CN106468546A - A kind of Architectural Equipment settlement monitor and its monitoring method - Google Patents

A kind of Architectural Equipment settlement monitor and its monitoring method Download PDF

Info

Publication number
CN106468546A
CN106468546A CN201510508039.9A CN201510508039A CN106468546A CN 106468546 A CN106468546 A CN 106468546A CN 201510508039 A CN201510508039 A CN 201510508039A CN 106468546 A CN106468546 A CN 106468546A
Authority
CN
China
Prior art keywords
data
monitor
building
settlement
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510508039.9A
Other languages
Chinese (zh)
Inventor
潘牧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Beidou Satellite Navigation Positioning Technology Co Ltd
Original Assignee
Tianjin Beidou Satellite Navigation Positioning Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Beidou Satellite Navigation Positioning Technology Co Ltd filed Critical Tianjin Beidou Satellite Navigation Positioning Technology Co Ltd
Priority to CN201510508039.9A priority Critical patent/CN106468546A/en
Publication of CN106468546A publication Critical patent/CN106468546A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

The invention discloses a kind of Architectural Equipment settlement monitor and its monitoring method, using global position system many stars continuous correction, the present invention adds that RTK dynamic coordinate realizes sedimentation skew latitude coordinates and the data variation of elevation coordinate captures in real time, data is shown on instrument display screen in real time simultaneously, while display, data separate GPRS communication module can be imported background control center by mobile Internet by rectifier, and data center analyzes building offset problem and altitude data statistics by its software differential data.The present invention can receive the Big Dipper four star signal and can carry out real-time observation, and monitoring accuracy is higher can reach cm level, and operational approach is simple, without manual control management, can carry out whole day uninterrupted monitoring in 24 hours to find settlement issues.

Description

A kind of Architectural Equipment settlement monitor and its monitoring method
Technical field
The present invention relates to building industry field, more particularly, to a kind of monitor of building settlement and its side Method.
Background technology
It is known that after the completion of a lot of large scale industry construction, skyscraper, electric power facility are built, by In the combined influence of various artificial origins and natural cause, facility can occur different degrees of sedimentation.This deposits In certain potential safety hazard, the service life of building can be shortened, reduce the safety of building.So Select a kind of monitoring instrument of real-time monitored sedimentation to have great importance, found by instrument real-time monitored Its settlement issues, it is to avoid because its sedimentation causes the destruction of building or the appearance of potential safety hazard.
Our Monitoring method of the subsidences now used are all by looking on the building built well mostly Fixing point and multiple observation station are combined with level gauge and molten steel object staff carries out interim monitoring, by water The settlement issues that quasi- instrument reading is built to determine height value to judge, but such method exists a lot Inevitably problem.
For example:
1. before measuring, forget tester.For existing technology, measurement sedimentation needs are carried out repeatedly The measurement of intermittent, so the high precision instrument of measurement sedimentation must carry out the correction of instrument before measuring, If not correcting the error that principle will occur in measurement process, lead to the inaccurate of measurement.
2. need multiple observation stations to be observed the sedimentation situation built.For in existing observation procedure, Want completely to be observed reaction to settlement issues it is necessary to one fixation of setting and multiple observation station are (former Then above it is no less than 6) regularly observed, very little cannot be good if selecting observation station React its settlement issues by apparatus measures, reduce monitoring accuracy.
3. Instrument measuring precision is relatively low.Certainty of measurement typically all exists present settlement monitor in the measurements 0.5m about, because its precision is too low, so its settlement issues can not accurately be reacted, should in real With during it is possible to due to the problem of precision cause build sedimentation.
4. measurement distance is restricted.For in building settlement e measurement technology at this stage, to tested building Requirement for height is generally limited to 30m, if building is too high being possible to affect the accuracy value of measurement, Not can solve settlement issues.
Content of the invention
The invention aims to solving the above problems, devise a kind of sedimentation based on RTK system Monitor.It eliminates above-mentioned various interference, is a high accuracy, the device of high standard settlement monitoring And method.
Realizing above-mentioned purpose technical scheme is that settlement monitor is to utilize global position system (BDS+GPS+GLONASS+Galileo) continuous correction of many stars adds that RTK dynamic coordinate realizes sedimentation skew The data variation of latitude coordinates and elevation coordinate captures in real time, data is shown in instrument simultaneously in real time and shows On screen, after while display, data separate GPRS communication module can be imported by rectifier by mobile Internet Platform control centre, data center analyzes building offset problem and altitude data by its software differential data Statistics.
Described settlement monitor, is mainly made up of monitor, fixed support;Inside described monitor Include locating module, communication module, battery back-up module and power supply.
Described power supply external connection power line, powers to monitor, reserve battery is charged simultaneously;? When emergency mains terminals cannot be powered, battery back-up module automatic, is that monitor is powered.
There is spirit bubble on described fixed support, during for installing, determining whether settlement monitor is balance State.
There is fixed column described fixed support side, and fixed column has fixed screw, and fixed column is used for sinking Fall monitor is fixed on building.
Settlement monitor, from being installed to data monitoring, is carried out as follows:
Firstth, the installation of fixing point.Settlement monitor, will be settled by correct reconnaissance using front in measurement Monitor is fixed on building body.
Secondth, the selection of benchmark latitude coordinates and elevation coordinate.By the fixed position of settlement monitor Selection of setting we can measure latitude and longitude coordinates value (x, y) and measure height value as building Build reference coordinate and the reference elevation value of centre-of gravity shift measure of the change.
3rd, the change observation of latitude coordinates value and height value.When building is in no settling phase, sink The longitude and latitude data of fall monitor and altitude data will consistent with benchmark data will not change.
But,
1., if the latitude coordinates of settlement monitor change and are treated as centre-of gravity shift, also imply that building Layer starts to offset perpendicularity generation offset issue;
If 2. the height value of settlement monitor changes and is treated as building generation sedimentation change, then this A little data will be reacted to master control backstage at once, and whether backstage Master Control Center, by the analysis to data, is seen Within the scope of safety, if once exceeding sedimentation safety value, backstage will be notified that related personnel is carried out The solution of problem, so just effectively avoids and causes the destruction of building or potential safety hazard because of its sedimentation Occur.
4th, background network transmission.Background system passes through networking, and Master Control Center can be apart from rover station RTK Nearest place produces a VRS virtual reference station to carry out the differential data and rover station RTK between by mistake Difference resolves, and after RTCM differential corrections, the Centimeter Level high accuracy that can be effectively obtained real-time measurement is sat Mark information.
Compared with existing settlement monitoring technology, it is an advantage of the current invention that it can receive the Big Dipper four star signal Real-time observation can be carried out, and monitoring accuracy is higher can reach cm level, operational approach is simple, need not be artificial Control management, whole day uninterrupted monitoring in 24 hours can be carried out to find settlement issues.
Brief description
Fig. 1 is settlement monitor schematic view of the mounting position;
Fig. 2 is settlement monitor schematic diagram;
Fig. 3 is data transfer schematic diagram;
Wherein:1- monitor, 2- fixed support, 3- building, 4- external power supply, 5- fixed screw, 6- spirit bubble, 7- fixed column.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is specifically described.
As illustrated, the present invention devises a kind of settlement monitor based on RTK system.It eliminates Above-mentioned various interference, is a high accuracy, the device of high standard settlement monitoring and method.
Realizing above-mentioned purpose technical scheme is that settlement monitor is to utilize global position system (BDS+GPS+GLONASS+Galileo) continuous correction of many stars adds that RTK dynamic coordinate realizes sedimentation skew The data variation of latitude coordinates and elevation coordinate captures in real time, data is shown in instrument simultaneously in real time and shows On screen, after while display, data separate GPRS communication module can be imported by rectifier by mobile Internet Platform control centre, data center analyzes building offset problem and altitude data by its software differential data Statistics.
Described settlement monitor, is mainly made up of monitor 1, fixed support 2;Described monitor Inside includes locating module, communication module, battery back-up module and power supply.
Described power supply external connection power line 4, powers to monitor, reserve battery is charged simultaneously; When emergency mains terminals cannot be powered, battery back-up module automatic, is that monitor is powered.
Spirit bubble 6 being had on described fixed support, during for installing, determining whether settlement monitor is flat The state of weighing apparatus.
There is fixed column 7 described fixed support side, and fixed column has fixed screw 5, and fixed column is used for will Settlement monitor is fixed on building.
Settlement monitor, from being installed to data monitoring, is carried out as follows:
Firstth, the installation of fixing point.Settlement monitor 1, will be sunk by correct reconnaissance using front in measurement Fall monitor is fixed on building body.Generally select the higher position point of building, and surrounding be shelter, Without interference with signal transmission.
Secondth, the selection of benchmark latitude coordinates and elevation coordinate.By the fixed position of settlement monitor Selection of setting, records latitude and longitude coordinates value (x, y) and records a height value as building center of gravity The reference coordinate of offset variation measurement and reference elevation value.
3rd, the change observation of latitude coordinates value and height value.When building is in no settling phase, sink The longitude and latitude data of fall monitor and altitude data will consistent with benchmark data will not change.
But,
1., if the latitude coordinates of settlement monitor change and are treated as centre-of gravity shift, also imply that building Layer starts to offset perpendicularity generation offset issue;
If 2. the height value of settlement monitor changes and is treated as building generation sedimentation change;
So these data will be reacted to master control backstage at once, and backstage Master Control Center is by dividing to data Whether analysis, see within the scope of safety, if once exceeding sedimentation safety value, backstage will be notified that phase Pass personnel carry out the solution of problem, so just effectively avoid because its sedimentation cause building destruction or The appearance of potential safety hazard.
4th, background network transmission.Background system passes through networking, and Master Control Center can be apart from rover station RTK Nearest place produces a VRS virtual reference station to carry out the differential data and rover station RTK between by mistake Difference resolves, and after RTCM differential corrections, the Centimeter Level high accuracy that can be effectively obtained real-time measurement is sat Mark information.
It is described further with reference to example:
20 layers of certain city's office block, high 66.73 meters, because floor is higher, the measurement work of sedimentation and The vertical operation of floor is particularly important.The design requirement of perpendicularity is that (H is that building is total to (1/1000) H High), total deviation cannot be greater than 50mm, and sedimentation height value total deviation requires to be not more than 30mm.So building Descent precision and side-play amount are needed to carry out strict Monitoring and Controlling, to ensure building during building use Itself and use safety.
After the high level place of showing up of office block carries out the selection of instrument installation site, settlement monitor is solid Determine frame and enter luggage to fix, by the parameter setting of instrument is determined skew latitude coordinates (x, y) with And two reference values that a height value changes as its sedimentation.During the use of office block, greatly The height value in building and latitude coordinates value are constant, but are as the increase of building use time, and its this The minimizing in body life-span, office block is within certain a period of time it may happen that offseting or settle, once there is this The situation of sample, backstage will show the change of this data at once, because the data of rectifier is by VRS Network technology uploads in real time in backstage Master Control Center, thus data after changing, Master Control Center will Shown, whether backstage Master Control Center will be analyzed to its delta data simultaneously, see qualified Change in this, if not within excursion, related personnel will be informed in time in backstage, allow relevant people Member's effective solve problem within the shortest time, makes office block etc. obtain safety guarantee.
Data passes through network one VRS phantom station of generation near rectifier, carries out with settlement monitor The real time differential of data resolves, and realizes the high-precision correction of building settlement value.
Technique scheme only embodies the optimal technical scheme of technical solution of the present invention, the art Technical staff some of which partly may be made some change and all embody the principle of the present invention, Belong within protection scope of the present invention.

Claims (2)

1. a kind of Architectural Equipment Monitoring method of the subsidence, is characterized in that building settlement monitoring from being installed to data Monitoring is carried out as follows:
Firstth, the installation of fixing point, instrument will settles prison by correct reconnaissance in measurement using front Survey instrument to be fixed on building body;
Secondth, the selection of benchmark latitude coordinates and elevation coordinate, by the fixation of settlement monitor Position Selection of setting we can measure latitude and longitude coordinates value (x, y) and measure an elevation Value is as the reference coordinate building centre-of gravity shift measure of the change and reference elevation value;
3rd, the change observation of latitude coordinates value and height value;When building is in no settling phase, The longitude and latitude data of settlement monitor and altitude data will consistent with benchmark data will not change;
1. the latitude coordinates of settlement monitor change and are treated as centre-of gravity shift, and floor starts to offset There is offset issue in perpendicularity;
2. the height value of settlement monitor changes, and building occurs sedimentation change,
Data will be reacted to master control backstage at once, backstage Master Control Center by the analysis to data, See whether within the scope of safety, if once exceeding sedimentation safety value, backstage will be notified that phase Pass personnel carry out the solution of problem, so just effectively avoid and cause the broken of building because of its sedimentation Evil idea or the appearance of potential safety hazard;
4th, background network transmission, background system passes through networking, and Master Control Center can be in distance flowing The nearest place of the RTK that stands produces a VRS virtual reference station to carry out and rover station RTK between Differential data error resolves, and after RTCM differential corrections, can be effectively obtained real-time measurement Centimeter Level high-precision coordinate information.
2. a kind of Architectural Equipment settlement monitor, is mainly made up of monitor, fixed support;Its feature It is inside described monitor, to include locating module, communication module, battery back-up module and power supply; Described power supply external connection power line, powers to monitor, reserve battery is charged simultaneously;Institute There is spirit bubble on the fixed support stated;There is fixed column described fixed support side, and fixed column has Fixed screw, fixed column is used for for settlement monitor being fixed on building.
CN201510508039.9A 2015-08-19 2015-08-19 A kind of Architectural Equipment settlement monitor and its monitoring method Pending CN106468546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510508039.9A CN106468546A (en) 2015-08-19 2015-08-19 A kind of Architectural Equipment settlement monitor and its monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510508039.9A CN106468546A (en) 2015-08-19 2015-08-19 A kind of Architectural Equipment settlement monitor and its monitoring method

Publications (1)

Publication Number Publication Date
CN106468546A true CN106468546A (en) 2017-03-01

Family

ID=58214320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510508039.9A Pending CN106468546A (en) 2015-08-19 2015-08-19 A kind of Architectural Equipment settlement monitor and its monitoring method

Country Status (1)

Country Link
CN (1) CN106468546A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109073760A (en) * 2017-12-15 2018-12-21 深圳市大疆创新科技有限公司 RTK measuring device
CN111352129A (en) * 2020-03-24 2020-06-30 广东星舆科技有限公司 Method and device for monitoring differential quality and computer medium
CN113048941A (en) * 2021-02-26 2021-06-29 福建潭晟建筑工程有限公司 Building engineering is with straightness and settlement monitoring system that hangs down based on thing networking
CN113251999A (en) * 2021-05-19 2021-08-13 河北建筑工程学院 Real-time measuring method for monitoring deformation of building on line

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928586A (en) * 2006-05-09 2007-03-14 西安展意信息科技有限公司 RTK-GPS technique based high altitude measuring device and method thereof
CN201173773Y (en) * 2008-03-14 2008-12-31 河南工程学院 GPS RTK total station type measuring apparatus
CN103398682A (en) * 2013-08-08 2013-11-20 宁波海创天下信息科技有限公司 Bridge displacement monitoring system and bridge displacement monitoring method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928586A (en) * 2006-05-09 2007-03-14 西安展意信息科技有限公司 RTK-GPS technique based high altitude measuring device and method thereof
CN201173773Y (en) * 2008-03-14 2008-12-31 河南工程学院 GPS RTK total station type measuring apparatus
CN103398682A (en) * 2013-08-08 2013-11-20 宁波海创天下信息科技有限公司 Bridge displacement monitoring system and bridge displacement monitoring method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴浩 等: "《GPS原理及工程安全监测应用》", 31 January 2014 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109073760A (en) * 2017-12-15 2018-12-21 深圳市大疆创新科技有限公司 RTK measuring device
WO2019113950A1 (en) * 2017-12-15 2019-06-20 深圳市大疆创新科技有限公司 Rtk measuring device
CN111352129A (en) * 2020-03-24 2020-06-30 广东星舆科技有限公司 Method and device for monitoring differential quality and computer medium
CN111352129B (en) * 2020-03-24 2022-05-24 广东星舆科技有限公司 Method and device for monitoring differential quality and computer medium
CN113048941A (en) * 2021-02-26 2021-06-29 福建潭晟建筑工程有限公司 Building engineering is with straightness and settlement monitoring system that hangs down based on thing networking
CN113251999A (en) * 2021-05-19 2021-08-13 河北建筑工程学院 Real-time measuring method for monitoring deformation of building on line
CN113251999B (en) * 2021-05-19 2022-08-02 河北建筑工程学院 Real-time measuring device for monitoring deformation of building on line

Similar Documents

Publication Publication Date Title
WO2022001104A1 (en) Integrated monitoring method for internal and external deformation of rock-fill dam
CN106468546A (en) A kind of Architectural Equipment settlement monitor and its monitoring method
CN102080960B (en) Super-high-rise building verticality measuring and controlling method based on GPS (Global Positioning System)
CN110260840B (en) Method and system for measuring absolute settlement of bridge pier of cross-sea long bridge
CN111429575B (en) Three-dimensional visual monitoring method, system, equipment and storage medium
CN104297771B (en) GNSS device and method for precisely and quickly measuring elevation
CN106526636A (en) High precision deformation monitoring device and method based on Beidou positioning
CN108007378B (en) Deformation monitoring integrated system and use method thereof
CN107101578B (en) A kind of underground measuring point coordinate measurement method
CN102032893A (en) Hand-held attitude measuring terminal
CN106840115A (en) Electromagnetic levitation type bridge main tower tower top deviation measurement device and its measuring method
CN210741454U (en) Bridge pier deformation monitoring system
CN105973213B (en) A kind of laser plumbing method and system for taking correction for deflection of vertical into account
CN107514022A (en) A kind of bull-dozer guides system
CN207923118U (en) A kind of high precision measuring device of long-range measurement displacement
CN104316027B (en) Composite level own-side height determination method
CN106500676A (en) Electromagnetic levitation type bridge pier top deviation measurement device and its measuring method
CN107588773B (en) A kind of multi-node collaborative air navigation aid based on dead reckoning and ranging information
CN115164707A (en) Monitoring device and method for monitoring structural deformation by satellite positioning
CN114877864A (en) Method and system for monitoring transformer substation settlement displacement by combining Beidou and static level
CN106468549B (en) Construction verticality measuring method based on RTK system
CN114167461A (en) Engineering measurement method and CORS system
CN204902833U (en) Measuring instrument
CN108507530A (en) A kind of high precision measuring device and method of long-range measurement displacement
CN106153002B (en) A kind of local measurement of higher degree system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170301

RJ01 Rejection of invention patent application after publication