CN205875740U - Standardized batter brace system of structure of encorbelmenting greatly construction die carrier - Google Patents

Standardized batter brace system of structure of encorbelmenting greatly construction die carrier Download PDF

Info

Publication number
CN205875740U
CN205875740U CN201620872984.7U CN201620872984U CN205875740U CN 205875740 U CN205875740 U CN 205875740U CN 201620872984 U CN201620872984 U CN 201620872984U CN 205875740 U CN205875740 U CN 205875740U
Authority
CN
China
Prior art keywords
steel
channel
section
section steel
angle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620872984.7U
Other languages
Chinese (zh)
Inventor
门贤君
曾文
黄晓彬
王宇浩
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201620872984.7U priority Critical patent/CN205875740U/en
Application granted granted Critical
Publication of CN205875740U publication Critical patent/CN205875740U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to an architectural engineering technology field, concretely relates to standardized batter brace system of structure of encorbelmenting greatly construction die carrier, it includes that I -steel, first channel -section steel, second channel -section steel, T shape angle steel, steel sheet connecting piece, angle cleat, the anchor of I -steel U -loop bury piece, steel tube frame underlay square steel, truss vaulting pole anchor angle steel, I -steel connecting piece, hoisting ring, I -steel one end is connected with the anchor of I -steel U -loop and buries the piece, the I -steel top is equipped with the hoisting ring, through the butt joint of I -steel connecting piece between the I -steel, connect through T shape angle steel between I -steel and the first channel -section steel, first channel -section steel passes through the steel sheet connecting piece and the second channel -section steel is connected, the utility model relates to a standardized batter brace system of structure of encorbelmenting greatly construction die carrier, it utilizes the advantage of truss -like member, makes characteristic of materials obtain better utilization, can select the shaped steel of small bore for use, can practice thrift steel in a large number than single shaped steel bracing formula, and can all select normalized member for use, but the independent assortment satisfy different floor heights, difference and encorbelment the die carrier of size and support the demand, be convenient for have enough to meet the need reuse.

Description

A kind of long cantilever construction construction mould bases standardization batter brace system
Technical field
This utility model relates to construction engineering technical field, is specifically related to a kind of long cantilever construction construction mould bases standardization purlin Frame diagonal brace system.
Background technology
Construction high and medium large cantilever concrete structure construction, common process mainly has console model full hall bracing frame, list Root type steel inclined strut type suspension supporting beam supports, and console model bracing frame should not use because excessively wasting with material, and shaped steel diagonal-bracing type is not because of can yet Meeting different floor height and span demand, belong to disposable input, and need heavy in section section bar, economy is the highest.
Summary of the invention
The purpose of this utility model is the defect for prior art and deficiency, it is provided that a kind of simple in construction, and design is closed Reason, a kind of long cantilever construction easy to use construction mould bases standardization batter brace system, it include I-steel, the first channel-section steel, Second channel-section steel, T-shaped angle steel, steel plate connector, angle cleat, I-steel U-loop anchoring embedded part, steel tube frame underlay square steel, Truss stay rod anchoring angle steel, I-steel connector, hoisting ring;I-steel one end connects has I-steel U-loop to anchor embedded part;I-shaped Steel is arranged over hoisting ring and steel tube frame underlay square steel;Docked by I-steel connector between I-steel;I-steel and By T-shaped Bolted angle connection between first channel-section steel;First channel-section steel is connected by steel plate connector and the second channel-section steel;Angle cleat is positioned at On first channel-section steel;Truss stay rod anchoring angle steel is positioned at bottom the first channel-section steel.
After using said structure, this utility model has the beneficial effect that a kind of long cantilever construction described in the utility model is executed Work mould bases standardization batter brace system, it utilizes the advantage of truss-like rod member, makes material property preferably be utilized, optional With the shaped steel of small bore, the single shaped steel diagonal-bracing type of ratio can a large amount of saving steels, and can the rod member of all selection standards, can free group Close, meet different floor heights, the encorbelment mould bases of size of difference supports demand, it is simple to turnover recycling.
Accompanying drawing explanation
Accompanying drawing described herein is used to offer and is further appreciated by of the present utility model, constitutes of the application Point, but it is not intended that improper restriction of the present utility model, in the accompanying drawings:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the enlarged drawing of part A in Fig. 1;
Fig. 3 is the enlarged drawing of part B in Fig. 1;
Description of reference numerals:
1-I-steel, 2-the first channel-section steel, 3-the second channel-section steel, 4-T shape angle steel, 5-steel plate connector, 6-angle cleat, 7-work Word steel U-loop anchoring embedded part, 8-steel tube frame underlay square steel, 9-truss stay rod anchoring angle steel, 10-I-steel connector, 11- Hoisting ring, 2-1 the first channel-section steel fixed screw holes, 3-1 the second channel-section steel fixed screw holes, 4-1T shape angle steel fixed screw holes, 5-1 steel Plate connector fixed screw holes.
Detailed description of the invention
Describe this utility model in detail below in conjunction with accompanying drawing and specific embodiment, illustrative examples therein with And explanation is only used for explaining this utility model, but it is not intended as restriction of the present utility model.
As it can be seen, a kind of long cantilever construction construction mould bases standardization batter brace body described in this detailed description of the invention System, it includes I-steel the 1, first channel-section steel the 2, second channel-section steel 3, T-shaped angle steel 4, steel plate connector 5, angle cleat 6, I-steel U-shaped Ring anchoring embedded part 7, steel tube frame underlay square steel 8, truss stay rod anchoring angle steel 9, I-steel connector 10, hoisting ring 11;Work Word steel 1 one end connects has I-steel U-loop to anchor embedded part 7;I-steel 1 is arranged over hoisting ring 11 and steel tube frame underlay side Steel 8;Docked by I-steel connector 10 between I-steel 1;Connected by T-shaped angle steel 4 between I-steel 1 and the first channel-section steel 2; First channel-section steel 2 is connected by steel plate connector 5 and the second channel-section steel 3;Angle cleat 6 is positioned on the first channel-section steel 2;Truss stay rod anchors Angle steel position 9 is bottom the first channel-section steel 2.
Further: described first channel-section steel 2 two ends are equipped with the first channel-section steel fixed screw holes 2-1.
Further: described second channel-section steel 3 two ends are equipped with the second channel-section steel fixed screw holes 3-1.
Further: the lower plate of described T-shaped angle steel 4 is provided with T-shaped angle steel fixed screw holes 4-1.
Further: described steel plate connector 5 is provided with steel plate connector fixed screw holes 5-1.
First channel-section steel the 2, second channel-section steel 3, between T-shaped angle steel 4 and steel plate connector 5 all by the screw being each provided with Hole, is fixed with screw;I-steel U-loop anchoring embedded part 7 and truss stay rod anchoring angle steel 9 are embedded in design attitude in advance; Steel tube frame underlay square steel 8 is for building the steel pipe above I-steel.
Installation method
1, pre-buried embedded part is installed in next layer of beam slab of cantilevered structure;
2, channel-section steel, I-steel are carried out assembly on ground, become the truss of a whole Pin;
3, utilize the hoisting ring arranged on I-steel, lift whole truss structure with tower crane, install in high-altitude;
5, the spacing short I-steel of I-steel afterbody is installed, by truss stay rod and ground anchoring Bolted angle connection, check steady Solidity.
6, square steel under steel tube frame is installed, bracing frame steel pipe, installation form system, examination are installed.
A kind of long cantilever construction construction mould bases standardization batter brace system described in the utility model, it utilizes truss-like The advantage of rod member, makes material property preferably be utilized, and can be selected for the shaped steel of small bore, can be a large amount of than single shaped steel diagonal-bracing type Saving steel, and can the rod member of all selection standards, can independent assortment, meet different floor heights, the encorbelment mould bases of size of difference props up Support demand, it is simple to turnover recycling.
The above is only better embodiment of the present utility model, therefore all according to described in this utility model patent claim Structure, feature and principle done equivalence change or modify, be all included in this utility model patent claim.

Claims (5)

1. long cantilever construction construction mould bases standardization batter brace system, it is characterised in that: it include I-steel (1), the The anchoring of one channel-section steel (2), the second channel-section steel (3), T-shaped angle steel (4), steel plate connector (5), angle cleat (6), I-steel U-loop is buried Part (7), steel tube frame underlay square steel (8), truss stay rod anchoring angle steel (9), I-steel connector (10), hoisting ring (11); I-steel (1) one end connects I-steel U-loop anchoring embedded part (7);I-steel (1) is arranged over hoisting ring (11) and steel pipe props up Support underlay square steel (8);Docked by I-steel connector (10) between I-steel (1);I-steel (1) and the first channel-section steel (2) Between by T-shaped angle steel (4) connect;First channel-section steel (2) is connected by steel plate connector (5) and the second channel-section steel (3);Angle cleat (6) it is positioned on the first channel-section steel (2);Truss stay rod anchoring angle steel position (9) is in the first channel-section steel (2) bottom.
A kind of long cantilever construction construction mould bases standardization batter brace system the most according to claim 1, it is characterised in that: Described first channel-section steel (2) two ends are equipped with the first channel-section steel fixed screw holes (2-1).
A kind of long cantilever construction construction mould bases standardization batter brace system the most according to claim 1, it is characterised in that: Described second channel-section steel (3) two ends are equipped with the second channel-section steel fixed screw holes (3-1).
A kind of long cantilever construction construction mould bases standardization batter brace system the most according to claim 1, it is characterised in that: The lower plate of described T-shaped angle steel (4) is provided with T-shaped angle steel fixed screw holes (4-1).
A kind of long cantilever construction construction mould bases standardization batter brace system the most according to claim 1, it is characterised in that: Described steel plate connector (5) is provided with steel plate connector fixed screw holes (5-1).
CN201620872984.7U 2016-08-13 2016-08-13 Standardized batter brace system of structure of encorbelmenting greatly construction die carrier Expired - Fee Related CN205875740U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620872984.7U CN205875740U (en) 2016-08-13 2016-08-13 Standardized batter brace system of structure of encorbelmenting greatly construction die carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620872984.7U CN205875740U (en) 2016-08-13 2016-08-13 Standardized batter brace system of structure of encorbelmenting greatly construction die carrier

Publications (1)

Publication Number Publication Date
CN205875740U true CN205875740U (en) 2017-01-11

Family

ID=57702766

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620872984.7U Expired - Fee Related CN205875740U (en) 2016-08-13 2016-08-13 Standardized batter brace system of structure of encorbelmenting greatly construction die carrier

Country Status (1)

Country Link
CN (1) CN205875740U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108593332A (en) * 2018-06-29 2018-09-28 机械科学研究总院海西(福建)分院有限公司 Automatic sampling machine people, bar automatic sampling equipment and sampling method comprising it
CN109898821A (en) * 2019-03-21 2019-06-18 陕西建工第九建设集团有限公司 A kind of construction method of high-altitude overhanging template support frame body
CN110700543A (en) * 2019-10-16 2020-01-17 上海建工一建集团有限公司 Steel truss inclined strut system structure with section steel cantilever and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108593332A (en) * 2018-06-29 2018-09-28 机械科学研究总院海西(福建)分院有限公司 Automatic sampling machine people, bar automatic sampling equipment and sampling method comprising it
CN109898821A (en) * 2019-03-21 2019-06-18 陕西建工第九建设集团有限公司 A kind of construction method of high-altitude overhanging template support frame body
CN109898821B (en) * 2019-03-21 2019-12-17 陕西建工第九建设集团有限公司 Construction method of high-altitude cantilever formwork support frame body
CN110700543A (en) * 2019-10-16 2020-01-17 上海建工一建集团有限公司 Steel truss inclined strut system structure with section steel cantilever and construction method thereof

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN104929373B (en) Large span Square Steel Tubes Truss and its accumulation slippage construction method
CN105569358A (en) Construction method of special-shaped curved surface roof with large span and multiple curvatures
CN208734119U (en) A kind of steel pipe column and Bailey beam combined type load-carrying members
CN203947771U (en) A kind of Bailey beam pendent form support system
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN104453197A (en) High-altitude large-cantilever concrete structure structural steel supporting platform
CN205875740U (en) Standardized batter brace system of structure of encorbelmenting greatly construction die carrier
CN214062435U (en) Support system for high-altitude ultra-long cantilever structure
CN105003090A (en) Temporary support frame for mounting assembly type steel structure
CN212053673U (en) Tower construction operation platform of dome
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN111218987A (en) Bearing type net rack construction method
CN205444975U (en) Large -scale room lid steel construction construction braced system with view platform
CN202401769U (en) Detachable concrete cloth machine for self-elevating creeping formwork system
CN206722428U (en) A kind of building roof lighting Zhongting steel construction jacking apparatus
CN204876631U (en) Assembled steel structure installation uses interim support frame
CN111155759A (en) Novel unit truss type concrete frame structure formwork supporting system and construction method thereof
CN104264781B (en) Latticed cylinder Steel Shell and construction method thereof
CN103758342A (en) Tool-type top form for buildings
CN106988520B (en) Construction method and support system for high-rise suspension structure
CN105464215A (en) Reverse construction method construction method of hanging structure incapable of being provided with vertical temporary support
CN215212427U (en) Adjustable unloading platform with steel structure for building
CN202347884U (en) Overhaul platform for water turbine

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170111

Termination date: 20210813

CF01 Termination of patent right due to non-payment of annual fee