CN108286266A - A method of exempt to remove using object in light and dark digging in combination and builds underground structure - Google Patents

A method of exempt to remove using object in light and dark digging in combination and builds underground structure Download PDF

Info

Publication number
CN108286266A
CN108286266A CN201810258016.0A CN201810258016A CN108286266A CN 108286266 A CN108286266 A CN 108286266A CN 201810258016 A CN201810258016 A CN 201810258016A CN 108286266 A CN108286266 A CN 108286266A
Authority
CN
China
Prior art keywords
construction
underground structure
light
branch
combination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810258016.0A
Other languages
Chinese (zh)
Inventor
谢保良
王宏斌
刘久安
杨静
范普刚
祁昌俊
李玉宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Railway First Engineering Group Co Ltd
Second Engineering Co Ltd of China Railway First Engineering Group Co Ltd
Original Assignee
Second Construction Co Ltd of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Railway First Engineering Group Co Ltd filed Critical Second Construction Co Ltd of China Railway First Engineering Group Co Ltd
Priority to CN201810258016.0A priority Critical patent/CN108286266A/en
Publication of CN108286266A publication Critical patent/CN108286266A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The method for building underground structure of removing is exempted from using object in light and dark digging in combination the invention discloses a kind of, is included the following steps:Determine open cut and boring construction range and the separation of underground structure;The construction for carrying out open cut carries out just branch construction and partial excavation construction on the node that open cut is reserved;First branch is removed, and water-proof system construction and the construction of two linings are started.The more full cut and cover method of the present invention, which is reduced, removes, and ensures project progress, while housing demolition expense has saved construction investment up to hundred million yuan;Maintain underground structure system constant, on ground function without influence;Reduce the amount of abolishing, reduces building waste and the wasting of resources;Reduce project cost.

Description

A method of exempt to remove using object in light and dark digging in combination and builds underground structure
Technical field
The present invention relates to underground structure technical field is built, it particularly relates to which a kind of using light and dark digging upper object in combination Exempt from the method for building underground structure of removing.
Background technology
In the construction process of subway station, on the basis of satisfying the requirements, cut and cover tunneling is generally used, is made with reducing engineering Valence, while reducing difficulty of construction.In the case where meeting surface buildings and can not remove, can be used mode that bright, tunneling combines into Row subway station is built.In traditional mode, light and dark digging is combined with two ways:The first, according to barrier mileage by station Section is drawn, building corresponds to mileage and uses tunneling boring subsurface excavation method.This method tunneling heavy workload, project cost are high.The second, it applies respectively Open cut and hidden digging structure are done, closed structural system is respectively formed, to ensure the stress of structure in construction.Finally regard structure function Need independent open cut and hidden digging structure are connected to.It is more to do so structure piecemeal, the structure amount of abolishing is big, final light and dark digging Connection is also possible to part limiting structure function.
Invention content
For above-mentioned technical problem in the related technology, present invention proposition is a kind of, and using light and dark digging, upper object exempts to remove in combination The method for building underground structure can overcome the above-mentioned deficiency of the prior art.
To realize the above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A method of exempt to remove using object in light and dark digging in combination and build underground structure, includes the following steps:
S1:Determine open cut and boring construction range and the separation of underground structure;
S2:The construction for carrying out open cut, specifically includes:
S2.1:The construction of open excavation section fender post;
S2.2:The construction of Guan Liang;
S2.3:The excavation and support of open excavation section foundation pit;
S2.4:After structure built by opencut method is constructed, it should be layered rammed earth, and carry out the backfill of the earthwork;
S3:Just branch construction and partial excavation construction are carried out on the node that open cut is reserved;
S4:First branch is removed, and water-proof system construction and the construction of two linings are started.
Further, step S2.1 goes along with sb. to guard him in pile driving construction, the construction of step S2.2 Guan Liangs and improves stake top absolute altitude, using concrete Support, timely structure return and build and backfill back-pressure.
Further, just branch is formed to the top soil body using the double-deck long pipe shed in step S3.
Further, the trepanning in stake of alloy water drilling is applied before long pipe shed performs.
Further, pipe canopy is performed using auger bore, and is jumped hole when performing and performed, and is performed and is spaced in 5 holes or more, After single hole pore-forming, the filling of down tube slip casting immediately.
Further, in step S3, partial excavation construction specially first performs No.1 pilot tunnel and No. two pilot tunnels, then performs three Number pilot tunnel, No. four pilot tunnels, No. seven pilot tunnels and No. eight pilot tunnels, are completed at the same time abolishing for open cut fender post.
Further, step S4 Zhong Chu Zhi Caiyong branches remove, and perform two linings in time after the dismounting of first branch, and two linings are adopted Use full framing.
Further, the first branch in step S3 and bis- villages step S4 Zhong are E font structures.
Further, the water-proof system in step S4 specifically includes:
S4.1:Open cut side wall uses bentonite waterproof blanket, and the waterproof layer of tunneling side is ECB splash guards;
S4.2:ECB splash guards use polyurethane coating film, and by ECB splash guards and the polyurethane coating film at top open cut part into Row overlap joint;
S4.3:It is laid with tunneling waterproof layer, the overlap joint of bentonite waterproof blanket and ECB splash guards should be carried out at this time, the lap of splice is not small In 20cm, ECB splash guards are crimped using bentonite, are pasted with bentonite fluid sealant between bentonite and ECB splash guards.
Beneficial effects of the present invention:The more full cut and cover method of the present invention, which is reduced, removes, and ensures project progress, while housing demolition expense With up to hundred million yuan, construction investment has been saved;Maintain underground structure system constant, on ground function without influence;Reduce the amount of abolishing, subtracts Building waste and the wasting of resources are lacked;Reduce project cost.
Description of the drawings
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the present invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of structural schematic diagram of the permanent station structure described according to embodiments of the present invention;
Fig. 2-Fig. 4 is the schematic diagram of three steps in removing;
Fig. 5 is bentonite waterproof blanket and drainage systems overlapped joints schematic diagram;
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belong to what the present invention protected Range.
It is described according to embodiments of the present invention that a kind of using light and dark digging, upper object exempts to remove and builds the side of underground structure in combination Method includes the following steps:
S1:Determine open cut and boring construction range and the separation of underground structure;
S2:The construction for carrying out open cut, specifically includes:
S2.1:The construction of open excavation section fender post;
S2.2:The construction of Guan Liang;
S2.3:The excavation and support of open excavation section foundation pit;
S2.4:After structure built by opencut method is constructed, it should be layered rammed earth, and carry out the backfill of the earthwork;
S3:Just branch construction and partial excavation construction are carried out on the node that open cut is reserved;
S4:First branch is removed, and water-proof system construction and the construction of two linings are started.
In one embodiment, step S2.1 goes along with sb. to guard him in pile driving construction, the construction of step S2.2 Guan Liangs and improves stake top absolute altitude, adopts With concrete support, timely structure returns and builds and backfill back-pressure.
In one embodiment, just branch is formed to the top soil body using the double-deck long pipe shed in step S3.
In one embodiment, the trepanning in stake of alloy water drilling is applied before long pipe shed performs.
In one embodiment, pipe canopy is performed using auger bore, and is jumped hole when performing and performed, and is performed and is spaced in 5 It is more than a hole, after single hole pore-forming, the filling of down tube slip casting immediately.
In one embodiment, in step S3, partial excavation construction specially first performs No.1 pilot tunnel and No. two pilot tunnels, No. three pilot tunnels, No. four pilot tunnels, No. seven pilot tunnels and No. eight pilot tunnels are performed again, are completed at the same time abolishing for open cut fender post.
In one embodiment, step S4 Zhong Chu Zhi Caiyong branches remove, and perform two linings in time after the dismounting of first branch, And two serve as a contrast using full framing.
In one embodiment, the first branch in step S3 and bis- villages step S4 Zhong are E font structures.
In one embodiment, the water-proof system in step S4 specifically includes:
S4.1:Open cut side wall uses bentonite waterproof blanket, and the waterproof layer of tunneling side is ECB splash guards;
S4.2:ECB splash guards use polyurethane coating film, and by ECB splash guards and the polyurethane coating film at top open cut part into Row overlap joint;
S4.3:It is laid with tunneling waterproof layer, the overlap joint of bentonite waterproof blanket and ECB splash guards should be carried out at this time, the lap of splice is not small In 20cm, ECB splash guards are crimped using bentonite, are pasted with bentonite fluid sealant between bentonite and ECB splash guards.
In order to facilitate understand the present invention above-mentioned technical proposal, below by way of in specifically used mode to the present invention it is above-mentioned Technical solution is described in detail.
When specifically used, according to the present invention a kind of using light and dark digging, upper object exempts to remove and builds underground knot in combination The method of structure, by taking Zhenyang occupies the building of subway station nearby as an example:As shown in Figs. 1-5:Zhenyang occupies big restaurant and is located at the stations Zhu Shikou base The east side in hole, wire center mileage about K32+365.000 are approximately perpendicular to foundation pit side and are arranged in strip.It is two layers that Zhenyang, which occupies, Brickwork construction, East and West direction grow 21 meters, and north and south is 6 meters wide.House stretches into subway No. 8 cities Xian Zhu mouthful station main body foundation pit 3.7 meters.Base About 1 meter of plinth buried depth adds 50 centimetre of 28 cushion lime basis for 50 centimetres of brick walls.Materials for wall is that (after fraction plus section is common brick Blue bricks), roofing is thin watt common, and roof truss is wooden truss, and column is log.The House Property is private house-property, builds physical property The restaurants Zhi Wei, have been stopped using, and build up without a date, belong to dilapidated house.The range of removal is included in by government, in the Olympic Games in 2008 It can start to remove when Qianmen Dajie transformation early period, but due to various reasons, remove have no resolution always.Since station line position is true It is fixed, wear house under inevitable.In the case where house can not remove, to ensure normal the applying of the stations Zhu Shikou open-cut foundation ditch Work, is arranged U-shaped isolation pile in premises perimeter first, house is isolated to outside foundation pit, the structure for house not influence area of first constructing. Then boring construction house is got off station structure again.Subway station nearby is occupied in order to by the way of light and dark digging combination, complete Zhenyang Build, it is thus necessary to determine that following item:
1, the boundary of works area and separation of open cut and tunneling:It is to be adopted using the station whole section near corresponding Zhenyang Curie's journey section With tunneling, part nearby only still is occupied to Zhenyang and carries out tunneling.How far isolation pile could not only protect house apart from house, but also advantageous In implementing boring construction, operating expenses is reduced.
2, building structure analysis and the selection of construction:The emphasis of house protection needs to combine house at which position Structure type there is emphasis protect.Tunneling vault uses which kind of tunneling engineering method vault or flat-top, tunneling use.
3, the ancillary measure of house protection:Which feasible ancillary measure to be conducive to the safety in house using.
4, the processing of light and dark digging combination node:It is the weak link of construction in conjunction with node, needs special node way.
5, the determination of the Protection parameters such as building settlement index and monitoring measurement.
Below for problem above, illustrates or discuss respectively.
1, the boundary of works area and separation of open cut and tunneling:
In the determination of light and dark digging boundary of works area, should consider in terms of open cut and tunneling two.Zhenyang is occupied in coverage Station structure, tunneling boring implement tunneling, be conducive to the rule of open-cut foundation ditch shape, reduce due to Zhenyang occupy influence and caused by The external corner of foundation pit, it is advantageous to the stability of foundation pit.But boring construction is costly relative to open cut increase, is cost-effective Project dug underground amount should be reduced to the greatest extent, meanwhile, only 4.5 meters of station earthing, there is also certain technical difficulty for large area boring construction. Therefore the quality for considering light and dark digging, should reduce the workload of tunneling to the greatest extent.
The determination of distance in isolation pile and house needs consider the following factors:The operating space of isolation pile construction machinery.Every House foundation is reduced and is disturbed from stake and Guan Liang construction, Guan Liang bottom should as possible be located at except basic 45 ° of angles of flare.It answers the position of stake In conjunction with station structure construction joint location determination, light and dark digging station structure seaming position as possible is reserved in simple in structure, and stress is smaller Position.The limitation of boring construction minimum space, need to there are operating spaces appropriate to tunneling.The case where meeting conditions above Under, the range of tunneling less as possible, and then reduce project cost and construction risk.According to conditions above, light and dark digging west side has a common boundary The position to the east of structure armpit angle is arranged in face, and south and north flanks are arranged for 3 meters according to fender post edge apart from house foundation, is less Guan Liang excavates the disturbance to house foundation, and Guan Liang top is put on to ground.In summary it can determine that tunneling is ranging from wide by 6.85 Rice, is about 14 meters of section.
2, building structure analysis and the selection of construction
Closing foundation ditch side Zhenyang residence is additionally arranged two attached three-legged structures by an inclined roof and forms, and therefore, give support to a roof triangle The twice wall of truss is the main load bearing wall in house, and west side wall is located on hidden digging structure, is to be influenced maximum by tunneling Position, therefore reinforce it is particularly important in conceptual design to the supporting of the wall.Since tunneling width reaches 7 meters or so, it is Surface subsidence is reduced, big hole should be divided into duck eye, is excavated advantageously using CRD methods.Due to structure top earthing only 4.5 meters of left sides The right side forms larger limitation to arch camber at the top of first branch, therefore using the first branch structure of flat-top.Supporting for reinforcement to house west side wall, The position of CRD median septums is arranged in western headwall hereinafter, to increase support rigidity.
3, the ancillary measure of house protection
After determining tunneling excavation method, in conjunction with engineering method, supporting construction and formation condition, ancillary measure need to be taken, is further added Strong boring construction excavates and supporting measure can ensure construction safety.Since first branch structure is flat-tope structure, to prevent ground from collapsing It collapses, bimetallic tube canopy is set on vault.It caves in thin silt to reduce, the used time is the cohesive strength for increasing the soil body, is reduced The east side soil body carries out supporting using deep hole grouting to first branch structure to fine sand layer after excavation.
The processing of 4 light and dark digging combination nodes
The position that light and dark digging combines is the key point that structural strength, the weak spot of waterproof and the construction of light and dark digging engineering method combine.Under It is introduced in face of the structure connection of position of joints, waterproofing process.
The first branch of tunneling part and two linings are the structure of E fonts.Two lined steel muscle are connect by the reserved steel bar of structure built by opencut method It refutes device with structure built by opencut method to be connected, the shear resistance of concrete is increased by reserved concrete shear slot, forms the stress of closure System (two lining node in such as figure).To ensure the closure and force structure of just branch system, in tunneling top position, using in open cut Structure roof reserves grid tie point to realize the closure (grids top node in such as figure) of grid.It is interim to reinforce structure built by opencut method The intensity of system, before hidden digging structure does not complete, the position of corresponding structure built by opencut method beam column, according to 500mm (between grid etc. Away from) it is provided with temporary support of 40 I-steel as structure.In grating base, grid and bottom fender post reinforcing bar are connected It connects, ensures the fixation of grid end.
In water-proof system, open cut side wall uses bentonite waterproof blanket, top plate to use polyurethane coating film waterproof.Tunneling is prevented Water layer is ECB splash guards.Waterproof should be carried out in construction from the following aspects:1) the reserved of open cut waterproof is carried out.2) tunneling is anti- Water and the overlap joint of open cut waterproof are handled.3) the reinforcement processing of waterproof weak node.
Open cut side wall waterproof be waterproof blanket, structure built by opencut method construction finish tunneling at the beginning of branch construction complete, start waterproof and Two lining constructions, elapsed-time standards is longer, is easily invaded by outside moisture, damp failure, therefore reserved overlap joint trouble is anti-using plastics etc. Water material will protect after reserved waterproof blanket winding up.Pass through the external disturbances such as broken pile and first branch excavation during waterproof exposes, Iron sheet or other hard materials should be used to be protected.Before the lining construction of tunneling two, it is laid with tunneling waterproof layer, should be carried out at this time swollen The overlap joint of profit native waterproof blanket and ECB splash guards.The lap of splice is not less than 20cm.Using bentonite crimp ECB splash guards, the two it Between pasted with bentonite fluid sealant.
It is difficult to reserve overlap joint for polyurethane coating film destructible at top.It therefore should be in advance by the poly- of ECB splash guards and top Urethane film is overlapped in open cut part, and ECB splash guards are reserved to tunneling and are overlapped.
Even if using the above treatment measures, the weak spot that batch position is still waterproof is connect.Therefore it should be used in structure Two pass water-swellable water-stop glue carries out joint strengthening.Built-in slip casting pipe is answered in construction simultaneously, and Ying Shui is used after the completion of construction Mud carries out grouting reinforcing to structure.
The determination of the Protection parameters such as building settlement index
The general of the sedimentation index in house determines according to the assessment result of professional house appraisal agency.But due to the House Property etc. The reason of aspect, the assessment fail smoothly to carry out.Therefore determine that sedimentation index is answered under conditions of lacking necessary assessed information Integrated structure feature, the attainable standard of construction technology determine sedimentation index jointly.Meanwhile tour of the reinforcement to house in construction And monitoring.If any special circumstances, necessary adjustment is carried out to index in time.
House roof truss span reaches 13 meters, and the relative settlement of concern house load bearing wall is the major control point of monitoring. Sedimentation index digs stage sedimentation and tunneling just branch stage sedimentation clearly, the first branch of tunneling is removed and two lining stages sedimentation three phases.
Branch stage at the beginning of construction process control divides open-cut foundation ditch stage, tunneling according to the sequencing of construction and first branch remove and Two lining stage three parts.It is introduced separately below:
1 open-cut controls
Structure built by opencut method construct emphasis from go along with sb. to guard him pile driving construction, Guan Liang construction, foundation pit excavation and bracing, structure construction and supporting removal, The processes such as backfilling of earthwork are controlled.Meanwhile it should be carried out in open-cut and hidden digging structure connecting portion is reserved.
Going along with sb. to guard him pile driving construction uses rotary drilling rig, the stage emphasis to carry out the quality control of mud off, prevent collapse hole Phenomena such as, influence the stabilization of house foundation.After the completion of going along with sb. to guard him pile driving construction, excavation performs Guan Liang.The support of Guan Liang layer uses coagulation Soil support.Concrete support can bidirectional stress.Be conducive to foundation pit external corner Deformation control.The support at other positions, when implementation, first apply The straight support in work face house, after construction to be supported, then performs corner buttresses.To ensure corner buttresses along external corner direction Power can be undertaken by straight support, prevent the outside deformation of external corner.Meanwhile when diagonal brace is constructed, the shearing resistance of purlin behind is pedaled and must be applied Do it is solid reliable, to ensure the transmission of diagonal brace axle power.
Before excavation of foundation pit, grouting and reinforcing is carried out in premises perimeter setting mini-valve tube, in Excavation Process, according to room The monitoring situation in room carries out benefit slurry in time using mini-valve tube to premises perimeter, is the important hand of open cut stage building settlement control Section.
During excavation of foundation pit, the coordination of excavation and support should be carried out, is ensured with digging with support.It constructs in structure built by opencut method In the process, it also should gradually be removed with structure construction, the moment ensures the stress balance of foundation pit supporting system.Structure built by opencut method construction finishes Afterwards, it should be layered rammed earth, tunneling broken pile construction can be carried out after being backfilled to ground, to ensure the backfill earthwork to the above stake of top plate Restricted back-pressure effect.
2 preliminary bracing Construction controls
Include advance support construction, partial excavation two key links of construction in first branch construction overall process.Wherein in partial excavation Abolishing for isolation pile influences maximum to building settlement.It excavates and is excavated using 8 pilot tunnels of CRD methods point.Sequence of excavation presses icon Number carry out.Detailed process is as follows:
Pipe canopy is performed first before excavating, and the top soil body is formed with the double-deck long pipe shed and is supported.Pipe canopy applies alloy water drilling before performing The trepanning in stake, and stake cannot be directly cut off, ensure that stake occupies Zhenyang the effect of going along with sb. to guard him of the periphery soil body.Pipe canopy is drilled to using spiral Hole can generate the soil body certain crowd in-out effects, reduce the sedimentation in house.The drilling equipment using high pressure geomantic omen class should be avoided, To reduce the loss of the soil body.Pipe roof construction should jump hole and perform, and perform and be spaced in 5 holes or more.After single hole pore-forming, down tube is noted immediately Slurry filling, cannot wait for that porous pore-forming unifies slip casting, to ensure the promptness of filling.
Excavation construction, first perform Zhenyang occupy lower part 1., 2. number hole, then construct 3., 4. number hole.3., 4., 7., 8. number During pilot tunnel is implemented, it is completed at the same time abolishing for row's open cut fender post.Wherein 3. the cut-out of number hole stake generates whole stress system Influence it is maximum, meanwhile, the point of broken pile is nearest apart from house foundation, and disturbance is maximum.Static(al) measure should be used as possible, reduce shake It is dynamic, to the sedimentation in less house.
Before the 3. cut-out of number pilot tunnel stake, the pre-buried reinforcing bar connector more than open cut top plate.It is former after fender post is abolished Open cut reserves connector and is disclosed for out.Spreading reinforcing bar is connected in connector, then is connect with grid with reinforcing bar.
First branch is removed and two lining Construction controls
First branch removes the completion for being related to final structure system with two lining constructions, and during system transform, interim branch is removed by branch Support gradually replaces interim just branch structure with permanent lining, secondary lining.Dismounting few as possible, the method being supported in time are followed in construction. Branch structure at the beginning of 14.7 meters of direction being excavated abolishes point three sections of progress.Two lining structures of intermediate bin are first performed, the segment structure is 5 meters wide, 80~100cm waterproofs and structure are reserved per side get rid of stubble and be also required to the same period abolish.Both sides retain about 4m per side and just prop up.Two linings are using full Hall holder full framing and newly pours structure collective effect, forms new hold before two lining concrete structures are not up to design strength Power structure.
According to above step, when intermediate bin is constructed, structure base slab is performed, only the part for influencing bottom plate is abolished. The time is abolished in this way, on the one hand reducing, it is ensured that bottom plate performs in time, meanwhile, top does not abolish first branch structure and both sides The space concrete slab girder construction that concrete structure is formed, still has supporting role to top.Similarly, second step is abolished also only broken Except structure construction position is influenced, reduces just branch and remove to integrally-built decrease, guarantee construction safety can be played, protect house Effect.Just branch dismounting is walked in intermediate bin third to finish, and after the completion of structure construction, effective supporter is formd to house lower part System.After the completion of 5 meters of intermediate bin width, in addition just branch structure and pipe booth structure are to the expansion effect of lower support power on top, More effective supporting is formd to house foundation position.
In conclusion the more full cut and cover method of the present invention reduces removal, guarantee project progress, while housing demolition expense up to hundred million Member has saved construction investment;Maintain underground structure system constant, on ground function without influence;Reduce the amount of abolishing, reduces and build Building refuse and the wasting of resources;Reduce project cost.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention god.

Claims (9)

1. a kind of, using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, which is characterized in that including walking as follows Suddenly:
S1:Determine open cut and boring construction range and the separation of underground structure;
S2:The construction for carrying out open cut, specifically includes:
S2.1:The construction of open excavation section fender post;
S2.2:The construction of Guan Liang;
S2.3:The excavation and support of open excavation section foundation pit;
S2.4:After structure built by opencut method is constructed, it should be layered rammed earth, and carry out the backfill of the earthwork;
S3:Just branch construction and partial excavation construction are carried out on the node that open cut is reserved;
S4:First branch is removed, and water-proof system construction and the construction of two linings are started.
2. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It being characterized in that, step S2.1 goes along with sb. to guard him in pile driving construction, the construction of step S2.2 Guan Liangs and improves stake top absolute altitude, using concrete support, and When structure return build and backfill back-pressure.
3. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, just branch is formed to the top soil body using the double-deck long pipe shed in step S3.
4. it is according to claim 3 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, the trepanning in stake of alloy water drilling is applied before long pipe shed performs.
5. it is according to claim 4 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, pipe canopy is performed using auger bore, and is jumped hole when performing and performed, and is performed and is spaced in 5 holes or more, single hole pore-forming Afterwards, down tube slip casting immediately is filled.
6. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, Be characterized in that, in step S3, partial excavation construction specially first perform No.1 pilot tunnel and No. two pilot tunnels, then perform No. three pilot tunnels, No. four pilot tunnels, No. seven pilot tunnels and No. eight pilot tunnels, are completed at the same time abolishing for open cut fender post.
7. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, step S4 Zhong Chu Zhi Caiyong branches remove, and perform two linings in time after the dismounting of first branch, and two linings are using full hall branch Frame.
8. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, the first branch and bis- villages step S4 Zhong in step S3 are E font structures.
9. it is according to claim 1 it is a kind of using light and dark digging, upper object exempts from the method for building underground structure of removing in combination, It is characterized in that, the water-proof system in step S4 specifically includes:
S4.1:Open cut side wall uses bentonite waterproof blanket, and the waterproof layer of tunneling side is ECB splash guards;
S4.2:ECB splash guards use polyurethane coating film, and by ECB splash guards and the polyurethane coating film at top open cut part into Row overlap joint;
S4.3:It is laid with tunneling waterproof layer, the overlap joint of bentonite waterproof blanket and ECB splash guards should be carried out at this time, the lap of splice is not small In 20cm, ECB splash guards are crimped using bentonite, are pasted with bentonite fluid sealant between bentonite and ECB splash guards.
CN201810258016.0A 2018-03-27 2018-03-27 A method of exempt to remove using object in light and dark digging in combination and builds underground structure Pending CN108286266A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810258016.0A CN108286266A (en) 2018-03-27 2018-03-27 A method of exempt to remove using object in light and dark digging in combination and builds underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810258016.0A CN108286266A (en) 2018-03-27 2018-03-27 A method of exempt to remove using object in light and dark digging in combination and builds underground structure

Publications (1)

Publication Number Publication Date
CN108286266A true CN108286266A (en) 2018-07-17

Family

ID=62833915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810258016.0A Pending CN108286266A (en) 2018-03-27 2018-03-27 A method of exempt to remove using object in light and dark digging in combination and builds underground structure

Country Status (1)

Country Link
CN (1) CN108286266A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978673A (en) * 2018-07-23 2018-12-11 河南工业大学 A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN109056810A (en) * 2018-09-19 2018-12-21 中铁二院工程集团有限责任公司 The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN109322330A (en) * 2018-11-27 2019-02-12 成都市建筑设计研究院 A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN109736586A (en) * 2018-12-14 2019-05-10 成都市建筑设计研究院 A method of it abolishing existing underground station side wall and punches transformation
CN110080780A (en) * 2019-04-26 2019-08-02 中铁二十三局集团第六工程有限公司 A kind of rapid constructing method for urban underground space
CN110206549A (en) * 2019-05-15 2019-09-06 深圳市综合交通设计研究院有限公司 A kind of municipal traffic tunnel light and dark digging transformational structure and conversion construction method
CN110700378A (en) * 2019-06-11 2020-01-17 安徽省中功立业建设工程有限责任公司 Construction method for finished sewage pipe network under complex geological conditions
CN110984236A (en) * 2019-11-25 2020-04-10 中交二航局第三工程有限公司 Construction method for connecting point of sleeved type light and shade excavation structural portal interface
CN111456773A (en) * 2020-04-16 2020-07-28 成都市建筑设计研究院 Close-fitting open-and-underground excavation combined subway station structure and construction method thereof
CN111456087A (en) * 2020-04-23 2020-07-28 中铁二十局集团第五工程有限公司 Basement structure regional small-section earthwork excavation method
CN111550100A (en) * 2020-05-13 2020-08-18 北京中岩智泊科技有限公司 Construction method of underground excavation amplification type stereo garage
CN111749275A (en) * 2020-06-23 2020-10-09 中国建筑第二工程局有限公司 Cover-excavation top-down underground passage structure and construction method thereof
CN112507556A (en) * 2020-12-11 2021-03-16 中国石油大学(华东) Method for evaluating damage of building wall in blasting accident
CN113106979A (en) * 2021-04-13 2021-07-13 中铁十四局集团有限公司 Excavation method of upper cover foundation pit and construction method of upper cover added layer
CN114319437A (en) * 2022-01-05 2022-04-12 中铁十四局集团隧道工程有限公司 Construction method for building retaining wall structure at open-cut storey-adding vertical shaft by subsurface excavation
CN115162346A (en) * 2022-08-22 2022-10-11 中国新兴建设开发有限责任公司 Underground excavated underground passage and foundation pit row pile anchoring and connecting structure and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100701885B1 (en) * 2006-01-18 2007-03-30 주식회사 엠 Non-open cut pipe installation method
CN102758632A (en) * 2012-07-19 2012-10-31 中铁隧道集团有限公司 Rock stratum double initial support layering method for establishing large-scale underground structure
CN103939115A (en) * 2014-05-04 2014-07-23 北京市市政工程设计研究总院有限公司 Semi-subsurface excavation method construction shed tunnel method and structure
CN105386779A (en) * 2015-10-19 2016-03-09 北京城建设计发展集团股份有限公司 Arch column method for building large-scale underground structure in shallow buried rock stratums

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100701885B1 (en) * 2006-01-18 2007-03-30 주식회사 엠 Non-open cut pipe installation method
CN102758632A (en) * 2012-07-19 2012-10-31 中铁隧道集团有限公司 Rock stratum double initial support layering method for establishing large-scale underground structure
CN103939115A (en) * 2014-05-04 2014-07-23 北京市市政工程设计研究总院有限公司 Semi-subsurface excavation method construction shed tunnel method and structure
CN105386779A (en) * 2015-10-19 2016-03-09 北京城建设计发展集团股份有限公司 Arch column method for building large-scale underground structure in shallow buried rock stratums

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘鑫: ""地铁车站明暗挖交界部位防水综合施工技术"", 《建筑工程技术与设计》 *
姚少玉: ""明暗挖结合分离岛式车站临近高架桥桩施工技术研究"", 《建筑技术开发》 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978673A (en) * 2018-07-23 2018-12-11 河南工业大学 A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN109056810A (en) * 2018-09-19 2018-12-21 中铁二院工程集团有限责任公司 The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN109322330A (en) * 2018-11-27 2019-02-12 成都市建筑设计研究院 A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN109736586A (en) * 2018-12-14 2019-05-10 成都市建筑设计研究院 A method of it abolishing existing underground station side wall and punches transformation
CN110080780A (en) * 2019-04-26 2019-08-02 中铁二十三局集团第六工程有限公司 A kind of rapid constructing method for urban underground space
CN110206549A (en) * 2019-05-15 2019-09-06 深圳市综合交通设计研究院有限公司 A kind of municipal traffic tunnel light and dark digging transformational structure and conversion construction method
CN110700378A (en) * 2019-06-11 2020-01-17 安徽省中功立业建设工程有限责任公司 Construction method for finished sewage pipe network under complex geological conditions
CN110984236B (en) * 2019-11-25 2021-06-01 中交二航局第三工程有限公司 Construction method for connecting point of sleeved type light and shade excavation structural portal interface
CN110984236A (en) * 2019-11-25 2020-04-10 中交二航局第三工程有限公司 Construction method for connecting point of sleeved type light and shade excavation structural portal interface
CN111456773A (en) * 2020-04-16 2020-07-28 成都市建筑设计研究院 Close-fitting open-and-underground excavation combined subway station structure and construction method thereof
CN111456773B (en) * 2020-04-16 2024-05-24 成都市建筑设计研究院有限公司 Close-fitting type subway station structure combining light and shade excavation and construction method thereof
CN111456087A (en) * 2020-04-23 2020-07-28 中铁二十局集团第五工程有限公司 Basement structure regional small-section earthwork excavation method
CN111550100A (en) * 2020-05-13 2020-08-18 北京中岩智泊科技有限公司 Construction method of underground excavation amplification type stereo garage
CN111749275A (en) * 2020-06-23 2020-10-09 中国建筑第二工程局有限公司 Cover-excavation top-down underground passage structure and construction method thereof
CN112507556A (en) * 2020-12-11 2021-03-16 中国石油大学(华东) Method for evaluating damage of building wall in blasting accident
CN112507556B (en) * 2020-12-11 2022-04-08 中国石油大学(华东) Method for evaluating damage of building wall in blasting accident
CN113106979A (en) * 2021-04-13 2021-07-13 中铁十四局集团有限公司 Excavation method of upper cover foundation pit and construction method of upper cover added layer
CN113106979B (en) * 2021-04-13 2023-08-04 中铁十四局集团有限公司 Excavation method of upper cover foundation pit and construction method for upper cover storey addition
CN114319437A (en) * 2022-01-05 2022-04-12 中铁十四局集团隧道工程有限公司 Construction method for building retaining wall structure at open-cut storey-adding vertical shaft by subsurface excavation
CN115162346A (en) * 2022-08-22 2022-10-11 中国新兴建设开发有限责任公司 Underground excavated underground passage and foundation pit row pile anchoring and connecting structure and construction method thereof
CN115162346B (en) * 2022-08-22 2024-02-06 中国新兴建设开发有限责任公司 Underground excavation underground passage and foundation pit row pile anchoring connection structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN108286266A (en) A method of exempt to remove using object in light and dark digging in combination and builds underground structure
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN110080242A (en) The construction method of basement pile wall interaction structural system
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN107503755A (en) A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN109958445A (en) The frame construction method in Large Underground space is buried for an ultra shallow
CN109899087A (en) A kind of hole column tunneling is inverse to build underground structure and construction method
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN103015431A (en) Foundation pit supporting method for manual dig-hole cement-soil steel pile
CN108867723A (en) The method of frame structure building rectification and underground increasing layer
Powderham The observational method-application through progressive modification
CN207211188U (en) Outer wall of underground structure HCMW engineering methods overlap wall
CN113931637A (en) Shallow-buried water-rich softer rock tunnel construction method
CN210195766U (en) Underground structure is built in same direction as digging to hunch lid
CN110512649A (en) The excavating construction method of basement and communication channel structure is added under existing building
CN109024668A (en) A kind of construction method of multilayer subway station
CN209430204U (en) Anti- dash forward of one kind gushes back cover structure
CN207211187U (en) Outer wall of underground structure HCMW engineering method composite walls
CN207989047U (en) One kind secretly checking room equipment opening
Measor et al. FEATURES IN THE DESIGN AND CONSTRUCTION OF THE SHELL CENTRE, LONDON.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180717

RJ01 Rejection of invention patent application after publication