CN104120686B - A kind of high-elastic die-cushion A seating compound dam - Google Patents

A kind of high-elastic die-cushion A seating compound dam Download PDF

Info

Publication number
CN104120686B
CN104120686B CN201410361477.2A CN201410361477A CN104120686B CN 104120686 B CN104120686 B CN 104120686B CN 201410361477 A CN201410361477 A CN 201410361477A CN 104120686 B CN104120686 B CN 104120686B
Authority
CN
China
Prior art keywords
district
toe wall
downstream
dam
upstream
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410361477.2A
Other languages
Chinese (zh)
Other versions
CN104120686A (en
Inventor
姚栓喜
谢小平
蔡新合
杨存龙
雷艳
孙玉军
郝丽莎
张晓将
魏坚政
王君利
庞秀兰
吴峻峰
苏晓军
许建军
李锋
刘世隆
张伟
李晓刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huanghe Hydropower Development Co Ltd
PowerChina Northwest Engineering Corp Ltd
Original Assignee
Huanghe Hydropower Development Co Ltd
PowerChina Northwest Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huanghe Hydropower Development Co Ltd, PowerChina Northwest Engineering Corp Ltd filed Critical Huanghe Hydropower Development Co Ltd
Priority to CN201410361477.2A priority Critical patent/CN104120686B/en
Publication of CN104120686A publication Critical patent/CN104120686A/en
Application granted granted Critical
Publication of CN104120686B publication Critical patent/CN104120686B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention belongs to water power hydraulic engineering hydraulic structure technical field, specifically provide a kind of high-elastic die-cushion A seating compound dam, comprise set gradually from upstream to downstream concrete slab, bed course district, transition region, main rockfill area, upstream and downstream time rockfill area, the bottom of described concrete slab, bed course district, transition region is provided with High-toe wall district, the bottom of main rockfill area, described upstream and downstream time rockfill area is provided with low compression district, described low compression district be placed in High-toe wall district downstream and below the crest level in High-toe wall district.The setting in this invention High-toe wall district and low compression district, reduces distortion and the stress of dam body and concrete slab, reaches the standard of 200m level rock, make 300m level rock technical feasibility, economic security.

Description

A kind of high-elastic die-cushion A seating compound dam
Technical field
The invention belongs to water power hydraulic engineering hydraulic structure technical field, be specifically related to a kind of high-elastic die-cushion A seating compound dam.
Background technology
Along with water power implementation, in the abundant southwest of hydraulic power potentials, the Northwest, large quantities of high dam is built, building or yet to be built.Earth and rockfill dam is modal a kind of dam type in current Dam constructions, is also a kind of dam type with fastest developing speed, accounts for more than 95% of built dam sum.Whole world height of dam has more than 29000 more than the earth and rockfill dam of 15m, and wherein China has more than 15000 seats, mainly comprises homogeneous earth dam, core wall dam and Concrete Face Rockfill Dam etc.
Reinforced concrete face rockfill dam is the new dam type of the one later stage seventies in last century starting to grow up, it embodies the good feature of safety, economy, easy construction and compliance in practice, develop very fast although start late, the dark favor by Ba Gongjie.According to incompletely statistics, by September, 2011, in the world built, at the rock built and plan to build, all occupy the forefront from engineering quantity, height of dam to project scale.China is built and have more than 270 building rock so far, and sum accounts for global 50%.Along with the accumulation of Dam Construction experience and the raising of design level, the height of rock is also in continuous increase, and Shuibuya Dam, up to 233m, is built most high CFRD in the world, also becomes the successful case of 250m level high CFRD.250 ~ 300m level superelevation rock that great Shi gorge, Ci Haxia, Gu Shui, Ma Ji, Ru Mei etc. plan to build is at present also in the middle of project study, the safety issue of dam work bound pair superelevation rock, main exist to worry below: (1) can not correct Prediction superelevation face dam dam settlement and sedimentation cause panel deformation, stress and the requirement to sealing material; (2) whether existing laboratory facilities adopt material for scale model, can the physico-mechanical properties of correct Prediction superelevation face dam dam permeation stability problem and dam material; Due to the existence of above-mentioned uncertain factor, whether the concrete slab materials and structures form of high anti-extrusion, high cracking resistance can be proposed, whether can propose the joint water stop structure form and the material that meet the large deformation of superelevation face dam, become present Ba Gongjie and studied more problem.
But, water cloth a strip of land between hills build up the successful case becoming 250m level high CFRD, with accept by Ba Gong circle.If the distortion magnitude of the distortion of the 300m level superelevation rock planned to build, panel deflection and stress, joint seal reaches the degree of 200m level rock, can also accept for Ba Gongjie, also just solve the technical bottleneck of 300m level superelevation rock.
Summary of the invention
The object of the invention is to overcome the technical feasibility problems such as the distortion of 300m level superelevation rock in prior art, panel deflection and stress.
For this reason, the invention provides a kind of high-elastic die-cushion A seating compound dam, comprise set gradually from upstream to downstream concrete slab, bed course district, transition region, main rockfill area, upstream and downstream time rockfill area, the bottom of described concrete slab, bed course district, transition region is provided with High-toe wall district, the bottom of main rockfill area, described upstream and downstream time rockfill area is provided with low compression district, described low compression district be placed in High-toe wall district downstream and below the crest level in High-toe wall district.
Above-mentioned concrete slab and High-toe wall district upstream side are disposed with ballast district and bedding district by upstream to downstream.
The end elevation in above-mentioned ballast district and bedding district is higher than more than 10m bottom low compression district.
The thickness in the above bedding district of head upstream side point of above-mentioned High-toe wall district is not less than 10m.
Above-mentioned High-toe wall district upstream side slope ratio is 1:t, and the span of t is 0 ~ 0.2, and downstream, High-toe wall district is 1:S with the subregion slope ratio in low compression district, and S is not less than 0.5.
Above-mentioned High-toe wall district is consistent with the height in low compression district, and its height is 0.1 ~ 0.4 with the ratio of the height of dam on compound dam.
The bottom in above-mentioned High-toe wall district is provided with High-toe wall Foundation Consolidation Grouting floor.
In above-mentioned High-toe wall district, irrigation gallery is set, curtain grouting layer is set in irrigation gallery.
The slope of above-mentioned concrete slab, bed course district and transition region, than identical, be 1:m, and the span of m is 1.35 ~ 1.7; The downstream side slope ratio of time rockfill area, downstream is 1:n, and the span of n is 1.25 ~ 1.8.
The subregion slope ratio of main rockfill area, above-mentioned upstream and time rockfill area, downstream is 1:k, and the span of k is 0 ~ 1.35.
Beneficial effect of the present invention is as follows:
(1) the low compression district arranged bottom high-elastic die-cushion A seating compound dam dam body, the High-toe wall Foundation Consolidation Grouting floor of High-toe wall district and bottom thereof and curtain grouting floor with in dam body, top arrange main rockfill area, upstream, time rockfill area, downstream together with concrete slab, define closed seepage prevention system.
(2) the high-elastic die-cushion A seating compound dam of the present invention's proposition, the stress of 300m level superelevation rock, sedimentation and the distortion dividing crack structure etc. safety indexes can be made, meet the requirement of existing " Concrete Face Rockfill Dam design specifications " (DL/T5016-2011, SL228-98) and " concrete gravity dam design specifications " (L5108-1999, SL319-2005), make 300m level superelevation rock feasible technically.
(3) the high-elastic die-cushion A seating compound dam that the present invention proposes makes full use of local building rockfill materials, meets the requirement of economy, has good society, economy and ecological benefits.
Below with reference to accompanying drawing, the present invention is described in further details.
Accompanying drawing explanation
Fig. 1 is the section structure schematic diagram on the present invention's high-elastic die-cushion A seating compound dam.
Description of reference numerals: 1, concrete slab; 2, bed course district; 3, transition region; 4, main rockfill area, upstream; 5, time rockfill area, downstream; 6, High-toe wall district; 7, High-toe wall Foundation Consolidation Grouting layer; 8, curtain grouting layer; 9, low compression district; 10, bedding district; 11, ballast district.
Detailed description of the invention
Embodiment 1:
In order to overcome the distortion of 300m level superelevation rock in prior art, the technical feasibility problems such as panel deflection and stress, present embodiments provide a kind of high-elastic die-cushion A seating compound dam as shown in Figure 1, comprise the concrete slab 1 set gradually to downstream from upstream, bed course district 2, transition region 3, main rockfill area 4, upstream and time rockfill area 5, downstream, described concrete slab 1, bed course district 2, the bottom of transition region 3 is provided with High-toe wall district 6, the bottom of main rockfill area 4, described upstream and time rockfill area 5, downstream is provided with low compression district 9, described low compression district 9 be placed in High-toe wall district 6 downstream and below the crest level in High-toe wall district 6.
Wherein, High-toe wall district 6 is according to design of gravity dam, and design standard observes the relevant regulations of " concrete gravity dam design specifications " (L5108-1999, SL319-2005).The height in High-toe wall district 6, according to reducing the stress of concrete slab 1, being deformed into the magnitude of 200m level rock; The setting in High-toe wall district 6, can effectively reduce the static stress and distortion of concrete slab 1; The structure of concrete slab 1 and water-stopping structure thereof and material are selected according to the requirement of 200m level rock.
And the High-toe wall district 6 that is arranged so that in low compression district 9 meets the requirement of related specifications and stress stable to it, simultaneously, the setting in low compression district 9, distortion and the stress of dam body and concrete slab 1 can be reduced, reach the standard of 200m level rock, make 300m level rock technical feasibility, economic security, 300m level rock can be accepted by people.
In addition, low compression district 9 can adopt a kind of low compression material, bedding material in such as conventional design or its modified materials, Transition Materials, dry lean concrete material, roller-compacting concrete material, modification sand gravel material etc., also the combination of above-mentioned different materials can be adopted, low compression district 9 selects the material that in above-mentioned material, construction is simple, cost is low as far as possible, meets cost-effectiveness requirement.
Embodiment 2:
On the basis of embodiment 1, in order to play a protective role to concrete slab 1 and High-toe wall district 6, described concrete slab 1 and High-toe wall district 6 upstream side are disposed with ballast district 11 and bedding district 10 by upstream to downstream; The end elevation in described ballast district 11 and bedding district 10 is higher than more than 10m bottom low compression district 9; The thickness in the above bedding district 10 of head upstream side point of described High-toe wall district 6 is not less than 10m, and meets the allowable gradient requirement in bedding district 10.
And described High-toe wall district 6 upstream side slope is than being 1:t, and the span of t is 0 ~ 0.2, and downstream, High-toe wall district 6 is 1:S with the subregion slope ratio in low compression district 9, and S is not less than 0.5, and determines according to engineering is actual.Described High-toe wall district 6 is consistent with the height in low compression district 9, and its height is 0.1 ~ 0.4 with the ratio of the height of dam on compound dam, and its ratio is the smaller the better, and determines according to engineering is actual.
The bottom in described High-toe wall district 6 is provided with High-toe wall Foundation Consolidation Grouting floor 7; In described High-toe wall district 6, irrigation gallery is set, curtain grouting layer 8 is set in irrigation gallery; Concrete slab 1, High-toe wall district 6, High-toe wall Foundation Consolidation Grouting floor 7 and curtain grouting floor 8 are as the leakage preventing structure of this dam body.
The slope of described concrete slab 1, bed course district 2 and transition region 3, than identical, be 1:m, and the span of m is 1.35 ~ 1.7; The downstream side slope ratio of time rockfill area 5, downstream is 1:n, and the span of n is 1.25 ~ 1.8; The subregion slope ratio of main rockfill area 4, described upstream and time rockfill area 5, downstream is 1:k, and the span of k is 0 ~ 1.35, and determines according to engineering is actual, generally gets 0.2.
In addition, in the present embodiment, bed course district 2, transition region 3, main rockfill area 4, upstream, time rockfill area 5, downstream, ballast district 11 and bedding district 10 all can adopt rockfill materials to fill, and comprise built-up area excavated material, stock ground block building stones and stock ground sand gravel material etc.The selection of rockfill materials must meet the related request of " Concrete Face Rockfill Dam design specifications " (DL/T5016-2011, SL228-98).The present embodiment makes full use of the excavated material of building, reduces the area of rejected material and slag field, reduces dam construction to the impact of environment, reduces construction costs, improve the economic indicator of dam body and hinge, have good economy, society and environmental ecological benefit.
It should be noted that the above-mentioned parameter in the present embodiment must meet the requirement of " Concrete Face Rockfill Dam design specifications " (DL/T5016-2011, SL228-98) and " concrete gravity dam design specifications " (L5108-1999, SL319-2005).Main rockfill area 4, upstream and downstream time rockfill area 5 dam structure, dam body settlement, distortion, stress and panel deflection and stress, periphery fissure, vertical lap seam displacement etc. must be checked, meet the regulation of " Concrete Face Rockfill Dam design specifications " (DL/T5016-2011, SL228-98); The stress of High-toe wall must be checked and stablize, meeting the relevant regulations of " concrete gravity dam design specifications " (L5108-1999, SL319-2005); The osmotic stability of dam body Ge Liao district (comprising low compression district) must be checked.The leakage preventing structure of High-toe wall district 6 as low compression district 9 and the key components of dam body seepage structure, adopt concreting, and arrange closed water-stopping system.Low compression district 9 selects the materials such as bedding material, Transition Materials, roller compacted concrete or modification sand gravel material, adopts compaction type construction method.
More than exemplifying is only illustrate of the present invention, does not form the restriction to protection scope of the present invention, everyly all belongs within protection scope of the present invention with the same or analogous design of the present invention.

Claims (1)

1. a high-elastic die-cushion A seating compound dam, comprise the concrete slab (1) set gradually to downstream from upstream, bed course district (2), transition region (3), main rockfill area, upstream (4) and time rockfill area (5), downstream, it is characterized in that: described concrete slab (1), bed course district (2), the bottom of transition region (3) is provided with High-toe wall district (6), the bottom of main rockfill area, described upstream (4) and time rockfill area (5), downstream is provided with low compression district (9), described low compression district (9) be placed in High-toe wall district (6) downstream and below the crest level of High-toe wall district (6),
Described concrete slab (1) and High-toe wall district (6) upstream side are disposed with ballast district (11) and bedding district (10) by upstream to downstream;
The end elevation of described ballast district (11) and bedding district (10) is higher than low compression district (9) bottom more than 10m;
The thickness of the above bedding district (10) of described High-toe wall district (6) head upstream side point is not less than 10m;
Described High-toe wall district (6) upstream side slope ratio is 1:t, and the span of t is 0 ~ 0.2, and the subregion slope ratio of (6) downstream, High-toe wall district and low compression district (9) is 1:S, and S is not less than 0.5;
Described High-toe wall district (6) is consistent with the height of low compression district (9), and its height is 0.1 ~ 0.4 with the ratio of the height of dam on compound dam;
The bottom of described High-toe wall district (6) is provided with High-toe wall Foundation Consolidation Grouting floor (7);
In described High-toe wall district (6), irrigation gallery is set, curtain grouting layer (8) is set in irrigation gallery
The slope of described concrete slab (1), bed course district (2) and transition region (3), than identical, be 1:m, and the span of m is 1.35 ~ 1.7; The downstream side slope ratio of time rockfill area (5), downstream is 1:n, and the span of n is 1.25 ~ 1.8;
The subregion slope ratio of main rockfill area, described upstream (4) and time rockfill area (5), downstream is 1:k, and the span of k is 0 ~ 1.35.
CN201410361477.2A 2014-07-28 2014-07-28 A kind of high-elastic die-cushion A seating compound dam Active CN104120686B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410361477.2A CN104120686B (en) 2014-07-28 2014-07-28 A kind of high-elastic die-cushion A seating compound dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410361477.2A CN104120686B (en) 2014-07-28 2014-07-28 A kind of high-elastic die-cushion A seating compound dam

Publications (2)

Publication Number Publication Date
CN104120686A CN104120686A (en) 2014-10-29
CN104120686B true CN104120686B (en) 2016-04-13

Family

ID=51766303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410361477.2A Active CN104120686B (en) 2014-07-28 2014-07-28 A kind of high-elastic die-cushion A seating compound dam

Country Status (1)

Country Link
CN (1) CN104120686B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695386A (en) * 2015-04-09 2015-06-10 中国电建集团成都勘测设计研究院有限公司 Blocking and discharge structure and method for ditch water treatment
CN105155470A (en) * 2015-06-23 2015-12-16 武汉大学 Self-healing anti-seepage structure for concrete faced rockfill dam
CN105064289B (en) * 2015-08-04 2017-03-22 中国电建集团华东勘测设计研究院有限公司 Concrete panel structure applied to high-toe wall and construction method
CN105297685B (en) * 2015-11-23 2017-10-24 中国电建集团贵阳勘测设计研究院有限公司 A kind of pedestal CFRD and its construction method
CN105672191B (en) * 2016-01-15 2017-06-16 河海大学 A kind of mixed dam model test apparatus and application method
CN106120662B (en) * 2016-08-17 2019-04-16 中国电建集团西北勘测设计研究院有限公司 A kind of part high-modulus rock-faced dam dam
CN106284215B (en) * 2016-08-17 2019-03-15 中国电建集团西北勘测设计研究院有限公司 A kind of mixed dam
CN106638487B (en) * 2017-01-19 2019-10-25 中国电力建设股份有限公司 A kind of construction method combining checkdam and the combined dam
CN106836144A (en) * 2017-01-25 2017-06-13 中国电建集团西北勘测设计研究院有限公司 A kind of method of the maintenanceability of buttress type duplex face dam and raising panel
CN110939108A (en) * 2019-12-27 2020-03-31 中水北方勘测设计研究有限责任公司 Structure for preventing concrete face dam high-toe wall from being damaged
CN112921900B (en) * 2021-01-29 2022-06-07 中国电建集团华东勘测设计研究院有限公司 Geomembrane and asphalt concrete panel double-channel anchoring anti-seepage structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2258780C1 (en) * 2004-03-03 2005-08-20 Пехтин Владимир Алексеевич Earth-filled dam built on permafrost ground
CN101672026A (en) * 2009-09-18 2010-03-17 中国水电顾问集团华东勘测设计研究院 Face plate rock-fill dam structure of reasonably utilizing sand gravel material and construction method thereof
CN201972137U (en) * 2011-03-16 2011-09-14 华北水利水电学院 Steel-structure combined type interlayer steel plate rock-fill dam
CN103410123A (en) * 2013-08-13 2013-11-27 中国水电顾问集团成都勘测设计研究院 Retaining dam for hydraulic and hydro-power engineering

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2258780C1 (en) * 2004-03-03 2005-08-20 Пехтин Владимир Алексеевич Earth-filled dam built on permafrost ground
CN101672026A (en) * 2009-09-18 2010-03-17 中国水电顾问集团华东勘测设计研究院 Face plate rock-fill dam structure of reasonably utilizing sand gravel material and construction method thereof
CN201972137U (en) * 2011-03-16 2011-09-14 华北水利水电学院 Steel-structure combined type interlayer steel plate rock-fill dam
CN103410123A (en) * 2013-08-13 2013-11-27 中国水电顾问集团成都勘测设计研究院 Retaining dam for hydraulic and hydro-power engineering

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"梨园水电站混凝土面板堆石坝坝体不同介质结合部填筑处理措施";杨玺成;《水利水电技术》;20140531;第45卷(第5期);第52-54页 *

Also Published As

Publication number Publication date
CN104120686A (en) 2014-10-29

Similar Documents

Publication Publication Date Title
CN104120686B (en) A kind of high-elastic die-cushion A seating compound dam
CN106284215B (en) A kind of mixed dam
CN104099903B (en) High-base asphalt concrete core dam
CN106120662B (en) A kind of part high-modulus rock-faced dam dam
CN104110012A (en) Low-permeability rock-fill material concrete panel rock-fill dam
CN203373705U (en) Ecological slope protection
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN103397617A (en) Extrusion-wall type geomembrane-faced rockfill dam
CN206219897U (en) Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN205934862U (en) Local high -modulus enrockment concrete -faced rockfill dam structure
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN204456058U (en) A kind of constructing structure reducing building base subsidence speed
CN106567365B (en) Earth and rockfill dam longitudinal reinforcement construction method
CN206157496U (en) Moderate -low speed magnetic levitation traffic engineering single line location pile foundation combined type support rail girder construction of filling
CN101603298B (en) Dam joint structure and construction method thereof
CN205934861U (en) Mix dam structure
CN206157485U (en) Moderate -low speed magnetic levitation single line excavation location pile foundation combined type support rail roof beam transition section structure
CN214271529U (en) Foam concrete light roadbed structure above subway tunnel
CN206127736U (en) Moderate -low speed magnetic levitation double -line compound framing formula support rail roof beam transition section structure of location pile foundation that fills
CN103939112A (en) Down-cross cheuch tunnel double-layer forepoling structure
CN104631425B (en) A kind of flyash of accelerating arranges the method oozing consolidation
CN113846663A (en) Concrete continuous tooth wall structure without structural joint and construction method
CN203835406U (en) Double-layer forepoling structure for underneath pass valley tunnel
CN203741782U (en) Multi-section face plate structure of high concrete faced rockfill dam
Fan et al. Water pressure and stress characteristics of lining structure in water rich karst tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Yao Shuanxi

Inventor after: Wang Junli

Inventor after: Pang Xiulan

Inventor after: Wu Junfeng

Inventor after: Su Xiaojun

Inventor after: Xu Jianjun

Inventor after: Li Feng

Inventor after: Liu Shilong

Inventor after: Zhang Wei

Inventor after: Li Xiaogang

Inventor after: Xie Xiaoping

Inventor after: Cai Xinhe

Inventor after: Yang Cunlong

Inventor after: Lei Yan

Inventor after: Sun Yujun

Inventor after: Hao Lisha

Inventor after: Zhang Xiaojiang

Inventor after: Wei Jianzheng

Inventor before: Cai Xinhe

Inventor before: Yao Shuanxi

Inventor before: Lei Yan

Inventor before: Hao Lisha

Inventor before: Zhang Xiaojiang

Inventor before: Wei Jianzheng

Inventor before: Wang Junli

Inventor before: Wu Junfeng

Inventor before: Li Feng

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160307

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 survey and Design Institute of the northwest department of science and technology

Applicant after: Co., Ltd of northwest survey and design research institute of electricity Jian group of China

Applicant after: Huanghe Hydropower Development Co., Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 survey and Design Institute of the northwest department of science and technology

Applicant before: Co., Ltd of northwest survey and design research institute of electricity Jian group of China

C14 Grant of patent or utility model
GR01 Patent grant