CN103821335A - High-altitude long-span cantilever formwork - Google Patents

High-altitude long-span cantilever formwork Download PDF

Info

Publication number
CN103821335A
CN103821335A CN201410072036.0A CN201410072036A CN103821335A CN 103821335 A CN103821335 A CN 103821335A CN 201410072036 A CN201410072036 A CN 201410072036A CN 103821335 A CN103821335 A CN 103821335A
Authority
CN
China
Prior art keywords
vertical rod
oblique vertical
support bar
cantilever beams
oblique
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410072036.0A
Other languages
Chinese (zh)
Inventor
斯勇
徐晓忠
陈志远
谢永章
廖小军
陆建飞
赵鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201410072036.0A priority Critical patent/CN103821335A/en
Publication of CN103821335A publication Critical patent/CN103821335A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a high-altitude long-span cantilever formwork which comprises a cantilever beam, wherein one end of the cantilever beam is connected with an embedded part on an upper-layer floor; a lower surface of a section of the cantilever beam extending out of the floor is connected with a first inclined vertical rod and a second inclined vertical rod; the lower ends of the first inclined vertical rod and the second inclined vertical rod are connected with each other and the joint is connected with the embedded part on a lower-layer floor; a plurality of supporting rods are arranged between the first inclined vertical rod and the second inclined vertical rod; a large triangular plane formed by the first inclined vertical rod, the second inclined vertical rod and the cantilever beam is cut into a plurality of small triangular planes by the supporting rods. The high-altitude long-span cantilever formwork has the advantages of short construction period, low cost, high rigidity and higher safety and stability.

Description

The high-altitude long-span mould bases of encorbelmenting
Technical field
The present invention relates to the high-altitude long-span mould bases of encorbelmenting.
Background technology
Overlength is corniced outward and mouthful is applied in architectural design, can build serious, simple and unsophisticated architectural style, is therefore deeply subject to liking of building designers.In work progress, need to use the cantilevered structure of large span as support, use common ground steel pipe scaffold as support system, long construction period, material cost is high, adopts steel pipe builder's jack as braced structures, and materials'use amount is relatively low, construct comparatively simple, but the rigidity of steel pipe builder's jack is less, less stable, cannot meet the construction requirement of large load.
Summary of the invention
Technical problem to be solved by this invention is just to provide a kind of high-altitude long-span mould bases of encorbelmenting, short construction period, and cost is low, greatly and more safety and stability of rigidity.
For solving the problems of the technologies described above, the present invention adopts following technical scheme:
The high-altitude long-span mould bases of encorbelmenting, comprise Cantilever Beams, described Cantilever Beams one end is connected with the built-in fitting of upper floor, described Cantilever Beams stretches out flooring section soffit and connects the first oblique vertical rod and the second oblique vertical rod, the described first oblique vertical rod interconnects with the lower end of the second oblique vertical rod and tie point is connected with the built-in fitting of lower floor flooring, between the described first oblique vertical rod and the second oblique vertical rod, be provided with several support bars, the large planar delta that described support bar forms the first oblique vertical rod and the second oblique vertical rod and Cantilever Beams is divided into several little planar deltas.
Preferably, the mid point that flooring section soffit is stretched out with Cantilever Beams respectively in the upper end of the described first oblique vertical rod and the second oblique vertical rod is connected with end points.
Preferably, described support bar comprises two transverse support bar and two vertical supporting bars, described transverse support bar left end is connected with the trisection point of the first oblique vertical rod, described transverse support bar right-hand member is connected with the trisection point of the second oblique vertical rod, and the upper and lower two ends of described vertical supporting bar are connected with the quadrangle diagonal angle that the first oblique vertical rod, the second oblique vertical rod form with transverse support bar respectively.
Preferably, described Cantilever Beams adopts 16# i iron, and the described first oblique vertical rod, the second oblique vertical rod and support bar adopt 12# i iron.
Preferably, described support bar both sides are respectively equipped with steel pipe, and described steel pipe two ends and support bar two ends are weldingly connected.
The present invention adopts technique scheme, the first oblique vertical rod and the second oblique vertical rod are set below Cantilever Beams as support bar, Cantilever Beams and the first oblique vertical rod, the second oblique vertical rod forms planar delta, structure is more stable, reinforce and be provided with support bar between the first oblique vertical rod and the second oblique vertical rod, the large planar delta that support bar further forms the first oblique vertical rod and the second oblique vertical rod and Cantilever Beams is again divided into several little planar deltas, further strengthened the encorbelmenting rigidity of mould bases, this mould bases of encorbelmenting can be processed as entirety in advance, lift afterwards to job site and reinforce, therefore can greatly shorten construction period.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the invention will be further described:
Fig. 1 is structural representation of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is elaborated.
As shown in Figure 1, the present invention includes Cantilever Beams 1, described Cantilever Beams one end is connected with the built-in fitting 2 of upper floor, described Cantilever Beams stretches out flooring section soffit and connects the first oblique vertical rod 301 and the second oblique vertical rod 302, the described first oblique vertical rod interconnects with the lower end of the second oblique vertical rod and tie point is connected with the built-in fitting of lower floor flooring, between the described first oblique vertical rod and the second oblique vertical rod, be provided with several support bars 4, the large planar delta that described support bar forms the first oblique vertical rod and the second oblique vertical rod and Cantilever Beams is divided into several little planar deltas.The mid point that flooring section soffit is stretched out with Cantilever Beams 1 respectively in the upper end of the described first oblique vertical rod 301 and the second oblique vertical rod 302 is connected with end points.Described support bar 4 comprises two transverse support bar 401 and two vertical supporting bars 402, described transverse support bar left end is connected with the trisection point of the first oblique vertical rod 301, described transverse support bar right-hand member is connected with the trisection point of the second oblique vertical rod 302, and described vertical supporting bar is connected with the quadrangle diagonal angle that the first oblique vertical rod, the second oblique vertical rod form with transverse support bar respectively at two ends Shang Xia 402.Described Cantilever Beams 1 adopts 16# i iron, and the described first oblique vertical rod 301, the second oblique vertical rod 302 and support bar 4 adopt 12# i iron.Described support bar 4 both sides are respectively equipped with steel pipe 5, and described steel pipe two ends and support bar two ends are weldingly connected.
Specific construction technique of the present invention, comprises the steps:
The present invention includes following steps:
Step 1, assembles the mould bases of encorbelmenting;
Step 2, floor is measured unwrapping wire built-in fitting is set;
Step 3, lifts the mould bases of encorbelmenting;
Step 4, formwork erection;
Step 5, load test.
Assemble the mould bases of encorbelmenting, according to the Mold Base Design figure that encorbelments, successively by the first oblique vertical rod and the second oblique vertical rod and Cantilever Beams bottom welding, afterwards the first oblique vertical rod and the second oblique vertical rod are welded as a whole, then measure and draw trisection point in the first oblique vertical rod and the second oblique vertical rod, welding afterwards support bar and the support bar both sides steel pipe for reinforcing, can there is not out-of-plane distortion in the mould bases of guaranteeing to encorbelment.
When floor measurement unwrapping wire arranges built-in fitting, on floor face, eject line of ink marker full-size drawing according to floor height and cantilever span, and on upper and lower two layers of floor embedding built-in fitting, built-in fitting is selected Ф 25 reinforcing bars, at the embedding round steel anchor ring of upper floor, and make round steel anchor ring and built-in fitting be positioned at same plane.
When mould bases is encorbelmented in lifting, lift by tower crane the mould bases of encorbelmenting, floor face 2m is stretched into in the Cantilever Beams one end of encorbelmenting on mould bases, then anchor in floor with Ф 20 round steel anchor rings at Cantilever Beams 0.4m, 1.4m place, Cantilever Beams bottom and diagonal member lower end and the built-in fitting of encorbelmenting on mould bases are weldingly connected.
When formwork erection, set up scaffold floor on the mould bases top of encorbelmenting, on scaffold floor, lay wooden springboard.
When load test, on template, do loading test step by step, load is pressed least favorable place and is considered, get respectively 80%, 100%, 120% of its design load and carry out loading test, the every step of loading test is carried out 2 hours, in the outermost of eaves board and the outermost of truss, observation point is set respectively, and compares with the original point being located on frame column, whether observation deformation values exceedes design load.

Claims (5)

1. the high-altitude long-span mould bases of encorbelmenting, it is characterized in that: comprise Cantilever Beams (1), described Cantilever Beams one end is connected with the built-in fitting (2) of upper floor, described Cantilever Beams stretches out flooring section soffit and connects the first oblique vertical rod (301) and the second oblique vertical rod (302), the described first oblique vertical rod interconnects with the lower end of the second oblique vertical rod and tie point is connected with the built-in fitting of lower floor flooring, between the described first oblique vertical rod and the second oblique vertical rod, be provided with several support bars (4), the large planar delta that described support bar forms the first oblique vertical rod and the second oblique vertical rod and Cantilever Beams is divided into several little planar deltas.
2. the high-altitude long-span according to claim 1 mould bases of encorbelmenting, is characterized in that: the mid point that flooring section soffit is stretched out with Cantilever Beams (1) respectively in the upper end of the described first oblique vertical rod (301) and the second oblique vertical rod (302) is connected with end points.
3. the high-altitude long-span according to claim 1 mould bases of encorbelmenting, it is characterized in that: described support bar (4) comprises two transverse support bar (401) and two vertical supporting bars (402), described transverse support bar left end is connected with the trisection point of the first oblique vertical rod (301), described transverse support bar right-hand member is connected with the trisection point of the second oblique vertical rod (302), and the upper and lower two ends of described vertical supporting bar (402) are connected with the quadrangle diagonal angle that the first oblique vertical rod, the second oblique vertical rod form with transverse support bar respectively.
4. the high-altitude long-span according to claim 1 mould bases of encorbelmenting, is characterized in that: described Cantilever Beams (1) adopts 16# i iron, the described first oblique vertical rod (301), the second oblique vertical rod (302) and support bar (4) employing 12# i iron.
5. the high-altitude long-span according to claim 3 mould bases of encorbelmenting, is characterized in that: described support bar (4) both sides are respectively equipped with steel pipe (5), and described steel pipe two ends and support bar two ends are weldingly connected.
CN201410072036.0A 2014-02-28 2014-02-28 High-altitude long-span cantilever formwork Pending CN103821335A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410072036.0A CN103821335A (en) 2014-02-28 2014-02-28 High-altitude long-span cantilever formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410072036.0A CN103821335A (en) 2014-02-28 2014-02-28 High-altitude long-span cantilever formwork

Publications (1)

Publication Number Publication Date
CN103821335A true CN103821335A (en) 2014-05-28

Family

ID=50756600

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410072036.0A Pending CN103821335A (en) 2014-02-28 2014-02-28 High-altitude long-span cantilever formwork

Country Status (1)

Country Link
CN (1) CN103821335A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119904A (en) * 2017-05-26 2017-09-01 中国十七冶集团有限公司 A kind of cantilevered structure truss combined support system
CN111042508A (en) * 2019-11-29 2020-04-21 中国建筑第四工程局有限公司 High-altitude overlong cantilever support member and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040216392A1 (en) * 1997-05-16 2004-11-04 Preston John Clement Partly retractable construction platform
CN101736893A (en) * 2009-12-16 2010-06-16 通广建工集团有限公司 Overhanging type scaffold supporting system
CN202689491U (en) * 2012-06-27 2013-01-23 江苏正威建设有限公司 Lower supporting type overhanging scaffold
CN203701549U (en) * 2014-02-28 2014-07-09 中天建设集团有限公司 High-altitude large-span cantilever formwork

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040216392A1 (en) * 1997-05-16 2004-11-04 Preston John Clement Partly retractable construction platform
CN101736893A (en) * 2009-12-16 2010-06-16 通广建工集团有限公司 Overhanging type scaffold supporting system
CN202689491U (en) * 2012-06-27 2013-01-23 江苏正威建设有限公司 Lower supporting type overhanging scaffold
CN203701549U (en) * 2014-02-28 2014-07-09 中天建设集团有限公司 High-altitude large-span cantilever formwork

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
BAIFAN711: "《21高空大跨度悬挑模架设计施工技术总结》", 《百度文库》, 15 August 2013 (2013-08-15) *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107119904A (en) * 2017-05-26 2017-09-01 中国十七冶集团有限公司 A kind of cantilevered structure truss combined support system
CN111042508A (en) * 2019-11-29 2020-04-21 中国建筑第四工程局有限公司 High-altitude overlong cantilever support member and construction method thereof

Similar Documents

Publication Publication Date Title
CN109056548B (en) Steel arch construction method
CN107090932B (en) Construction method of large-span thin-wall plane arch truss based on stiff ring beam
CN102535845A (en) Construction method of bearing frame of corridor structure
CN101148861A (en) Beret truss type hanging basket and assembling method thereof
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN107571392B (en) A kind of beam making bench for the construction of transverse tensioning method prestressing force prefabricated small box girder
CN104480922B (en) Space truss formwork system and construction method thereof
CN106854941B (en) A kind of construction method of big section Stand Inclined Beams and batter post
CN203701549U (en) High-altitude large-span cantilever formwork
CN105442853B (en) A kind of long-span deformed Elements of Space Grid Truss and landing Steel Structure Installation construction method
CN203961281U (en) Steel bar girder beam form frame and H section steel beam-cast-in-place concrete floor formwork system
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN103821360A (en) Construction method for high-altitude long-span cantilever formwork
CN106150525A (en) A kind of rock anchorage beam construction trolley and construction method thereof
CN106320183A (en) Assembly type bent cap formwork system
CN103821335A (en) High-altitude long-span cantilever formwork
CN205875740U (en) Standardized batter brace system of structure of encorbelmenting greatly construction die carrier
CN210140771U (en) Construction work platform hoisting frame of high mound of bridge
CN104404883A (en) Inner working platform for rapid construction of bridge pier and construction method using inner working platform
CN107178037A (en) The outer frame connecting structure of trestle vase-shaped column-type pier pier shaft and its construction technology
CN216786863U (en) Cast-in-place box girder 0# block template system
CN102995560A (en) Thin-wall hollow pier lifting frame and use method thereof
CN206111212U (en) Rock -anchored beam construction trolley car
CN105370027A (en) Construction method for integrally lifted and supported steel platform structure in high-rise suspended structure
CN205444935U (en) Special -shaped steel space frame construction and installation structure of complicated large -span department

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140528