CN103939115B - A kind of method of half shallow mining method hangar tunnel and structure - Google Patents

A kind of method of half shallow mining method hangar tunnel and structure Download PDF

Info

Publication number
CN103939115B
CN103939115B CN201410184031.7A CN201410184031A CN103939115B CN 103939115 B CN103939115 B CN 103939115B CN 201410184031 A CN201410184031 A CN 201410184031A CN 103939115 B CN103939115 B CN 103939115B
Authority
CN
China
Prior art keywords
construction
wall
top board
mining method
side arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410184031.7A
Other languages
Chinese (zh)
Other versions
CN103939115A (en
Inventor
徐加民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201410184031.7A priority Critical patent/CN103939115B/en
Publication of CN103939115A publication Critical patent/CN103939115A/en
Application granted granted Critical
Publication of CN103939115B publication Critical patent/CN103939115B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses method and the structure of a kind of half shallow mining method hangar tunnel, this shed hole structure is surrounded successively by external wall and basis thereof, top board, inner side arch wall, base plate;External wall uses and is beneficial to gravity-flow ventilation and the introversion of daylighting, window body of wall;Top board uses the variable cross-section form ensureing twice Guan Bi of structure with overall stress, its employing oblique section, end, will be connected realization in reinforcing bar inserts slope body by boring connect with hidden digging structure preliminary bracing, secondary liner structure respectively;Inner side arch wall uses the tunneling i.e. preliminary bracing of composite lining structure and the liner structure form of secondary liner structure combination;Select grouting with small pipe or anchor pole as tunneling advance support respectively according to country rock situation.The present invention had both overcome open-cut earthwork evacuation amount and big, big to the environmental destruction deficiency of interim side slope protection quantities, can reduce again difficulty and the security risk of boring construction, improve mechanized construction degree.

Description

A kind of method of half shallow mining method hangar tunnel and structure
Technical field
The present invention relates to a kind of shed hole structure using half shallow mining method, be particularly suited for being close to mountain Landform.
Background technology
Shed hole structure is half Tunnel Engineering of outside open type.In the engineering such as mountain highway, railway In planning and construction, tradition can be avoided to put the excavation in the excavation of slope for shed hole structure and protected working amount is big Shortcoming, effectively safeguards ecological environment, is also beneficial to operation security.Shed hole structure typically uses open-cut, Earthwork evacuation amount and interim side slope protection quantities are the biggest, and often cost is higher, is also unfavorable for water Soil keeps and the maintenance of ecological environment.
The Chen Shuwang finding Yunnan Communicaiton Planning & Design Research Institute through patent retrieval has one " shed hole structure of a kind of shallow mining method " (Patent publication No CN 101713294 A) patent of invention, A kind of method mentioning boring construction shed hole structure, is characterized in that: by peg board formula side wall and batter post, batter post Between longitudinal binder and connect bottom side wall the coupling beam with inclined column foundation and constitute, use subsurface excavation method from bottom to top Construction.It mainly the steps include: to excavate lateral pilot tunnel in side wall foundation portion;Use and excavate side from bottom to top Wall top pile foundation;Mortar flag stone between backfill pilot tunnel scope stake;Pour pile foundation armored concrete;Excavation batter post Basis, and apply pile foundation top and expose breast boards;Construction batter post and longitudinal binder;Divide bench excavation hangar tunnel The interior soil body;Remove lateral pilot tunnel supporting, complete side wall breast boards, pour bottom coupling beam;Apply road surface and Pipe trench structure.
CN 101713294 A patent of invention excavates lateral pilot tunnel, and excavates side wall from bottom to top Top pile foundation working space is narrow and small, operates relatively difficult, is unfavorable for mechanized construction;Repeatedly excavation disturbance The soil body, easy unstability between stake;Operation is more complicated, needs to remove workload bigger;Implement difficulty and wind Danger is relatively big, there is certain potential safety hazard.
Summary of the invention
The present invention provides method and the structure of a kind of half shallow mining method hangar tunnel, has both overcome open cut to execute Work earthwork evacuation amount and the deficiency that side slope protection quantities is big, big to environmental destruction temporarily, again may be used To reduce difficulty and the security risk of boring construction, improve mechanized construction degree.
The technical scheme is that: the structure of a kind of half shallow mining method hangar tunnel, this shed hole structure Surrounded successively by external wall and basis thereof, top board, inner side arch wall, base plate;External wall uses and is beneficial to nature Ventilate and the introversion of daylighting, window body of wall;Top board uses and ensures twice Guan Bi of structure and the change of overall stress Section form, its employing oblique section, end, leads to hidden digging structure preliminary bracing, secondary liner structure respectively Cross in boring will connect reinforcing bar insertion slope body and realize connecting;Inner side arch wall uses tunneling composite lining knot The liner structure form of structure, i.e. preliminary bracing and secondary liner structure combination;Select respectively according to country rock situation With grouting with small pipe or anchor pole as tunneling advance support.
Exterior sidewall structure includes using batter post and connection beam.
Top board includes using arched or slab construction.
Inner side arch wall includes using stalk, sloping core or bent wall.
The method of the half shallow mining method hangar tunnel of the present invention, first excavation external wall basis groove, Construction external wall basis;Construction external wall;Construction top board;Construction grouting with small pipe or anchor pole 4 constructing Ductule or anchor pole consolidation structure;Divide bench excavation inner side arch wall preliminary bracing structure of constructing;The construction end Plate;Arch wall secondary liner structure inside construction;Apply road surface, by-wash, greening of banketing.
The medicine have the advantages that and reducing excavation and protected working amount, reducing and ecological ring is broken While Huai, save operation ventilation, lighting expense use, build up landscape effect preferable, improve operation comfortableness, And construction organization is simple, convenient, it is simple to mechanized construction, reduce difficulty of construction and risk.
Accompanying drawing explanation
Fig. 1 is the shed hole structure cross-sectional configuration figure of the present invention.
Fig. 2 is the working procedure block diagram of the shed hole structure of the present invention.
In figure, each portion is numbered: 1. external wall basis;2. external wall;3. top board;4. ductule Slip casting or suspension roof support;5. ductule or anchor pole consolidation structure;6. arch wall preliminary bracing structure inside; 7. base plate;8. arch wall secondary liner structure inside;9. road surface and by-wash;10. banket greening.
Detailed description of the invention
The present invention is further described with enforcement below in conjunction with the accompanying drawings.
As it is shown in figure 1, the present invention proposes the shed hole structure of half boring construction: in external wall uses Incline, window body of wall, it is simple to gravity-flow ventilation, daylighting, save illumination and ventilate, improve stress condition, and There is provided ventilation, the window of daylighting for boring construction, improve construction operation environment.Inner side uses boring construction, Combining lineament, reduce the disturbance to Rock And Soil, operation is simple, reduces the difficulty of boring construction And risk, it also avoid discarded and projects.
Slope body suitably processes so that top board basis consolidates;Top board uses variable cross-section, and end uses bevel Face, is connected with hidden digging structure preliminary bracing, secondary liner structure respectively, for easy to connect, by boring Reinforcing bar will be connected insert in the body of slope.Select grouting with small pipe or anchor pole as tunneling respectively according to country rock situation Advance support, soil layer or weak surrounding rock can use conduit grouting support, and hard rock can use suspension roof support, little Conduit or anchor pole outer end casting concrete consolidation;Tunneling divides step construction, with excavation with supporting;In construction Strengthen construction monitoring, carry out dynamic design and Dynamic Construction;
As in figure 2 it is shown, the present invention proposes the construction procedure of the shed hole structure of half boring construction: first First excavation external wall basis groove, external wall basis 1 of constructing;Construction external wall 2;Construction top board 3;Execute Make grouting with small pipe or anchor pole 4 construct ductule or anchor pole consolidation structure 5;In dividing bench excavation and constructing Side arch wall preliminary bracing structure 6;Construction base plate 7;Arch wall secondary liner structure 8 inside construction;Apply road Face, by-wash 9, greening 10 of banketing.

Claims (5)

1. the structure of one and half shallow mining method hangar tunnels, it is characterised in that this shed hole structure by external wall and Its basis, top board, inner side arch wall, base plate surround successively;External wall uses and is beneficial to gravity-flow ventilation and daylighting Introversion, window body of wall;Top board uses and ensures twice Guan Bi of structure and the variable cross-section form of overall stress, Its employing oblique section, end, respectively with hidden digging structure preliminary bracing, secondary liner structure will even by boring Connect in reinforcing bar inserts slope body and realize connecting;Inner side arch wall uses tunneling composite lining structure, i.e. the initial stage props up Protect and the liner structure form of secondary liner structure combination;Grouting with small pipe is selected respectively according to country rock situation Or anchor pole is as tunneling advance support.
The structure of a kind of half shallow mining method hangar tunnel the most according to claim 1, it is characterised in that Exterior sidewall structure includes using batter post and connection beam.
The structure of a kind of half shallow mining method hangar tunnel the most according to claim 1, it is characterised in that Top board includes using arched or slab construction.
The structure of a kind of half shallow mining method hangar tunnel the most according to claim 1, it is characterised in that Inner side arch wall includes using stalk, sloping core or bent wall.
5. a method for half shallow mining method hangar tunnel, first excavation external wall basis groove, outside construction Side wall basis;Construction external wall;Construction top board;Construction grouting with small pipe or anchor pole and construct ductule or Anchor pole consolidation structure;Divide bench excavation inner side arch wall preliminary bracing structure of constructing;Construction base plate;Construction Inner side arch wall secondary liner structure;Apply road surface, by-wash, greening of banketing.
CN201410184031.7A 2014-05-04 2014-05-04 A kind of method of half shallow mining method hangar tunnel and structure Active CN103939115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410184031.7A CN103939115B (en) 2014-05-04 2014-05-04 A kind of method of half shallow mining method hangar tunnel and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410184031.7A CN103939115B (en) 2014-05-04 2014-05-04 A kind of method of half shallow mining method hangar tunnel and structure

Publications (2)

Publication Number Publication Date
CN103939115A CN103939115A (en) 2014-07-23
CN103939115B true CN103939115B (en) 2016-11-09

Family

ID=51186961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410184031.7A Active CN103939115B (en) 2014-05-04 2014-05-04 A kind of method of half shallow mining method hangar tunnel and structure

Country Status (1)

Country Link
CN (1) CN103939115B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869041A (en) * 2017-03-02 2017-06-20 衡阳市金泓建筑装饰设计有限公司 Bang Shan highways with top protection structure
CN108286266A (en) * 2018-03-27 2018-07-17 中铁局集团第二工程有限公司 A method of exempt to remove using object in light and dark digging in combination and builds underground structure
CN109869163A (en) * 2019-04-03 2019-06-11 北京市市政工程设计研究总院有限公司 A kind of construction method and structure of tunnel
CN112253172B (en) * 2020-10-16 2024-06-28 中铁第四勘察设计院集团有限公司 Tunnel bottom lining structure provided with tie beam and construction method thereof
CN112647536A (en) * 2020-12-04 2021-04-13 四川省交通勘察设计研究院有限公司 Open cut tunnel construction method without side slope disturbance
CN116717271B (en) * 2023-05-09 2024-02-13 长江勘测规划设计研究有限责任公司 Mountain-side integral type middle-wall multi-arch shed tunnel structure and construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3790377B2 (en) * 1998-12-18 2006-06-28 東日本旅客鉄道株式会社 Tunnel construction lining element and tunnel lining method
CN101713294A (en) * 2009-11-05 2010-05-26 陈树汪 Hangar tunnel structure constructed by subsurface excavation method
CN103321659B (en) * 2013-07-22 2015-04-22 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN103410532A (en) * 2013-08-07 2013-11-27 葛洲坝新疆工程局(有限公司) T-typed step-by-step parallel excavation method of soft-rock tunnel cavern

Also Published As

Publication number Publication date
CN103939115A (en) 2014-07-23

Similar Documents

Publication Publication Date Title
CN103939115B (en) A kind of method of half shallow mining method hangar tunnel and structure
CN105839643B (en) A kind of tunnel construction method of use pattern foundation pit supporting structure
CN102733827B (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN107762533B (en) A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel
CN104806267B (en) The shield end reinforcement system and its construction method of land pebble stratum super-front large pipe shed
CN107060803B (en) Tunnel construction method by utilizing pipe curtain grouting
CN102493822A (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN105626083A (en) Construction method for permeable ribbed multiple-arch tunnel
CN101709651A (en) Grouting water blocking method for undersea tunnel
CN101324071B (en) Pervious rib type arch beam tunnel
CN105863650A (en) Tunneling construction method with first wall construction and second tunneling construction
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN102182472A (en) Backfill repairing method for tunnel collapse cavity
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN103016027B (en) Tunnel or roadway excavating method under weak and broken complicated geological conditions
CN109611103B (en) Method for reinforcing shield section suspended boulder group
CN104373128A (en) Advance precipitation construction method of oversized-section double-side lower pilot tunnels of water-rich tunnel
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN103306713A (en) Networked reinforcement method for cross-layer drilling of outburst coal seam
CN106988760A (en) Facility-sliding strata tunnel portal reinforcing construction and construction method
CN102678126A (en) Method for excavating mountain tunnels in weak surrounding rock-fractured zones or shallow covered slope sections
CN107044293A (en) A kind of construction method in tunnel
CN109853399A (en) Big section for arch bridge tilts tunnel type skewback structure and its construction method
JP4132442B2 (en) Tunnel construction method
CN204311456U (en) Foundation ditch strengthening structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant