CN105604580A - Tunnel inverted arch construction movable formwork - Google Patents
Tunnel inverted arch construction movable formwork Download PDFInfo
- Publication number
- CN105604580A CN105604580A CN201610162825.2A CN201610162825A CN105604580A CN 105604580 A CN105604580 A CN 105604580A CN 201610162825 A CN201610162825 A CN 201610162825A CN 105604580 A CN105604580 A CN 105604580A
- Authority
- CN
- China
- Prior art keywords
- longeron
- side template
- formwork
- crossbeams
- beams
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 31
- 238000009415 formwork Methods 0.000 title claims abstract description 30
- 238000006073 displacement reaction Methods 0.000 claims description 5
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 241000124815 Barbus barbus Species 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention provides a tunnel inverted arch construction movable formwork. The tunnel inverted arch construction movable formwork comprises an arc-shaped side formwork, a central ditch formwork and two beams which are parallel to each other, the two ends of the side formwork are rotatably connected with the ends of the beams respectively, and the two ends of the central ditch formwork are fixedly connected with the middles of the beams respectively; a middle longitudinal beam perpendicular to the beams is arranged above the middles of the beams, and side longitudinal beams perpendicular to the beams are arranged above the two ends of the beams respectively; formwork lifting hydraulic jacks are arranged at the two ends of the middle longitudinal beam, lateral hydraulic jacks for pushing the side formwork are arranged on the outer sides of the side longitudinal beams, side formwork lifting supports are arranged above the middles of the side longitudinal beams, side formwork traction motors are arranged on the side formwork lifting supports, and the side formwork traction motors are connected with the side formwork through chain blocks.
Description
Technical field
The present invention relates to tunnel invert construction equipment field, be specifically related to a kind of mould bases of tunnel invert pouring construction.
Background technology
Constructing tunnel process, it is a critical process that inverted arch and inverted arch are filled construction, how to ensure efficiency of construction and the construction of inverted archQuality becomes key element. The small-sized combined steel formwork of many employings in work progress at present, globality is poor, and the fixing difficulty of template is large,Construction Linear Control is bad, and efficiency of construction is low.
In prior art, Chinese Patent Application No. 201420824474.3, name are called " a kind of self-propelled tunnel invert construction platformCar " patent of invention, its using the arc formwork of each side as an integral installation on a chassis, pallet bottom install roller,Can automatic moving, but separately construction of width about when its construction, globality is poor; At Chinese periodical " Sichuan building " the 32nd volume 1In the document of phase a section " application in tunnel of inverted arch mobile formwork quick construction technology " by name, disclose a kind of entirety and movedDynamic formula mould bases, has also adopted integral curved side template, and it connects left and right width side template by termination beam (crossbeam), and establish centreHave Central drain template, it adopts the trestle matching track crane of establishing guide rail to realize mould bases integrated moving, and structure is comparatively complicated, andIts inverted arch and inverted arch are filled and will be constructed respectively, have reduced efficiency of construction.
Summary of the invention
The object of the invention is to the defect existing for inverted arch construction in prior art, a kind of tunnel invert mobile mould of constructing is providedFrame, improves the construction quality of inverted arch, shortens inverted arch and constructs activity duration of every circulation, improves efficiency of construction.
Technical scheme of the present invention is as follows:
A kind of tunnel invert construction mobile formwork, comprises and it is characterized in that side template, the Central drain template of arc: be provided with twoThe crossbeam that root is parallel to each other, the two ends of described side template is rotationally connected with the end of described two crossbeams respectively, described Central drainThe two ends of template are fixedly connected with the middle part of two crossbeams respectively; The middle part top of described two crossbeams, be provided with two beam vertical inLongeron, the top, two ends of described two crossbeams, is respectively equipped with the limit longeron with two beam vertical; The two ends of described middle longeron, are provided withMould bases lifting hydraulic jack, the outside of described limit longeron is provided with the side hydraulic jack for pushing tow side template, and described limit is verticalThe top, middle part of beam is provided with side template lifting bracket, and described side template lifting bracket is provided with side template traction electric machine, described side formBetween plate traction electric machine and side template, be connected by cucurbit jack.
Further, described crossbeam below is also provided with arc support, and the bottom of described arc support is provided with support bar, described support barBe connected by latch with described arc support.
Further, the both sides of middle longeron are also provided with guide rail, described crossbeam top and middle longeron junction be provided with can along on longeronThe roller that guide rail moves; One end of described middle longeron is provided with the displacement motor that traction crossbeam moves forward and backward along described guide rail.
Further, the bottom of described limit longeron is also provided with the slide rail extending longitudinally along limit longeron, is provided with traction mould bases edge on guide railThe mould bases traction electric machine that slide rail slides.
Inverted arch mould bases provided by the invention is compared with the prior art has following beneficial effect:
Mould bases is integrated moving voluntarily, and formwork erection is quick, overall perfusion, and parallel operations, synchronous coordination, does not interfere with each other; Curved sideTemplate reels by jack, and can disposablely complete inverted arch and fill construction in layer, and Central drain construction, save constructionOperation, has accelerated the construction speed that inverted arch and inverted arch are filled greatly; Build linear quality good, ensured construction quality.
Brief description of the drawings
Fig. 1 is top view of the present invention;
Fig. 2 is transverse side view of the present invention.
Detailed description of the invention
As shown in Figure 1 and Figure 2, tunnel invert provided by the invention construction mobile formwork, comprises side template 1, the center of arcDitch template 2, is also provided with two crossbeams that are parallel to each other 3, and the two ends of described side template 1 is respectively with described two crossbeams 3End is rotationally connected, and the two ends of described Central drain template 2 are fixedly connected with the middle part of two crossbeams 3 respectively; Described two crossbeamsTop, middle part, is provided with the middle longeron 4 vertical with two crossbeams 3, and the top, two ends of described two crossbeams 3, is respectively equipped with and two crossbeamsVertical limit longeron 5; The two ends of described middle longeron 4, are provided with mould bases lifting hydraulic jack 6, the outside of described limit longeron 5Be provided with the side hydraulic jack 7 for pushing tow side template, the top, middle part of described limit longeron is provided with side template lifting bracket 8,Described side template lifting bracket 8 is provided with side template traction electric machine 9, between described side template traction electric machine 9 and side template, passes through calabashReed jack 10 connects.
When the present invention specifically implements, also can arc support 11 be set below described crossbeam, establish the bottom of described arc support 11Have support bar 12, described support bar 12 is connected by latch with described arc support 11. When formwork erection, by support bar to mould basesSupport and fix.
Occupation mode of the present invention is as follows:
After tunnel invert has excavated, before inverted arch pouring construction, mould bases is moved to assigned address and start formwork erection, start mould bases literHydraulic jack 6 is fallen, by mobile formwork vertical adjustment to design altitude; Under arc support below crossbeam, support is set simultaneouslyBar 12 is also fixed by latch, to mould bases integrated support and fixing; Determine plan-position and the elevation of the above side template of inverted arch face,Start the side hydraulic jack 7 on the longeron of limit, pushing tow side template is laterally received by starting side template traction electric machine 9 simultaneouslyPutting cucurbit jack 10 coordinates side hydraulic jack location inverted arch to fill the position of the following curved side template of face.
After completing, formwork erection can carry out concreting. First build inverted arch, after inverted arch concrete initial set, start side template and leadDraw motor and promote cucurbit jack 10, more than the curved side template inverted arch face of filling is partly upwards promoted to inverted arch filling face below, systemOne builds inverted arch fill concrete, realizes that inverted arch, inverted arch are filled and Central drain is built once and completed.
When inverted arch fill concrete is solidified to designing requirement, start the demoulding. Starting mould bases lifting hydraulic jack upwards indulges in pushing towBeam upwards raises mould bases entirety, makes concrete demoulding.
When the present invention specifically implements, accurately locate for realizing mould bases, also can guide rail 13 be set in the both sides of middle longeron 4, in instituteState crossbeam top and middle longeron junction arrange can along in the roller 14 that moves of guide rail on longeron; One end of described middle longeron is provided withThe displacement motor 15 that traction crossbeam moves forward and backward along described guide rail. Displacement motor 15 drives cross beam movement by chain and sprocket wheel.When formwork erection, draw crossbeam and template by displacement motor and move forward and backward and better realize Template Location.
Further, the present invention in the specific implementation, also can arrange the cunning extending longitudinally along limit longeron in the bottom of described limit longeron 5Rail 16 arranges the mould bases traction electric machine 17 that traction mould bases slides along slide rail on guide rail, realizes mould bases is carried out to integrated moving.After having constructed in a position, longeron in rising by mould bases lifting hydraulic jack, arranges slide rail along longeron end, limit, logicalCross mould bases traction electric machine traction mould bases and be forwarded to next construction location along slide rail.
Claims (4)
1. a tunnel invert construction mobile formwork, comprises and it is characterized in that side template, the Central drain template of arc: establishHave two crossbeams that are parallel to each other, the two ends of described side template is rotationally connected with the end of described two crossbeams respectively, described centerThe two ends of ditch template are fixedly connected with the middle part of two crossbeams respectively; The top, middle part of described two crossbeams, is provided with and two beam verticalMiddle longeron, the two ends top of described two crossbeams, is respectively equipped with the limit longeron with two beam vertical; The two ends of described middle longeron,Be provided with mould bases lifting hydraulic jack, the outside of described limit longeron is provided with the side hydraulic jack for pushing tow side template, described inThe top, middle part of limit longeron is provided with side template lifting bracket, and described side template lifting bracket is provided with side template traction electric machine, described inBetween side template traction electric machine and side template, be connected by cucurbit jack.
2. tunnel invert construction mobile formwork according to claim 1, is characterized in that: described crossbeam below is provided with arcShape support, the bottom of described arc support is provided with support bar, and described support bar is connected by latch with described arc support.
3. tunnel invert construction mobile formwork according to claim 1, is characterized in that: the both sides of middle longeron are provided with leadsRail, described crossbeam top and middle longeron junction be provided with can along in the roller that moves of guide rail on longeron; One end of described middle longeronBe provided with the displacement motor that traction crossbeam moves forward and backward along described guide rail.
4. tunnel invert construction mobile formwork according to claim 1, is characterized in that: establish the bottom of described limit longeronHave the slide rail extending longitudinally along limit longeron, described guide rail is provided with the mould bases traction electric machine that traction mould bases slides along slide rail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610162825.2A CN105604580A (en) | 2016-03-21 | 2016-03-21 | Tunnel inverted arch construction movable formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610162825.2A CN105604580A (en) | 2016-03-21 | 2016-03-21 | Tunnel inverted arch construction movable formwork |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105604580A true CN105604580A (en) | 2016-05-25 |
Family
ID=55984865
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610162825.2A Pending CN105604580A (en) | 2016-03-21 | 2016-03-21 | Tunnel inverted arch construction movable formwork |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105604580A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106761825A (en) * | 2016-12-23 | 2017-05-31 | 泰安东岳重工有限公司 | For the inverted arch trestle device in tunnel |
CN106939793A (en) * | 2017-04-21 | 2017-07-11 | 四川省创力隧道机械设备有限公司 | It is easy to the tunnel central trench chassis efficiently constructed |
CN107059625A (en) * | 2016-12-22 | 2017-08-18 | 中铁五局集团有限公司 | A kind of access bridge hoisting mechanism of stepping type self movable trestle |
CN113669082A (en) * | 2021-09-09 | 2021-11-19 | 中铁隧道集团二处有限公司 | Tunnel inverted arch filling construction method containing central ditch |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007291794A (en) * | 2006-04-27 | 2007-11-08 | Kumagai Gumi Co Ltd | Form device |
CN201666157U (en) * | 2010-03-08 | 2010-12-08 | 中铁隧道集团四处有限公司 | Inverted arch integral type moving die carrier |
CN102146799A (en) * | 2011-03-10 | 2011-08-10 | 中铁二局股份有限公司 | Construction equipment for inverted arch of two-track tunnel of high-speed railway |
CN102230383A (en) * | 2011-06-14 | 2011-11-02 | 中交隧道工程局有限公司 | All-hydraulic tunnel inverted arch trestle-type moving die frame |
CN102444406A (en) * | 2010-10-15 | 2012-05-09 | 中铁五局(集团)有限公司 | Needle beam type inverted arch lining sliding framework and construction method thereof |
CN103325710A (en) * | 2013-06-25 | 2013-09-25 | 南通皋鑫电子股份有限公司 | Method of testing three-inch diffusion silicon piece surface nickel plating thickness |
CN204386615U (en) * | 2014-12-24 | 2015-06-10 | 中铁四局集团第五工程有限公司 | A kind of self-propelled tunnel invert construction trolley |
CN205605224U (en) * | 2016-03-21 | 2016-09-28 | 中交第四公路工程局有限公司 | Tunnel invert moving die carrier that is under construction |
-
2016
- 2016-03-21 CN CN201610162825.2A patent/CN105604580A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007291794A (en) * | 2006-04-27 | 2007-11-08 | Kumagai Gumi Co Ltd | Form device |
CN201666157U (en) * | 2010-03-08 | 2010-12-08 | 中铁隧道集团四处有限公司 | Inverted arch integral type moving die carrier |
CN102444406A (en) * | 2010-10-15 | 2012-05-09 | 中铁五局(集团)有限公司 | Needle beam type inverted arch lining sliding framework and construction method thereof |
CN102146799A (en) * | 2011-03-10 | 2011-08-10 | 中铁二局股份有限公司 | Construction equipment for inverted arch of two-track tunnel of high-speed railway |
CN102230383A (en) * | 2011-06-14 | 2011-11-02 | 中交隧道工程局有限公司 | All-hydraulic tunnel inverted arch trestle-type moving die frame |
CN103325710A (en) * | 2013-06-25 | 2013-09-25 | 南通皋鑫电子股份有限公司 | Method of testing three-inch diffusion silicon piece surface nickel plating thickness |
CN204386615U (en) * | 2014-12-24 | 2015-06-10 | 中铁四局集团第五工程有限公司 | A kind of self-propelled tunnel invert construction trolley |
CN205605224U (en) * | 2016-03-21 | 2016-09-28 | 中交第四公路工程局有限公司 | Tunnel invert moving die carrier that is under construction |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059625A (en) * | 2016-12-22 | 2017-08-18 | 中铁五局集团有限公司 | A kind of access bridge hoisting mechanism of stepping type self movable trestle |
CN106761825A (en) * | 2016-12-23 | 2017-05-31 | 泰安东岳重工有限公司 | For the inverted arch trestle device in tunnel |
CN106761825B (en) * | 2016-12-23 | 2018-08-31 | 泰安东岳重工有限公司 | Inverted arch trestle device for tunnel |
CN106939793A (en) * | 2017-04-21 | 2017-07-11 | 四川省创力隧道机械设备有限公司 | It is easy to the tunnel central trench chassis efficiently constructed |
CN106939793B (en) * | 2017-04-21 | 2023-07-18 | 四川省创力隧道机械设备有限公司 | Tunnel center ditch trolley convenient for efficient construction |
CN113669082A (en) * | 2021-09-09 | 2021-11-19 | 中铁隧道集团二处有限公司 | Tunnel inverted arch filling construction method containing central ditch |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109681238B (en) | Two linings of tunnel side wall are pour and prefabricated section of jurisdiction of vault is forwardded and is used template platform truck | |
CN105604580A (en) | Tunnel inverted arch construction movable formwork | |
CN103016028A (en) | Hydraulic self-propelled steel form carrier for tunnel secondary lining operation | |
CN110513125B (en) | Inner and outer mould trolley lining system for open cut underdrain | |
CN207212365U (en) | A kind of wall arch is separable can Monolithic lining chassis | |
CN104790977A (en) | Tunnel primary lining formwork trolley and construction method thereof | |
CN111022079A (en) | Trestle type full-section inverted arch two-lining trolley equipment and construction method thereof | |
CN204627623U (en) | Tunnel just serves as a contrast formwork jumbo | |
CN204457807U (en) | A kind of tunnel ditch cable channel hydraulic formwork trolley | |
JP4318042B2 (en) | Tunnel construction method | |
CN109139050B (en) | Self-propelled integrated tunnel inverted arch device | |
CN105065035A (en) | Light pushing-sliding tunnel lining trolley | |
CN204492846U (en) | Movable type with inverted arch lining device crosses car trestle | |
CN107060831B (en) | Be used for tunnel slot construction equipment | |
CN110894792A (en) | Trestle type lower opening full-section synchronous construction equipment and construction method thereof | |
CN205605224U (en) | Tunnel invert moving die carrier that is under construction | |
CN109371851B (en) | Groove making machine with multiple bottom die head cover supporting frames | |
CN212744018U (en) | Traveling system of mobile trolley | |
CN104832194A (en) | Full-automatic hydraulic concrete-lining steel-moulding-plate trolley | |
CN104500106A (en) | Tunnel inverted arch construction die carrier and tunnel inverted arch construction process | |
CN205295849U (en) | Mechanized ditch template | |
CN210637087U (en) | Inner and outer mould trolley lining system for open-cut underground canal | |
CN211081965U (en) | Self-walking hydraulic trestle | |
CN206785405U (en) | One kind is used for tunnel groove constructing device | |
CN210105880U (en) | Alternate hydraulic lifting template ditch cable trough trolley device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160525 |