CN104453204B - Overarm scaffold board - Google Patents
Overarm scaffold board Download PDFInfo
- Publication number
- CN104453204B CN104453204B CN201410745881.XA CN201410745881A CN104453204B CN 104453204 B CN104453204 B CN 104453204B CN 201410745881 A CN201410745881 A CN 201410745881A CN 104453204 B CN104453204 B CN 104453204B
- Authority
- CN
- China
- Prior art keywords
- angle bar
- plate face
- vertical section
- horizontal segment
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
- Movable Scaffolding (AREA)
Abstract
This patent is a kind of overarm scaffold board, including horizontal body plate and reinforcement anchorage bar, one lateral edges of described horizontal body plate is provided with the two or more draw-in groove with this edge-perpendicular, strengthen anchorage bar is provided with the vertical section angle bar and horizontal segment angle bar that are mutually perpendicular to and link together, its vertical section angle bar includes vertical section angle bar the first plate face and vertical section angle bar the second plate face, horizontal segment angle bar includes horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face, vertical section angle bar the first plate face is connected on draw-in groove, wherein vertical section angle bar the second plate face is provided with the connecting hole for being connected with scaffold, horizontal segment angle bar the first plate face is basic horizontal and is connected with horizontal body plate.This patent is mainly used in construction, solves scaffold scaffold board dismounting difficulty when operation and installs inconvenience, and ornaments instrument and material easily drop, the problem that builder easily steps on sky.
Description
Technical field
The present invention relates to a kind of building implement, particularly relate to the scaffold board of a kind of construction.
Background technology
At present, when builder carries out operation on scaffold, it is desirable to have scaffold board is laid thereon as the platform of the support stood and ornaments instrument and material.There is the gap of several tens cm between the scaffold and the building that currently use, cause furnishing instrument when scaffold carries out operation and material easily drops, builder easily steps on empty dangerous.
Summary of the invention
It is an object of the invention to provide the scaffold board of a kind of construction, solve ornaments instrument and material on existing scaffold and easily drop, the problem that builder easily steps on sky.
The present invention is a kind of overarm scaffold board, including horizontal body plate and reinforcement anchorage bar, one lateral edges of described horizontal body plate is provided with the two or more draw-in groove with this edge-perpendicular, strengthen anchorage bar is provided with the vertical section angle bar and horizontal segment angle bar that are mutually perpendicular to and link together, its vertical section angle bar includes vertical section angle bar the first plate face and vertical section angle bar the second plate face, horizontal segment angle bar includes horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face, vertical section angle bar the first plate face is connected on draw-in groove, wherein vertical section angle bar the second plate face is provided with the connecting hole for being connected with scaffold, horizontal segment angle bar the first plate face is basic horizontal and is connected with horizontal body plate.
The feature of technique scheme is, this scaffold board provides an assistance platform when construction operation, and this assistance platform has that dismounting is easily easy for installation, and ornaments instrument and material do not fall out, and builder can the advantage of safety work.
Further, described reinforcement anchorage bar is L-shaped so that easier for installation.
Further, described vertical section angle bar the first plate face and vertical section angle bar the second plate face are mutually perpendicular to, and horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face are mutually perpendicular to, in order to coordinate the horizontal main board can more effectively stable connection.
Further, horizontal segment angle bar the first plate face is provided with two through holes, and horizontal body plate is provided with the respective through hole mated with horizontal segment angle bar the first plate face, and connects with bolt so that horizontal body plate and horizontal segment angle bar can be easy for installation and removal.
Accompanying drawing explanation
Fig. 1 is front view of the present invention;
Fig. 2 is the top view of horizontal body plate of the present invention;
Fig. 3 is the top view of angle bar of the present invention.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation:
Such as Fig. 1, Fig. 2, shown in Fig. 3: the overarm scaffold board of the present invention, including horizontal body plate 1 and reinforcement anchorage bar, one lateral edges of described horizontal body plate 1 is provided with the two or more draw-in groove 12 with this edge-perpendicular, strengthen anchorage bar is provided with the vertical section angle bar 21 and horizontal segment angle bar 22 that are mutually perpendicular to and link together, its vertical section angle bar 21 includes the first iron plate face, orthogonal vertical section angle and vertical section angle bar the second plate face, horizontal segment angle bar 22 includes orthogonal horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face, vertical section angle bar the first plate face is connected on draw-in groove 12, wherein vertical section angle bar the second plate face is provided with the connecting hole for being connected with scaffold, horizontal segment angle bar the first plate face is basic horizontal and is connected with horizontal body plate 1.
In Fig. 2 and Fig. 3, the through hole 13 on horizontal body plate is the through hole matched with the through hole 23 on horizontal segment angle bar the first plate face, and two through holes are that bolt connects, the holding capacity of main board of improving the standard.Wherein strengthening anchorage bar is L-shaped.
Above-described is only the preferred embodiment of the present invention; should be understood that; for a person skilled in the art; under the premise without departing from present configuration; some deformation and improvement can also be made; these also should be considered as protection scope of the present invention, and these are all without affecting effect of the invention process and practical applicability.
Claims (4)
1. an overarm scaffold board, it is characterized in that: include horizontal body plate and strengthen anchorage bar, one lateral edges of described horizontal body plate is provided with the two or more draw-in groove with this edge-perpendicular, strengthen anchorage bar is provided with the vertical section angle bar and horizontal segment angle bar that are mutually perpendicular to and link together, its vertical section angle bar includes vertical section angle bar the first plate face and vertical section angle bar the second plate face, horizontal segment angle bar includes horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face, vertical section angle bar the first plate face is connected on draw-in groove, wherein vertical section angle bar the second plate face is provided with the connecting hole for being connected with scaffold, horizontal segment angle bar the first plate face is basic horizontal and is connected with horizontal body plate.
2. hang oneself from a beam as claimed in claim 1 scaffold board, it is characterized in that: described reinforcement anchorage bar is L-shaped.
3. hanging oneself from a beam as claimed in claim 1 scaffold board, it is characterized in that: described vertical section angle bar the first plate face and vertical section angle bar the second plate face are mutually perpendicular to, horizontal segment angle bar the first plate face and horizontal segment angle bar the second plate face are mutually perpendicular to.
4. hanging oneself from a beam as claimed in claim 1 scaffold board, it is characterized in that: horizontal segment angle bar the first plate face is provided with two through holes, horizontal body plate is provided with the respective through hole mated with horizontal segment angle bar the first plate face, and connects with bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410745881.XA CN104453204B (en) | 2014-12-09 | 2014-12-09 | Overarm scaffold board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410745881.XA CN104453204B (en) | 2014-12-09 | 2014-12-09 | Overarm scaffold board |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104453204A CN104453204A (en) | 2015-03-25 |
CN104453204B true CN104453204B (en) | 2016-07-06 |
Family
ID=52899893
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410745881.XA Active CN104453204B (en) | 2014-12-09 | 2014-12-09 | Overarm scaffold board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104453204B (en) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4621028B2 (en) * | 2004-01-21 | 2011-01-26 | 株式会社ラリック | Scaffolding plate structure |
CN201137294Y (en) * | 2007-12-21 | 2008-10-22 | 中天建设集团有限公司 | Scaffold board fixing clip |
CN202596150U (en) * | 2012-05-11 | 2012-12-12 | 张愉快 | Scaffold pedal |
CN203034789U (en) * | 2012-12-29 | 2013-07-03 | 上海建工一建集团有限公司 | Metal scaffold floor fixing member |
CN203160674U (en) * | 2013-02-04 | 2013-08-28 | 中天建设集团有限公司天津分公司 | Scaffold board fixing clamp |
CN204357098U (en) * | 2014-12-09 | 2015-05-27 | 重庆建工第九建设有限公司 | Overarm scaffold floor |
-
2014
- 2014-12-09 CN CN201410745881.XA patent/CN104453204B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104453204A (en) | 2015-03-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203247859U (en) | Alignment device for butt joint perpendicularity of large steel columns | |
CN204645570U (en) | One can have enough to meet the need elevator shaft protective platform | |
CN204357098U (en) | Overarm scaffold floor | |
CN104453204B (en) | Overarm scaffold board | |
CN205802864U (en) | Novel architecture lowering or hoisting gear | |
CN204738548U (en) | Design safe plain net of encorbelmenting | |
CN204001818U (en) | Construction work telescopic support steelframe | |
CN204174915U (en) | Scaffold | |
CN202031309U (en) | Suspending operation platform for structural concrete constructions | |
CN204675629U (en) | The suspender that a kind of mill housing is installed or removed | |
CN203257080U (en) | Adjustable overhang supporting device for building construction | |
CN104372935A (en) | Scaffold | |
CN204609847U (en) | A kind of new pumping unit positioning base | |
CN205116726U (en) | Building templates link for civil engineering | |
CN205742944U (en) | A kind of construction operation scaffold | |
CN103552905A (en) | Pipe fitting hoisting box | |
CN205088785U (en) | Reinforced concrete frame | |
CN204163358U (en) | Scaffold | |
CN204646308U (en) | A kind of transporting bracket device | |
CN204386097U (en) | A kind of structural sheeting structure | |
CN204324669U (en) | A kind of wedge-caulking device of mining locker voussoir | |
CN204163395U (en) | A kind of square plate scaffold | |
CN201589010U (en) | Overhead gantry for laying lines for large-scale equipment in construction site | |
CN202824270U (en) | Steel tube straightening support for scaffold | |
CN207423664U (en) | The fixed frame of one discharge plate fastener strength experiment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |