CN103510523B - 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法 - Google Patents

深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法 Download PDF

Info

Publication number
CN103510523B
CN103510523B CN201310504479.8A CN201310504479A CN103510523B CN 103510523 B CN103510523 B CN 103510523B CN 201310504479 A CN201310504479 A CN 201310504479A CN 103510523 B CN103510523 B CN 103510523B
Authority
CN
China
Prior art keywords
brace summer
monitoring
cutting
cut
foundation ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310504479.8A
Other languages
English (en)
Other versions
CN103510523A (zh
Inventor
何金城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
He Jincheng
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310504479.8A priority Critical patent/CN103510523B/zh
Publication of CN103510523A publication Critical patent/CN103510523A/zh
Application granted granted Critical
Publication of CN103510523B publication Critical patent/CN103510523B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法,包括内力监测、切割拆除、基坑内转运、支撑梁整体吊运、支撑梁场外破碎等步骤。本发明在地下水平薄板结构上施工,对施工平台没有特殊要求,不需要对地下薄板结构钢管支撑***进行加强处理,仅需对地下水平薄板预留洞口和预留伸缩缝位置进行局部加强处理。并且支撑梁切割拆除时,下部不需搭设钢管支架。现场钢管支架材料一次投入量大量减少,并可提前拆除提高钢管支架周转率。

Description

深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法
技术领域
本发明涉及一种深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法。
背景技术
近年来,伴随着城市高速发展、人口密度增长,城市建筑不断朝着高深两面发展,高层建筑成为城市建设的主旋律,相应多层地下室、地下隧道、地铁、商业街等配套的建立,使待建工程常常邻近高层建筑或地下构筑物等,建筑周边环境的复杂使基坑锚杆锚索支护体系的使用受到了限制,“支护桩或连续墙+内支撑”支护体系代之在近年来得到大量应用,尤其以钢筋混凝土内支撑为主,大大提高了深基坑的稳定性。并且随着地下深度的增加,内支撑的层数也从一层支撑增加到多层支撑。
常用的混凝土支撑梁拆除方法有火药***拆除、机械拆除、人工拆除等。而作为临时支撑结构,因其多处于城市闹市区,周围或建筑物密集,或临近运营地铁,临时支撑结构拆除必须确保不对临时支撑体系、周边建筑、地下设施造成不利影响。而多层内支撑梁拆除施工时往往是借助已施工的地下水平结构作为施工平台,这就对拆除方法也提出更高的挑战。
发明内容
本发明的目的在于提供一种施工工期短,对地下水平永久结构要求低,施工成本低的深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法。
本发明的技术解决方案是:
一种深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法,其特征是:包括下列步骤:
(一)内力监测
在拆除内支撑结构前以及整个拆除过程中进行内力监测,首先是对基坑位移和内支撑梁的内力监测,根据检测结果得出内力分布情况,卸荷时根据内力分布情况均匀卸荷;
在拆除过程中对以下部位进行重点监测:
⑴坑外地下水位监测:采用钢尺水位计在预先布置的水位观测井进行监测;
⑵地面沉降监测:用水准仪,标尺在布置好的基点上进行监测,用本次监测标高减去上次标高为本次沉降量,减去初始标高为累计沉降量;
⑶支护桩桩顶沉降和水平位移监测:在支护桩顶设置测点,在远离基坑位置设置基准点,用水准仪和标尺进行监测;
⑷支护桩深层水平位移监测:用测斜仪,预埋测斜管内壁有两组90 度的纵向导槽,导槽控制测斜方位,测试时,测斜仪探头沉至孔底,在温度稳定后,自下而上逐段测出位移;
⑸内支撑轴力监测:将混凝土应变计埋设在内支撑梁钢筋间隙处,固定好后用线缆仔细引出,放在预先做好的线盒内,用频率读数仪进行监测;
⑹支撑立柱桩沉降监测:用水准仪在立柱桩设置的基点上进行监测;
⑺围护桩内力监测:将钢筋计焊接在钻孔支护桩主筋上进行预埋,用频率读数仪进行监测;
⑻周边建筑物沉降位移监测:用水准仪在设置好的基点上进行监测;
(二)切割拆除
切割卸荷
用绳锯切割机将支撑体系中联系梁、主梁切断卸荷,两组同时对称作业,保持结构换撑平稳过渡;
切割拆除
⑴根据支撑梁拆除顺序,在待拆支撑梁上画好切割线;
⑵支撑梁下方安装平板车并用锲型木刹块固定车轮;如下方结构有预留孔洞,采用钢结构平台板铺设;
⑶固定绳锯机:在正对着支撑梁切割线位置固定好绳锯机,绳锯机与待拆支撑梁呈垂直状态;
⑷安装绳索:将金刚石绳索缠绕在主动轮及辅助轮上,并在支撑梁上画好的切割线位置缠绕好,调试绳锯机及金刚石绳索,使金刚石绳索收紧;
⑸切割卸载:在切割前对金刚石绳锯机进行试转和空转,确定设备运转、水源供应正常的情况下,再进行切割;采用对称方式对支撑梁进行切割卸载;
⑹在基坑支撑应力释放后基坑各项数据监测稳定的情况下切割分段支撑梁;
(三)基坑内转运
⑴在地下水平永久结构薄弱部位铺设已经制作完成的钢结构平台,确保平板车通过时结构薄弱部位不受荷载而产生裂缝;
⑵在基坑侧壁固定卷扬机,并在运输路线弯折部位固定转向滑轮;
⑶支撑梁切割完成后,支撑梁切割分段平稳地落于平板车上,拆出用于固定平板车的锲型木刹块,用卷扬机水平牵引平板车至吊机起吊半径以内;
(四)支撑梁整体吊运
⑴在基坑侧壁可以架设吊机的一侧部位架设起吊吊机;
⑵将转运至基坑边起吊半径内的支撑梁切割段采用钢丝绳绑扎固定;
⑶吊机支撑梁切割段采用钢丝绳吊运至基坑外运输车辆上运出工地;
(五)支撑梁场外破碎
支撑梁切割段运输至避免靠近居民区和市中心集中的场地外指定位置;在指定位置采用降尘措施集中破碎。
本发明在地下水平薄板结构上施工,对施工平台没有特殊要求,不需要对地下薄板结构钢管支撑***进行加强处理,仅需对地下水平薄板预留洞口和预留伸缩缝位置进行局部加强处理。并且支撑梁切割拆除时,下部不需搭设钢管支架。现场钢管支架材料一次投入量大量减少,并可提前拆除提高钢管支架周转率。支撑梁采用绳锯机分段切割方式,避免重载机械和拆除混凝土渣对水平结构超负荷导致的结构裂缝,且分段切割有效控制每个切割段的荷载对水平结构影响。同时对局部铺设钢平台保护水平结构的薄弱部位,确保了水平结构各个部位的质量控制。支撑梁分段切割,采用自制平板车转运至可吊运的基坑边缘,减小基坑边吊机起吊半径和吊机移位次数,且保证吊机无法靠近的部位的支撑梁切割,从而确保基坑边可架设小吨位吊机保证了基坑安全稳定。支撑梁采用整体吊运方式,大大缩短基坑内的支撑梁拆除的混凝土渣清理时间,并且基坑边吊机仅做流水起吊作业,加快施工节奏,节省工期。支撑梁分段切割降低了劳动强度,操作安全可靠,动力强劲,提高了切割能力和劳动生产率。施工过程噪音低、无粉尘、操作简便绿色环保。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法,其特征是:包括下列步骤:
(一)内力监测
在拆除内支撑结构前以及整个拆除过程中进行内力监测,首先是对基坑位移和内支撑梁的内力监测,根据检测结果得出内力分布情况,卸荷时根据内力分布情况均匀卸荷;
在拆除过程中对以下部位进行重点监测:
⑴坑外地下水位监测:采用钢尺水位计在预先布置的水位观测井进行监测;
⑵地面沉降监测:用水准仪,标尺在布置好的基点上进行监测,用本次监测标高减去上次标高为本次沉降量,减去初始标高为累计沉降量;
⑶支护桩桩顶沉降和水平位移监测:在支护桩顶设置测点,在远离基坑位置设置基准点,用水准仪和标尺进行监测;
⑷支护桩深层水平位移监测:用测斜仪,预埋测斜管内壁有两组90 度的纵向导槽,导槽控制测斜方位,测试时,测斜仪探头沉至孔底,在温度稳定后,自下而上逐段测出位移;
⑸内支撑轴力监测:将混凝土应变计埋设在内支撑梁钢筋间隙处,固定好后用线缆仔细引出,放在预先做好的线盒内,用频率读数仪进行监测;
⑹支撑立柱桩沉降监测:用水准仪在立柱桩设置的基点上进行监测;
⑺围护桩内力监测:将钢筋计焊接在钻孔支护桩主筋上进行预埋,用频率读数仪进行监测;
⑻周边建筑物沉降位移监测:用水准仪在设置好的基点上进行监测;
(二)切割拆除
切割卸荷
用绳锯切割机将支撑体系中联系梁、主梁切断卸荷,两组同时对称作业,保持结构换撑平稳过渡;
切割拆除
⑴根据支撑梁拆除顺序,在待拆支撑梁上画好切割线;
⑵支撑梁下方安装平板车并用锲型木刹块固定车轮;如下方结构有预留孔洞,采用钢结构平台板铺设;
⑶固定绳锯机:在正对着支撑梁切割线位置固定好绳锯机,绳锯机与待拆支撑梁呈垂直状态;
⑷安装绳索:将金刚石绳索缠绕在主动轮及辅助轮上,并在支撑梁上画好的切割线位置缠绕好,调试绳锯机及金刚石绳索,使金刚石绳索收紧;
⑸切割卸载:在切割前对金刚石绳锯机进行试转和空转,确定设备运转、水源供应正常的情况下,再进行切割;采用对称方式对支撑梁进行切割卸载;
⑹在基坑支撑应力释放后基坑各项数据监测稳定的情况下切割分段支撑梁;
(三)基坑内转运
⑴在地下水平永久结构薄弱部位铺设已经制作完成的钢结构平台,确保平板车通过时结构薄弱部位不受荷载而产生裂缝;
⑵在基坑侧壁固定卷扬机,并在运输路线弯折部位固定转向滑轮;
⑶支撑梁切割完成后,支撑梁切割分段平稳地落于平板车上,拆出用于固定平板车的锲型木刹块,用卷扬机水平牵引平板车至吊机起吊半径以内;
(四)支撑梁整体吊运
⑴在基坑侧壁可以架设吊机的一侧部位架设起吊吊机;
⑵将转运至基坑边起吊半径内的支撑梁切割段采用钢丝绳绑扎固定;
⑶吊机支撑梁切割段采用钢丝绳吊运至基坑外运输车辆上运出工地;
(五)支撑梁场外破碎
支撑梁切割段运输至避免靠近居民区和市中心集中的场地外指定位置;在指定位置采用降尘措施集中破碎。

Claims (1)

1.一种深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法,其特征是:包括下列步骤:
(一)内力监测
在拆除内支撑结构前以及整个拆除过程中进行内力监测,首先是对基坑位移和内支撑梁的内力监测,根据检测结果得出内力分布情况,卸荷时根据内力分布情况均匀卸荷;
在拆除过程中对以下部位进行重点监测:
⑴坑外地下水位监测:采用钢尺水位计在预先布置的水位观测井进行监测;
⑵地面沉降监测:用水准仪,标尺在布置好的基点上进行监测,用本次监测标高减去上次标高为本次沉降量,减去初始标高为累计沉降量;
⑶支护桩桩顶沉降和水平位移监测:在支护桩顶设置测点,在远离基坑位置设置基准点,用水准仪和标尺进行监测;
⑷支护桩深层水平位移监测:用测斜仪,预埋测斜管内壁有两组90度的纵向导槽,导槽控制测斜方位,测试时,测斜仪探头沉至孔底,在温度稳定后,自下而上逐段测出位移;
⑸内支撑轴力监测:将混凝土应变计埋设在内支撑梁钢筋间隙处,固定好后用线缆仔细引出,放在预先做好的线盒内,用频率读数仪进行监测;
⑹支撑立柱桩沉降监测:用水准仪在立柱桩设置的基点上进行监测;
⑺围护桩内力监测:将钢筋计焊接在钻孔支护桩主筋上进行预埋,用频率读数仪进行监测;
⑻周边建筑物沉降位移监测:用水准仪在设置好的基点上进行监测;
(二)切割拆除
切割卸荷
用绳锯切割机将支撑体系中联系梁、主梁切断卸荷,两组同时对称作业,保持结构换撑平稳过渡;
切割拆除
⑴根据支撑梁拆除顺序,在待拆支撑梁上画好切割线;
⑵支撑梁下方安装平板车并用锲型木刹块固定车轮;如下方结构有预留孔洞,采用钢结构平台板铺设;
⑶固定绳锯机:在正对着支撑梁切割线位置固定好绳锯机,绳锯机与待拆支撑梁呈垂直状态;
⑷安装绳索:将金刚石绳索缠绕在主动轮及辅助轮上,并在支撑梁上画好的切割线位置缠绕好,调试绳锯机及金刚石绳索,使金刚石绳索收紧;
⑸切割卸载:在切割前对金刚石绳锯机进行试转和空转,确定设备运转、水源供应正常的情况下,再进行切割;采用对称方式对支撑梁进行切割卸载;
⑹在基坑支撑应力释放后基坑各项数据监测稳定的情况下切割分段支撑梁;
(三)基坑内转运
⑴在地下水平永久结构薄弱部位铺设已经制作完成的钢结构平台,确保平板车通过时结构薄弱部位不受荷载而产生裂缝;
⑵在基坑侧壁固定卷扬机,并在运输路线弯折部位固定转向滑轮;
⑶支撑梁切割完成后,支撑梁切割分段平稳地落于平板车上,拆出用于固定平板车的锲型木刹块,用卷扬机水平牵引平板车至吊机起吊半径以内;
(四)支撑梁整体吊运
⑴在基坑侧壁可以架设吊机的一侧部位架设起吊吊机;
⑵将转运至基坑边起吊半径内的支撑梁切割段采用钢丝绳绑扎固定;
⑶支撑梁切割段采用钢丝绳吊运至基坑外运输车辆上运出工地;
(五)支撑梁场外破碎
支撑梁切割段运输至避免靠近居民区和市中心集中的场地外指定位置;在指定位置采用降尘措施集中破碎。
CN201310504479.8A 2013-10-24 2013-10-24 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法 Active CN103510523B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310504479.8A CN103510523B (zh) 2013-10-24 2013-10-24 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310504479.8A CN103510523B (zh) 2013-10-24 2013-10-24 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法

Publications (2)

Publication Number Publication Date
CN103510523A CN103510523A (zh) 2014-01-15
CN103510523B true CN103510523B (zh) 2014-10-29

Family

ID=49893902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310504479.8A Active CN103510523B (zh) 2013-10-24 2013-10-24 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法

Country Status (1)

Country Link
CN (1) CN103510523B (zh)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404968B (zh) * 2014-12-10 2016-05-25 中建三局第一建设工程有限责任公司 基坑内支撑梁拆除装置及基坑内支撑梁拆除方法
CN105220894B (zh) * 2015-11-16 2016-08-17 中国华西企业有限公司 内支撑绳锯无损切割拆除结构及其施工工法
CN105569377A (zh) * 2016-02-29 2016-05-11 上海建工五建集团有限公司 一种钢筋混凝土支撑梁的拆除方法
CN105783618B (zh) * 2016-03-18 2018-07-13 中国水利水电第十一工程局有限公司 挑流鼻坎降坎***拆除施工方法
CN106337419A (zh) * 2016-08-26 2017-01-18 中国十七冶集团有限公司 一种深基坑钢筋混凝土内支撑快速拆卸的装置
CN106894421A (zh) * 2017-01-19 2017-06-27 中国建筑第八工程局有限公司 基坑内支撑梁的拆除方法
CN108166500A (zh) * 2017-12-12 2018-06-15 武汉科技大学 一种临江深基坑混凝土切割拆除及回收方法
CN109989406B (zh) * 2017-12-30 2020-10-20 广州协安建设工程有限公司 基坑换撑施工工法
CN108612109B (zh) * 2018-04-27 2020-12-01 中国二十冶集团有限公司 混凝土支撑梁无托架拆除方法
CN108824842A (zh) * 2018-05-29 2018-11-16 五冶集团上海有限公司 一种脱硫塔拆除方法
CN109056741B (zh) * 2018-08-17 2020-08-11 江苏东合南岩土科技股份有限公司 多层钢支撑中的下层钢支撑的拆除方法
CN109056742A (zh) * 2018-08-23 2018-12-21 中国水利水电第八工程局有限公司 液压升降承重平台辅助拆除钢筋混凝土支撑梁的施工方法
CN109356167B (zh) * 2018-11-22 2020-11-10 深圳市福田建安建设集团有限公司 深基坑支撑拆除体系及施工方法
CN109505307A (zh) * 2018-11-30 2019-03-22 上海宝冶集团有限公司 用于大型box基础施工的支护结构换撑及拆除方法
CN109723062A (zh) * 2019-01-18 2019-05-07 济南轨道交通集团有限公司 基于近接深基坑施工环境的重载设备吊装装置及吊装方法
CN111531722A (zh) * 2020-05-28 2020-08-14 广州市黄埔建筑工程总公司 基坑支护支撑梁绳锯切割拆除方法
CN112343064A (zh) * 2020-11-27 2021-02-09 中铁七局集团第五工程有限公司 深基坑大截面环形混凝土支撑梁拆除的施工方法
CN113654423B (zh) * 2021-08-31 2023-09-22 湖北工业大学 钢筋混凝土梁柱预埋孔机械切割与异地***绿色拆除方法
CN115506371A (zh) * 2022-10-28 2022-12-23 中建一局集团建设发展有限公司 一种深基坑超高内支撑拆除的施工方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH700374B1 (de) * 2009-02-10 2012-11-30 Betag Betontaglio Sa Seilsägeeinheit sowie Verfahren zum Betrieb einer solchen Seilsägeeinheit.
WO2011107818A1 (en) * 2010-03-01 2011-09-09 Bouygues Travaux Publics Method of cutting foundation elements in the ground
CN203113351U (zh) * 2013-03-08 2013-08-07 中国建筑第四工程局有限公司 便于快速拆除基坑内支撑的结构

Also Published As

Publication number Publication date
CN103510523A (zh) 2014-01-15

Similar Documents

Publication Publication Date Title
CN103510523B (zh) 深基坑多层钢筋混凝土内支撑梁分段切割整体吊运方法
CN103291085B (zh) 混凝土静力切割拆除施工方法
CN202227476U (zh) 一种高空大跨度悬挑连廊型钢混凝土结构
CN105926669A (zh) 一种地铁车站施工方法
CN102444203A (zh) 一种高空大跨度悬挑连廊型钢混凝土结构及施工方法
CN110485429A (zh) 一种预应力型钢装配式组合内支撑施工方法
CN114164764B (zh) 一种高填方桥梁承台结构施工方法
CN110670615A (zh) 一种基于受限空间的地铁绿色建造施工调适方法
CN103485360A (zh) 一种钢平台塔吊基础及其施工方法
CN111058458A (zh) 基于绞吸式地连墙局部替代排桩支护的施工方法及结构
CN103939114A (zh) 一种悬轨式台车衬砌施工方法
CN204738556U (zh) 一种用于文物建筑整体移位的装置
CN105926672A (zh) 一种地铁暗挖车站钢管柱施工方法
CN107503344A (zh) 周转式分节钢护筒护壁人工挖孔灌注桩的施工方法
CN110295765B (zh) 一种建筑遗址迁出保护的施工方法
CN114908805A (zh) 一种上跨地铁的明挖隧道抽条施工方法
CN103669634A (zh) 后浇筑阻尼墙的施工方法及结构
CN112963015B (zh) 与下方既有地铁线路共线连接的隧道拆除施工方法
CN109736591A (zh) 一种适用于施工升降机地下室顶板的加固结构及加固方法
CN112412467B (zh) 公路特长隧道200~600m通风竖井“反井法”施工方法
CN101319894A (zh) 地下空间开挖引起的地面沉降测试方法
CN108677978B (zh) 一种桥梁无粘结预应力拼接双壁钢围堰下沉施工工法
CN216515083U (zh) 一种高填方桥梁承台结构
CN109024670B (zh) 埋地高压电缆上穿地下综合管廊保护加固体系及加固方法
CN103590839B (zh) 地铁车站现浇结构门式支架施工工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HE JINCHENG

Free format text: FORMER OWNER: CHENG JUN

Effective date: 20140910

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: He Jincheng

Inventor before: Cheng Jun

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226300 NANTONG, JIANGSU PROVINCE TO: 225400 TAIZHOU, JIANGSU PROVINCE

Free format text: CORRECT: INVENTOR; FROM: CHENG JUN TO: HE JINCHENG

TA01 Transfer of patent application right

Effective date of registration: 20140910

Address after: 225400, No. 68 middle Ping Lu, Taixing City, Jiangsu, Taizhou

Applicant after: He Jincheng

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 room 2208

Applicant before: Cheng Jun

C14 Grant of patent or utility model
GR01 Patent grant