CN102849626B - Indoor non-standard crane installation method - Google Patents

Indoor non-standard crane installation method Download PDF

Info

Publication number
CN102849626B
CN102849626B CN201210359461.9A CN201210359461A CN102849626B CN 102849626 B CN102849626 B CN 102849626B CN 201210359461 A CN201210359461 A CN 201210359461A CN 102849626 B CN102849626 B CN 102849626B
Authority
CN
China
Prior art keywords
crane
main beam
lifting
runway
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210359461.9A
Other languages
Chinese (zh)
Other versions
CN102849626A (en
Inventor
隋杰明
马荣全
亓立刚
郭佳
郭春华
宁传红
崔爱珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201210359461.9A priority Critical patent/CN102849626B/en
Publication of CN102849626A publication Critical patent/CN102849626A/en
Application granted granted Critical
Publication of CN102849626B publication Critical patent/CN102849626B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an indoor non-standard crane installation method which comprises the following steps of: firstly, when a concrete roof structure on which cranes need to be installed is constructed, reserving a lifting opening to install a temporary lifting truss girder and a lifting beam, installing a hydraulic synchronous lifting system above the lifting beam and pre-installing crane rails; then lifting two band pulleys and crane girders of crane girder rails by the hydraulic synchronous lifting system, placing pulleys of two crane girders on the crane rails and in the lifting process, ensuring the crane girders to be shifted relative to the crane rails so as the span of the crane girders is less than the span between the crane rails, wherein the installation distance between the two crane girders is greater than the distance between the cranes; and finally, lifting the cranes by the hydraulic synchronous lifting system and when the cranes are lifted to the positions higher than the elevations of the crane girder rails, folding and connecting the crane girders at both sides and arranging the cranes on the crane girder rails.

Description

A kind of Indoor non-standard crane installation method
Technical field
The present invention relates to a kind of crane installation method, especially, relate to the installation method of the heavy non-standard crane of a kind of large span indoor ultrahigh.
Background technology
Along with the development of industrial building, traverse crane is the indispensable hanging device in a lot of industrial premises, a new generation's carrier rocket full vibrations tower indoor 100t traverse crane span 22.5m, the overall wide 7.55m of girder, rail level absolute altitude 81.53m, crane total weight is about 130t, wherein, girder 1 weight is 34.8t, girder 2 weight is 30t, the total weight such as dolly and suspension hook is 45t, how before roof structure is closed, open type hoisting method is adopted in general highly lower engineering, due to the particularity of the structure of this type of engineering, by the impact of 89m tall concrete structure roof construction, described non-standard crane cannot adopt open type hoisting method, and it is narrow and small because installing three dimensional space, crane weight is large, radius of turn is large, setting height(from bottom) is high, driving pendulum bit space is little, the factor restrictions such as the large single-point low bearing capacity of roof structure span, conventional closed hanging method can not meet the installation needs of this crane, therefore, need to design a kind of new method to realize the installation of the heavy nonstandard driving of indoor ultrahigh.
Summary of the invention
Main purpose of the present invention there is provided a kind of Indoor non-standard crane installation method, realizes the heavy non-standard crane of indoor ultrahigh and installs safely and effectively.
Indoor non-standard crane installation method of the present invention; comprise a. first reserved lifting hole when the concrete roof structure construction need installing crane; to install interim boist truss beam and lifting beam, hydraulic synchronizing lifting system is installed above lifting beam, and installs crane runway in advance; B. the main beam of crane of hydraulic synchronizing lifting system improving two panels band pulley and main beam of crane track is then passed through, in lifting process, the angles of whole main beam of crane, span between crane runway is less than to make main beam of crane span, when main beam of crane is promoted to higher than crane runway, make main beam of crane perpendicular to crane runway, the pulley of two panels main beam of crane is placed on crane runway, and the installing space of two panels main beam of crane is greater than hoist room distance; C., finally by hydraulic synchronizing lifting system improving crane, when crane is promoted to higher than main beam of crane track level measuring, both sides main beam of crane is closed up and connects and crane is installed on main beam of crane track.
Preferably, first must carry out detection debugging to hydraulic synchronizing lifting system, start again after comfirmation test is qualified to promote operation.
Preferably, the swing in described main beam of crane lifting process is adjusted in step b further by the cable wind rope of bottom, main beam of crane two ends and the guideline on top, two ends.
Preferably, hydraulic synchronizing lifting system bottom is provided with plain thrust bearing, to adjust the skew between main beam of crane and crane runway.
Preferably, main beam of crane is that single-point promotes, and crane is that two point promotes.
Preferably, the lifting suspension centre of main beam of crane is positioned at the inclined 20cm place of main beam of crane mid point.
Preferably, when main beam of crane is promoted to higher than crane runway 100mm, suspend and promote with the direction adjusting main beam of crane, the pulley center line at main beam of crane two ends is overlapped with crane runway line of centers, then slowly fall to being placed on crane runway by main beam of crane, the pulley of main beam of crane is placed in crane runway slidably.
Preferably, when crane is promoted to higher than main beam of crane track level measuring 100mm, both sides main beam of crane is closed up and connects and crane is installed on main beam of crane track.
The invention has the beneficial effects as follows:
Adopt hydraulic synchronizing lifting system, lifting process is stablized, cost-saving;
Hydraulic synchronizing lifting system be arranged on described concrete structure roofing on temporary support truss, then be connected with lower suspension centre special bottom anchor by described steel strand, load transmission is clear and definite, safe and reliable;
Mounting plane thrust baring bottom described lifting liquid decorum lifter, for adjusting described main beam of crane pivot angle;
Adopt the closed installation method of " roofing top hydraulic pressure lift, monolithic girder single-point lifting+pivot angle, dolly Integral lifting girder close up in place ", can adjust according to agent structure form the interim lifting sub-truss of described suspension centre, solve an installation difficult problem for the heavy non-standard crane of indoor ultrahigh.
Accompanying drawing explanation
Fig. 1 is the plan sketch that the present invention installs interim boist truss and lifting beam.
Fig. 2 is the generalized section that the present invention installs interim boist truss and lifting beam.
Fig. 3 is main beam of crane lifting process plan sketch of the present invention.
Fig. 4 is main beam of crane lifting process generalized section of the present invention.
Fig. 5 is the plan sketch that main beam of crane of the present invention is located in crane runway.
Fig. 6 is the generalized section that main beam of crane of the present invention is located in crane runway.
Fig. 7 is the plan sketch that crane of the present invention promotes and installs.
Fig. 8 is the generalized section that crane of the present invention promotes and installs.
Detailed description of the invention
Technical scheme of the present invention is described in detail referring to accompanying drawing.
As shown in Figure 1, 2,1 is main structure body, 9 is long-span roofing, first the reserved lifting hole when the concrete roof structure construction need installing crane, to install interim boist truss beam 2 and lifting beam 3, being provided with hydraulic synchronizing lifting system 4 above lifting beam 3, promoting and direction for controlling, hydraulic synchronizing lifting system 4 connects suspender 5 by steel strand 10 through lifting beam 3.
Then to hydraulic synchronizing lifting system 4 detect qualified after debug, as examination promote, counterweight balance and static test, the qualified rear formal lifting of comfirmation test.
Shown in Fig. 3, Fig. 4, the crane that mounted crane runway 7 can be used for being about to install in advance slides, before installation crane, need two panels main beam of crane 6 is first installed, wherein respectively there is a pulley 17 at main beam of crane 6 two ends, and are provided with main beam of crane track 15 in main beam of crane 6, as shown in Figure 8.First wherein a slice main beam of crane 6 being transported to promotes immediately below suspension centre 8, wherein a slice main beam of crane 6 is promoted by above-mentioned suspender 5, in lifting process, the angles of the whole main beam of crane in the lifting of described main beam of crane 6 is adjusted by the cable wind rope 12 of bottom, main beam of crane 6 two ends and the guideline 13 on top, two ends, its angles and crane runway 7 is made to there is certain deviation, the span of main beam of crane 6 is made to be less than span between crane runway 7, guarantee that main beam of crane 6 can not encounter perimeter body structure in lifting process, two does not have obstacle.
Shown in Fig. 5 and Fig. 6, described main beam of crane 6 shifts out lifting region, when being promoted to a little more than crane runway 7, control it by hydraulic synchronizing lifting system 4 and suspend lifting, and adjust the direction of main beam of crane 6, make its angles vertical with crane runway 7, and pulley 17 line of centers at main beam of crane 6 two ends overlaps with crane runway 7 line of centers, then main beam of crane 6 is slowly fallen to being placed on crane runway 7, the pulley 17 of main beam of crane 6 is placed in crane runway 7 slidably, namely installs a slice main beam of crane.Another sheet main beam of crane 6 is installed in the same way again, makes the installing space of two panels main beam of crane 6 on crane runway 7 be greater than vehicle-width.
Again see shown in Fig. 7 and Fig. 8, after above-mentioned two panels main beam of crane 6 is located in crane runway 7, the installation of crane 14 can be carried out, crane 14 is promoted by hydraulic synchronizing lifting system 4, after the main beam of crane track 15 that described crane 14 is promoted to a little more than above-mentioned main beam of crane 6, two panels main beam of crane 6 is closed up connection, and adjust the position of main beam of crane 6, be located at immediately below crane 14, then by crane 14 slowly under be put on main beam of crane track 15, complete lifting.
After such crane installs, can slide along main beam of crane track 15 on main beam of crane 6, main beam of crane 6 can carry out the slip with main beam of crane track 15 vertical direction on crane runway 7 simultaneously, and namely crane can slide as required at four corners of the world four direction.
Preferably, plain thrust bearing 11 is installed bottom hydraulic synchronizing lifting system 4, more effectively can adjusts the direction promoting thing.
Preferably, promote suspension centre 8 and be positioned at the inclined 20cm place of main beam of crane mid point.
Preferably, when main beam of crane 6 is promoted to higher than crane runway 7 about 100mm, suspends and promote with the direction adjusting main beam of crane 6.
Preferably, when crane 14 is promoted to higher than main beam of crane track 15 absolute altitude 100mm, both sides main beam of crane 6 is closed up connection.
Preferably, main beam of crane 6 is single-point lifting, and crane 14 is that two point promotes.
Although Indoor non-standard crane installation method of the present invention is described with reference to current instantiation, but those skilled in the art should be realized that, above example is only used to the present invention is described, change and the amendment that also can make various equivalence when not departing from spirit of the present invention all will drop in the scope of claims of the present invention.

Claims (8)

1. an Indoor non-standard crane installation method, is characterized in that:
A. first reserve when the concrete roof structure construction need installing crane and promote hole, to install interim boist truss beam and lifting beam, hydraulic synchronizing lifting system is installed above lifting beam, and installs crane runway in advance;
B. the main beam of crane of hydraulic synchronizing lifting system improving two panels band pulley and main beam of crane track is then passed through, in lifting process, the angles of adjustment main beam of crane, span between crane runway is less than to make main beam of crane span, when main beam of crane is promoted to higher than crane runway, make main beam of crane perpendicular to crane runway, the pulley of two panels main beam of crane is placed on crane runway, and the installing space of two panels main beam of crane is greater than hoist room distance;
C., finally by hydraulic synchronizing lifting system improving crane, when crane is promoted to higher than main beam of crane track level measuring, both sides main beam of crane is closed up and connects and crane is installed on main beam of crane track.
2. Indoor non-standard crane installation method as claimed in claim 1, is characterized in that: first must carry out detection debugging to hydraulic synchronizing lifting system, start to promote operation after comfirmation test is qualified again.
3. Indoor non-standard crane installation method as claimed in claim 1, be is characterized in that: adjusted the swing in described main beam of crane lifting process in step b further by the cable wind rope of bottom, main beam of crane two ends and the guideline on top, two ends.
4. Indoor non-standard crane installation method as claimed in claim 1, is characterized in that: hydraulic synchronizing lifting system bottom is provided with plain thrust bearing to adjust the skew between main beam of crane and crane runway.
5. Indoor non-standard crane installation method as claimed in claim 1, is characterized in that: main beam of crane is that single-point promotes, and crane is that two point promotes.
6. Indoor non-standard crane installation method as claimed in claim 1, is characterized in that: the lifting suspension centre of main beam of crane is positioned at the inclined 20cm place of main beam of crane mid point.
7. Indoor non-standard crane installation method as claimed in claim 1, it is characterized in that: when main beam of crane is promoted to higher than crane runway 100mm, suspend and promote with the direction adjusting main beam of crane, the pulley center line at main beam of crane two ends is overlapped with crane runway line of centers, then slowly fall to being placed on crane runway by main beam of crane, the pulley of main beam of crane is placed in crane runway slidably.
8. Indoor non-standard crane installation method as claimed in claim 1, is characterized in that: when crane is promoted to higher than main beam of crane track level measuring 100mm, is closed up by both sides main beam of crane and connects and installed on main beam of crane track by crane.
CN201210359461.9A 2012-09-24 2012-09-24 Indoor non-standard crane installation method Active CN102849626B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210359461.9A CN102849626B (en) 2012-09-24 2012-09-24 Indoor non-standard crane installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210359461.9A CN102849626B (en) 2012-09-24 2012-09-24 Indoor non-standard crane installation method

Publications (2)

Publication Number Publication Date
CN102849626A CN102849626A (en) 2013-01-02
CN102849626B true CN102849626B (en) 2014-12-31

Family

ID=47396680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210359461.9A Active CN102849626B (en) 2012-09-24 2012-09-24 Indoor non-standard crane installation method

Country Status (1)

Country Link
CN (1) CN102849626B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103318768B (en) * 2013-01-16 2015-01-21 上海振华重工(集团)股份有限公司 Assembling method of quayside with low posture
CN103086276B (en) * 2013-01-20 2014-07-02 北京首钢建设集团有限公司 Construction method for hoisting bridge type crane in high-rise well tower type building
CN103121629B (en) * 2013-02-05 2015-01-07 山西太行建设开发有限公司 Hoisting method of large support equipment for basement
CN112249915A (en) * 2020-09-27 2021-01-22 上海宝冶集团有限公司 Large bridge crane hoisting method for closed occasions of factory buildings

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100417586C (en) * 2006-04-13 2008-09-10 中国机械工业建设总公司 Integral lifting method of large bridge crane and its appts
CN101723252A (en) * 2009-11-11 2010-06-09 甘肃省电力公司刘家峡水电厂 Overhead-traveling installation method of 400t overhead travelling crane replacement equipment
CN102267664A (en) * 2011-05-27 2011-12-07 中国一冶集团有限公司 Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5473294B2 (en) * 2008-10-31 2014-04-16 山九株式会社 Overhead crane installation method and installation system
JP5698474B2 (en) * 2010-07-26 2015-04-08 山九株式会社 Installation method of overhead crane

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100417586C (en) * 2006-04-13 2008-09-10 中国机械工业建设总公司 Integral lifting method of large bridge crane and its appts
CN101723252A (en) * 2009-11-11 2010-06-09 甘肃省电力公司刘家峡水电厂 Overhead-traveling installation method of 400t overhead travelling crane replacement equipment
CN102267664A (en) * 2011-05-27 2011-12-07 中国一冶集团有限公司 Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
大型桥式起重机"梁吊法"的探讨与实践;吴京涛,蒋家挺,李华宏;《南方金属》;20050630(第3期);第37-40页 *

Also Published As

Publication number Publication date
CN102849626A (en) 2013-01-02

Similar Documents

Publication Publication Date Title
CN201228206Y (en) Self-made small-sized hoisting machine
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN102979313B (en) Steel truss upper air installing construction method that conversion layer is overweight
CN103911956B (en) A kind of large span stayed-cable bridge steel truss girder mounting method
CN102849626B (en) Indoor non-standard crane installation method
CN102251486B (en) Jacking bracket system for segmented mounting of bridge tower and construction process thereof
CN104652298A (en) Integral lowering and removing system of span box girders based on bridge deck support and construction method of integral lowering and removing system
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN105442458A (en) Method for hanging and installing stay cable of cable-stayed bridge special-shaped tower pillar
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
CN101537976A (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN109231023B (en) Method for installing jib system of portal crane
CN102953553A (en) Method for mounting large-span pipe truss by using boom luffing mechanism
CN110670879A (en) High-rise hoisting method for large equipment
CN110759222A (en) Take quick hoist device of PC wallboard of counter weight
CN102493666A (en) High-altitude translation installation and construction method for super-large super-heavy member
CN204434116U (en) A kind of hanging device for interior courtyard lifting pipeline
CN106285019B (en) A kind of overhead traveling crane installation method under confined space
CN101264845A (en) Crown block high altitude integrated suspension transposition construction method
CN206590793U (en) Connect arm assembly and the movable arm tower crane comprising the device in the air
CN112458900A (en) Combined hoisting construction method for bridge deck crane at closure section of steel-concrete composite beam cable-stayed bridge
CN104627849B (en) Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
WO2022233156A1 (en) Method for disposing lifting power apparatus in attached lifting/lowering scaffold
CN105155427A (en) Construction method for laying suspension bridge catwalk

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Sui Jieming

Inventor after: Ma Rongquan

Inventor after: Qi Ligang

Inventor after: Guo Jia

Inventor after: Guo Chunhua

Inventor after: Ning Chuanhong

Inventor after: Cui Aizhen

Inventor before: Sui Jieming

Inventor before: Qi Ligang

Inventor before: Guo Jia

Inventor before: Ning Chuanhong

Inventor before: Cui Aizhen

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: SUI JIEMING QI LIGANG GUO JIA NING CHUANHONG CUI AIZHEN TO: SUI JIEMING MARONGQUAN QI LIGANG GUO JIA GUO CHUNHUA NING CHUANHONG CUI AIZHEN

C14 Grant of patent or utility model
GR01 Patent grant