CN104895008B - The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection - Google Patents

The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection Download PDF

Info

Publication number
CN104895008B
CN104895008B CN201510313886.XA CN201510313886A CN104895008B CN 104895008 B CN104895008 B CN 104895008B CN 201510313886 A CN201510313886 A CN 201510313886A CN 104895008 B CN104895008 B CN 104895008B
Authority
CN
China
Prior art keywords
ecological
wall
concrete
sheet pile
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510313886.XA
Other languages
Chinese (zh)
Other versions
CN104895008A (en
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huayuan Environment Construction Co ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201510313886.XA priority Critical patent/CN104895008B/en
Publication of CN104895008A publication Critical patent/CN104895008A/en
Application granted granted Critical
Publication of CN104895008B publication Critical patent/CN104895008B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses the construction method of a kind of environmentally friendly ecology wallboard type with ribbing barricade shore protection, comprise the following steps: set sheet pile at the scene, sheet pile interval arranges rib wall, is provided with the slot of certain depth in the sheet pile of rib wall site;Make prefabricated pile and Ecological Wall;Being inserted in by prefabricated pile in the default slot of sheet pile, concrete perfusion is attached;Ecological Wall is connected with prefabricated pile by the plug at its two ends;Anchor cable is set on shore protection is domatic, and on domatic, spray pervious concrete layer;In the ecological hole of Ecological Wall, plant vegetation, pour eco-concrete at the ecological hole absolute altitude of row at Ecological Wall and pervious concrete interlayer;Eco-concrete backfills planting soil, planting soil is planted vegetation, completes the construction of environmentally friendly ecology wallboard type with ribbing barricade shore protection.

Description

The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection
Technical field
The present invention relates to a kind of Ecological Retaining Wall bank protection construction method, particularly to a kind of environmentally friendly ecology wallboard type with ribbing barricade bank protection construction method.
Background technology
Traditional bank protection structure mainly has reinforced earth bank protection structure, grouts or placed rockfill bank protection structure, cast-in-place concrete Form Gravity Breast Wall bank protection structure and precast concrete block bank protection structure etc., these bank protection structures are firm, durable, it is widely used in the bank-protection works such as navigation channel, river, harbour, but there is also many deficiencies, as big in differential settlement, destruction ecological environment, stability in the large difference etc..
At present, for the problem that existing bank protection structure differential settlement is big, the mode that general employing sets sheet pile solves, wherein reinforced concrete sheet pile is because of its long-lived feature, more cost performance in Practical Project, but conventional steel bar concrete sheet pile exists and sets that difficulty, structure be thick and heavy and the shortcoming such as run-of-bank gravel slope connectivity difference.The problem destroying ecological environment for existing bank protection structure, typically can improve by the way of planting green vegetation on back fill course after wall, but this traditional approach still destroys resource function and the ecological functions in navigation channel, also destroy navigation channel, river biological chain simultaneously, cause ecological deterioration.For the problem of stability in the large difference, generally use the mode of later stage artificial second consolidation to alleviate, both wasted time and energy, and be difficult to again fundamentally solve problems.
Therefore, need badly at present and seek a kind of can meet the band Ecological Retaining Wall bank protection construction method that intensity is big, it is amphibious to take into account, easy construction is saved simultaneously.
Summary of the invention
It is an object of the invention to overcome drawbacks described above or the deficiencies in the prior art, it is provided that a kind of environmentally friendly ecology wallboard type with ribbing barricade bank protection construction method.It is an object of the invention to be achieved through the following technical solutions:
The construction method of a kind of environmentally friendly ecology wallboard type with ribbing barricade shore protection, it is characterised in that described barricade shore protection is mainly by Ecological Wall, sheet pile, rib wall, prefabricated pile, anchor cable, eco-concrete, pervious concrete layer, planting soil and vegetation composition;Sheet pile sets along shore protection, and sheet pile interval arranges rib wall, is provided with slot in the sheet pile of rib wall site, and prefabricated pile is fixed in slot;Ecological Wall is connected with prefabricated pile by the plug at its two ends;Ecological Wall is formed by eco-concrete is prefabricated, is provided with ecological hole and dowel in the wall body of Ecological Wall, and ribs is connected with Ecological Wall by dowel;On shore protection is domatic, it is inserted with anchor cable, and sprays pervious concrete layer;Having poured eco-concrete between Ecological Wall and pervious concrete layer, laid planting soil on eco-concrete, vegetation is planted in the ecological hole of planting soil and Ecological Wall;
Shown construction method mainly comprises the steps that
(1) according to design requirement, setting sheet pile at the scene, sheet pile arranges rib wall every 2-3m, arranges slot in the sheet pile of rib wall site;
(2) making prefabricated pile and Ecological Wall, Ecological Wall two ends are arranged plug, arrange ribs, plug and ribs and fixed with Ecological Wall by dowel, be provided with groove in prefabricated pile in Ecological Wall wall body, are attached for the plug with Ecological Wall two ends;
(3) being inserted in by prefabricated pile in the slot that sheet pile is preset, concrete perfusion is attached;
(4) after prefabricated pile has connected, Ecological Wall is connected with prefabricated pile by the plug at its two ends;
(5) anchor cable is set on shore protection is domatic, and on domatic, spray pervious concrete layer;In the ecological hole of Ecological Wall, plant vegetation, pour eco-concrete at the ecological hole absolute altitude of row at Ecological Wall and pervious concrete interlayer;
(6) on eco-concrete, backfill planting soil, planting soil is planted vegetation, completes the construction of environmentally friendly ecology wallboard type with ribbing barricade shore protection.
Further, ecological hole by outer and in big from little change, horizontally set vegetation in ecological hole.
Rib wall progressively reduces from top to bottom, in upside-down triangle shape.
Each parts in environmentally friendly ecology wallboard type with ribbing barricade shore protection in the present invention are the most prefabricated to be formed, quality controllable, and uses rigid foundation, and seriality is good, intensity is big, stability is high, applied widely, it is ensured that shore protection quality.
In the present invention, the junction at sheet pile and prefabricated pile have employed rib wall type structure, it is ensured that the intensity of junction and fixing.
In the present invention, prefabricated pile and Ecological Wall use plug-in type connected mode, improve efficiency of construction.
Horizontally set ecosystem in the present invention, does not the most weaken the ecological value of shore protection, and also add shore protection barricade can usable floor area.
Accompanying drawing explanation
Fig. 1 is environmentally friendly ecology wallboard type with ribbing barricade shore protection profile.
Fig. 2 is construction process figure.
Fig. 3 is Ecological Retaining Wall schematic diagram.
In figure: 1-Ecological Wall;2-ecology hole;3-dowel;4-plug;5-ribs;6-sheet pile;7-rib wall;8-prefabricated pile;9-slot;10-rolling earth behind retaining wall;11-anchor cable;12-pervious concrete layer;13-eco-concrete;14-planting soil;15-vegetation.
Detailed description of the invention
Fig. 1 is environmentally friendly ecology wallboard type with ribbing barricade shore protection profile.Fig. 2 is construction process portion.Fig. 3 is Ecological Wall schematic diagram.
As shown in Figure 1-Figure 3 main is made up of Ecological Wall 1, sheet pile 6, rib wall 7, prefabricated pile 8, anchor cable 11, eco-concrete 13, pervious concrete layer 12, planting soil 14 and vegetation 15.
Sheet pile 6 sets along shore protection, and sheet pile 6 interval arranges rib wall 7, is provided with slot 9 in the sheet pile of rib wall site, and prefabricated pile 8 is fixed in slot 9.
Ecological Wall 1 is connected with prefabricated pile 8 by the plug 4 at its two ends.Ecological Wall 1 is formed by eco-concrete is prefabricated, is provided with ecological hole 2 and dowel 3 in the wall body of Ecological Wall 1, and ribs 5 is connected with Ecological Wall 1 by dowel 3.
On shore protection is domatic, it is inserted with anchor cable 11, and sprays pervious concrete layer 13;Having poured eco-concrete 13 between Ecological Wall 1 and pervious concrete layer 12, laid planting soil 14 on eco-concrete 13,15 kinds of vegetation is planted in the ecological hole 2 of planting soil 14 and Ecological Wall 1.
The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection comprises the following steps:
Shown in Fig. 1 and Fig. 2, set 0.75m thickness, 2.5m length, sheet pile 6 deep for 7m at the scene, and arrange every 2.5m spacing at sheet pile 6 top and to grow tall and be the rib wall 7 of 1.25m, rib wall 7 the most progressively reduces, outer ribs wall 7 is 0.2m beyond the Breadth Maximum of sheet pile 6, interior side rib wall 7 is 0.3m beyond the Breadth Maximum of sheet pile 6, in upside-down triangle shape, be provided with in the sheet pile 6 at rib wall 7 position one long × wide × deeply for the slot 9 of 0.56m × 0.56m × 1.00m, for the connection with top prefabricated pile 8.
The square prefabricated pile 8 that the making length of side is 0.55m, height is 3m, the offside of square prefabricated pile 8 is arranged is easy to the groove that Ecological Wall 1 connects, groove shapes is consistent with the shape of the plug 4 in Ecological Wall 1, the thickness of Ecological Wall 1 is 0.35m, height is 3m, a length of 2.5m, up and down one ecological hole 2 is set every 0.5m, ecological hole 2 is by outer and inner big from little change, diameter gradually changes to 20cm from 10cm, by dowel 3, ribs 5 and Ecological Wall 1 are attached, the a length of 3m of ribs 5, wide height is respectively 0.25cm.Prefabricated Ecological Wall 1 is inserted connection respectively along the groove of prefabricated pile 8 both sides.
After prefabricated pile 8, Ecological Wall 1, sheet pile 6, the connection work of rib wall 7 complete, rolling earth behind retaining wall 10 domatic on the anchor cable 11 of a diameter of 10cm, a length of 5 ~ 10m is set, and on domatic, spray the thick pervious concrete layer 12 of about 20cm, for anchoring anchor cable 11, then ecological hole 2 in Ecological Wall 1 is laterally buried underground vegetation 15, between Ecological Wall 1 and rolling earth behind retaining wall 10, pours eco-concrete 13 afterwards at ecological hole 2 absolute altitude of row on.
After eco-concrete 13 reaches design strength, carry out the backfilling working of planting soil 14, and vegetation 15 is set on planting soil 14, be finally completed the construction working of environmentally friendly ecology wallboard type with ribbing barricade shore protection.
Above-mentioned detailed description of the invention limits technical scheme the most in any form, and the technical scheme that the mode of every employing equivalent or equivalent transformation is obtained all falls within protection scope of the present invention.

Claims (3)

1. the construction method of an environmentally friendly ecology wallboard type with ribbing barricade shore protection, it is characterised in that described barricade shore protection is mainly by Ecological Wall, sheet pile, rib wall, prefabricated pile, anchor cable, eco-concrete, pervious concrete layer, planting soil and vegetation composition;Sheet pile sets along shore protection, and sheet pile interval arranges rib wall, is provided with slot in the sheet pile of rib wall site, and prefabricated pile is fixed in slot;Ecological Wall is connected with prefabricated pile by the plug at its two ends;Ecological Wall is formed by eco-concrete is prefabricated, is provided with ecological hole and dowel in the wall body of Ecological Wall, and ribs is connected with Ecological Wall by dowel;On shore protection is domatic, it is inserted with anchor cable, and sprays pervious concrete layer;Having poured eco-concrete between Ecological Wall and pervious concrete layer, laid planting soil on eco-concrete, vegetation is planted in the ecological hole of planting soil and Ecological Wall;
Described construction method mainly comprises the steps that
(1) according to design requirement, setting sheet pile at the scene, sheet pile arranges rib wall every 2-3m, arranges slot in the sheet pile of rib wall site;
(2) making prefabricated pile and Ecological Wall, Ecological Wall two ends are arranged plug, arrange ribs, plug and ribs and fixed with Ecological Wall by dowel, be provided with groove in prefabricated pile in Ecological Wall wall body, are attached for the plug with Ecological Wall two ends;
(3) being inserted in by prefabricated pile in the slot that sheet pile is preset, concrete perfusion is attached;
(4) after prefabricated pile has connected, Ecological Wall is connected with prefabricated pile by the plug at its two ends;
(5) anchor cable is set on shore protection is domatic, and on domatic, spray pervious concrete layer;In the ecological hole of Ecological Wall, plant vegetation, pour eco-concrete at the ecological hole absolute altitude of row at Ecological Wall and pervious concrete interlayer;
(6) on eco-concrete, backfill planting soil, planting soil is planted vegetation, completes the construction of environmentally friendly ecology wallboard type with ribbing barricade shore protection.
Construction method the most according to claim 1, it is characterised in that ecological hole by outer and in big from little change, horizontally set vegetation in ecological hole.
Construction method the most according to claim 1, it is characterised in that rib wall progressively reduces from top to bottom, in upside-down triangle shape.
CN201510313886.XA 2015-06-09 2015-06-09 The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection Expired - Fee Related CN104895008B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510313886.XA CN104895008B (en) 2015-06-09 2015-06-09 The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510313886.XA CN104895008B (en) 2015-06-09 2015-06-09 The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection

Publications (2)

Publication Number Publication Date
CN104895008A CN104895008A (en) 2015-09-09
CN104895008B true CN104895008B (en) 2016-11-09

Family

ID=54027938

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510313886.XA Expired - Fee Related CN104895008B (en) 2015-06-09 2015-06-09 The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection

Country Status (1)

Country Link
CN (1) CN104895008B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318370A (en) * 2019-07-06 2019-10-11 南通市规划设计院有限公司 A kind of ecological revetment and its construction method
CN110424328B (en) * 2019-07-19 2021-09-07 杭州江润科技有限公司 Ecological sheet pile revetment and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6048139A (en) * 1998-01-21 2000-04-11 Donovan, Iii; Murtha Vincent Arrangement for shoreline construction, maintenance, and protection, and methods for making and using the same
CN1632231A (en) * 2004-12-27 2005-06-29 河海大学 Landscape type multi-stage stepwise artificial wetland protection slope forming method
KR20110051474A (en) * 2009-11-10 2011-05-18 (주)부전 이엔씨 Eco-friendly retaining wall using phc pile
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN203808009U (en) * 2014-04-12 2014-09-03 江阴市江港堤闸管理处 Ecological harbor dyke protection bank

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6048139A (en) * 1998-01-21 2000-04-11 Donovan, Iii; Murtha Vincent Arrangement for shoreline construction, maintenance, and protection, and methods for making and using the same
CN1632231A (en) * 2004-12-27 2005-06-29 河海大学 Landscape type multi-stage stepwise artificial wetland protection slope forming method
KR20110051474A (en) * 2009-11-10 2011-05-18 (주)부전 이엔씨 Eco-friendly retaining wall using phc pile
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN203808009U (en) * 2014-04-12 2014-09-03 江阴市江港堤闸管理处 Ecological harbor dyke protection bank

Also Published As

Publication number Publication date
CN104895008A (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN204780764U (en) Ecological wallboard formula barricade shore protection with ribbing of environment friendly
CN102635120B (en) Circular deep foundation ditch is without Construction of Supporting structure and construction method
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN203741868U (en) Reinforced concrete retaining wall structure with combined anchor wire
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN104389320A (en) Construction method of pile foundation anchor rope prestress high retaining wall
EP3269879A1 (en) Hard road construction method for natural groundwater recharge
CN103437370A (en) Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN206752667U (en) A kind of basement barrier wall structure
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN103215950B (en) Pile foundation extension construction method in backfilling area
CN104895008B (en) The construction method of environmentally friendly ecology wallboard type with ribbing barricade shore protection
CN204000848U (en) A kind of socketed pile for subaqueous construction
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN105421314B (en) A kind of construction method of the three-dimensional regulator control system of accumulated water Farmland Water
CN204898465U (en) Ecological drainage facility of permafrost region dish
CN209066479U (en) Assembled green ecological reinforced earth retaining wall
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN206143783U (en) Prevent supporting device on mud stone landslide
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN103866779A (en) Construction method of water stopping surrounding and protecting structure of soft soil foundation building foundation pit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181224

Address after: Room 212, Room 212, Room 215-220 and Room 515, 35 Changjiang Road, Zhenjiang City, Jiangsu Province, 2002

Patentee after: JIANGSU HUAYUAN ENVIRONMENT CONSTRUCTION Co.,Ltd.

Address before: 310015 office room 1901, block C, Wanda Plaza, intersection of Gongshu District Shi Xiang Road and Hang Hang Road, Hangzhou, Zhejiang.

Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161109

CF01 Termination of patent right due to non-payment of annual fee