CN106115474B - The method for improving of super high steel structure pylon - Google Patents

The method for improving of super high steel structure pylon Download PDF

Info

Publication number
CN106115474B
CN106115474B CN201610761984.4A CN201610761984A CN106115474B CN 106115474 B CN106115474 B CN 106115474B CN 201610761984 A CN201610761984 A CN 201610761984A CN 106115474 B CN106115474 B CN 106115474B
Authority
CN
China
Prior art keywords
component
temporary
super high
steel structure
lifting member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610761984.4A
Other languages
Chinese (zh)
Other versions
CN106115474A (en
Inventor
罗正山
陶雄壮
张昆
冯剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kocel Steel Structure Co Ltd
Original Assignee
Kocel Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kocel Steel Structure Co Ltd filed Critical Kocel Steel Structure Co Ltd
Priority to CN201610761984.4A priority Critical patent/CN106115474B/en
Publication of CN106115474A publication Critical patent/CN106115474A/en
Application granted granted Critical
Publication of CN106115474B publication Critical patent/CN106115474B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/62Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Jib Cranes (AREA)

Abstract

It is an object of the invention to provide a kind of method for improving of super high steel structure pylon, it is related to the technical field of pylon construction and installation, including:Temporary component and second component are installed on the first part, temporary component and second component form lifting member;Lifting device is set between lifting member and first component;Lifting device action is controlled so that lifting member rises to setting position relative to first component;Second component is fixedly connected with first component;Engaged mechanism between polishing second component and first component.By the present invention, the technical problem of super high steel structure top tower crane installation difficulty present in prior art is alleviated.

Description

The method for improving of super high steel structure pylon
Technical field
The present invention relates to the technical field of pylon installation, more particularly, to a kind of lifting of super high steel structure pylon Method.
Background technology
As the strategic decision of nation-building conservation-minded society is implemented, the development of super high steel structure is increasingly taken seriously, Steel construction has green, energy-saving and environmental protection function, the development trend that will be built as China.Resistance of super high-rise steel structures is a kind of The building system of new energy-conserving and environment-protective, there is the characteristics of in light weight, intensity is high, anti-seismic performance is good.Steel construction market prospects, it is special Be not high-rise building present market it is very tempting.
Apply the application of the super high steel structure pylon in high-rise building commonplace, but due to Super High steel knot The top of structure pylon is higher, and tower crane can not realize the lifting on super high steel structure pylon top under normal circumstances.
To sum up, problem of the prior art is the technical problem of super high steel structure top tower crane installation difficulty.
The content of the invention
It is an object of the invention to provide a kind of method for improving of super high steel structure pylon, is deposited in the prior art with alleviating Super high steel structure top tower crane installation difficulty technical problem.
A kind of method for improving of super high steel structure pylon provided by the invention, including:
Temporary component and second component are installed on the first part, temporary component and second component form lifting member;
Lifting device is set between lifting member and first component;
Lifting device action is controlled so that lifting member rises to setting position relative to first component;
Second component is fixedly connected with first component;
Engaged mechanism between polishing second component and first component.
Further, temporary component is installed on the first part and second component, temporary component and second component is formed The step of lifting member, includes:
Temporary component is positioned in first component;
Second component is positioned over to the top of temporary component;
Second component and temporary component are connected, form lifting member.
Further, the first component is the part for the pylon installed.
Further, set between lifting member and first component the step of lifting device and be:
Lifting device is installed on the top crossbeam of first component;
Lifting device is connected with temporary component.
Further, lifting device action is controlled so that lifting member rises to the step of setting position relative to first component Before rapid, multiple limiters are first set on the girder of the top end of first component, to prevent during lifting, lift structure Part topples.
Further, the lifting device is hydraulic rockshaft, is welded on the top crossbeam of first component, the hydraulic pressure The suspension centre of lifter and the hanger of temporary component connect.
Further, second component is fixedly connected with into step with first component includes:
, will be spacing after control lifting device is acted so that lifting member rises to setting position relative to first component Device is welded and fixed with temporary component, to ensure that it is stable.
Further, the engaged mechanism between polishing second component and first component, step include:
The part of engaged mechanism is adjusted to setting height(from bottom) with tower crane;
Assembly welding is carried out to the part of the monomer of engaged mechanism in the periphery of temporary component;
Engaged mechanism is welded and fixed with second component and first component respectively.
Further, after the engaged mechanism between polishing second component and first component, temporary component is removed.
Further, after temporary component dismounting, by remaining girder steel polishing, installation is completed.
The method for improving of super high steel structure pylon provided by the invention, first on the first part install temporary component with And second component, temporary component and second component form lifting member;Then set and carry between lifting member and first component Rise device;Lifting device action is controlled so that lifting member rises to setting position relative to first component;Then by the second structure Part is fixedly connected with first component;The finally engaged mechanism between polishing second component and first component, installation is completed, it is above-mentioned Step, i.e. by the pylon top installation of super high steel structure, alleviates super high steel structure top tower crane not using tower crane The technical problem of installation difficulty.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The required accompanying drawing used is briefly described in embodiment or description of the prior art, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is that the lifting member of the method for improving of super high steel structure pylon provided in an embodiment of the present invention is in the first structure Schematic diagram in part;
Fig. 2 is that the lifting member of the method for improving of super high steel structure pylon provided in an embodiment of the present invention is in rising shape The schematic diagram of state;
Fig. 3 is that the lifting member of the method for improving of super high steel structure pylon provided in an embodiment of the present invention is in stopping The schematic diagram of the state of liter;
Fig. 4 is attached wall around the temporary component of the method for improving of super high steel structure pylon provided in an embodiment of the present invention Schematic diagram;
Fig. 5 is the structural representation of each component of the method for improving of super high steel structure pylon provided in an embodiment of the present invention Figure.
Reference:
100- first components;200- temporary components;300- second components;
400- lifting devices;500- engaged mechanisms;600- limiters;
700- tower cranes.
Embodiment
Technical scheme is clearly and completely described below in conjunction with accompanying drawing, it is clear that described implementation Example is part of the embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of creative work is not made, belongs to the scope of protection of the invention.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, merely to Be easy to the description present invention and simplify description, rather than instruction or imply signified device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that instruction or hint relative importance.
In the description of the invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
In the installation process of super high steel structure pylon, the mode of generally use tower crane lifting, work as super high steel structure After pylon is installed to certain height, tower crane can not also be completed, and cause the lifting difficulty on super high steel structure pylon top Technical problem.
The central idea of the present invention is to provide a kind of method for improving of super high steel structure pylon, by temporary component by the After two member lifts, the installation of top pylon is completed in the peripheral polishing engaged mechanism of temporary component, alleviates Super High steel The technical problem of structure top end tower crane installation difficulty.
The present embodiment provides a kind of method for improving of super high steel structure pylon, and as shown in Figure 1,2,3, 4, including step is such as Under:
S110, temporary component 200 and second component 300, temporary component 200 and second are installed in first component 100 Component 300 forms lifting member;
S120, lifting device 400 is set between lifting member and first component 100;
S130, control lifting device 400 are acted so that lifting member rises to setting position relative to first component 100;
S140, second component 300 is fixedly connected with first component 100;
S150, the engaged mechanism between polishing second component 300 and first component 100.
Above-mentioned lifting device 400 can be the lifter positioned at the top of first component 100.The lifting device 400 can be with According to needs easy for construction, flexibly choose, for example, by the way of for slinging lifting using top, the lifting device 400 is to carry Rise device;By the way of jacking up lifting using bottom, lifting device 400 can be positioned at lifting member bottom in first component 100 The hoisting frame in portion.
The method for improving of super high steel structure pylon provided in an embodiment of the present invention, is installed in first component 100 first Temporary component 200 and second component 300, temporary component 200 and second component 300 form lifting member;Then in lifting structure Lifting device 400 is set between part and first component 100;Control lifting device 400 is acted so that lifting member is relative to first Component 100 rises to setting position;Then second component 300 is fixedly connected with first component 100;Last polishing second component Engaged mechanism between 300 and first component 100, installation is completed, above-mentioned step is not using tower crane i.e. by Super High steel knot The pylon top installation of structure, alleviate the technical problem of super high steel structure top tower crane installation difficulty.
In specific operation, temporary component 200 and second component 300, temporary component are installed in first component 100 200 and second component 300 formed lifting member step S110 include:As shown in figure 1,
S111, temporary component 200 is positioned in first component 100;
S112, second component 300 is positioned over to the top of temporary component 200;
Second component 300 and temporary component 200 are connected, form lifting member.
Above-mentioned first component 100 is the part for the pylon installed.
It is positioned in view of temporary component 200 in first component 100, so, first component 100 is in one end close to top In distance, inside does not have secondary beam, and space is provided for being put into for temporary component 200.
In the specific time, the step S120 of lifting device 400 is set between lifting member and first component 100 For:As shown in Figure 1,5,
S121, lifting device 400 is installed on the top crossbeam of first component 100;So operation can be lifted The bottom of device and lifting member has maximum lifting distance, also has the range of lift of maximum, can be by lifting member What is risen is higher.
S122, lifting device 400 is connected with temporary component.
Control lifting device act so that the step of lifting member rises to setting position relative to first component 100 it Before, multiple limiters 600 are first set on the girder of the top end of first component 100, as shown in Fig. 2,5, to prevent from being lifted During, lifting member is toppled.
For the stability of further lifting member, limiter 600 is four or three layers, and four respectively from the corner angle of pylon Inner side is stretched out, and extends to the lateral wall of temporary component 200, three layers since the top of first component 100, successively downwards, the 3rd Layer is installed in the middle part of the height of temporary component 200.
In specific operation, the lifting device 400 is hydraulic rockshaft, and the top for being welded in first component 100 is horizontal Liang Shang, the suspension centre of the hydraulic rockshaft and the hanger of temporary component connect.
Second component is fixedly connected with into step S140 with first component includes:
As shown in figure 3, in control lifting device action so that lifting member rises to setting position relative to first component Afterwards, limiter 600 is welded and fixed with temporary component, to ensure that it is stable.Limiter 600 is welded in temporary component 200 On lateral wall, because second component is higher by first component 100 above first component 100, the major part of temporary component 200, Therefore, it is above-mentioned by the way of limiter 600 and temporary component 200 weld, the center of gravity of lifting member can be changed, increase carries Rise the stability of component.
Engaged mechanism 500 between polishing second component and first component, as Fig. 4 steps S150 includes:
S151, the part tower crane 700 of engaged mechanism 500 is adjusted to setting height(from bottom);
S152, assembly welding is carried out to the part of the monomer of engaged mechanism 500 in the periphery of temporary component 200;
S153, engaged mechanism 500 is welded and fixed with second component 300 and first component 100 respectively.
In specific operation, after the engaged mechanism between polishing second component 300 and first component 100, Temporary component is removed.Removing temporary component can provide necessarily for the inside between first component 100 and second component 300 Space, secondary beam is installed, increases the connective stability between first component 100 and second component 300.
After pylon installation terminates, after temporary component dismounting, by remaining girder steel polishing, installation is completed.
Finally it should be noted that:Various embodiments above is merely illustrative of the technical solution of the present invention, rather than its limitations;To the greatest extent The present invention is described in detail with reference to foregoing embodiments for pipe, it will be understood by those within the art that:Its according to The technical scheme described in foregoing embodiments can so be modified, either which part or all technical characteristic are entered Row equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from various embodiments of the present invention technology The scope of scheme.

Claims (7)

  1. A kind of 1. method for improving of super high steel structure pylon, it is characterised in that including:
    Temporary component and second component are installed on the first part, temporary component and second component form lifting member;
    Lifting device is set between lifting member and first component;
    Lifting device action is controlled so that lifting member rises to setting position relative to first component;
    Second component is fixedly connected with first component;
    Engaged mechanism between polishing second component and first component;
    The step of installing temporary component and second component, temporary component and second component formation lifting member on the first part Including:
    Temporary component is positioned in first component;
    Second component is positioned over to the top of temporary component;
    Second component and temporary component are connected, form lifting member;
    The first component is the part for the pylon installed;
    Set between lifting member and first component the step of lifting device and be:
    Lifting device is installed on the top crossbeam of first component;
    Lifting device is connected with temporary component.
  2. 2. the method for improving of super high steel structure pylon according to claim 1, it is characterised in that
    Lifting device is controlled to act so that before the step of lifting member rises to setting position relative to first component, first Multiple limiters are first set on the girder of the top end of component.
  3. 3. the method for improving of super high steel structure pylon according to claim 1 or 2, it is characterised in that the lifting dress Hydraulic rockshaft is set to, is welded on the top crossbeam of first component, the suspension centre of the hydraulic rockshaft and hanging for temporary component Ear connects.
  4. 4. the method for improving of super high steel structure pylon according to claim 3, it is characterised in that
    Second component is fixedly connected with into step with first component includes:
    After control lifting device is acted so that lifting member rises to setting position relative to first component, by limiter with Temporary component is welded and fixed.
  5. 5. the method for improving of super high steel structure pylon according to claim 4, it is characterised in that
    Engaged mechanism between polishing second component and first component, step include:
    The part of engaged mechanism is adjusted to setting height(from bottom) with tower crane;
    Assembly welding is carried out to the part of the monomer of engaged mechanism in the periphery of temporary component;
    Engaged mechanism is welded and fixed with second component and first component respectively.
  6. 6. the method for improving of super high steel structure pylon according to claim 5, it is characterised in that in polishing second component After engaged mechanism between first component, temporary component is removed.
  7. 7. the method for improving of super high steel structure pylon according to claim 6, it is characterised in that removed in temporary component Afterwards, by remaining girder steel polishing, installation is completed.
CN201610761984.4A 2016-08-29 2016-08-29 The method for improving of super high steel structure pylon Active CN106115474B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610761984.4A CN106115474B (en) 2016-08-29 2016-08-29 The method for improving of super high steel structure pylon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610761984.4A CN106115474B (en) 2016-08-29 2016-08-29 The method for improving of super high steel structure pylon

Publications (2)

Publication Number Publication Date
CN106115474A CN106115474A (en) 2016-11-16
CN106115474B true CN106115474B (en) 2018-03-23

Family

ID=57272188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610761984.4A Active CN106115474B (en) 2016-08-29 2016-08-29 The method for improving of super high steel structure pylon

Country Status (1)

Country Link
CN (1) CN106115474B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114873497B (en) * 2022-05-24 2023-06-16 中国长江三峡集团有限公司 Vertical lifting installation device and method for variable-diameter unbalanced load equipment

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101619630A (en) * 2009-06-30 2010-01-06 武汉京冶地基基础工程有限责任公司 Mounting method of steel chimney and implementary jacking device
CN101700855A (en) * 2009-10-31 2010-05-05 唐福强 Method and device for lifting weight on top floor of super high-rise building
CN102108737A (en) * 2011-01-18 2011-06-29 东北电业管理局烟塔工程公司 Hydraulic lifting inverted construction method for steel inner cylinder of chimney in thermal power plant
CN102496771A (en) * 2011-12-19 2012-06-13 宝钢钢构有限公司 Method and device for installing large-sized steel structural antenna
CN102733644A (en) * 2012-07-12 2012-10-17 广州建筑股份有限公司 Super-altitude roof super-long antenna hoisting construction method and system
CN103243930A (en) * 2013-04-23 2013-08-14 重庆大学 System and method for modularized construction of super high-rise steel structures
CN104652813A (en) * 2015-01-30 2015-05-27 上海绿地建设(集团)有限公司 Tower crane construction technology used for super high-rise building steel structure
CN104863259A (en) * 2015-05-06 2015-08-26 浙江中南建设集团钢结构有限公司 Upside-down construction method for large-span ultra-high signal-layer cylindrical architectural steel structure
CN105776067A (en) * 2016-05-25 2016-07-20 中国能源建设集团湖南火电建设有限公司 Lifting device and inverted installing method for reducing absorption tower

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101619630A (en) * 2009-06-30 2010-01-06 武汉京冶地基基础工程有限责任公司 Mounting method of steel chimney and implementary jacking device
CN101700855A (en) * 2009-10-31 2010-05-05 唐福强 Method and device for lifting weight on top floor of super high-rise building
CN102108737A (en) * 2011-01-18 2011-06-29 东北电业管理局烟塔工程公司 Hydraulic lifting inverted construction method for steel inner cylinder of chimney in thermal power plant
CN102496771A (en) * 2011-12-19 2012-06-13 宝钢钢构有限公司 Method and device for installing large-sized steel structural antenna
CN102733644A (en) * 2012-07-12 2012-10-17 广州建筑股份有限公司 Super-altitude roof super-long antenna hoisting construction method and system
CN103243930A (en) * 2013-04-23 2013-08-14 重庆大学 System and method for modularized construction of super high-rise steel structures
CN104652813A (en) * 2015-01-30 2015-05-27 上海绿地建设(集团)有限公司 Tower crane construction technology used for super high-rise building steel structure
CN104863259A (en) * 2015-05-06 2015-08-26 浙江中南建设集团钢结构有限公司 Upside-down construction method for large-span ultra-high signal-layer cylindrical architectural steel structure
CN105776067A (en) * 2016-05-25 2016-07-20 中国能源建设集团湖南火电建设有限公司 Lifting device and inverted installing method for reducing absorption tower

Also Published As

Publication number Publication date
CN106115474A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
CN102251486B (en) Jacking bracket system for segmented mounting of bridge tower and construction process thereof
CN106115474B (en) The method for improving of super high steel structure pylon
CN104989111B (en) Steel construction high level construction method for hanging
CN104032966A (en) Partitioning, hoisting, overhead closing and mounting method for arc-shaped double-layer net racks
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN103663144A (en) Special turnover device used for steel members
CN105239804B (en) Assembly and lift-erecting method of indirect air-cooling system stretching platforms
CN206529229U (en) It is a kind of to increase the tower crane device of independence and freedom height
CN102849626B (en) Indoor non-standard crane installation method
CN206590793U (en) Connect arm assembly and the movable arm tower crane comprising the device in the air
CN101660660B (en) Novel installing method of gas cabinet
CN104444810B (en) Large-scale plate overturns construction method
CA2992914C (en) Assembly method for dc converter valve
CN105731271A (en) Combined tower crane for roof construction and construction method thereof
CN205500626U (en) Climbing mechanism in tower crane
CN109371848A (en) The longitudinal temporary connecting structure and method of suspension bridge concrete stiffening girder installation
CN211169496U (en) Take quick hoist device of PC wallboard of counter weight
CN111254832B (en) Integral hoisting closure method and system for long section of cable-stayed bridge steel girder
CN209145257U (en) Hang lift-type pit shaft platform
CN206580444U (en) A kind of urban construction building prefabricated components hanging apparatus
CN205346600U (en) Big plate -girder hoist and mount specialized tool
CN108756259A (en) A kind of the auxiliary mounting assembly and installation method of large-scale steel structure component
CN202466428U (en) Hoisting structure for hoisting prefabricated box girder segment
CN213112186U (en) Hoisting device for assembled component
CN201620407U (en) Offshore petroleum drilling platform skid block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant