CN105463993B - Movable formwork suitable for multiple beams and construction method - Google Patents
Movable formwork suitable for multiple beams and construction method Download PDFInfo
- Publication number
- CN105463993B CN105463993B CN201510825147.9A CN201510825147A CN105463993B CN 105463993 B CN105463993 B CN 105463993B CN 201510825147 A CN201510825147 A CN 201510825147A CN 105463993 B CN105463993 B CN 105463993B
- Authority
- CN
- China
- Prior art keywords
- side form
- suspension bracket
- mobile formwork
- beams
- mould
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a movable formwork suitable for multiple beams and a construction method. The movable formwork comprises main beams, a hanging bracket and a casting mold. The direction of the pair of fixedly connected main beams is identical with the length direction of a bridge. Guide beams are arranged at the front end and the rear end of each main beam. A front supporting leg, a middle supporting leg and a rear supporting leg are arranged on the bottom face of each main beam in a sliding mode. The hanging bracket is arranged on the outer sides of the two main beams. A through track beam is arranged on the bottom face of the hanging bracket. The casting mold is movably arranged on the lower side of the hanging bracket and comprises a side mold body and a bottom mold body vertically arranged on the lower side of the side mold body. Reverse hooking wheels are arranged on the upper portion of the side mold body. The cross section of the track beam is in an I shape, and the reverse hooking wheels are movably arranged in an I-shaped cavity of the track beam. By the adoption of only one movable formwork, the multiple transverse beams are cast and transversely moved; besides, the position of the movable formwork does not need to be moved in the transverse direction, materials are saved, the number of hole passing times is reduced, operation is easier, and the safety of bridge construction is improved.
Description
Technical field
The present invention relates to field of bridge construction, and in particular to suitable for the mobile formwork and construction method of several beams.
Background technology
Mobile formwork is applied widely, for the bridge of several beams of concretes of lateral arrangement in the construction of concrete-bridge
Beam engineering, the current general Construction Through Form on Traveler using with width number equal number, each mobile formwork will via, it is so total
Via number of times is just more, or completes whole beams of concrete constructions of a width using a mobile formwork in one direction, then will
Mobile formwork is disassembled and reinstalls to other width, then a width of constructing in the same way, is so circulated, as only one of which is moved
Dynamic model frame, than the via number of times that other width are out moved to from a width more than the former mode.The former method is using more
Mobile formwork, waste of resource and manpower, although the latter more saves material, are loaded and unloaded more loaded down with trivial details.No matter the former or
The latter, mobile formwork (refer to mobile formwork from the one of bridge across moving to the adjacent length direction across along bridge) during via twice
A width beams of concrete can only be poured.And via is the maximum operation of security risk during Construction Through Form on Traveler, therefore should use up
Amount reduces the via number of times of mobile formwork.
As can be seen here, in the bridge construction of several beams there is a problem of via often at present.
The content of the invention
For the defect that prior art is present, it is an object of the invention to provide a kind of mobile formwork suitable for several beams
And construction method, it is intended to the via number of times of mobile formwork when several beams are constructed is reduced, security risk is reduced.
The technical solution adopted in the present invention there is provided a kind of construction method of the mobile formwork for several beams, including
Following steps:
The side form for pouring mould is fixed with suspension bracket, the first width beam is poured,
Side form is taken apart with suspension bracket, and mould will be poured and integrally transfer, make the anti-hook wheel on side form top hang over the track of suspension bracket
Liang Shang, will pour mould and be divided into before and after's two parts, be longitudinally moved to below the nose girder of rear and front end respectively,
The the first width beam for having poured is moved to into precalculated position along the width of bridge,
Mould will be poured again and moves back into original position, and repeat the above steps from the nose girder of rear and front end, until laterally all mixed
Solidifying Tu Liang complete to pour with it is traversing,
Mobile formwork is integrally moved forward, via is completed.
Above-mentioned suitable for the construction method of the mobile formwork of several beams, before the side form for pouring mould is fixed with suspension bracket,
Lifted using hydraulic means or jack device or transfer side form.
Above-mentioned suitable for the construction method of the mobile formwork of several beams, when fixed, reinforcement is added, by suspension bracket, side
Mould and the reinforcement are fixed using bearing pin, and make three form three-legged structure.
Above-mentioned suitable for the construction method of the mobile formwork of several beams, after side form is pulled down from suspension bracket, side form
It is anti-to hook on the track girder that wheel card is leaned against under suspension bracket.
The present invention also provides a kind of mobile formwork suitable for several beams, including:
The girder that a pair consistent with bridge length direction are fixedly connected, its front-end and back-end are provided with nose girder, and its bottom surface is slided
It is dynamic to be provided with front leg strut, middle supporting leg and rear support leg,
The suspension bracket being arranged on the outside of girder described in two, the bottom surface of the suspension bracket are provided with elongated track girder,
The mould that pours being movably arranged under the suspension bracket, including side form and the bed die being vertically set on below the side form,
The top of the side form is provided with anti-hook and takes turns, and the cross section of the track girder is in I shape, and the anti-hook wheel is movably arranged on described
The I-shaped intracavity of track girder.
The above-mentioned mobile formwork suitable for several beams, the suspension bracket is provided with stub axis hole, and the side form is provided with
The secondary pin shaft hole equivalently-sized with the stub axis hole.
The above-mentioned mobile formwork suitable for several beams, on the side form, reinforcement is additionally provided with, with the suspension bracket, described
Side form forms three-legged structure.
The above-mentioned mobile formwork suitable for several beams, the side form is provided with vertical with the suspension bracket for controlling which
The hydraulic means or jack device of straight distance.
The present invention, only with a mobile formwork, several horizontal crossbeams is poured and traversing, and mobile formwork is in horizontal stroke
To shift position is not needed, material is both saved, reduced via number of times, operation is more simple, improves the peace of bridge construction
Quan Xing.
Description of the drawings
Fig. 1 is side view of the present invention in casting concrete beam;
Fig. 2 be Fig. 1 in regard to I-I to profile;
Fig. 3 is profile of the present invention when the second horizontal width beams of concrete is poured
Fig. 4 is the schematic enlarged-scale view at A in Fig. 2 (during casting concrete);
Fig. 5 is elevation of the present invention when template system is opened;
Fig. 6 is the schematic enlarged-scale view at A in Fig. 2 (when pouring mould opening).
Specific embodiment
The invention provides a kind of mobile formwork and construction method suitable for several beams, reduces via number of times, operation
Simply, improve the safety of bridge construction.The present invention is given specifically with reference to specific embodiment and Figure of description
It is bright.
As shown in Figure 1 and Figure 5, the invention provides a kind of mobile formwork suitable for several beams, including girder 11, suspension bracket
13 and pour mould 12.
A pair girders 11 consistent with bridge length direction are fixedly connected, and its front-end and back-end is provided with nose girder 14, its bottom surface
Slip is provided with front leg strut 15, middle supporting leg 16 and rear support leg 17.
As shown in Figure 2, Figure 3 and Figure 4, suspension bracket 13 is arranged on the outside of two girders 11, and the bottom surface of suspension bracket 13 is provided with elongated rail
Road beam 18.Pour mould 12 to be movably arranged on below suspension bracket 13, including side form 121 and the bed die being vertically set on below side form 121
122。
As shown in Figure 4 and Figure 6, the top of side form 121 is provided with anti-hook and takes turns 110, and the cross section of track girder 18 is in I shape, instead
Hook the I-shaped intracavity that wheel 110 is movably arranged on track girder 18.Suspension bracket 13 is provided with stub axis hole, and side form 121 is provided with and stub
The equivalently-sized secondary pin shaft hole of axis hole, can be fixed by bearing pin 19 between suspension bracket 13, side form 12.Can also set up on side form 121
Reinforcement, forms three-legged structure with suspension bracket 13, side form 121, increases stability.
Side form 121 is provided with for controlling its hydraulic means or jack device with the vertical dimension of suspension bracket 13.
Present invention also offers a kind of construction method of the mobile formwork for several beams, comprises the following steps:
The side form 121 for pouring mould 12 is fixed with suspension bracket 13, the first width beam 311 is poured,
Side form 121 is taken apart with suspension bracket 13, and 12 overall decentralization of mould will be poured, hang the anti-hook wheel 110 on 121 top of side form
On the track girder 18 of suspension bracket 13, it is two parts in front and back that will pour 12 points of mould, longitudinally moves to the nose girder 14 of rear and front end respectively
Lower section,
Will be the first width beam 311 for having poured traversing to precalculated position along the width of bridge,
Mould 12 will be poured again and moves back into original position, and repeat the above steps from the nose girder 14 of rear and front end, until horizontal institute
Have beams of concrete complete to pour with it is traversing (from the point of view of can be with reference to Fig. 2 and Fig. 3, in the horizontal including multiple beams, such as adjacent first
Width beam 311 and the second width beam 312),
Interim supporting leg is added in the front end of nose girder 14, it is overall that mobile formwork was carried out before first time along bridge length direction
Move, next sky bridge pier 23 is reached to interim supporting leg,
Middle supporting leg 16, front leg strut 15 and rear support leg 17 being had bad luck successively, front leg strut 15 is placed on sky bridge pier, middle supporting leg 16 is put
In 31 front end of processing beam for newly completing, rear support leg 17 is placed in the middle part of the processing beam 31 for newly completing, then again by mobile formwork entirety
Second reach is carried out, via is completed.
Preferably, when moving forward for the first time, when interim supporting leg reaches empty bridge pier 23, in the arrival of rear support leg 17 near supporting leg 16,
Middle supporting leg 16 comes to nothing and hangs on girder 11, and now mobile formwork is in rear support leg 17, front leg strut 15, the supported at three point of interim supporting leg
State,
Have bad luck middle supporting leg 16 so as to reach near front leg strut 15, front leg strut 15 is come to nothing and hangs on girder 11, now moved
Mould bases is in rear support leg 17, middle supporting leg 16, the supported at three point state of interim supporting leg,
Have bad luck front leg strut 15 so as to reach empty bridge pier 23, make interim supporting leg come to nothing and hang on the nose girder 14 of rear end, now
Mobile formwork is in front leg strut 15,2 points of supports of middle supporting leg 16.
Preferably, lifted using hydraulic means or jack device or transfer side form 121.
Preferably, when fixed, reinforcement added, suspension bracket 13, side form 121 and reinforcement is fixed using bearing pin, and is made three
Person forms three-legged structure.
Preferably, after pull down side form 121 from suspension bracket 13, the anti-card of hook wheel 110 of side form 121 leans against the rail under suspension bracket 13
On road beam 18.
The present invention, only with a mobile formwork, several horizontal crossbeams is poured and traversing, and mobile formwork is in horizontal stroke
To shift position is not needed, material is both saved, reduced via number of times, operation is more simple, improves the peace of bridge construction
Quan Xing.
The present invention is not limited to above-mentioned preferred forms, and anyone should learn the knot made under the enlightenment of the present invention
Structure change, it is every with of the invention with same or like technical scheme, each fall within protection scope of the present invention.
Claims (7)
1. the construction method of the mobile formwork of several beams is applied to, it is characterised in that comprised the following steps:
The side form for pouring mould is fixed with suspension bracket, the first width beam is poured,
Side form is taken apart with suspension bracket, and mould will be poured and integrally transfer, the anti-hook wheel on side form top is hung on the track girder of suspension bracket,
Mould will be poured and be divided into before and after's two parts, be longitudinally moved to below the nose girder of rear and front end respectively,
Will be the first width beam for having poured traversing to precalculated position along the width of bridge,
Mould will be poured again and moves back into original position, and repeat the above steps from the nose girder of rear and front end, until horizontal all concrete
Liang Jun complete to pour with it is traversing,
Mobile formwork is integrally moved forward, via is completed.
2. the construction method of the mobile formwork of several beams is applied to as claimed in claim 1, it is characterised in that filled using hydraulic pressure
Put or jack device is lifted or transfers side form.
3. the construction method of the mobile formwork of several beams is applied to as claimed in claim 1, it is characterised in that when fixed, plus
If reinforcement, suspension bracket, side form and the reinforcement are fixed using bearing pin, and make three form three-legged structure.
4. suitable for the mobile formwork of several beams, it is characterised in that include:
The girder that a pair consistent with bridge length direction are fixedly connected, its front-end and back-end are provided with nose girder, and its bottom surface is slided and set
There are front leg strut, middle supporting leg and rear support leg,
The suspension bracket being arranged on the outside of girder described in two, the bottom surface of the suspension bracket are provided with elongated track girder,
The mould that pours being movably arranged under the suspension bracket, including side form and the bed die being vertically set on below the side form, it is described
The top of side form is provided with anti-hook and takes turns, and the cross section of the track girder is in I shape, and the anti-hook wheel is movably arranged on the track
The I-shaped intracavity of beam, the mould that pours are divided into before and after's two parts, can longitudinally move to respectively below the nose girder of rear and front end.
5. the mobile formwork of several beams is applied to as claimed in claim 4, it is characterised in that the suspension bracket is provided with stub axle
Hole, the side form are provided with the secondary pin shaft hole equivalently-sized with the stub axis hole.
6. the mobile formwork of several beams is applied to as claimed in claim 4, it is characterised in that reinforcing is additionally provided with the side form
Beam, forms three-legged structure with the suspension bracket, the side form.
7. the mobile formwork of several beams is applied to as claimed in claim 4, it is characterised in that the side form is provided with for controlling
Make its hydraulic means or jack device with the vertical dimension of the suspension bracket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510825147.9A CN105463993B (en) | 2015-11-24 | 2015-11-24 | Movable formwork suitable for multiple beams and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510825147.9A CN105463993B (en) | 2015-11-24 | 2015-11-24 | Movable formwork suitable for multiple beams and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105463993A CN105463993A (en) | 2016-04-06 |
CN105463993B true CN105463993B (en) | 2017-04-26 |
Family
ID=55602114
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510825147.9A Active CN105463993B (en) | 2015-11-24 | 2015-11-24 | Movable formwork suitable for multiple beams and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105463993B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105887688B (en) * | 2016-04-27 | 2018-04-03 | 中建五局土木工程有限公司 | Drop in beam formwork elevation measuring adjusting means, mobile formwork and absolute altitude adjusting method |
CN106149639B (en) * | 2016-08-30 | 2018-02-27 | 郑州新大方重工科技有限公司 | A kind of mobile formwork of single rectangle top opening enclosed type water conservancy aqueduct construction |
CN106758863B (en) * | 2016-11-17 | 2018-05-04 | 中交路桥华东工程有限公司 | A kind of overall fan-shaped across the width method for traversing of mobile formwork girder |
CN108086169B (en) * | 2017-12-13 | 2019-08-09 | 中国铁建大桥工程局集团有限公司 | The installation method for improving of bridge construction mobile formwork |
CN107881925A (en) * | 2017-12-20 | 2018-04-06 | 长沙理工大学 | Gantry crane system and its construction method that a kind of mobile formwork of arranging in pairs or groups uses |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201003145Y (en) * | 2007-02-12 | 2008-01-09 | 郑州大方桥梁机械有限公司 | Upward and self-walking type mobile die carrier |
JP2009127317A (en) * | 2007-11-26 | 2009-06-11 | Sanshin Kogyo Kk | Bridge construction apparatus |
CN201713764U (en) * | 2010-04-29 | 2011-01-19 | 郑州市华中建机有限公司 | Movable formwork apparatus |
CN204401473U (en) * | 2015-01-15 | 2015-06-17 | 中铁四局集团第二工程有限公司 | Upstroke movable framework steel bar overall binding lifting construction device |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101462202B1 (en) * | 2013-10-16 | 2014-12-24 | 주식회사 비엔지컨설턴트 | Form traveller for through bridge |
-
2015
- 2015-11-24 CN CN201510825147.9A patent/CN105463993B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201003145Y (en) * | 2007-02-12 | 2008-01-09 | 郑州大方桥梁机械有限公司 | Upward and self-walking type mobile die carrier |
JP2009127317A (en) * | 2007-11-26 | 2009-06-11 | Sanshin Kogyo Kk | Bridge construction apparatus |
CN201713764U (en) * | 2010-04-29 | 2011-01-19 | 郑州市华中建机有限公司 | Movable formwork apparatus |
CN204401473U (en) * | 2015-01-15 | 2015-06-17 | 中铁四局集团第二工程有限公司 | Upstroke movable framework steel bar overall binding lifting construction device |
Also Published As
Publication number | Publication date |
---|---|
CN105463993A (en) | 2016-04-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105463993B (en) | Movable formwork suitable for multiple beams and construction method | |
CN102094392B (en) | Lower supported hanging basket in bridge construction and application thereof | |
CN103074854B (en) | Rear supporting point triangular bracket hanging basket and bridge construction method using same | |
CN206368328U (en) | A kind of box beam four moves integrally die carrier structure across one-piece casting | |
CN105926929B (en) | A kind of pouring construction method of stalk concrete | |
CN102174796B (en) | Cantilever casting construction cradle with underlaid main truss | |
CN108086170B (en) | The hole construction method excessively of mobile formwork and mobile formwork | |
CN107100074A (en) | A kind of lower bearing arch bridge concrete bridge deck construction method | |
CN104594198B (en) | For the method for setting up juxtaposition case beam in tunnel | |
CN102605720B (en) | Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method | |
CN206784172U (en) | Overpass anti-collision wall formwork hoisting conveyance | |
CN201972099U (en) | Through type hanging basket in bridge construction | |
CN108005114A (en) | A kind of piping lane pours mould | |
CN106401606B (en) | Template trestle trolley | |
CN210766432U (en) | Internal mold system of hanging basket | |
CN204778321U (en) | Reinforcement cage hoisting device | |
CN207775925U (en) | A kind of piping lane pours mold | |
CN207293909U (en) | A kind of precast beam reinforced bar skeleton hanging apparatus | |
CN106836644B (en) | A kind of method of construction of reinforced column | |
CN206655477U (en) | wall hole template | |
CN207453986U (en) | A kind of mobile jumbo device of underground pipe gallery construction | |
CN206873310U (en) | A kind of arch bridge main girder construction Hanging Basket | |
CN207987783U (en) | A kind of middle cross beam suspension system of suspended pouring construction hanging basket | |
CN204311360U (en) | A kind of traversing carriage being applied to the simple supported box beam section assembling of bridge construction | |
CN206902572U (en) | Construction mould bases |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |