CN104607815A - 一种制作并控制起重机主梁拱度的方法 - Google Patents
一种制作并控制起重机主梁拱度的方法 Download PDFInfo
- Publication number
- CN104607815A CN104607815A CN201410785717.1A CN201410785717A CN104607815A CN 104607815 A CN104607815 A CN 104607815A CN 201410785717 A CN201410785717 A CN 201410785717A CN 104607815 A CN104607815 A CN 104607815A
- Authority
- CN
- China
- Prior art keywords
- welding
- web
- welded
- camber
- moulding bed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K31/00—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
- B23K31/02—Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K2101/00—Articles made by soldering, welding or cutting
- B23K2101/28—Beams
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
一种制作并控制起重机主梁拱度的方法,属于起重机结构制作技术领域;腹板先按纵长度焊接接板,再按预留拱度切割成型,腹板上的纵向长筋全部与腹板装配焊接到位,矫形整平后上胎架与底板装配,完成内横隔板与腹板的焊接,再完成腹板与底板的纵向长焊缝,为了控制焊接变形,应从中间逐渐向两侧完成焊接,梁的两侧也对称施焊,组成U型梁;其有益效果是:首先利用余料、残料制作,本身就是资源的再利用,成本的节约,通过结构和胎架的刚性连接,再加上胎架预留的拱度值,这样使结构的成型精度全部得到控制,也避免了火工矫形对材料造成二次损伤,焊接顺序合理。
Description
技术领域
一种制作并控制起重机主梁拱度的方法,属于起重机结构制作技术领域。
背景技术
目前,国内起重机建造,尤其主梁建造,传统方法是将起重机主梁以铸造平台为水平基准进行建造,通过在梁中间增加调节垫块及火工矫形的方法来控制主梁的拱度,此传统方法的缺点是铸造平台需求量大且转运复杂,调节垫块不能控制结构的变形,影响结构的整体尺寸精度,而火工矫形则影响材料的性能。
发明内容
鉴于已有技术存在的缺陷,本发明的目的是提供一种制作并控制起重机主梁拱度的方法,利用余料、废料制作工装胎架代替铸造平台,通过预留胎架的高度来实现主梁的拱度,这样不仅能大幅度的节约成本提高效率,且主梁的拱度及尺寸精度能最大程度的得到保证。
为实现上述目的,本发明所采用的技术解决方案是:一种制作并控制起重机主梁拱度的方法,具体步骤是:
a)利用板材切割的余料或者料头拼焊成角钢或T型材,将其全部预制成统一长度,作为胎架型材;
b)将预制好的胎架型材焊接到车间地面预埋件上,计算出起重机主梁的预留拱度;
c)利用经纬仪将此预留拱度值全部过渡到每根胎架型材上,在此高度上加焊横向型材;
d)敷设主梁底板使之与预留拱度相符,并将其与胎架固定一体;
e)装配梁内的横隔板,焊接矫形;
f)封盖主梁顶板。
所述焊接矫形过程具体为:腹板先按纵长度焊接接板,再按预留拱度切割成型,腹板上的纵向长筋全部与腹板装配焊接到位,矫形整平后上胎架与底板装配,完成内横隔板与腹板的焊接 ,再完成腹板与底板的纵向长焊缝,为了控制焊接变形,应从中间逐渐向两侧完成焊接,梁的两侧也对称施焊,组成U型梁。
一种制作并控制起重机主梁拱度的方法,其有益效果是:首先利用余料、残料制作,本身就是资源的再利用,成本的节约,通过结构和胎架的刚性连接,再加上胎架预留的拱度值,这样使结构的成型精度全部得到控制,也避免了火工矫形对材料造成二次损伤,焊接顺序合理。
附图说明
图1是一种制作并控制起重机主梁拱度的方法的胎架结构图;
图2为底板装配图;
图3为腹板装配图;
图4为主梁顶板装配图;
图5为拱度值曲线示意图。
图中附图标记为:1、地面预埋件,2、底板,3、横向型材,4、横隔板,5、腹板,6、顶板。
具体实施方式
下面根据附图出示的一种制作并控制起重机主梁拱度的方法的结构图做具体如下说明:一种制作并控制起重机主梁拱度的方法,具体步骤是:
a)利用板材切割的余料或者料头拼焊成角钢或T型材,将其全部预制成统一长度,作为胎架型材;
b)将预制好的胎架型材焊接到车间地面预埋件1上,计算出起重机主梁的预留拱度;
c)利用经纬仪将此预留拱度值全部过渡到每根胎架型材上,在此高度上加焊横向型材3;
d)敷设主梁底板2使之与预留拱度相符,并将其与胎架固定一体;
e)装配梁内的横隔板4,焊接矫形;
f)封盖主梁顶板6。
所述焊接矫形过程具体为:腹板5先按纵长度焊接接板,再按预留拱度切割成型,腹板5上的纵向长筋全部与腹板5装配焊接到位,矫形整平后上胎架与底板2装配,完成内横隔板3与腹板5的焊接 ,再完成腹板5与底板2的纵向长焊缝,为了控制焊接变形,应从中间逐渐向两侧完成焊接,梁的两侧也对称施焊,组成U型梁。
Claims (2)
1.一种制作并控制起重机主梁拱度的方法,其特征是具体步骤为:一种制作并控制起重机主梁拱度的方法,具体步骤是:
a)利用板材切割的余料或者料头拼焊成角钢或T型材,将其全部预制成统一长度,作为胎架型材;
b)将预制好的胎架型材焊接到车间地面预埋件上,计算出起重机主梁的预留拱度;
c)利用经纬仪将此预留拱度值全部过渡到每根胎架型材上,在此高度上加焊横向型材;
d)敷设主梁底板使之与预留拱度相符,并将其与胎架固定一体;
e)装配梁内的横隔板,焊接矫形;
f)封盖主梁顶板。
2.根据权利要求1所述的一种制作并控制起重机主梁拱度的方法,其特征是:所述焊接矫形过程具体为:腹板先按纵长度焊接接板,再按预留拱度切割成型,腹板上的纵向长筋全部与腹板装配焊接到位,矫形整平后上胎架与底板装配,完成内横隔板与腹板的焊接 ,再完成腹板与底板的纵向长焊缝,为了控制焊接变形,应从中间逐渐向两侧完成焊接,梁的两侧也对称施焊,组成U型梁。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410785717.1A CN104607815B (zh) | 2014-12-18 | 2014-12-18 | 一种制作并控制起重机主梁拱度的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410785717.1A CN104607815B (zh) | 2014-12-18 | 2014-12-18 | 一种制作并控制起重机主梁拱度的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104607815A true CN104607815A (zh) | 2015-05-13 |
CN104607815B CN104607815B (zh) | 2016-08-17 |
Family
ID=53142600
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410785717.1A Active CN104607815B (zh) | 2014-12-18 | 2014-12-18 | 一种制作并控制起重机主梁拱度的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104607815B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107879248A (zh) * | 2017-07-21 | 2018-04-06 | 南通振华重型装备制造有限公司 | 一种大梁轨道制作工艺 |
CN108747065A (zh) * | 2018-05-22 | 2018-11-06 | 南京宝色股份公司 | 一种大规格薄壁ta5合金带t型筋板片的制造工艺 |
CN110153577A (zh) * | 2018-02-11 | 2019-08-23 | 上海振华重工(集团)股份有限公司 | 一种异形箱体机器人自动化焊接方法 |
CN115476064A (zh) * | 2022-09-14 | 2022-12-16 | 南通中远海运重工装备有限公司 | 轮胎门式起重机主梁制造工艺 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0218292A (ja) * | 1988-07-07 | 1990-01-22 | Nippon Hoisuto Kk | クレーンガーダの製造方法 |
JPH0233090A (ja) * | 1988-07-20 | 1990-02-02 | Nippon Hoisuto Kk | クレーンガーダとその製造方法 |
CN101691186A (zh) * | 2009-10-10 | 2010-04-07 | 吕传水 | 一种高刚度予应力起重机主梁的生产工艺 |
CN102251657A (zh) * | 2011-04-08 | 2011-11-23 | 重庆建工集团股份有限公司 | 一种装配式框架梁板的起拱支模方法 |
CN102489939A (zh) * | 2011-11-24 | 2012-06-13 | 吕传水 | 一种起重机主梁的生产工艺 |
CN102587289A (zh) * | 2012-03-31 | 2012-07-18 | 中铁宝桥(扬州)有限公司 | 一种钢箱梁自动控制预拼装装置及拼装方法 |
-
2014
- 2014-12-18 CN CN201410785717.1A patent/CN104607815B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0218292A (ja) * | 1988-07-07 | 1990-01-22 | Nippon Hoisuto Kk | クレーンガーダの製造方法 |
JPH0233090A (ja) * | 1988-07-20 | 1990-02-02 | Nippon Hoisuto Kk | クレーンガーダとその製造方法 |
CN101691186A (zh) * | 2009-10-10 | 2010-04-07 | 吕传水 | 一种高刚度予应力起重机主梁的生产工艺 |
CN102251657A (zh) * | 2011-04-08 | 2011-11-23 | 重庆建工集团股份有限公司 | 一种装配式框架梁板的起拱支模方法 |
CN102489939A (zh) * | 2011-11-24 | 2012-06-13 | 吕传水 | 一种起重机主梁的生产工艺 |
CN102587289A (zh) * | 2012-03-31 | 2012-07-18 | 中铁宝桥(扬州)有限公司 | 一种钢箱梁自动控制预拼装装置及拼装方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107879248A (zh) * | 2017-07-21 | 2018-04-06 | 南通振华重型装备制造有限公司 | 一种大梁轨道制作工艺 |
CN110153577A (zh) * | 2018-02-11 | 2019-08-23 | 上海振华重工(集团)股份有限公司 | 一种异形箱体机器人自动化焊接方法 |
CN108747065A (zh) * | 2018-05-22 | 2018-11-06 | 南京宝色股份公司 | 一种大规格薄壁ta5合金带t型筋板片的制造工艺 |
CN115476064A (zh) * | 2022-09-14 | 2022-12-16 | 南通中远海运重工装备有限公司 | 轮胎门式起重机主梁制造工艺 |
CN115476064B (zh) * | 2022-09-14 | 2023-06-30 | 南通中远海运重工装备有限公司 | 轮胎门式起重机主梁制造工艺 |
Also Published As
Publication number | Publication date |
---|---|
CN104607815B (zh) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104947803B (zh) | 一种预制板柱榫卯式连接节点及安装方法 | |
CN102535642B (zh) | 空间自由曲面网壳钢结构的装配式节点及其装配方法 | |
CN104607815A (zh) | 一种制作并控制起重机主梁拱度的方法 | |
CN107143034A (zh) | 一种装配式混凝土框架结构梁柱刚性连接节点 | |
CN204781363U (zh) | 一种钢与混凝土组合结构的新型抗震梁柱节点 | |
CN103659182A (zh) | 弯扭箱型梁360°旋转楼梯的制作方法 | |
CN204530421U (zh) | 用于倒t盖梁桥面连续构造施工支座梁体密贴的预制箱梁 | |
CN104563305A (zh) | 一种混凝土叠合梁与钢管混凝土柱连接节点及施工方法 | |
CN103230965A (zh) | 钢吊车梁成品焊接变形平面度矫正方法 | |
CN203583901U (zh) | 一种任意桁架万能拼装胎架 | |
CN102350594A (zh) | 门型吊架装配十字型钢柱的方法 | |
CN206873673U (zh) | 一种装配式钢结构外挂墙板节点 | |
CN103669665A (zh) | 钢筋桁架楼承板施工的标高差节点施工工艺 | |
CN204266124U (zh) | 大节段钢箱梁预拼装胎架 | |
CN103321153B (zh) | 一种中小跨径槽形梁桥的施工方法 | |
CN203271113U (zh) | 一种用于浇筑拱形混凝土预制梁板的模板 | |
CN105083804B (zh) | 集装箱用拼接钢板及其制造方法以及集装箱 | |
CN205296489U (zh) | 一种超高轻钢龙骨防火隔墙施工结构 | |
CN104563525B (zh) | 一种箱式钢拱梁整体卧式组对方法 | |
CN204221939U (zh) | 一种预制混凝土电缆沟盖板模具*** | |
CN105756233A (zh) | 一种梁墙复合外墙构件 | |
CN104727213B (zh) | 组装式钢混拱形桥t梁板 | |
CN202192391U (zh) | 一种适用于装配十字型钢柱的门型吊架 | |
CN103696499A (zh) | 钢结构梁柱连接用铸钢节点 | |
CN105317146A (zh) | 建筑用钢结构抗震楼板及制作方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |