CN105350458B - Construction method of composite structure platform for construction of Y-shaped pier of bridge - Google Patents
Construction method of composite structure platform for construction of Y-shaped pier of bridge Download PDFInfo
- Publication number
- CN105350458B CN105350458B CN201510785177.1A CN201510785177A CN105350458B CN 105350458 B CN105350458 B CN 105350458B CN 201510785177 A CN201510785177 A CN 201510785177A CN 105350458 B CN105350458 B CN 105350458B
- Authority
- CN
- China
- Prior art keywords
- type
- poured
- column
- cushion cap
- piers
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a mounting method of a composite structure platform for construction of a Y-shaped pier of a bridge. The method comprises the following steps that (1) a plurality of vertical pre-embedded steel plates are arranged on the left side and the right side of a bearing platform formwork at intervals respectively, and a plurality of horizontal pre-embedded steel plates are arranged on the top faces of the positions, on the left side and the right side of a stand column of the Y-shaped pier to be poured, of the bearing platform formwork at intervals respectively; (2) a bearing platform is poured; (3) a plurality of section steel beams are erected on the two sides of the stand column of the Y-shaped pier to be poured respectively; (4) the stand column of the Y-shaped pier is poured; (5) the bottom ends of a plurality of concrete-filled steel tube inclined struts are welded and connected to the vertical pre-embedded steel plates and the horizontal pre-embedded steel plates respectively, and the other ends of the concrete-filled steel tube inclined struts are welded to the correspondingly-arranged section steel beams respectively; (6) bailey beams and distribution beams are sequentially laid on the section steel beams on the same side; and (7) Y-shaped pier formwork supporting frames are distributed on the distribution beams on the left side and the right side respectively. According to the method, the shear strength of concrete is greatly improved.
Description
Technical field
The present invention relates to field of bridge construction, relate in particular to a kind of bridge Y types pier construction combinative structure platform and
Its installation method.
Background technology
At present, known Y types bridge construction platform has various ways, but there is a problem that certain.For universal not
And geological conditions compared with hard formation blocked up suitable for Muddy Bottoms coating, it is impossible to which the intensity of effectively utilizes pier shaft is transmitting vertical lotus
Carry, supporting removal is difficult after the completion of construction, typically can only be cut off using the bottom, produce larger waste to material, and in navigation
Under conditions of having high demands cannot the bottom cut off, universality is poor, it is impossible to greatest extent play steel platform load-carrying properties.
The construction method of the great-angle Y type pier stud announced by publication No. CN104746435A employs substantial amounts of steel-pipe pile knot
Structure and slant-pull structure system, need to carry out substantial amounts of piling construction, and steel using amount are big.Y types pier construction terminate after steel-pipe pile not
Easily pull out, waste of material can only be caused by the way of excision.
The concrete structure formwork bracing frame of the bridge V-type bridge pier announced by publication No. CN202390763U, its V for adopting
Type bracing frame is the method for carrying out bent cap concrete structure construction after the construction of V limbs, it is impossible to which effectively application is constructed with V limbs.
A kind of wide-angle V-shaped pier that publication No. C102888815A and CN202954299U are announced and 0# block box beams are poured
Building construction method needs to lay a large amount of supports, and material consumption is big, also needs to process ground.
A kind of Y types pier template and support system and publication No. CN101481902A that publication No. CN203007846U is announced
The V type pier inclined leg combined type support for continuous rigid frame bridge announced and layered cast-in-situ construction method, its erection depend on enclosing for pontic
Fender pile and the drilled pile for separately setting, and multiple tracks is laid to lacing wire, support connection complicated so that the program is fitted in implementation process
Answering property is poor, and enforcement difficulty is big, does not apply to and is not provided with fender post and does not set the suspended deck structure of drilled pile.
The content of the invention
It is an object of the invention to overcome the shortcomings of prior art, there is provided a kind of installation effectiveness is high, inherent structure is affected
It is little, strong applicability, construction method of the big bridge Y types pier construction of bearing capacity with combinative structure platform.
For reaching above-mentioned purpose, the present invention adopts following technical proposals:
A kind of installation method of the bridge Y types pier construction of the present invention with combinative structure platform, it comprises the following steps:
(1) the multiple vertical pre-embedded steel slabs of setting are longitudinally respectively separated and to be poured in the left and right sides of cushion cap template along cushion cap
The multiple horizontal pre-buried steels of setting are respectively separated longitudinally along cushion cap on the top surface of the cushion cap template of the column left and right sides of the Y type piers built
Plate;
(2) cushion cap is poured in cushion cap template;
(3) many root type girder steels of height such as install respectively in the horizontal direction in the column both sides of Y type piers to be poured and make
It is located on the inside of described many root type girder steels in the column of Y type piers to be poured, then by the column of Y type piers to be poured
Reinforcing bar makes the column of section steel beam and Y type piers through default reinforced hole on the inner side edge of a wing of the section steel beam being correspondingly arranged and web
Reinforcing bar be connected;
(4) pour the column of Y type piers;
(5) when the concrete strength of the column of Y type piers reaches requirement, many concrete filled steel tube diagonal brace bottoms are welded respectively
It is connected on vertical pre-embedded steel slab and horizontal pre-embedded steel slab in succession and the other end is respectively welded on the section steel beam being correspondingly arranged;
(6) Bailey beam is laid on many root type girder steels of the homonymy for having supported, and described Bailey beam is adopted with section steel beam
Take spot welding and securing member is fixed;
(7) distribution beam is laid respectively in Bailey beam described in the left and right sides, described distribution beam and Bailey beam are using fastening
Part and spot welding connection;
(8) the outer wall shape respectively according to Y type socle V-arrangements to be poured in the distribution beam of the left and right sides lays Y type piers
Formwork-support.
Using the invention has the beneficial effects as follows:
(1) platform is supported on cushion cap eventually through concrete filled steel tube diagonal brace and is connected with pier stud by pre-buried mode, right
Underlying geological condition does not require that assembling and disassembling is convenient, and steel using amount is few, easy construction;
(2) concrete filled steel tube has good mechanical property, has compared to traditional steel pipe support structure preferably anti-
Pressure performance.
(3) the original reinforcing bar of pillarwork can be passed through from the reinforced hole of section steel beam, will not be because of the pre-buried connection of section steel beam
Laying to the intrinsic reinforcing bar of structure is impacted;
(4) reinforcing bar penetrated in opening up the shaped steel flange of beam of reinforced hole, web improves the ductility of anchor structure, it is to avoid
The brittle break of anchor system;
(5), in casting process, the concrete performance of tapping can be improved, and the shearing resistance for substantially increasing concrete is strong
Degree;
(6) combined system is applicable to current known any pier shaft height, the battered leg of the Y type piers of battered leg angle and pours and apply
Work platform, intensity are high, flexible arrangement.
Description of the drawings
Fig. 1 is the bridge Y types built using a kind of installation method of bridge Y types pier construction combinative structure platform of the invention
The front view of pier structure;
Fig. 2 is that a kind of work progress of the installation method of bridge Y types pier construction combinative structure platform of the present invention is faced
Figure;
Fig. 3 is the detail structure figure of the embedded region A of section steel beam shown in Fig. 2.
Specific embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
A kind of construction method of the bridge Y types pier construction of the present invention with combinative structure platform, it comprises the following steps:
(1) the multiple vertical pre-embedded steel slabs 8 of setting are longitudinally respectively separated in the left and right sides of cushion cap template along cushion cap and treating
It is pre- the multiple levels of setting to be respectively separated longitudinally along cushion cap on the top surface of the cushion cap template of 2 left and right sides of column of the Y type piers for pouring
Bury steel plate 9;
(2) cushion cap 1 is poured in cushion cap template;
(3) many root type girder steels 4 for the height such as installing respectively in the horizontal direction in 2 both sides of column of Y type piers to be poured are simultaneously
The inner side of described many root type girder steels 4 is made to be located in the column 2 of Y type piers to be poured, then by the vertical of Y type piers to be poured
The reinforcing bar 10 of post 2 through default reinforced hole 11 on the inner side edge of a wing of section steel beam 4 and web being correspondingly arranged make section steel beam 4 with
The reinforcing bar 10 of the column 2 of Y type piers is connected;
(4) pour the column 2 of Y type piers;
(5) when the concrete strength of the column 2 of Y type piers reaches requirement, many 3 bottoms of concrete filled steel tube diagonal brace are distinguished
It is welded to connect on vertical pre-embedded steel slab 8 and horizontal pre-embedded steel slab 9 and the other end is respectively welded at the section steel beam 4 being correspondingly arranged
On;
(6) laying Bailey beam 5, described Bailey beam 5 and section steel beam on many root type girder steels 4 of the homonymy for having supported
4 take spot welding and securing member to be fixed;
(7) lay distribution beam 6 in Bailey beam described in the left and right sides 5 respectively, described distribution beam 6 is adopted with Bailey beam 4
Securing member and spot welding connection;
(8) the outer wall shape respectively according to Y type socle V-arrangements to be poured in left and right sides distribution beam 6 lays Y type piers
Formwork-support 7.
The structure of the bridge Y type pier construction combinative structure platforms poured using the inventive method is included:On a left side for cushion cap 1
Right both sides are respectively provided with multiple vertical pre-embedded steel slabs 8 and the edge on the top surface of the cushion cap of 2 left and right sides of column of Y type piers
Cushion cap is longitudinally respectively provided with multiple horizontal pre-embedded steel slabs 9, in 2 both sides of column of described Y type piers respectively along level side
To many root type girder steels 4 for the height such as installing and the inner side of described many root type girder steels 4 is made to be located in the column 2 of Y type piers, it is described
The reinforcing bar 10 of column 2 of Y type piers make through default reinforced hole 11 on the 4 inner side edge of a wing of section steel beam that is correspondingly arranged and web
Section steel beam 4 is connected with the reinforcing bar 10 of the column 2 of Y type piers, and many 3 bottoms of concrete filled steel tube diagonal brace are respectively welded and are connected to vertically
On pre-embedded steel slab 8 and horizontal pre-embedded steel slab 9 and the other end is respectively welded on the section steel beam 4 being correspondingly arranged, in many of homonymy
Bailey beam 5 is fixed with root type girder steel 4, is respectively fixed with distribution beam 6, in the left and right sides in Bailey beam described in the left and right sides 5
Y type piers formwork-support 7 is laid with according to Y type socle V-arrangement outer wall shapes to be poured respectively in distribution beam 6.
Embodiment 1
(1) the multiple vertical pre-embedded steel slabs 8 of setting are longitudinally respectively separated in the left and right sides of cushion cap template along cushion cap and treating
It is pre- the multiple levels of setting to be respectively separated longitudinally along cushion cap on the top surface of the cushion cap template of 2 left and right sides of column of the Y type piers for pouring
Bury steel plate 9;
(2) cushion cap 1 is poured in cushion cap template;
(3) many root type girder steels 4 for the height such as installing respectively in the horizontal direction in 2 both sides of column of Y type piers to be poured are simultaneously
The inner side of described many root type girder steels 4 is made to be located in the column 2 of Y type piers to be poured, then by the vertical of Y type piers to be poured
The reinforcing bar 10 of post 2 through default reinforced hole 11 on the inner side edge of a wing of section steel beam 4 and web being correspondingly arranged make section steel beam 4 with
The reinforcing bar 10 of the column 2 of Y type piers is connected;
(4) pour the column 2 of Y type piers;
(5) when the concrete strength of the column 2 of Y type piers reaches requirement, many 3 bottoms of concrete filled steel tube diagonal brace are distinguished
It is welded to connect on vertical pre-embedded steel slab 8 and horizontal pre-embedded steel slab 9 and the other end is respectively welded at the section steel beam 4 being correspondingly arranged
On;
(6) laying Bailey beam 5, described Bailey beam 5 and section steel beam on many root type girder steels 4 of the homonymy for having supported
4 take spot welding and securing member to be fixed;
(7) lay distribution beam 6 in Bailey beam described in the left and right sides 5 respectively, described distribution beam 6 is adopted with Bailey beam 4
Securing member and spot welding connection;
(8) the outer wall shape respectively according to Y type socle V-arrangements to be poured in left and right sides distribution beam 6 lays Y type piers
Formwork-support 7.
With Y type piers formwork-support 7 as supporting the concrete for pouring Y type piers.Concrete filled steel tube has good after testing
Mechanical property, has more preferable compressive property compared to traditional steel pipe support structure.
Claims (1)
1. a kind of bridge Y types pier is constructed and uses the installation method of combinative structure platform, it is characterised in that it comprises the following steps:
(1) the multiple vertical pre-embedded steel slabs of setting are longitudinally respectively separated and to be poured in the left and right sides of cushion cap template along cushion cap
The multiple horizontal pre-embedded steel slabs of setting are respectively separated longitudinally along cushion cap on the top surface of the cushion cap template of the column left and right sides of Y type piers;
(2) cushion cap is poured in cushion cap template;
(3) many root type girder steels of height such as install respectively in the horizontal direction in the column both sides of Y type piers to be poured and make described
Many root type girder steels on the inside of be located in the column of Y type piers to be poured, then by the reinforcing bar of the column of Y type piers to be poured
Through on the inner side edge of a wing of the section steel beam being correspondingly arranged and web, default reinforced hole makes the steel of section steel beam and the column of Y type piers
Muscle is connected;
(4) pour the column of Y type piers;
(5) when the concrete strength of the column of Y type piers reaches requirement, many concrete filled steel tube diagonal brace bottoms are respectively welded into company
It is connected on vertical pre-embedded steel slab and horizontal pre-embedded steel slab and the other end is respectively welded on the section steel beam being correspondingly arranged;
(6) Bailey beam is laid on many root type girder steels of the homonymy for having supported, described Bailey beam and section steel beam are taken a little
Weldering and securing member are fixed;
(7) lay distribution beam in Bailey beam described in the left and right sides respectively, described distribution beam and Bailey beam adopt securing member and
Spot welding connects;
(8) the outer wall shape respectively according to Y type socle V-arrangements to be poured in the distribution beam of the left and right sides lays Y type pier templates
Bracing frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510785177.1A CN105350458B (en) | 2015-11-16 | 2015-11-16 | Construction method of composite structure platform for construction of Y-shaped pier of bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510785177.1A CN105350458B (en) | 2015-11-16 | 2015-11-16 | Construction method of composite structure platform for construction of Y-shaped pier of bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105350458A CN105350458A (en) | 2016-02-24 |
CN105350458B true CN105350458B (en) | 2017-03-22 |
Family
ID=55326511
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510785177.1A Active CN105350458B (en) | 2015-11-16 | 2015-11-16 | Construction method of composite structure platform for construction of Y-shaped pier of bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105350458B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105821770B (en) * | 2016-04-01 | 2017-05-24 | 上海城建市政工程(集团)有限公司 | Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower |
CN105951607A (en) * | 2016-07-06 | 2016-09-21 | 苏文藏 | Reinforced V-shaped bridge pier bracket |
CN108661166A (en) * | 2018-07-04 | 2018-10-16 | 西南交通大学 | A kind of aluminium alloy truss node and concrete connecting structure and its installation method |
CN110205945B (en) * | 2019-07-03 | 2024-01-09 | 浙江中天恒筑钢构有限公司 | Detachable and adjustable Y-shaped steel structure pier self-balancing device and construction method |
CN111501531A (en) * | 2020-03-31 | 2020-08-07 | 上海城建市政工程(集团)有限公司 | Construction method of V-shaped thin-wall pier and 0# block main beam supporting system |
CN111979918A (en) * | 2020-07-08 | 2020-11-24 | 中交第二航务工程局有限公司 | V-shaped pier combined construction method suitable for marine environment |
CN112343171A (en) * | 2020-11-02 | 2021-02-09 | 中国建筑第八工程局有限公司 | Steel pipe column V-shaped steel support construction method |
CN117230701B (en) * | 2023-10-24 | 2024-05-28 | 中铁四局集团有限公司 | Overweight load arc V pier bridge sector bracket and construction method |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000045229A (en) * | 1998-07-28 | 2000-02-15 | Nishimatsu Constr Co Ltd | Constructing method of bridge |
CN101200877A (en) * | 2007-12-24 | 2008-06-18 | 贵州省桥梁工程总公司 | Non-support construction process for triangle frame |
CN202323772U (en) * | 2011-12-02 | 2012-07-11 | 中国建筑第七工程局有限公司 | Upside-down hanging construction device for steel stranded wires of bridge V-shaped support |
CN102888815B (en) * | 2012-10-16 | 2015-08-26 | 上海城建市政工程(集团)有限公司 | The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam |
CN203007846U (en) * | 2012-12-19 | 2013-06-19 | 中铁十局集团第三建设有限公司 | Y-type block template and support system |
CN104746435B (en) * | 2015-04-03 | 2016-03-30 | 中国建筑第六工程局有限公司 | A kind of construction method of great-angle Y type pier stud |
-
2015
- 2015-11-16 CN CN201510785177.1A patent/CN105350458B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105350458A (en) | 2016-02-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105350458B (en) | Construction method of composite structure platform for construction of Y-shaped pier of bridge | |
KR100958014B1 (en) | Construction method of steel composite girder bridge | |
CN107165272A (en) | Prestressing force assembly concrete frame joint attachment structure and its construction method | |
CN106869012B (en) | Using the prefabricated thin-wall bent cap of prestressing with bond system | |
CN105951848A (en) | Non-intermittent composite transfer structure for super-deep foundation pit support and construction method | |
CN106012872B (en) | Continuous rigid frame bridge without dorsal funciculus oblique pull reinforcement system and construction method | |
CN108005401A (en) | A kind of support and change method of the column of existing frame structure base isolation reinforcement | |
CN107245953B (en) | A kind of crossed construction method of multilayer bridge structure | |
CN109235662A (en) | A kind of column board connecting equipment comprising multiple shear connector | |
CN109811633A (en) | A kind of corrugated steel and Combined concrete double curvature arched bridge and preparation method thereof | |
CN105803924B (en) | Mixed passenger and freight railway Simple T-Girders pavement combining structure and combined method | |
CN106436591A (en) | Steel cantilever combined bridge deck slab widening and reconstruction structure and construction method thereof | |
CN103883052A (en) | Upturned beam and cast-in-place slab overall pouring construction method | |
CN209907210U (en) | Integral pouring template system for T-shaped beam sidewalk board and sound barrier base | |
CN106958319A (en) | Precast concrete post component and connected node | |
CN205531016U (en) | Precast concrete post component and connected node | |
CN102852281A (en) | Prestressed precast main beam with laying gaps | |
CN205242268U (en) | Anchor triangular bracket | |
CN206408639U (en) | Assembled steel reinforced concrete composite bridge | |
CN110541429B (en) | Energy-consuming bolt type connecting method for connecting concrete prefabricated column and foundation | |
CN209194354U (en) | High-altitude long-span binder base-supporting shellfish thunder support construction | |
CN208502394U (en) | A kind of antidetonation connection structure of steel construction pipe fitting and fabricated base | |
CN102852279A (en) | Prestressed reinforced concrete superposed beam having convex-concave superposed surfaces | |
CN111996899B (en) | Method for building large-span channel in artificial landscape mountain | |
CN216109354U (en) | Conversion layer steel column mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190314 Address after: 402260 Third Floor, No. 599 Qingqi Road, Binjiang New Town, Jiangjin District, Chongqing Co-patentee after: China Construction Sixth Engineering Bureau Co., Ltd. Patentee after: Zhongjian Bridge Co., Ltd. Address before: 300451 No. 72 Hangzhou Road, Tanggu District, Tianjin Patentee before: China Construction Sixth Engineering Bureau Co., Ltd. |