CN106499048B - Pit structure installation method - Google Patents

Pit structure installation method Download PDF

Info

Publication number
CN106499048B
CN106499048B CN201611113024.3A CN201611113024A CN106499048B CN 106499048 B CN106499048 B CN 106499048B CN 201611113024 A CN201611113024 A CN 201611113024A CN 106499048 B CN106499048 B CN 106499048B
Authority
CN
China
Prior art keywords
cushion cap
pit
steel plate
installation method
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611113024.3A
Other languages
Chinese (zh)
Other versions
CN106499048A (en
Inventor
***
胡国良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang canyuan Home Textile Co., Ltd
Original Assignee
Ningbo Ever Elevator Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Ever Elevator Technology Development Co Ltd filed Critical Ningbo Ever Elevator Technology Development Co Ltd
Priority to CN201611113024.3A priority Critical patent/CN106499048B/en
Publication of CN106499048A publication Critical patent/CN106499048A/en
Application granted granted Critical
Publication of CN106499048B publication Critical patent/CN106499048B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The present invention provides a kind of pit structure installation method.The pit structure installation method includes the following steps: to provide foundation pit, concrete is poured in foundation pit and sets up the first cushion cap;Multiple support rods are provided, the bottom end of multiple support rods is fixed in first cushion cap;Second cushion cap is provided, second cushion cap is fixed in the top of multiple support rods;Pit connection frame is provided, the pit connection frame is fixed in the top of second cushion cap;To casting concrete in foundation pit, make the excessively described pit connection frame of concrete cover.The pit structure installation method, the support rod of the second cushion cap and connection first cushion cap and the second cushion cap is added on first cushion cap, and the support rod has stretching structure, the levelness of adjustable second cushion cap solves the problems, such as that the foundation pit that elevator pit structure is generated using overlong time is subside, cushion cap deforms.

Description

Pit structure installation method
Technical field
The present invention relates to elevator shaft fields, and in particular to the pit structure installation method of elevator shaft.
Background technique
Aging blocks building in, sometimes according to production, life needs, it is necessary to add elevator building outside, outside building elevator build in Except aging blocks, need to build the hoistway outside independently of building, therefore hoistway frame is stable and firm particularly significant.Pit structure from Well pit stretches out, and connection hoistway frame and pit cushion cap, pit structure and being bonded for hoistway frame are related to entire hoistway Stablize safety, pit structure is one of the important composition component of elevator shaft construction.In the prior art, hoistway frame bottom and bottom Hole cushion cap framework of steel reinforcement directly welds, and after-pouring concrete covers pit structure and hoistway frame bottom weld, completes well with this The connection of road frame and pit structure.
This kind of pit structure mounting means is excessively coarse simple, there is connection shakiness, be easy to cause stand-off error, is difficult to entangle Inclined problem.
Summary of the invention
Present invention solves the technical problem that being to improve a kind of simple and convenient structure, stable connection, stand-off error little Yi to correct Pit structure installation method.
The present invention provides a kind of pit structure installation method, includes the following steps:
Step S1, provides foundation pit, and concrete is poured in foundation pit and sets up the first cushion cap;
Step S2 provides multiple support rods, and the bottom end of multiple support rods is fixed in first cushion cap;
Step S3 provides the second cushion cap, and second cushion cap is fixed in the top of multiple support rods;
Step S4 provides pit connection frame, and the pit connection frame is fixed in the top of second cushion cap;
Step S5 makes the excessively described pit connection frame of concrete cover to casting concrete in foundation pit.
Preferably, the installation method of the pit connection frame, includes the following steps;
Step S41, provides foundation bolt and anchor nut, and the anchor nut is fixed on second cushion cap, is connect The foundation bolt is installed in the anchor nut;
Step S42, provides the first steel plate for having multiple first mounting holes, and first steel plate is fixed in the lower margin spiral shell At the top of bolt;
Step S43 adjusts the height of the foundation bolt, makes the first steel plate height in same level;
Step S44, provides the hoistway frame that bottom has the second steel plate, and second steel plate has multiple second mounting holes, passes through It connects bolt to connect the second steel plate of hoistway frame and the first steel plate, to fix hoistway frame.
Preferably, in step s3, second cushion cap is parallel to the horizontal plane in the height for adjusting the support rod.
Preferably, the second cushion cap described in multiple they sup-ports is suspended at the top of first cushion cap, and described first The size of the central axis of cushion cap and second cushion cap and first cushion cap is greater than the size of second cushion cap.
Preferably, the support rod includes connection first cushion cap and has the first support bar of first through hole, connection institute It states the second cushion cap and has the second support bar and fixed link of the second through-hole, one end of the second support bar is inserted in described first In support rod, and the first through hole and second lead to the hole site are opposite, the fixed link be inserted in the first through hole and Second through-hole simultaneously runs through the first support bar and the second support bar.
Preferably, the quantity of the support rod is four, is respectively arranged on four apex angles of first cushion cap.
Preferably, first steel plate is fixed at the top of the foundation bolt, and there are four first for the first steel plate formation Mounting hole.
Preferably, there are four the second mounting holes for the second steel plate formation.
Preferably, first steel plate and second steel plate abutting and first mounting hole and second mounting hole Position is corresponding, and the connection bolt-through is set to first mounting hole and second mounting hole.
Compared with the relevant technologies, pit structure installation method provided by the invention is had the following beneficial effects:
One, the support rod of the second cushion cap and connection first cushion cap and the second cushion cap is added on first cushion cap, And the support rod has stretching structure, the levelness of adjustable second cushion cap solves elevator pit structure and uses the time The problem of foundation pit that is too long and generating is subside, cushion cap deforms.
Two, the hoistway frame in the prior art and the bottom are replaced by the close bolt of the first steel plate and the second steel plate The framework of steel reinforcement of hole cushion cap directly welds, and has not only improved fixed stability and intensity, but also reduce the subsequent mixed mud that pours and apply Stand-off error caused by work is conducive to the hoistway frame and is bonded with the accurate of the pit cushion cap.
Detailed description of the invention
Fig. 1 is the step flow chart of pit structure installation method of the present invention;
Fig. 2 is the stereogram exploded view of pit structure of the present invention;
Fig. 3 is the step flow chart of the installation method of pit connection frame of the present invention.
Specific embodiment
The invention will be further described with embodiment with reference to the accompanying drawing.
A kind of pit structure installation method, please refers to Fig. 1 and Fig. 2, wherein Fig. 1 is pit structure 1 of the present invention installation The step flow chart of method;Fig. 2 is the stereogram exploded view of pit structure of the present invention.The pit structure installation method includes as follows Step:
Step S1, provides foundation pit, and concrete is poured in foundation pit and sets up the first cushion cap 13;
Step S2 provides multiple support rods 10, and the bottom end of multiple support rods 10 is fixed in first cushion cap 13;
In the present embodiment, the quantity of the support rod 10 is four, is respectively arranged on four tops of first cushion cap 13 Angle.
Step S3 provides the second cushion cap 15, and second cushion cap 15 is fixed in the top of multiple support rods 10;
Specifically, multiple support rods 10 support second cushion cap 15 to be suspended at 13 top of the first cushion cap, institute The size for stating the central axis of the first cushion cap 13 and second cushion cap 15 and first cushion cap 13 is held greater than described second The size of platform 15.
The support rod 10 includes connecting first cushion cap 13 and having the first support bar 101 of first through hole 1011, connect It connects second cushion cap 15 and has the second support bar 103 and fixed link 105 of the second through-hole 1031, the second support bar 103 One end be inserted in the first support bar 101, and the first through hole 1011 is opposite with 1031 position of the second through-hole, The fixed link 105 is inserted in the first through hole 1011 and second through-hole 1031 and through the first support bar 101 With the second support bar 103.
The distance for being inserted into the first support bar 101 by the way that the second support bar 103 is arranged, reaches and adjusts support rod 10 Height, second cushion cap 15 is parallel to the horizontal plane.
Step S4 provides pit connection frame 11, and the pit connection frame 11 is fixed in the top of second cushion cap 15;
Step S5 makes the excessively described pit connection frame 11 of concrete cover to casting concrete in foundation pit.
Please in conjunction with refering to Fig. 3, Fig. 3 is the step flow chart of the installation method of pit connection frame of the present invention.The pit The installation method of connection frame, includes the following steps;
Step S41 provides foundation bolt 111 and anchor nut 113, and the anchor nut 113 is fixed in the second cushion cap On 15, the foundation bolt 111 is then installed in the anchor nut 113;
Step S42 provides the first steel plate 115 for having multiple first mounting holes 1151, first steel plate 115 is fixed in 111 top of foundation bolt;
Step S43 adjusts the height of the foundation bolt 111, makes 115 height of the first steel plate in same level;
Step S44, provides the hoistway frame 2 that bottom has the second steel plate 21, and second steel plate 21 has multiple second mounting holes 211, the second steel plate 21 of hoistway frame 2 and the first steel plate 115 are connected by connection bolt, to fix hoistway frame 2.
Specifically, the pit connection frame 11 includes foundation bolt 111, anchor nut 113 and the first steel plate 115, it is described Anchor nut 113 is fixed on second cushion cap 15, and the foundation bolt 111 is plugged in the anchor nut 113.
Further, the foundation bolt 111, the anchor nut 113 quantity be also four, the anchor nut 113 are embedded at four apex angles of second cushion cap 15.
First steel plate 115 is fixed in 111 top of the foundation bolt, and first steel plate 115 forms that there are four the One mounting hole 1151;The hoistway frame 2 includes the second steel plate 21, and there are four the second mounting holes 211 for the formation of the second steel plate 21.
First steel plate 115 and second steel plate 21 abut and first mounting hole 1151 and described second is installed 211 position of hole is corresponding, and the connection bolt-through is set to first mounting hole 1151 and second mounting hole 211, passes through First steel plate 115 is set to same level, reused by the mutual adjusting of the foundation bolt 111 and anchor nut 113 Connection bolt is fixedly connected with the hoistway frame 2 and the pit connection frame 11.
Compared with the relevant technologies, pit structure installation method provided by the invention is had the following beneficial effects:
One, the support rod of the second cushion cap and connection first cushion cap and the second cushion cap is added on first cushion cap, And the support rod has stretching structure, the levelness of adjustable second cushion cap solves elevator pit structure and uses the time The problem of foundation pit that is too long and generating is subside, cushion cap deforms.
Two, the hoistway frame in the prior art and the bottom are replaced by the close bolt of the first steel plate and the second steel plate The framework of steel reinforcement of hole cushion cap directly welds, and has not only improved fixed stability and intensity, but also reduce the subsequent mixed mud that pours and apply Stand-off error caused by work is conducive to the hoistway frame and is bonded with the accurate of the pit cushion cap.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (8)

1. a kind of pit structure installation method, the pit structure applied to installation elevator shaft frame, which is characterized in that including as follows Step:
Step S1, provides foundation pit, and concrete is poured in foundation pit and sets up the first cushion cap;
Step S2 provides multiple support rods, and the bottom end of multiple support rods is fixed in first cushion cap;
Step S3 provides the second cushion cap, and second cushion cap is fixed in the top of multiple support rods;
Step S4 provides pit connection frame, and the pit connection frame is fixed in the top of second cushion cap;
Step S5 makes the excessively described pit connection frame of concrete cover to casting concrete in foundation pit;
The step S4, includes the following steps;
Step S41, provides foundation bolt and anchor nut, and the anchor nut is fixed on second cushion cap, is then existed The installation foundation bolt in the anchor nut;
Step S42, provides the first steel plate for having multiple first mounting holes, and first steel plate is fixed in the foundation bolt top Portion;
Step S43 adjusts the height of the foundation bolt, makes the first steel plate height in same level;
Step S44, provides the hoistway frame that bottom has the second steel plate, and second steel plate has multiple second mounting holes, passes through connection Bolt connects the second steel plate of hoistway frame and the first steel plate, to fix hoistway frame.
2. pit structure installation method according to claim 1, it is characterised in that: in step s3, adjust the support Second cushion cap is parallel to the horizontal plane in the height of bar.
3. pit structure installation method according to claim 1, it is characterised in that: described in multiple they sup-ports Two cushion caps are suspended at the top of first cushion cap, the central axis and described first of first cushion cap and second cushion cap The size of cushion cap is greater than the size of second cushion cap.
4. pit structure installation method according to claim 1, it is characterised in that: the support rod includes connecting described the One cushion cap simultaneously has the first support bar of first through hole, connection second cushion cap and the second support bar and fixation that have the second through-hole Bar, one end of the second support bar are inserted in the first support bar, and the first through hole and second through-hole position Set opposite, the fixed link is inserted in the first through hole and second through-hole and through the first support bar and described the Two support rods.
5. pit structure installation method according to claim 1, it is characterised in that: the quantity of the support rod is four, It is respectively arranged on four apex angles of first cushion cap.
6. pit structure installation method according to claim 2, it is characterised in that: first steel plate is fixed in describedly At the top of foot bolt, there are four the first mounting holes for the first steel plate formation.
7. pit structure installation method according to claim 6, it is characterised in that: second steel plate forms that there are four the Two mounting holes.
8. pit structure installation method according to claim 7, it is characterised in that: first steel plate and second steel Plate abuts and first mounting hole and second position of mounting hole are corresponding, and the connection bolt-through is set to first peace Fill hole and second mounting hole.
CN201611113024.3A 2016-12-06 2016-12-06 Pit structure installation method Active CN106499048B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611113024.3A CN106499048B (en) 2016-12-06 2016-12-06 Pit structure installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611113024.3A CN106499048B (en) 2016-12-06 2016-12-06 Pit structure installation method

Publications (2)

Publication Number Publication Date
CN106499048A CN106499048A (en) 2017-03-15
CN106499048B true CN106499048B (en) 2019-08-16

Family

ID=58329568

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611113024.3A Active CN106499048B (en) 2016-12-06 2016-12-06 Pit structure installation method

Country Status (1)

Country Link
CN (1) CN106499048B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006298611A (en) * 2005-04-22 2006-11-02 Mitsubishi Electric Corp Buffer device for elevator
CN202245617U (en) * 2011-01-04 2012-05-30 张向阳 Elevator well wall assembled by adopting combined type derricks

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104340813B (en) * 2014-10-30 2016-09-14 中国建筑股份有限公司 A kind of installation construction method for elevator
CN106044466A (en) * 2016-08-12 2016-10-26 山东富士制御电梯有限公司 Levelness adjusting device for steel structure well for elevator

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006298611A (en) * 2005-04-22 2006-11-02 Mitsubishi Electric Corp Buffer device for elevator
CN202245617U (en) * 2011-01-04 2012-05-30 张向阳 Elevator well wall assembled by adopting combined type derricks

Also Published As

Publication number Publication date
CN106499048A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN102561712A (en) Accurate positioning frame for large steel column and equipment foundation fixing bolt and construction method thereof
CN203855292U (en) Escalator inclined section support device
CN105317052B (en) Tower crane foundation bolt fixing method
CN108035554A (en) The steel column supporting frame construction method of high-rise building frame column
CN109281333A (en) The cast iron platform of horizontal adjustable and large-scale cast iron stage+module mode
CN206589121U (en) It is a kind of to be used for precast beam, the diaphragm plate horizontal reinforcement mounting and positioning device of plate
CN205894490U (en) Steel core concrete column and pile foundation connection structure
CN106499048B (en) Pit structure installation method
CN106592623B (en) Pit structure installation method
KR20130025188A (en) Bar support for mass reinforced concrete member and method of upper bar arrangement using the same
CN102817482A (en) Steel column correcting device and correcting construction method thereof
CN202265906U (en) Fixing device for anchor bolts of embedded type steel tube concrete column feet
CN202595758U (en) Batter post foundation structure for overhead transmission line
RU2008130001A (en) METHOD OF MANAGEMENT OF MOVEMENTS, SEDIMENTS AND ROLL FOR THE FACILITATION OF FOUNDATIONS ON THE PILES, WHICH ARE MACRO-REGULATORS
CN206396887U (en) Pit structure
KR101282333B1 (en) Cross-type supporting structure and method for super-structure of bridge
JP3165719U (en) Infrastructure for facilities
CN204876084U (en) Steel column foot crab -bolt fixed bolster
CN106638937B (en) Pit structure and its installation method
CN106930406A (en) A kind of preparation method of Anchor Bolts in Steel Column Bases positioning structure
CN209308063U (en) The cast iron platform of horizontal adjustable and large-scale cast iron platform
CN106869162A (en) Steam turbine built-in fitting fixing device and method
CN103624462A (en) Steel bar cage leveling device
CN206396778U (en) Pit structure
CN206396780U (en) Pit structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191029

Address after: 314513 quchbon village, zhouquan Town, Tongxiang City, Jiaxing, Zhejiang

Patentee after: Zhejiang canyuan Home Textile Co., Ltd

Address before: 315040 room 233-3, building, No. 66, academician Road, high tech Zone, Zhejiang, Ningbo, China

Patentee before: Ningbo ever Elevator Technology Development Co., Ltd.

TR01 Transfer of patent right