CN213112186U - Hoisting device for assembled component - Google Patents

Hoisting device for assembled component Download PDF

Info

Publication number
CN213112186U
CN213112186U CN202021449666.2U CN202021449666U CN213112186U CN 213112186 U CN213112186 U CN 213112186U CN 202021449666 U CN202021449666 U CN 202021449666U CN 213112186 U CN213112186 U CN 213112186U
Authority
CN
China
Prior art keywords
leg
screw thread
connection
fixed arm
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021449666.2U
Other languages
Chinese (zh)
Inventor
仲小兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Golden Cube Concrete Products Co ltd
Original Assignee
Jiangsu Golden Cube Concrete Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Golden Cube Concrete Products Co ltd filed Critical Jiangsu Golden Cube Concrete Products Co ltd
Priority to CN202021449666.2U priority Critical patent/CN213112186U/en
Application granted granted Critical
Publication of CN213112186U publication Critical patent/CN213112186U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a hoist device for assembled component relates to assembled structure technical field, makes the problem that the component rocked easily when handling assembled component for solving ordinary hoist device among the prior art. First screw thread leg is installed to the top of first fixed arm, first screw thread leg and first fixed arm threaded connection, first cassette is installed to the top of first screw thread leg, first screw thread leg and first cassette welded connection, first lifting hook is installed to the below of first fixed arm, first lifting hook rotates with first fixed arm to be connected, second screw thread leg is installed to the below of second cassette, second screw thread leg and second cassette welded connection, the second fixed arm is installed to the below of second screw thread leg, second fixed arm and second screw thread leg threaded connection, the second lifting hook is installed to the below of second fixed arm, the second lifting hook rotates with the second fixed arm to be connected.

Description

Hoisting device for assembled component
Technical Field
The utility model relates to an assembled structure technical field specifically is a hoist device for assembled component.
Background
The prefabricated structure is a concrete structure formed by assembling and connecting prefabricated components serving as main stressed components, is one of important directions for the development of building structures in China, is beneficial to the development of building industrialization in China, improves production efficiency, saves energy, develops green and environment-friendly buildings, and is beneficial to improving and ensuring the quality of building engineering.
The assembly type building is a building which is formed by transferring a large amount of field operation work in the traditional building mode to a factory, processing and manufacturing building components and accessories (such as floor slabs, wall plates, stairs, balconies and the like) in the factory, transporting the components and the accessories to a building construction site, assembling and installing the components on the site in a reliable connection mode, wherein the components forming the assembly type building are the assembly type components, the assembly type components need to be lifted when being assembled, and the components are fixed and lifted by a crane and a lifting device generally, but common lifting devices on the market generally adopt steel wire rope fixing components, so that the components are easy to shake when being lifted and lifted, and the potential safety hazard of the field construction work is increased; therefore, there is an urgent need in the market to develop a lifting device for fabricated components to help people solve the existing problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a hoist device for assembled component to solve the problem that ordinary hoist device who provides among the above-mentioned background art made the component rock easily when the handling assembled component.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a hoist device for assembled component, includes hanging beam and first fixed arm, first screw thread leg is installed to the top of first fixed arm, first screw thread leg and first fixed arm threaded connection, first cassette is installed to the top of first screw thread leg, first screw thread leg and first cassette welded connection, first lifting hook is installed to the below of first fixed arm, first lifting hook rotates with first fixed arm to be connected.
Preferably, a lower connecting plate is installed below the hanging beam, the lower connecting plate is welded to the hanging beam, a lower fixing hole is formed in the lower connecting plate, the lower fixing hole and the lower connecting plate are arranged into an integral structure, the first clamping seat is fixedly connected with the lower fixing hole through a bolt, and a second clamping seat is installed below the lower connecting plate.
Preferably, there is the second cassette to pass through bolt fixed connection with lower fixed orifices, second screw thread leg is installed to the below of second cassette, second screw thread leg and second cassette welded connection, the second fixed arm is installed to the below of second screw thread leg, second fixed arm and second screw thread leg threaded connection, the second lifting hook is installed to the below of second fixed arm, the second lifting hook rotates with the second fixed arm to be connected.
Preferably, an upper connecting plate is installed above the hanging beam and is connected with the hanging beam in a welding mode, an upper fixing hole is formed in the upper connecting plate, the upper fixing hole and the upper connecting plate are arranged into an integral structure, a cross reinforcing rib is arranged on the inner side of the hanging beam, and the cross reinforcing rib and the hanging beam are arranged into an integral structure.
Preferably, the first connecting leg and the second connecting leg are installed above the upper connecting plate respectively, the first connecting leg and the second connecting leg are fixedly connected with the upper fixing hole, the first steel wire rope is installed above the first connecting leg, and the second steel wire rope is installed above the second connecting leg.
Preferably, first wire rope and first connecting leg fixed connection, second wire rope and second connecting leg fixed connection, triangle steadying plate is installed to first wire rope and second wire rope's top, first wire rope and second wire rope all with triangle steadying plate fixed connection, triangle steadying plate's inside is provided with the lewis hole, the lewis hole sets up structure as an organic whole with the lewis hole.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a through the setting of first fixed arm and second fixed arm, replace traditional wire rope for the fixed arm, through fixed arm and assembled component rigid connection, avoid wire rope to cross soft and lead to the condition emergence that the component rocked for component more stability when the handling, thereby the risk when having reduced the handling, make site operation operational environment's potential safety hazard obtain effectual reduction.
2. The utility model discloses a through the setting of first screw thread leg and second screw thread leg for two fixed arms can be changed, thereby can change into the suitable fixed arm of size with the size of military assembly formula component, thereby security when guaranteeing the component handling, firm nature when can fix, thereby make this hoist device use safe and reliable more.
Drawings
Fig. 1 is a front view of a lifting device for a fabricated component according to the present invention;
fig. 2 is a cross-sectional view of a first fixing arm of the present invention;
fig. 3 is a side view of the suspension beam of the present invention.
In the figure: 1. a hanging beam; 2. an upper connecting plate; 3. a lower connecting plate; 4. an upper fixing hole; 5. a lower fixing hole; 6. a triangular stabilizing plate; 7. a first wire rope; 8. a second wire rope; 9. a first connecting leg; 10. a second connecting leg; 11. a first fixed arm; 12. a first threaded leg; 13. a first card holder; 14. a first hook; 15. a second fixed arm; 16. a second threaded leg; 17. a second card holder; 18. a second hook; 19. a cross reinforcing rib; 20. and (5) lifting the hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, the present invention provides an embodiment: the utility model provides a hoist device for assembled component, includes hanging beam 1 and first fixed arm 11, first screw thread leg 12 is installed to the top of first fixed arm 11, first screw thread leg 12 and 11 threaded connection of first fixed arm, first cassette 13 is installed to the top of first screw thread leg 12, first screw thread leg 12 and first cassette 13 welded connection, first lifting hook 14 is installed to the below of first fixed arm 11, first lifting hook 14 rotates with first fixed arm 11 to be connected.
Further, lower connecting plate 3 is installed to the below of hanging beam 1, lower connecting plate 3 and hanging beam 1 welded connection, lower connecting plate 3's inside is provided with lower fixed orifices 5, lower fixed orifices 5 sets up structure as an organic whole with lower connecting plate 3, first cassette 13 passes through bolt fixed connection with lower fixed orifices 5, second cassette 17 is installed to the below of lower connecting plate 3, lower fixed orifices 5 are provided with a plurality of, and quantity is the dual, all have the position that corresponds each other between per two lower fixed orifices 5.
Further, a second clamping seat 17 is fixedly connected with the lower fixing hole 5 through a bolt, a second threaded leg 16 is installed below the second clamping seat 17, the second threaded leg 16 is connected with the second clamping seat 17 in a welding mode, a second fixing arm 15 is installed below the second threaded leg 16, the second fixing arm 15 is in threaded connection with the second threaded leg 16, a second hook 18 is installed below the second fixing arm 15, the second hook 18 is rotatably connected with the second fixing arm 15, penetrating holes are formed in the first threaded leg 12 and the second threaded leg 16, and the first threaded leg 12 and the second threaded leg 16 can be fixed with the first fixing arm 11 and the second fixing arm 15 through bolts and the penetrating holes.
Further, upper junction plate 2 is installed to the top of hanging beam 1, upper junction plate 2 and hanging beam 1 welded connection, upper junction plate 2's inside is provided with fixed orifices 4, upper fixed orifices 4 sets up structure as an organic whole with upper junction plate 2, the inboard of hanging beam 1 is provided with cross strengthening rib 19, cross strengthening rib 19 sets up structure as an organic whole with hanging beam 1, the setting up through cross strengthening rib 19 makes the inside of hanging beam 1 be the cavity design, can reduce the weight of hanging beam 1 under the intensity circumstances that does not reduce hanging beam 1.
Further, first connecting leg 9 and second connecting leg 10 are installed respectively to the top of upper junction plate 2, and first connecting leg 9 and second connecting leg 10 all with last fixed orifices 4 fixed connection, and first wire rope 7 is installed to the top of first connecting leg 9, and second wire rope 8 is installed to the top of second connecting leg 10, goes up fixed orifices 4 and is provided with a plurality of, and first connecting leg 9 and second connecting leg 10 all can install inside the last fixed orifices 4 of different positions.
Further, first wire rope 7 and first connecting leg 9 fixed connection, leg 10 fixed connection is connected with the second to second wire rope 8, triangle steadying plate 6 is installed to first wire rope 7 and second wire rope 8's top, first wire rope 7 and second wire rope 8 all with triangle steadying plate 6 fixed connection, triangle steadying plate 6's inside is provided with lifting eye 20, lifting eye 20 sets up structure as an organic whole with lifting eye 20, two angles departments at triangle steadying plate 6 are installed respectively to first wire rope 7 and second wire rope 8.
The working principle is as follows: when the device is used, the first lifting hook 14 and the second lifting hook 18 are hung on a fabricated component and are firmly fixed, the first clamping seat 13 and the second clamping seat 17 are installed inside the corresponding lower fixing hole 5 according to the size of the component, so that the first fixing arm 11 and the second fixing arm 15 are fixed, then the lifting hook of a crane is hung inside the lifting hole 20, the triangular stabilizing plate 6 is lifted by the crane, the triangular stabilizing plate 6 lifts the lifting beam 1 through the first steel wire rope 7 and the second steel wire rope 8, so that the component hung above the first lifting hook 14 and the second lifting hook 18 is lifted, after the component is lifted for fifty centimeters, the component is temporarily suspended, whether the first lifting hook 14 and the second lifting hook 18 are firmly fixed with the component is observed, and after the component is confirmed to be correct, the component is hung in an installation station for installation.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. A hoist device for prefabricated component, includes hanging beam (1) and first fixed arm (11), its characterized in that: first screw thread leg (12) are installed to the top of first fixed arm (11), first screw thread leg (12) and first fixed arm (11) threaded connection, first cassette (13) are installed to the top of first screw thread leg (12), first screw thread leg (12) and first cassette (13) welded connection, first lifting hook (14) are installed to the below of first fixed arm (11), first lifting hook (14) rotate with first fixed arm (11) and are connected.
2. A hoist device for fabricated construction according to claim 1, characterized in that: lower connecting plate (3) is installed to the below of hanging beam (1), lower connecting plate (3) and hanging beam (1) welded connection, the inside of lower connecting plate (3) is provided with down fixed orifices (5), lower fixed orifices (5) set up structure as an organic whole with lower connecting plate (3), first cassette (13) pass through bolt fixed connection with lower fixed orifices (5), second cassette (17) are installed to the below of lower connecting plate (3).
3. A hoist device for fabricated construction according to claim 2, characterized in that: there is second cassette (17) and lower fixed orifices (5) to pass through bolt fixed connection, second screw thread leg (16) are installed to the below of second cassette (17), second screw thread leg (16) and second cassette (17) welded connection, second fixed arm (15) are installed to the below of second screw thread leg (16), second fixed arm (15) and second screw thread leg (16) threaded connection, second lifting hook (18) are installed to the below of second fixed arm (15), second lifting hook (18) rotate with second fixed arm (15) and are connected.
4. A hoist device for fabricated construction according to claim 1, characterized in that: the improved hanging beam is characterized in that an upper connecting plate (2) is installed above the hanging beam (1), the upper connecting plate (2) is connected with the hanging beam (1) in a welded mode, an upper fixing hole (4) is formed in the upper connecting plate (2), the upper fixing hole (4) and the upper connecting plate (2) are arranged into a whole, a cross reinforcing rib (19) is arranged on the inner side of the hanging beam (1), and the cross reinforcing rib (19) and the hanging beam (1) are arranged into a whole.
5. A hoisting device for fabricated construction according to claim 4, characterized in that: first connection leg (9) and second connection leg (10) are installed respectively to the top of upper junction plate (2), first connection leg (9) and second connection leg (10) all with last fixed orifices (4) fixed connection, first wire rope (7) are installed to the top of first connection leg (9), second wire rope (8) are installed to the top of second connection leg (10).
6. A hoisting device for prefabricated components according to claim 5, characterized in that: first wire rope (7) and first connecting leg (9) fixed connection, second wire rope (8) and second connecting leg (10) fixed connection, triangle steadying plate (6) are installed to the top of first wire rope (7) and second wire rope (8), first wire rope (7) and second wire rope (8) all with triangle steadying plate (6) fixed connection, the inside of triangle steadying plate (6) is provided with lifting eye (20), lifting eye (20) set up structure as an organic whole with lifting eye (20).
CN202021449666.2U 2020-07-21 2020-07-21 Hoisting device for assembled component Active CN213112186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021449666.2U CN213112186U (en) 2020-07-21 2020-07-21 Hoisting device for assembled component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021449666.2U CN213112186U (en) 2020-07-21 2020-07-21 Hoisting device for assembled component

Publications (1)

Publication Number Publication Date
CN213112186U true CN213112186U (en) 2021-05-04

Family

ID=75678592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021449666.2U Active CN213112186U (en) 2020-07-21 2020-07-21 Hoisting device for assembled component

Country Status (1)

Country Link
CN (1) CN213112186U (en)

Similar Documents

Publication Publication Date Title
CN111021749A (en) Simple hoisting mechanism for bare concrete exterior wall cladding and construction method thereof
CN201785144U (en) Gin pole crane
CN101649683A (en) Method for hoisting power transmission iron tower by assembly holding pole technology
CN213112186U (en) Hoisting device for assembled component
CN108217429A (en) A kind of assemble type hanger and hanging method
CN210619969U (en) Prefabricated staircase hoist and mount subassembly
CN202441045U (en) Rail-type electric attached lifting scaffold
CN207079898U (en) Outer hanging basket structure
CN202988556U (en) Special lifting appliance for angle-steel type frame body
CN216129243U (en) Auxiliary lifting machine for wallboard for assembly type building
CN211691536U (en) Simple lifting mechanism for bare concrete exterior wall cladding
CN103058083B (en) Bolt sphere truss gig
CN204778496U (en) Platform sling structure of tower crane
CN206580444U (en) A kind of urban construction building prefabricated components hanging apparatus
CN113175203A (en) Method for setting lifting power equipment in attached lifting scaffold
CN205935718U (en) Hoist device of embedded integral side fascia
CN217808268U (en) Integrated multi-functional hoist of building of timber structure
CN215048216U (en) Tower crane device with balanced type hanging beam structure
CN106869508B (en) A kind of rotation lifting of assembled architecture steel box column is welded and fixed mounting process in place
CN221235055U (en) Stable structure for building construction hoisting
CN217458557U (en) Attachment structure of main building tower crane
CN218145401U (en) Simple cable reel lifting appliance
CN212334450U (en) Installation device for main steel structure in narrow site
CN205114898U (en) Tower owner hangs antiwind device of wire rope
CN213923700U (en) Precast concrete board assembly quality of building engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant