure, it is characterised in that described steel is enclosed and is connected by welding manner between purlin with described bracing members, described Larsen steel sheet pile.
7. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 6, it is characterised in that described steel encloses the junction of purlin and described bracing members, described Larsen steel sheet pile and is provided with stiffener.
8. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 7, it is characterised in that adopting 25cm gravel sand basis when ramming flat pipeline foundation, 5cm yellow ground lining is flat, and compactness is 90%.
9. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 8, it is characterised in that in described step 5 during backfill, after being backfilled to the elevation place of described bracing members, remove bracing members again.
10. it is parallel to the laying method of large-caliber drainage pipeline above existing subway tunnel structure as claimed in claim 1, it is characterised in that excavation lays a length of tubing every time, adopts the mode gone along with sb. to guard him equally and excavate to lay next length of tubing after having backfilled again.
CN201610086577.8A 2016-02-16 2016-02-16 Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure Pending CN105672450A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610086577.8A CN105672450A (en) 2016-02-16 2016-02-16 Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610086577.8A CN105672450A (en) 2016-02-16 2016-02-16 Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure

Publications (1)

Publication Number Publication Date
CN105672450A true CN105672450A (en) 2016-06-15

Family

ID=56304561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610086577.8A Pending CN105672450A (en) 2016-02-16 2016-02-16 Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure

Country Status (1)

Country Link
CN (1) CN105672450A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759384A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of method that use prefabricated pipeline base plate does Brace in Deep Footing Groove
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method
CN109339063A (en) * 2018-12-05 2019-02-15 济南热力集团有限公司 The guard method and its protection structure that fuel gas conduit is intersected in lower section when thermal pipe is laid with
CN109372013A (en) * 2018-10-25 2019-02-22 南京吉欧地下空间科技有限公司 It is a kind of for backfilling the EPS composite soil construction technology and method of pipe gallery on soft foundation
CN110396881A (en) * 2019-07-18 2019-11-01 湖北建科国际工程有限公司 The road construction method of section conllinear with rail traffic
CN110468938A (en) * 2019-07-02 2019-11-19 北京质诚捷讯水利工程有限公司 A kind of municipal drain pipeline construction method
CN112064751A (en) * 2020-08-08 2020-12-11 上海静安市政工程有限公司 Deep groove construction method for drainage pipeline

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2102043A (en) * 1981-07-16 1983-01-26 Richard Weiss Process and apparatus for jacking conduits in ground containing ground water
JPS60175628A (en) * 1984-02-21 1985-09-09 Sekisui Chem Co Ltd Burying method for pipe
CN103195158A (en) * 2013-04-03 2013-07-10 济南城建集团有限公司 Municipal drainage pipeline slurry balance pipe-jacking construction method
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2102043A (en) * 1981-07-16 1983-01-26 Richard Weiss Process and apparatus for jacking conduits in ground containing ground water
JPS60175628A (en) * 1984-02-21 1985-09-09 Sekisui Chem Co Ltd Burying method for pipe
CN103195158A (en) * 2013-04-03 2013-07-10 济南城建集团有限公司 Municipal drainage pipeline slurry balance pipe-jacking construction method
CN103343538A (en) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 A kind of high stream is moulded the steel sheet pile construction method for supporting under the soft base of deep layer

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
万水龙: "软土地基地下管道深基坑支护施工技术", 《江西建材》 *
程鉴基等: "砾石层防渗固结帷幕的化学渗透灌浆", 《建筑技术》 *
陈宗培等: "Φ1800玻璃钢夹砂管的施工与监理技术浅述", 《中国市政工程》 *
黄志巍等: "废弃老建筑群桩内深沟槽大管径雨水管道施工", 《中国市政工程》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759384A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 A kind of method that use prefabricated pipeline base plate does Brace in Deep Footing Groove
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method
CN109372013A (en) * 2018-10-25 2019-02-22 南京吉欧地下空间科技有限公司 It is a kind of for backfilling the EPS composite soil construction technology and method of pipe gallery on soft foundation
CN109372013B (en) * 2018-10-25 2021-06-04 南京吉欧地下空间科技有限公司 Comprehensive pipe gallery on soft foundation filled with EPS (expandable polystyrene) mixed soil and construction method
CN109339063A (en) * 2018-12-05 2019-02-15 济南热力集团有限公司 The guard method and its protection structure that fuel gas conduit is intersected in lower section when thermal pipe is laid with
CN110468938A (en) * 2019-07-02 2019-11-19 北京质诚捷讯水利工程有限公司 A kind of municipal drain pipeline construction method
CN110396881A (en) * 2019-07-18 2019-11-01 湖北建科国际工程有限公司 The road construction method of section conllinear with rail traffic
CN112064751A (en) * 2020-08-08 2020-12-11 上海静安市政工程有限公司 Deep groove construction method for drainage pipeline

Similar Documents

Publication Publication Date Title
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN106013172B (en) Double-row pile combines Deep Foundation Pit Support for Soft Soil structure and construction method with diagonal brace
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN205742213U (en) Foundation pit supporting construction
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN108060683A (en) A kind of middle weathering geology top-down construction method
CN107299630A (en) A kind of deep & thick silt matter riverbed piping lane crosses the river double steel plate pile cofferdam structure and construction method
CN105155558A (en) Combined retaining structure and construction method thereof
CN105649089A (en) Construction method for excavating foundation pit close to existing shallow foundation protection structure
CN106049196B (en) Flexible pile combines ballastless track roadbed construction method with stake raft with section
CN110671131A (en) Loess tunnel substrate reinforcing structure and method based on high-pressure jet grouting pile
JP2014531539A (en) Method for constructing retaining wall and retaining wall
CN108678000A (en) A kind of U-shaped retaining structure of roadbed Xia Chuan highways and its construction method
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN107386317A (en) Foam concrete lightweight barricade and construction method are excavated after a kind of first precompressed of deep ultra-soft soil
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN107090851A (en) The inverted side-wall construction method of downtown area open cut groove
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN111305027A (en) Rapid repairing construction method and repairing structure for subsidence of karst area pavement
CN211258631U (en) Loess tunnel basement reinforcement construction structure based on high pressure jet grouting pile
CN104894926B (en) Retaining structure and its construction method on the high embankment of existing railway
CN1563612A (en) Construction method for underground structure through half reverse course of action of inverting connection
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160615