CN105369833A - Grouting maintenance construction method for basement roof leakage - Google Patents

Grouting maintenance construction method for basement roof leakage Download PDF

Info

Publication number
CN105369833A
CN105369833A CN201510669754.0A CN201510669754A CN105369833A CN 105369833 A CN105369833 A CN 105369833A CN 201510669754 A CN201510669754 A CN 201510669754A CN 105369833 A CN105369833 A CN 105369833A
Authority
CN
China
Prior art keywords
grouting
leakage area
seepage
crack
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510669754.0A
Other languages
Chinese (zh)
Inventor
李金佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUNMING FENGXING WATERPROOF MATERIAL CO Ltd
Original Assignee
KUNMING FENGXING WATERPROOF MATERIAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUNMING FENGXING WATERPROOF MATERIAL CO Ltd filed Critical KUNMING FENGXING WATERPROOF MATERIAL CO Ltd
Priority to CN201510669754.0A priority Critical patent/CN105369833A/en
Publication of CN105369833A publication Critical patent/CN105369833A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/04Watertight packings for use under hydraulic pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention relates to a grouting maintenance construction method for basement roof leakage. The method comprises the steps that a construction position is determined firstly, and then holes are drilled in a structural slab; when a drill bit is in contact with two thirds of the structural slab, hole drilling is stopped, and a grouting head is placed in the drilled holes; a clearance between the drilled holes and the grouting head is blocked through a sealing material (leakage blocking material), and grouting equipment is connected with the grouting head; and the grouting equipment carries out grouting under pressure through the grouting head, and injected grout achieves full grouting and reinforcing on a concrete structural layer (weak part). Therefore, concrete strength and permeation resistance are improved. The method is simple, and the leakage blocking effect is good.

Description

Basement roof seepage slip casting maintenance engineering method
Technical field
The present invention relates to a kind of basement roof seepage slip casting maintenance engineering method.
Background technology
Along with the fast development of society, basement leakage problem has had influence on the normal life of people; Grouting method in the past can not meet the requirement of leak stopping, and seepage place cannot find accurately, wastes a large amount of human and material resources, financial resources.
Summary of the invention
Due to long neglected and in disrepair, usually there is the situation of seepage in basement roof, technical problem to be solved by this invention finds a kind of reasonably grouting for water plugging method, blocked by leakage area.
The technical scheme realizing above-mentioned purpose is as follows:
First layout on structural slab, and then hole, when bit contact stops boring to during 2/3rds position of seepage basal plane thickness, in boring, put into casting head afterwards and fix, then encapsulant (leak stopping the is precious) gap between shutoff boring and casting head is used, grouting equipment is connected with casting head, grouting equipment is by casting head grouting under pressure, the slurries injected are in the full slip casting of concrete (weak part), reinforcing, thus concrete strength, impermeability are improved.
The inventive method is simple, and plugging effect is good.
Accompanying drawing explanation
Fig. 1 is the distribution of leakage area on structural slab in the present invention
Fig. 2 is the schematic diagram that casting head inserts in boring
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in detail.
Fig. 1 and Fig. 2 is the schematic diagram bored on structural slab when putting boring.Concrete defect causes house to leak, and the shape of leakage area has a lot of situation, and such as leakage area is crack, hole, cellular defect etc.
Below with the top board of basement for structural slab 1 describes step of the present invention.
1. the leakage area (namely determining to need the position of construction) of structural slab 1 is first determined, leakage area is certain leakage point 2 or crack 3 normally, area around the position at leakage area place and leakage area forms seepage basal plane, and the dirt near cleaning seepage part, in order to grouting, hole around leakage area, boring forms injected hole 4, when bit contact stops boring to during 2/3rds position of structural slab thickness, if between leakage point relatively far apart, the several injected hole 4 of brill around independent leakage point, if several leakage point location comparison is near, can several leakage point be regarded as one, several injected hole 4 is bored in the periphery of these leakage points, pitch-row between injected hole 4 is 20cm-50cm, the setting of certain pitch-row is not fixing, can set according to the concrete condition of leakage area, the line of injected hole 4 is plum blossom-shaped or circular or arcuate structure, leakage area is surrounded, the effect of such slip casting can be relatively good, when leakage area is fracture shape, the both sides in crack all need to bore injected hole 4, ensure that the slip casting in crack is even, and injected hole 4 can be 5-15cm apart from the distance in leakage point or crack.
2. hole after all completing and place casting head 5 in boring, and the gap between casting head outer rim and boring seals, the gap between encapsulant shutoff boring and casting head can be used, when placing casting head 5, casting head 5 once can insert the bottom of injected hole 4, can in slip casting process, progressively move down casting head, solid to make slurries 6 fill, also further the gap between casting head and boring is filled up, realize sealing;
3. the grout outlet of the grouting equipment of preset pressure is connected with casting head after completing by above-mentioned steps, open grouting equipment afterwards and carry out grouting under pressure, slurries enter in injected hole 4 by casting head under the effect of the pressure, slurries are continued to inject the full leakage area of concrete (weak part), pressurization grouting is stopped when having pure slurries to emerge in the injected hole 4 near leakage area, in the present invention, grouting equipment is leak stopping grouting pump, general grouting pressure 0.3Mpa, injection rate≤0.01L/min.The casting head be connected with grouting equipment grout outlet injects another injected hole 4 be communicated with it by pressure, that says is connected herein, do not refer to and got through between two injected holes, because the position usually leaked, the defect such as crack or hole can extend to concrete position, therefore, when slurries are poured under the effect of the pressure, the minim channel between crack or hole, gap can be got through by the effect of pressure, such slurries flow between two injected holes, fill.
4. then grouting equipment sequentially moves to next place's casting head and proceeds grouting under pressure, carries out forward successively, until all casting heads have slurries to emerge just calculated grouting under pressure;
5. check that leakage area is with or without infiltration after 72 hours, without when infiltration, casting head is fractureed, by fast dry substance, seepage basal plane is closed, floating.
Crack have deeply have shallow, when crack deep (degree of depth in such as crack is more than or equal to 5cm), injected hole 4 is inclined hole, inclined hole through the two ends in crack, and fully fills slurries for making in crack, interval 20-50 minute after 4. step completes, preferred interval about 30 minutes, in crack, carrying out slip casting before grout cures again complete second time slip casting process, because slurries are for solidifying, also can again utilize casting head to be in the milk.
Can according to concrete condition determination grouting pressure, the grouting amount of leakage area when slip casting.
Before searching crack, first answer fracture analysis, and get stamen respectively by the difference of crack width, length, to determine the penetration of fracture rule of development, as non-through crack and the degree of depth is more shallow, can surfacing be done.
Finding crack is loaded down with trivial details a, elaboration, as surface is not easily dry, can dry with blowtorch, and with angle grinding machine polishing periphery, crack place, because of containing moisture content, can find immediately, and namely this way improves operating efficiency, can guarantee that again each subregion is without omission.
Crack repairing: slurries from each piece of casting head 5 (structural facades pours into from lower to upper), when slurries are emerged from injected hole, should should stop immediately, the crack place moved near second piece of casting head 5 continues perfusion, carries out forward successively.In filling process, if slurries have filled adjacent casting head 5 position, can tripping not note; Continue extend or have crack to intersect with it as found after slip casting that two ends, crack still have, should in this position perforations adding, again slip casting.Like this, the first time slip casting in whole piece crack just calculates end.
These are only the preferred embodiment of the embodiment of the present invention; not in order to limit the embodiment of the present invention; within all spirit in the embodiment of the present invention and principle, any amendment done, equivalent replacement, improvement etc., all should be included in the protection domain of the embodiment of the present invention.

Claims (6)

1. basement roof seepage slip casting maintenance engineering method, is characterized in that:
1. first determine the leakage area of structural slab, the area around the position at leakage area place and leakage area forms seepage basal plane, cleaning seepage basal plane; Hole around leakage area, when bit contact stops boring to during 2/3rds position of seepage basal plane thickness;
2. hole after all completing and place casting head in boring, and the gap between casting head outer rim and boring seals;
3. the grouting equipment of preset pressure is connected with casting head after completing by above-mentioned steps, open grouting equipment afterwards and carry out grouting under pressure, slurries continue to inject concrete by casting head under the effect of the pressure, stop pressurization grouting when having pure slurries to emerge in the casting head near leakage area;
4. then grouting equipment sequentially moves to next place's casting head and proceeds grouting under pressure, the grouting under pressure until all casting heads are all done;
5. check that leakage area is with or without infiltration after 72 hours, without when infiltration, casting head is fractureed, by the bore closed on seepage basal plane, floating.
2. basement roof seepage slip casting maintenance engineering method according to claim 1, is characterized in that: the pitch-row between boring is 20cm-50cm.
3. basement roof seepage slip casting maintenance engineering method according to claim 1, it is characterized in that: when leakage area is crack, described boring is inclined hole, and inclined hole is through the two ends in crack.
4. basement roof seepage slip casting maintenance engineering method according to claim 1, it is characterized in that: for making fully to fill slurries in crack, interval 20-50 minute after 4. step completes, carries out slip casting again before grout cures and fills up crack in crack, completes second time slip casting process.
5. basement roof seepage slip casting maintenance engineering method according to claim 1, is characterized in that: described grouting pressure is 0.3Mpa, injection rate≤0.01L/min.
6. basement roof seepage slip casting maintenance engineering method according to claim 1, is characterized in that: the boring around leakage area is plum blossom-shaped structure, and leakage area is positioned at plum blossom-shaped structure.
CN201510669754.0A 2015-10-15 2015-10-15 Grouting maintenance construction method for basement roof leakage Pending CN105369833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510669754.0A CN105369833A (en) 2015-10-15 2015-10-15 Grouting maintenance construction method for basement roof leakage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510669754.0A CN105369833A (en) 2015-10-15 2015-10-15 Grouting maintenance construction method for basement roof leakage

Publications (1)

Publication Number Publication Date
CN105369833A true CN105369833A (en) 2016-03-02

Family

ID=55372418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510669754.0A Pending CN105369833A (en) 2015-10-15 2015-10-15 Grouting maintenance construction method for basement roof leakage

Country Status (1)

Country Link
CN (1) CN105369833A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105937308A (en) * 2016-06-24 2016-09-14 武大巨成结构股份有限公司 Basement bottom plate seepage crack grouting structure and grouting method thereof
CN107201753A (en) * 2017-06-16 2017-09-26 潍坊学院 It is a kind of to be used for the high-pressure slip-casting blocking method of basement or top plate of underground parking garage
CN109098213A (en) * 2018-08-29 2018-12-28 中国建筑第四工程局有限公司 A kind of basement blocking method
CN109281492A (en) * 2018-09-30 2019-01-29 重庆市十八土鑫诚灌浆防水工程有限公司 A kind of construction repaired for existing waterproof layer slip casting reconstruction
CN109838113A (en) * 2019-03-04 2019-06-04 山东建筑大学 Microorganism induction generates the method that calcium carbonate blocks Basement Crack
CN110056203A (en) * 2019-03-26 2019-07-26 周伟 A kind of processing method of ground structure leak
CN110656910A (en) * 2019-10-23 2020-01-07 东方雨虹智能装备有限责任公司 Slip casting connector
CN110747872A (en) * 2019-10-23 2020-02-04 东方雨虹智能装备有限责任公司 Deep grouting device and method
CN111809914A (en) * 2020-07-21 2020-10-23 四川童燊防水工程有限公司 Basement roof plugging grouting and reinforcing construction method
CN113137081A (en) * 2021-04-26 2021-07-20 中国建筑第八工程局有限公司 Deformation joint acrylate grouting plugging construction method
CN113187261A (en) * 2021-04-27 2021-07-30 北京固斯特国际化工有限公司 Structural repairing and reinforcing method for concrete chimney and cooling tower
CN114458045A (en) * 2022-03-09 2022-05-10 鞍山益安房屋修缮有限责任公司 Grouting plugging method for water leakage of window of hard decoration building and curved grouting needle

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864778A (en) * 2010-06-30 2010-10-20 广东省基础工程公司 Method for leaking stoppage of external wall of underground structure
CN103174112A (en) * 2013-03-28 2013-06-26 葛洲坝集团试验检测有限公司 Grouting method of penetrability concrete cracks
CN103898873A (en) * 2014-03-25 2014-07-02 安徽水安建设集团股份有限公司 Water seepage plugging construction method of shaft construction seams under high water head
CN104234090A (en) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 Method for treating crack water seepage of concrete floor and wall body
CN104878772A (en) * 2015-05-26 2015-09-02 江苏省建筑科学研究院有限公司 Treating method for foundation slab leakage of deep foundation pit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864778A (en) * 2010-06-30 2010-10-20 广东省基础工程公司 Method for leaking stoppage of external wall of underground structure
CN103174112A (en) * 2013-03-28 2013-06-26 葛洲坝集团试验检测有限公司 Grouting method of penetrability concrete cracks
CN103898873A (en) * 2014-03-25 2014-07-02 安徽水安建设集团股份有限公司 Water seepage plugging construction method of shaft construction seams under high water head
CN104234090A (en) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 Method for treating crack water seepage of concrete floor and wall body
CN104878772A (en) * 2015-05-26 2015-09-02 江苏省建筑科学研究院有限公司 Treating method for foundation slab leakage of deep foundation pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周庆荣: "某高层建筑地下室顶板混凝土裂缝问题的原因及处理措施", 《混凝土与水泥制品》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105937308A (en) * 2016-06-24 2016-09-14 武大巨成结构股份有限公司 Basement bottom plate seepage crack grouting structure and grouting method thereof
CN107201753A (en) * 2017-06-16 2017-09-26 潍坊学院 It is a kind of to be used for the high-pressure slip-casting blocking method of basement or top plate of underground parking garage
CN107201753B (en) * 2017-06-16 2019-04-05 潍坊学院 It is a kind of for basement or the high-pressure slip-casting blocking method of top plate of underground parking garage
CN109098213A (en) * 2018-08-29 2018-12-28 中国建筑第四工程局有限公司 A kind of basement blocking method
CN109281492A (en) * 2018-09-30 2019-01-29 重庆市十八土鑫诚灌浆防水工程有限公司 A kind of construction repaired for existing waterproof layer slip casting reconstruction
CN109838113A (en) * 2019-03-04 2019-06-04 山东建筑大学 Microorganism induction generates the method that calcium carbonate blocks Basement Crack
CN110056203A (en) * 2019-03-26 2019-07-26 周伟 A kind of processing method of ground structure leak
CN110056203B (en) * 2019-03-26 2021-06-22 周伟 Method for treating water leakage of ground structure
CN110747872A (en) * 2019-10-23 2020-02-04 东方雨虹智能装备有限责任公司 Deep grouting device and method
CN110656910A (en) * 2019-10-23 2020-01-07 东方雨虹智能装备有限责任公司 Slip casting connector
CN110656910B (en) * 2019-10-23 2022-04-12 东方雨虹智能装备有限责任公司 Slip casting connector
CN111809914A (en) * 2020-07-21 2020-10-23 四川童燊防水工程有限公司 Basement roof plugging grouting and reinforcing construction method
CN113137081A (en) * 2021-04-26 2021-07-20 中国建筑第八工程局有限公司 Deformation joint acrylate grouting plugging construction method
CN113187261A (en) * 2021-04-27 2021-07-30 北京固斯特国际化工有限公司 Structural repairing and reinforcing method for concrete chimney and cooling tower
CN113187261B (en) * 2021-04-27 2022-06-24 北京固斯特国际化工有限公司 Structural repairing and reinforcing method for concrete chimney and cooling tower
CN114458045A (en) * 2022-03-09 2022-05-10 鞍山益安房屋修缮有限责任公司 Grouting plugging method for water leakage of window of hard decoration building and curved grouting needle

Similar Documents

Publication Publication Date Title
CN105369833A (en) Grouting maintenance construction method for basement roof leakage
CN107387123B (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece leakage phenomenon
CN108517899A (en) Mouth high-pressure grouting leak stopping processing method is buried in the leakage drilling of deep basal pit diaphram wall
KR101119232B1 (en) Method for reinforcing concrete structure using epxy resin
CN106381840B (en) Fracture plugging grouting method under a kind of high pressure moving water state
CN109098213A (en) A kind of basement blocking method
CN206539354U (en) A kind of tunnel double-lining surface seep water cure structure
CN104033164A (en) Method for solving disengagement and water seepage of internal arch of tunnel
CN106480993B (en) Administration structure and construction method in a kind of construction exterior wall leak repairing reinforcement
CN206143827U (en) Underground works crack repairing structure
CN109371861A (en) A kind of culvert of reinforced concrete subsiding crack infiltration Treatment Methods and repair structure
CN113323440A (en) Concrete gap repairing and anti-seepage treatment method
CN105926624A (en) Non-return type collecting hole grouting device and construction method thereof
CN111395263B (en) Leakage treatment method for roller compacted concrete dam body
KR101594576B1 (en) Method for preventing leakage of Concrete Dam Structure
KR20140115150A (en) Waterproofing method for an undergroung parking lot
CN104033165A (en) Repairing method and grout for tunnel defects
KR101248088B1 (en) Ground and structure reinforcing method for repair construction of construction structure
KR100718649B1 (en) Construction method for preventing a leak through crack of concrete structure
CN114198050A (en) Method for determining hole sealing parameters of extraction drill hole grouting and corresponding hole sealing method
CN112482415B (en) Consolidation grouting method for underground cavern under high external water pressure and flowing water condition
CN111519626B (en) Sleeve valve pipe reverse grouting method suitable for deep covering layer permanent curtain
CN110821498B (en) Safe and rapid water plugging and reinforcing method in strong water-rich soft surrounding rock of operation tunnel
CN209603074U (en) Reinforced structure at connecting part of geomembrane and concrete wall
CN105781580A (en) Tunnel crack repair method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160302

RJ01 Rejection of invention patent application after publication