CN103337041B - The concrete dam construction intelligent decision system of KBE and method thereof - Google Patents

The concrete dam construction intelligent decision system of KBE and method thereof Download PDF

Info

Publication number
CN103337041B
CN103337041B CN201310232318.8A CN201310232318A CN103337041B CN 103337041 B CN103337041 B CN 103337041B CN 201310232318 A CN201310232318 A CN 201310232318A CN 103337041 B CN103337041 B CN 103337041B
Authority
CN
China
Prior art keywords
rule
storehouse
construction
concrete
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310232318.8A
Other languages
Chinese (zh)
Other versions
CN103337041A (en
Inventor
周厚贵
戴志清
张开广
余英
孙昌忠
齐界夷
乐运红
曹生荣
秦敢
殷娟
杨帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gezhouba Xinjiang Engineering Co ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN201310232318.8A priority Critical patent/CN103337041B/en
Publication of CN103337041A publication Critical patent/CN103337041A/en
Application granted granted Critical
Publication of CN103337041B publication Critical patent/CN103337041B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to the concrete dam construction intelligent decision system of a kind of KBE, this system includes engineering information storehouse, construction rule base, intelligent inference system and functional module system.The concrete dam construction Intelligent Decision-making Method of the KBE that the present invention is set up and the concrete dam construction intelligent decision system of KBE, on the premise of following concrete dam construction technical specification and requiring, by the application of the methods such as the representation of knowledge of knowledge engineering, knowledge acquisition and knowledge reasoning, realize the management in concrete dam construction and decision-making work by intelligent inference system.

Description

The concrete dam construction intelligent decision system of KBE and method thereof
Technical field
The invention belongs to Construction of Hydropower Engineering field, the concrete dam pouring being specifically related to a kind of KBE is executed Work intelligent decision system and method.
Background technology
Concrete dam is one of big dam type of water conservancy and hydropower hinge two, has many comprehensive advantages, in water conservancy and hydropower work Cheng Jianshe is widely used.Concreting is the core content during concrete dam construction and crucial ring , all there is significant impact to construction speed, construction quality and the construction cost of whole engineering in joint.How to realize concrete dam pouring High-efficiency management in construction and science decision are to ensure that the key issue that concrete dam engineering is built smoothly.
Concrete dam construction management is according to engineering construction construction target, according to engineering with the key problem of decision-making The concrete condition of job site and integrated condition, by the reasonable disposition of all kinds of working sources and scheduling, ensureing engineering matter On the premise of amount, accelerating construction progress, reduction construction cost.The field management of concrete dam construction and decision-making cover mixed Position in storehouse layout during solidifying earth dam pouring construction, machinery scheduling, plan-validation, progress simulation, the plan of getting the raw materials ready, grouting plan, The comprehensive coordination of multiple problems such as water flowing scheme and process.
The influence factor of concrete dam construction totally can be divided into external factor and two aspects of internal factor.Right For concrete dam construction link, external factor can be considered uncontrollable factor, and internal factor is then considered as controllable factor.Outward Portion's factor mainly includes the outside construction environment such as hydrologic condition, meteorological condition and supply of electric power, expropriation of land immigrant, geological disaster. Internal factor mainly includes the requirement of dam construction technology, sandstone production system performance, device of concrete mixing system performance, concrete fortune The aspects such as communication system performance.These factors influence each other and restrict, and some factors has the feature such as dynamic and uncertainty.Cause This, concrete dam construction management has again quantitative Analysis to work with existing qualitative analysis work in decision making process, has higher Difficulty and complexity.
In current concrete dam construction field management work, rely primarily on the personal experience of construction manager And professional ability, all kinds of working sources are scheduling, mainly by manual type to being correlated with in concrete dam construction Problem is managed and decision-making.But in the face of the most complicated problem, particularly in large-scale concrete dam construction, storehouse Position is many, equipment is many, influence factor is many, and labor management can occur job site to dispatch because of inconsiderate with the mode of decision-making unavoidably Situation improperly, has a negative impact.Little, affect progress, increase cost, the most then cause quality problems even security incident.Cause How this, improve science and the reasonability of concrete dam construction, improves level of decision-making and the efficiency of management, becomes raising mixed The important step of solidifying earth dam its construction level, further performance concrete dam advantage.
Along with Other subjects theory, method, the development of technology and application, the construction technology of concrete dam and construction Management level are obtained for and are correspondingly improved.Information technology is exactly importance therein, data base, computer network, information The application of the related information technology such as system has played important for the construction technology level and the efficiency of management improving concrete dam Castering action.
But, as it has been described above, concrete dam construction management has again quantitative Analysis with decision-making existing qualitative analysis work Work, integrates decision making under certainty and unascertained decision, is comprehensive application technology rule, Regulations, a Zhuan Jiajing The integrated decision-making process tested, is a complicated intelligent inference process, in addition to application routine techniques is with method, certainly will need to borrow Help correlation theory and the method for artificial intelligence field.Integrated application information technology and artificial intelligence approach foundation have intelligence and push away The concrete dam construction intelligent decision system of reason ability, just can efficiently solve concrete dam construction management and decision-making Problem, improves its scientific level and efficiency, at utmost plays the comprehensive advantage of concrete dam, carries for relevant industries and department Carry out preferable comprehensive benefit.
Summary of the invention
The present invention has pushed the management of concrete dam construction and decision-making work to intelligent pattern from traditional mode, no Only be conducive to improving work efficiency, be more beneficial for overcoming the mistake contingent with decision-making or improper of labor management in traditional mode Part, is effectively improved rationalization level and scientific degree, it is ensured that the management level of concrete dam construction, improves Construction quality, accelerate construction speed, improve the comprehensive benefit of relevant industries and department, for playing concrete dam dam type Comprehensive advantage will play a significant role.
The technical solution used in the present invention:
A kind of concrete dam construction intelligent decision system of KBE, this system include engineering information storehouse, Construction rule base, intelligent inference system and functional module system;Engineering information storehouse includes arrangement and method for construction information, job site information With the data of three aspects of dam body model information, the basic data support providing comprehensive is run in engineering information storehouse for system;Construction Rule base is then responsible for the expert in the Its Relevant Technology Standards of storage and management concrete dam construction, technology requirement and industry Experience and the rule knowledge of other concrete dam construction;The thinking process of the intelligent inference system simulation mankind, with rule of constructing Then the rule in storehouse is reasoning foundation, and according to the related data in engineering information storehouse, based on data, reasoning obtains being correlated with Conclusion or constructing operation;Functional module system includes position in storehouse orchestration module, machinery scheduler module, plan-validation module, progress mould Intend module, schedule module of getting the raw materials ready, grouting schedule module and water flowing scheme module.
Above-mentioned engineering information storehouse specifically includes construction environment characteristic parameter, dam structure characteristic parameter, construction machinery spy Levy parameter, construction technical requirement parameter, material parameter, arrangement and method for construction parameter and engineering construction parameter.
Above-mentioned construction environment characteristic parameter includes rainfall, snowfall, water temperature and flow;Dam structure characteristic parameter bag Include monolith structural parameters, position in storehouse spatial parameter, hollow spaces parameter and concrete performance parameter;Construction machinery characteristic parameter includes The space orientation of concrete warehousing construction machinery, service behaviour, operation characteristic and working range;Construction technical requirement parameter includes The dam concrete pouring construction discrepancy in elevation limits, the intermittent time limits and temperature-controlled parameter;Material parameter includes dam concrete The production of match ratio, sandstone and storage system and concrete store system;Arrangement and method for construction parameter include concreting schedule requirement, Mechanization and special technical requirement;Engineering construction parameter includes on-the-spot the pouring position in storehouse, fill of concrete dam construction Slurry/water flowing position, respectively put in storage machinery current location.
Above-mentioned construction rule base specifically includes the requirement of dam concrete mix technology, concrete transportation technology requires, dam Body concrete pours rule, concrete water flowing cooling rule and dam body joint grouting rule.
Above-mentioned dam concrete mix technology requires to include concrete type, refrigeration requires and duration of mixing;Concrete Transportation technology requires to include the free-electron model height in transportation, transhipment number of times and haulage time dam concrete and pours rule Including discrepancy in elevation restriction, intermittent time and curing time in concreting process;Concrete water flowing cooling rule includes dam body The beginning and ending time of concrete water flowing, trigger condition, water temperature and flow;Dam body joint grouting rule includes that dam concrete coordinates The production of ratio, sandstone and storage system and concrete store system;Arrangement and method for construction parameter include dam body joint grouting time started, Trigger condition and grouting region.
The decision method of the concrete dam construction intelligent decision system of a kind of KBE, it includes walking as follows Rapid:
(1) conventionally form represents the premise of knowledge and the extraction of conclusion,
In current concrete dam construction management with decision making process, whether a certain position in storehouse concrete can pour needs Meet the restriction of before and after's discrepancy in elevation, the left and right discrepancy in elevation limits, the interlayer intermittent time limits, meteorological condition limits, adjacent position in storehouse is constructed about Restraint these to limit and constraints;When all of precondition meets, this position in storehouse can carry out pouring construction;From knowledge work The production rule angle of journey understands, with constraints, these limit can regard whether a certain position in storehouse can pour this rule as Precondition, " can pour " is then corresponding to the conclusion of this rule;
In the step for knowledge is extracted, it is whether the concrete position in storehouse represented with conventionally form can pour this One judges that work is converted into the premise part of rule, conclusion part, reliability form;Before whether concrete position in storehouse can pour Before and after's discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, 5 aspects of adjacent construction are put forward;Conclusion is for pouring or can not To pour, for 0-1 variable;According to concrete dam construction specification, this rule is completely reliable;
(2) rule premise, conclusion, the quantization of reliability, classification,
On the basis of (one) step work, carry out quantifying, classifying or classification by the premise of rule, conclusion, reliability;
The discrepancy in elevation front and back: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of front and back's position in storehouse, passes through Formal Languages Be expressed as Height_Diff-FB_Bin (x, y);The discrepancy in elevation before and after i.e. position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value;
The left and right discrepancy in elevation: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of left and right position in storehouse, passes through Formal Languages Be expressed as Height_Diff-LR_Bin (x, y);The i.e. left and right discrepancy in elevation of position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value;
Intermittent time: represent with absolute physical value, both poured the deadline plus rule with the bottom position in storehouse of current position in storehouse On the basis of the intermittent time that model requires or current engineering sets, it is judged that whether current time had arrived in this time period;Pass through Formal Languages is represented by Pause_time (x), and its value is absolute calendar time, its form be " MM/dd/yyyy hh: mm;ss”;
Meteorological condition: whether current position in storehouse can be poured by meteorological condition mainly considers from rainfall angle, can be right Rainfall carries out classification, as heavy rain, heavy rain, light rain, without rain;Being represented by Rain (t) by Formal Languages, " t " i.e. herein For drafting the time of moduling plan, the value of Rain (t) is according to the weather forecast parameter determination in data base;
Adjacent position in storehouse construction constraint: the construction constraint of adjacent position in storehouse refers to when certain position in storehouse casting concrete, adjacent thereto Other positions in storehouse because draining, template erection and the cause of failures that puts in storage cannot carry out concrete pouring construction simultaneously;This is constrained to 0-1 variable bound, when there are adjacent position in storehouse just at casting concrete, this position in storehouse can not casting concrete, this binding occurrence is 0;Otherwise, all positions in storehouse adjacent thereto are not the most at casting concrete, then current position in storehouse can carry out concrete pouring construction, should Binding occurrence is 1;It is represented by Adjoin_Bin (x) by Formal Languages;Which position in storehouse to be the adjacent storehouse of current position in storehouse as Position, determines according to the three-dimensional relationship of dam body model parameter;
Conclusion: whether can pour the judgement of sets of conditions according to above current position in storehouse, conclusion is for pouring or can not To pour, for 0-1 variable;By Formal Languages, FitPour-Bin (x) can be expressed as;
Reliability: according to concrete dam construction specification, this rule is completely reliable, i.e. reliability is 1:CF=1;
(3) formalization of production rule,
In the concrete dam construction intelligent decision system of KBE, before rule in (two) step Carry, the quantization of conclusion, reliability, classification, and the statement of Formal Languages, " during concrete dam construction certain Whether one position in storehouse concrete can pour under current state " judgement of this event can be expressed as following production rule Then:
The precondition of this rule be simultaneously meet before and after the discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, adjacent storehouse Position construction constraint, it may be assumed that P=Height_Diff-FB_Bin (x, y) ∧ Height_Diff-LR_Bin (x, y) ∧ Pause_time (x)∧Rain(t)∧Adjoin_Bin(x);The conclusion of this rule is that current position in storehouse can be with casting concrete, it may be assumed that C= FitPour-Bin(x);The credibility of rule is 1;So, current rule can be expressed as:
Height_Diff-FB_Bin(x,y)∧Height_Diff-LR_Bin(x,y)∧Pause_time(x)∧Rain (t)∧Adjoin_Bin(x)→FitPour-Bin(x)(1)
(4) rule inspection,
The inspection of rule is the important step of production rule acquisition work, be the examination to abovementioned steps gained knowledge and Check on;In this step, major tasks are that by reflecting that this rule is verified by the example of various condition of construction, look into See that its conclusion exported is the most correct;For the output incorrect situation of conclusion, need check its reasoning process in detail and find Reason;In rule inspection, it is accordingly required in particular to verify that the adaptability of this rule is with correct by some construction parameters in particular cases Property;If after system test, do not find current rule existing problems, then this rule warehouse-in is preserved;If it find that exist Problem, then need again to extract current rule and formalization, i.e. repeats step ()-step (three);
(5) again extract or formalization, for being found to have the rule of reasoning impropriety in checkout procedure, repeat step Suddenly (one)-step (three), extract or formalization again to this rule;
(6) warehouse-in, for rule qualified after inspection, is deposited in rule base, with the form of relational database Preserve.
The technique effect that the present invention obtains:
1, the concrete dam construction Intelligent Decision-making Method of the KBE that the present invention is set up and knowledge based The concrete dam construction intelligent decision system of engineering, in the premise following concrete dam construction technical specification and requirement Under, by the application of the methods such as the representation of knowledge of knowledge engineering, knowledge acquisition and knowledge reasoning, realized by intelligent inference system Management in concrete dam construction and decision-making work.The method and system that the present invention sets up achieves concrete dam pouring and executes Integrated, the automatization of work management and decision-making work, intellectuality, improve efficiency and the science of management and decision-making.
2, the concrete dam construction intelligent decision system of KBE that the present invention sets up has and pours position in storehouse Layout, machinery scheduling of putting in storage, arrangement and method for construction are verified, are poured progress simulation, the concrete plan of getting the raw materials ready, grouting plan, water flowing The function of seven aspects such as solution formulation, can meet the field management of concrete dam construction and the multinomial work of decision-making.And Native system is prone to foundation, easy to use, maintenance is simple, highly versatile, the degree of reliability are high.
3, the present invention has pushed the management of concrete dam construction and decision-making work to intelligent pattern from traditional mode, Not only contribute to improve work efficiency, be more beneficial for overcoming in traditional mode labor management and the contingent mistake of decision-making or not Work as part, be effectively improved rationalization level and scientific degree, it is ensured that the management level of concrete dam construction, carry High construction quality, accelerate construction speed, improve the comprehensive benefit of relevant industries and department, for playing concrete dam The comprehensive advantage of type will play a significant role.Generally speaking, the present invention not only has good economic outlook, more has good Social benefit.
Accompanying drawing explanation
Fig. 1 is the structural representation of decision system of the present invention;
Fig. 2 is the structure schematic flow sheet of decision system of the present invention;
Fig. 3 is the engineering information library structure schematic diagram of decision system of the present invention;
Fig. 4 is decision system decision method flow chart of the present invention;
Fig. 5 is the construction rule base schematic diagram of decision system of the present invention;
Fig. 6 is reasoning pattern and the workflow schematic diagram of decision system of the present invention.
Detailed description of the invention
Below in conjunction with the accompanying drawings embodiments of the present invention are described further.
See Fig. 1,3,5,6, the concrete dam construction intelligent decision system of a kind of KBE, this system Including engineering information storehouse, construction rule base, intelligent inference system and functional module system;Engineering information storehouse includes that arrangement and method for construction is believed Breath, job site information and the data of three aspects of dam body model information, the base providing comprehensive is run in engineering information storehouse for system Plinth data are supported;Construction rule base is then responsible for the Its Relevant Technology Standards of storage and management concrete dam construction, technology requirement And the expertise in industry and the rule knowledge of other concrete dam construction;The think of of the intelligent inference system simulation mankind Dimension process, with the rule constructed in rule base for reasoning foundation, according to the related data in engineering information storehouse, with data as base Plinth, reasoning obtains conclusion or the constructing operation being correlated with;Functional module system includes position in storehouse orchestration module, machinery scheduler module, side Case authentication module, progress analog module, schedule module of getting the raw materials ready, grouting schedule module and water flowing scheme module.
Described engineering information storehouse specifically includes construction environment characteristic parameter, dam structure characteristic parameter, construction machinery spy Levy parameter, construction technical requirement parameter, material parameter, arrangement and method for construction parameter and engineering construction parameter.Described construction ring Border characteristic parameter includes rainfall, snowfall, water temperature and flow;Dam structure characteristic parameter includes monolith structural parameters, position in storehouse Spatial parameter, hollow spaces parameter and concrete performance parameter;Construction machinery characteristic parameter includes concrete warehousing construction machinery Space orientation, service behaviour, operation characteristic and working range;Construction technical requirement parameter includes dam concrete pouring construction The discrepancy in elevation limits, the intermittent time limits and temperature-controlled parameter;Material parameter includes that dam concrete match ratio, sandstone produce and deposit Storage system and concrete storage system;Arrangement and method for construction parameter includes concreting schedule requirement, mechanization and special technique Requirement;Engineering construction parameter includes on-the-spot the pouring position in storehouse, be in the milk/water flowing position, respectively put in storage of concrete dam construction Machinery current location.
Described construction rule base specifically includes the requirement of dam concrete mix technology, concrete transportation technology requires, dam Body concrete pours rule, concrete water flowing cooling rule and dam body joint grouting rule.Described dam concrete mix skill Art requires to include concrete type, refrigeration requires and duration of mixing;Concrete transportation technology requires to include oneself in transportation The discrepancy in elevation limit that rule includes in concreting process is poured by falling height, transhipment number of times and haulage time dam concrete System, intermittent time and curing time;Concrete water flowing cooling rule includes the beginning and ending time of dam concrete water flowing, triggers bar Part, water temperature and flow;Dam body joint grouting rule includes the production of dam concrete match ratio, sandstone and storage system and concrete Storage system;Arrangement and method for construction parameter includes the time started of dam body joint grouting, trigger condition and grouting region.
The major function of this system includes:
Pour position in storehouse orchestration module: concrete dam construction management, with decision making process, needs to water according to current dam body Build situation, formulate continually each monolith, each bin level pour order, i.e. position in storehouse layout;And position in storehouse layout needs to meet work Journey schedule requirement, image schedule requirement, and a series of associated construction process constraint;The concrete dam of KBE waters Build construction intelligent decision system and can meet associated construction specification, dam according to the integrated information of current job site each side Body concrete pouring technique requires, on the premise of progress and image schedule requirement, inference system can formulate each that not yet pour Pouring sequentially of position in storehouse, i.e. pours position in storehouse layout work;
Put in storage machinery scheduler module: during the pouring construction of concrete dam, it usually needs multiple stage door machine, tower crane, cable The concrete transporting equipments such as machine, tower belt crane, belt feeder, by concrete transportation to face, storehouse to complete follow-up work, the most just deposit Multiple stage put in storage machinery scheduling problem;Corresponding with position in storehouse layout, in the scheduling process of concrete warehousing machinery, need to examine Consider the parameters such as its conevying efficiency, transport capacity, locus, brachium, positive and negative lift, bulk, the domain of walk, and dam body The phase relation column constraint of concreting;The concrete dam construction intelligent decision system of KBE can be according to working as The integrated information of front job site each side, is meeting associated construction specification, dam concrete pouring technique requirement, progress and shape On the premise of schedule requirement, inference system can arrange each concreting machinery that puts in storage to be responsible for the position in storehouse that pours successively, and The method of operation of every set concrete warehousing equipment;
Pouring plan authentication module: the concrete dam construction scheme that system outer (and system user) is inputted, bag Include and pour schedule, position in storehouse layout scheme, equipment scheduling scheme etc., the concrete dam construction intelligence of KBE Decision system can be according to the integrated information of current job site each side, and meeting associated construction specification, dam concrete waters On the premise of building technology requirement, progress and image schedule requirement, verify the feasibility of this pouring plan, as infeasible, be given former Cause and explanation;
Construction speed (process) analog module: relevant information based on current job site comprehensive condition, knowledge based work The concrete dam construction intelligent decision system of journey can meet associated construction specification, dam concrete pouring technique want Ask, on the premise of progress and image schedule requirement, formulate the dam concrete in following certain period of time pour schedule or Person remains the schedule that dam concrete pours, and the corresponding plan of getting the raw materials ready, grouting plan and water flowing cooling scheme, Realize the artificial intelligence to concrete pouring construction progress;
Get the raw materials ready schedule module: the concrete dam construction intelligent decision system of KBE can be intended at native system On the basis of fixed construction schedule, in conjunction with the concrete mix parameter at each position of dam body, reasoning and calculation obtains not Carry out the demand of all types of cement (according to parameter classified types) in the construction time, aggregate, additive etc., for construction management with certainly Plan uses;
Dam grouting schedule module: according to the practice of construction progress of concrete dam, the most each position in storehouse pour deadline, dam Body pours the associated construction parameter such as cope level, upper pond level, according to associated specifications and requirement, mixing of KBE Solidifying earth dam pouring construction intelligent decision system can obtain the position of dam body joint grouting with reasoning, recommend the construction ginsengs such as time started Number, for construction management and decision references and;
Cooling water flowing scheme module: according to the practice of construction progress of concrete dam, the most each position in storehouse pour the deadline and The hydrometeorological data of dam site location, according to associated specifications and requirement, the concrete dam pouring of KBE When construction intelligent decision system can obtain the start-stop of the initial stage water flowing in each district of dam body, water flowing in mid-term and later stage water flowing with reasoning Between, the parameter such as water temperature, flow, for construction management and decision-making.
See Fig. 1-6, the decision method of the concrete dam construction intelligent decision system of a kind of KBE, it Comprise the steps:
(1) conventionally form represents the premise of knowledge and the extraction of conclusion,
In current concrete dam construction management with decision making process, whether a certain position in storehouse concrete can pour needs Meet the restriction of before and after's discrepancy in elevation, the left and right discrepancy in elevation limits, the interlayer intermittent time limits, meteorological condition limits, adjacent position in storehouse is constructed about Restraint these to limit and constraints;When all of precondition meets, this position in storehouse can carry out pouring construction;From knowledge work The production rule angle of journey understands, with constraints, these limit can regard whether a certain position in storehouse can pour this rule as Precondition, " can pour " is then corresponding to the conclusion of this rule;
In the step for knowledge is extracted, it is whether the concrete position in storehouse represented with conventionally form can pour this One judges that work is converted into the premise part of rule, conclusion part, reliability form;Before whether concrete position in storehouse can pour Before and after's discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, 5 aspects of adjacent construction are put forward;Conclusion is for pouring or can not To pour, for 0-1 variable;According to concrete dam construction specification, this rule is completely reliable;
(2) rule premise, conclusion, the quantization of reliability, classification,
On the basis of (one) step work, carry out quantifying, classifying or classification by the premise of rule, conclusion, reliability;
The discrepancy in elevation front and back: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of front and back's position in storehouse, passes through Formal Languages Be expressed as Height_Diff-FB_Bin (x, y);The discrepancy in elevation before and after i.e. position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value;
The left and right discrepancy in elevation: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of left and right position in storehouse, passes through Formal Languages Be expressed as Height_Diff-LR_Bin (x, y);The i.e. left and right discrepancy in elevation of position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value;
Intermittent time: represent with absolute physical value, both poured the deadline plus rule with the bottom position in storehouse of current position in storehouse On the basis of the intermittent time that model requires or current engineering sets, it is judged that whether current time had arrived in this time period;Pass through Formal Languages is represented by Pause_time (x), and its value is absolute calendar time, its form be " MM/dd/yyyy hh: mm;ss”;
Meteorological condition: whether current position in storehouse can be poured by meteorological condition mainly considers from rainfall angle, can be right Rainfall carries out classification, as heavy rain, heavy rain, light rain, without rain;Being represented by Rain (t) by Formal Languages, " t " i.e. herein For drafting the time of moduling plan, the value of Rain (t) is according to the weather forecast parameter determination in data base;
Adjacent position in storehouse construction constraint: the construction constraint of adjacent position in storehouse refers to when certain position in storehouse casting concrete, adjacent thereto Other positions in storehouse because draining, template erection and the cause of failures that puts in storage cannot carry out concrete pouring construction simultaneously;This is constrained to 0-1 variable bound, when there are adjacent position in storehouse just at casting concrete, this position in storehouse can not casting concrete, this binding occurrence is 0;Otherwise, all positions in storehouse adjacent thereto are not the most at casting concrete, then current position in storehouse can carry out concrete pouring construction, should Binding occurrence is 1;It is represented by Adjoin_Bin (x) by Formal Languages;Which position in storehouse to be the adjacent storehouse of current position in storehouse as Position, determines according to the three-dimensional relationship of dam body model parameter;
Conclusion: whether can pour the judgement of sets of conditions according to above current position in storehouse, conclusion is for pouring or can not To pour, for 0-1 variable;By Formal Languages, FitPour-Bin (x) can be expressed as;
Reliability: according to concrete dam construction specification, this rule is completely reliable, i.e. reliability is 1:CF=1;
(3) formalization of production rule,
In the concrete dam construction intelligent decision system of KBE, before rule in (two) step Carry, the quantization of conclusion, reliability, classification, and the statement of Formal Languages, " during concrete dam construction certain Whether one position in storehouse concrete can pour under current state " judgement of this event can be expressed as following production rule Then:
The precondition of this rule be simultaneously meet before and after the discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, adjacent storehouse Position construction constraint, it may be assumed that P=Height_Diff-FB_Bin (x, y) ∧ Height_Diff-LR_Bin (x, y) ∧ Pause_time (x)∧Rain(t)∧Adjoin_Bin(x);The conclusion of this rule is that current position in storehouse can be with casting concrete, it may be assumed that C= FitPour-Bin(x);The credibility of rule is 1;So, current rule can be expressed as:
Height_Diff-FB_Bin(x,y)∧Height_Diff-LR_Bin(x,y)∧Pause_time(x)∧Rain (t)∧Adjoin_Bin(x)→FitPour-Bin(x)(1)
(4) rule inspection,
The inspection of rule is the important step of production rule acquisition work, be the examination to abovementioned steps gained knowledge and Check on;In this step, major tasks are that by reflecting that this rule is verified by the example of various condition of construction, look into See that its conclusion exported is the most correct;For the output incorrect situation of conclusion, need check its reasoning process in detail and find Reason;In rule inspection, it is accordingly required in particular to verify that the adaptability of this rule is with correct by some construction parameters in particular cases Property;If after system test, do not find current rule existing problems, then this rule warehouse-in is preserved;If it find that exist Problem, then need again to extract current rule and formalization, i.e. repeats step ()-step (three);
(5) again extract or formalization, for being found to have the rule of reasoning impropriety in checkout procedure, repeat step Suddenly (one)-step (three), extract or formalization again to this rule;
(6) warehouse-in, for rule qualified after inspection, is deposited in rule base, with the form of relational database Preserve.
Illustrate the detailed description of the invention of the present invention in conjunction with Figure of description, mainly include the coagulation of a kind of KBE Earth dam pouring construction intelligent decision system and the system constructing flow process of method, knowledge acquisition method, knowledge representation method, knowledge push away Reason method.It should be noted that the process described by this place and embodiment not limitation of the present invention, but in order to more preferably Ground describes present invention, is easy to the awareness and understanding present invention.
One, system constructing flow process
Fig. 2 is the building process schematic diagram of the concrete dam construction intelligent decision system of a kind of KBE. Its building process is divided into four steps, respectively builds data base, builds knowledge base, inference system design, the system integration and tune Examination.The main contents of each step are as follows:
(1) data base is built
Data base is the basis of the concrete dam construction intelligent decision system operation of a kind of KBE.Summarize For, the process building data base is i.e. to affect the construction machinery of concrete dam construction, dam body feature, construction ring The related datas such as border, technology requirement are sorted out, arrange, are quantified, and store through database table, through RDBM Relational Data Base Management system System realizes the management to data base and maintenance.The concrete dam of a kind of KBE of the particular content of data base such as Fig. 3 waters Build shown in the engineering information library structure of construction intelligent decision system.
(2) knowledge base is built
Knowledge base is the foundation that the concrete dam construction intelligent decision system of a kind of KBE makes inferences Place.The building process of knowledge base is divided into the work of two aspects, an aspect to be relevant during concrete dam construction The foundation of knowledge (i.e. rule) method for expressing, i.e. sets up concrete dam construction expressing for knowledge method;Another aspect is then It is the knowledge that will preserve with traditional media or represent, including engineering discipline, technology requirement, expertise etc., is built with the present invention Vertical mode shows, and i.e. sets up the acquisition methods of concrete dam construction knowledge.The particular content of knowledge base such as Fig. 5 mono- Shown in the construction rule base structure of the concrete dam construction intelligent decision system planting KBE.
The content of these two aspects will elaborate in " knowledge representation method " and " knowledge acquisition method " hereinafter.
(3) inference system design
Inference system design is on the basis of constructed data base and knowledge base, it is achieved from basic data, lead to Crossing the application of knowledge in knowledge base, reasoning obtains following construction schedule or the reasoning process of arrangement and method for construction.Inference system sets Meter includes RBR uncertain inference machine-processed, rule-based mechanism, RBR conflict resolution plan Slightly three aspect contents, its particular content will elaborate in " Method of Knowledge Reasoning " in " detailed description of the invention ".
(4) system integration and debugging
After the design of the structure and inference system that complete data base and knowledge base, carry out the integrated of system and adjust Examination.The step for purpose be the linking between real data storehouse, knowledge base, inference system three, and make this three work in coordination with Work, it is achieved the reasoning from concrete dam construction basic data to arrangement and method for construction.A kind of concrete of KBE The system integration of dam pouring construction intelligent decision system and the major tasks of debugging include the content of three aspects: one is data base Can the data inside comprised provide precondition, the i.e. completeness of production rule precondition for knowledge base;Two is rule Between conflicting, i.e. rule concordance, this partial content will be explained in the Strategy of Conflict Resolution of Process Based in detail State;Three is the explanation of reasoning process, and this partial content will elaborate in RBR designs.
Complete above quadrinomial job, i.e. achieve the concrete dam construction intelligent decision of a kind of KBE The building process of system, after the real data in input concrete dam engineering foundation data and work progress, can be carried out The management of concrete dam construction and decision-making work.
Two, knowledge acquisition method
The product of the concrete dam construction intelligent decision system of KBE as a kind of in the Fig. 4 in Figure of description Shown in raw formula Rule schematic flow sheet, obtain concrete dam construction dependency rule and be broadly divided into following six aspect work Make.
Below with a certain position in storehouse concrete during concrete dam construction whether can pour under current state into Example, illustrates that the knowledge of concrete dam construction extracts process.
(1) conventionally form represents the premise of knowledge and the extraction of conclusion
In current concrete dam construction management with decision making process, whether a certain position in storehouse concrete can pour needs Meet the restriction of before and after's discrepancy in elevation, the left and right discrepancy in elevation limits, the interlayer intermittent time limits, meteorological condition limits, adjacent position in storehouse is constructed about Restraint these to limit and constraints.I.e. when all of precondition meets, this position in storehouse can carry out pouring construction.From knowledge The production rule angle of engineering understands, with constraints, these limit can regard whether a certain position in storehouse can pour these rule as Precondition then, " can pour " is then corresponding to the conclusion of this rule.
In the step for knowledge is extracted, focus is whether may be used the concrete position in storehouse that represent with conventionally form With pour this judgement work be converted into rule premise part, conclusion part, reliability form.Concrete position in storehouse is the most permissible The premise poured has before and after's discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, 5 aspects of adjacent construction;Conclusion is for watering Build and maybe cannot pour, for 0-1 variable;According to concrete dam construction specification, this rule is completely reliable.
(2) rule premise, conclusion, the quantization of reliability, classification
On the basis of the first step works, carry out quantifying, classifying or classification by the premise of rule, conclusion, reliability.Above State as a example by the most whether a certain position in storehouse in concrete dam construction can pour this problem, elaborate this work Implementation.
The discrepancy in elevation front and back: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of front and back's position in storehouse, passes through Formal Languages Be expressed as Height_Diff-FB_Bin (x, y).The discrepancy in elevation before and after i.e. position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value.
The left and right discrepancy in elevation: represent with absolute physical value, i.e. represents with the actual discrepancy in elevation of left and right position in storehouse, passes through Formal Languages Be expressed as Height_Diff-LR_Bin (x, y).The i.e. left and right discrepancy in elevation of position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, Otherwise it is then negative value.
Intermittent time: represent with absolute physical value, both poured the deadline plus rule with the bottom position in storehouse of current position in storehouse On the basis of the intermittent time that model requires or current engineering sets, it is judged that whether current time had arrived in this time period.Pass through Formal Languages is represented by Pause_time (x), and its value is absolute calendar time, its form be " MM/dd/yyyy hh: mm;ss”。
Meteorological condition: whether current position in storehouse can be poured by meteorological condition mainly considers from rainfall angle, can be right Rainfall carries out classification, as heavy rain, heavy rain, light rain, without rain.Being represented by Rain (t) by Formal Languages, " t " i.e. herein For drafting the time of moduling plan, the value of Rain (t) is according to the weather forecast parameter determination in data base.In concrete dam work In journey Construction practices, the concrete of different performance is different to the requirement of rainfall;Additionally, with or without rainproof measure or rainproof measure Degree of perfection also has different impacts to this judgement, sweetly disposition in concrete engineering, and arranges corresponding Formal Languages As basis for estimation.
Adjacent position in storehouse construction constraint: the construction constraint of adjacent position in storehouse refers to when certain position in storehouse casting concrete, adjacent thereto Other positions in storehouse (elevation is the most identical) because draining, template erection, the reasons such as interference of putting in storage cannot carry out concrete simultaneously Pouring construction.This is constrained to 0-1 variable bound, and when there are adjacent position in storehouse just at casting concrete, this position in storehouse can not pour Concrete, this binding occurrence is 0;Otherwise, all positions in storehouse adjacent thereto are not the most at casting concrete, then current position in storehouse can be carried out Concrete pouring construction, this binding occurrence is 1.It is represented by Adjoin_Bin (x) by Formal Languages.As for which position in storehouse it is The adjacent position in storehouse of current position in storehouse, determines according to the three-dimensional relationship of dam body model parameter.
Conclusion: whether can pour the judgement of sets of conditions according to above current position in storehouse, conclusion is for pouring or can not To pour, for 0-1 variable.By Formal Languages, FitPour-Bin (x) can be expressed as.Require emphasis a bit herein, this According to the integrated condition of position in storehouse itself, one rule simply judges whether current position in storehouse can pour, do not necessarily mean that and necessarily may be used To pour or have to pour.
Reliability: according to concrete dam construction specification, this rule is completely reliable, i.e. reliability is 1:CF=1.
(3) formalization of production rule
In the concrete dam construction intelligent decision system of KBE, before rule in second step Carry, the quantization of conclusion, reliability, classification, and the statement of Formal Languages, " during concrete dam construction certain Whether one position in storehouse concrete can pour under current state " judgement of this event can be expressed as following production rule Then:
The precondition of this rule be simultaneously meet before and after the discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, adjacent storehouse Position construction constraint, it may be assumed that P=Height_Diff-FB_Bin (x, y) ∧ Height_Diff-LR_Bin (x, y) ∧ Pause_time (x)∧Rain(t)∧Adjoin_Bi n(x).The conclusion of this rule is that current position in storehouse can be with casting concrete, it may be assumed that C= FitPour-Bin(x).The credibility of rule is 1.So, current rule can be expressed as:
Height_Diff-FB_Bin(x,y)∧Height_Diff-LR_Bin(x,y)∧Pause_time(x)∧Rain (t)∧Adjoin_Bin(x)→FitPour-Bin(x)(1)
(4) rule inspection
The inspection of rule is the important step of production rule acquisition work, be the examination to abovementioned steps gained knowledge and Check on.In this step, major tasks are that by reflecting that this rule is verified by the example of various condition of construction, look into See that its conclusion exported is the most correct.For the output incorrect situation of conclusion, need check its reasoning process in detail and find Reason.In rule inspection, it is accordingly required in particular to verify that the adaptability of this rule is with correct by some construction parameters in particular cases Property.If after system test, do not find current rule existing problems, then this rule warehouse-in is preserved;If it find that exist Problem, then need again to extract current rule and formalization, i.e. repeats step 1-step 3.
(5) again extract or formalization
For being found to have the rule of reasoning impropriety in checkout procedure, repeat step 1-step 3, this rule is carried out Again extract or formalization.
(6) warehouse-in
For rule qualified after inspection, being deposited in rule base, concrete production rule is in rule base Storage mode i.e. knowledge representation method will describe in detail in the Part III " knowledge representation method " of " detailed description of the invention ".
Three, knowledge representation method
As a example by whether certain concrete position in storehouse can pour, elaborate the concrete dam pouring of a kind of KBE The knowledge representation method of construction intelligent decision system, i.e. the method for expressing of each rule-like of concrete dam construction.
As it has been described above, concrete dam construction process control rule (i.e. knowledge) is Activities during construction management Between causal conversion foundation, applicable production rule represents.Production rule is to represent with " P → C (CF) " form Statement.Data for utilizing ripe relational database technology powerful stores, retrieve, organize and operating capability realization is to rule The organization and management of knowledge, utilizes in the concrete dam construction intelligent decision system of a kind of KBE and closes coefficient According to library storage, management rule.All of rule in the concrete dam construction intelligent decision system of a kind of KBE It is saved in rule base (Rule Base).According to the feature of concrete dam construction dependency rule, concrete dam pouring is advised Relational database representation method then has carried out detailed design.
Concrete dam pouring rule base is divided into dictionary word bank (Dictionary sub-base) and rule word bank (Rule Sub-base) two parts.Dictionary word bank for deposit rule precondition and conclusion (being referred to as the fact), and the fact from The contents such as right language description.The structure of dictionary word bank is DICT_SB (Fact_ID, Fact, Nat_lang, CF).Wherein Fact_ ID is true coding, and the fact that Fact is to describe with formal language content, the fact that Nat_lang is to use natural language description Content (for explaining to user), CF refers to the credibility of the fact, is all set at the CF of all facts of reasoning original state Empty.Wherein, Fact_ID is major key.Dictionary in the concrete dam construction intelligent decision system of a kind of KBE The fragment in storehouse is as shown in table 1.
Table 1 dictionary word bank fragment
Illustrate:
(1) table 1 data are only the fragment of dictionary character library of rule base, and the regular quantity required when running of real system is relatively For huge and complicated.
(2) the part fact in table 1 is reflected as functional relationship, and the realization of its function need to rely on the set up system of the present invention Other functional modules in system.Such as: the neighbouring judgement of position in storehouse, the judgement of the judgement of left and right position in storehouse, front and back position in storehouse, it is required to borrow Help three-dimensional dam body model and spatial parameter determines.
(3) fact of the part in table 1 needs to make inferences with the data in field data storehouse for relying in reasoning process.
Rule word bank is used for depositing rule, including regular texture table and rule condition table.The structure of regular texture table is RULE_STRU(Rule_ID,Num,Fact_ID,CF,Active).Wherein Rule_ID is rule numbers;Num is this rule institute The condition item number needed;Fact_ID is the numbering of conclusion;CF is the credibility of rule;Active shows that this rule is the most Activate, it is to avoid reusing of rule, improve Reasoning Efficiency.The structure of rule condition table be RULE_Cond (Rule_ID, Fact_ID,Logic_relation,Active).Wherein Rule_ID represents rule numbers;Fact_ID represents condition number, should Rule has several condition just to have several records;Logic_relation is this condition logical relation in reasoning, including patrolling Volume with " ∧ " (" AND ") computing and logic or " ∨ " (" OR ") two kinds of operational forms of computing, represent that this condition is essential condition Or optional condition;Active is the mark that Fact_ID activates, it is to avoid rule terms and conditions repeated matching.
The CF(credibility of rule) refer to the degree of reliability that foundation rule condition is reached a conclusion.CF (P → C) ∈ [-1,1], Value and the implication of CF are as follows: CF=+1 represents that C mono-is set to very if P is true;CF=-1 represents that C mono-is set to vacation if P is true; CF=0 represents that C is not affected by the true and false of P;CF ∈ (-1,0) represents if P is true, and C is false to a certain extent;CF∈(0, 1) represent that, if P is true, C is true to a certain extent.
Regular texture table in rule word bank and the fragment of rule condition table respectively as shown in table 2, table 3, the fragment in table Reflect the most whether certain position in storehouse can carry out this construction rule of concreting.
Table 2 regular texture table fragment
Rule_ID Num Fact_ID CF Active
R0001 1 F0025 1 F
R0002 2 F0032 0.9 F
R0008 5 F0010 1 F
Table 3 rule condition table fragment
Rule_ID Fact_ID Logic_relation Active
R0008 F0002 AND F
R0008 F0003 AND F
R0008 F0006 AND F
R0008 F0007 AND F
R0008 F0009 AND F
There is above agreement, it is possible to the rule in the rule represented at natural language and relational database mutually turns Change.According to table 2, table 3, the form of rule R0008 is as follows:
Height_Diff-FB_Bin(x,y)∧Height_Diff-LR_Bin(x,y)∧Pause_time(x)∧Rain (t)∧Adjoin_Bin(x)→FitPour-Bin(x)(1)
Again according to table 1, rule R0008 can be explained further into: if a certain position in storehouse " x " meet simultaneously before and after the discrepancy in elevation, a left side The right discrepancy in elevation, intermittent time, meteorological condition, adjacent position in storehouse are constructed 5 item constraints, then this position in storehouse can carry out concreting, rule Reliability be " 1 ".Thus establish concrete dam construction specification and expertise knowledge and computer can be grasped One-to-one relationship between the rule knowledge made, it is achieved that the intelligence in the computer information system of rule knowledge represents and deposits Storage.
Four, Method of Knowledge Reasoning
Knowledge reasoning refers to from existing basic data, by answering various production rules and the comprehensive of knowledge With, obtain the current decision-making of system or action scheme through reasoning.Specific to concrete dam construction problem, refer to according to mixed Coagulate the current execution conditions of earth dam and construction environment, before the related specifications and technology following concrete dam construction requires Putting, reasoning obtains the process of current concrete dam construction scheme.
The concrete dam construction intelligent decision system of a kind of KBE and the Method of Knowledge Reasoning master of method Disappear including rule-based uncertain inference mechanism, RBR Model Design, the conflict of Process Based Solve three aspect contents of strategy.
The fact that during concrete dam construction and rule all exists uncertainty, with concrete dam construction Based on the uncertain true expression regular with uncertainty and memory mechanism, set up concrete dam construction rule-based Uncertain inference mechanism, it is achieved the uncertain inference of concrete dam pouring system, i.e. intelligent inference.
The uncertain inference mechanism of the concrete dam construction intelligent decision system of a kind of KBE uses C-F uncertain inference model, C-F model be uncertain inference uses the earliest, simple and effective a kind of inference method.
A kind of uncertain inference algorithm bag in the concrete dam construction intelligent decision system of KBE Include four parts, ask the credibility of conclusion, the same knot of two independent premise derivation including according to the credibility of premise and rule The merging of the credibility of opinion, the conjunction of premise, the extracting of premise, the most just can carry out various reasoning computing. Wherein CF (P) represents the credibility of premise;The credibility of CF (R) delegate rules;CF (C) represents the credibility of conclusion.
(1) credibility of conclusion is sought according to the credibility of premise and rule
CF(C)=CF(R)×max{0,CF(P)}
If CF (P) > 0, i.e. rule premise to be true to a certain degree, then calculates rule according to CF (P) and Rules control CF (R) Then credibility CF (C) of conclusion=CF (R) × CF (P);
If CF (P)=0, i.e. condition are true or false and know nothing, then CF (C)=0, say, that conclusion true and false also one without institute Know.
If CF (P) < 0, i.e. rule premise are false, illustrate that this rule can not be applied, then CF (C)=0.
The merging of the credibility of the same conclusion of (2) two independent premise derivation, also referred to as fresh evidence (premise) rule
When combining the credibility of the same conclusion that plural independent premise derives, first merge two of which, its knot Fruit merges with the 3rd again, and the rest may be inferred.
(3) conjunction of premise
For P=P1∧P2∧P3∧…∧Pn, have
CF(P)=CF(P1∧P2∧P3∧…∧Pn)=min{CF(P1),CF(P2),…,CF(Pn)}
From above formula, the CF of the conjunction of multiple premises is the CF of that minimum for CF premise.
(4) the extracting of premise
For P=P1∨P2∨P3∨…∨Pn, have
CF(P)=CF(P1∨P2∨P3∨…∨Pn)=max{CF(P1),CF(P2),…,CF(Pn)}
From above formula, the CF extracted of multiple premises is the CF of that maximum for CF premise.
For uncertain inference, when the credibility of certain conclusion is not 1, for same conclusions other rules still Make inferences, obtain the credibility of conclusion, and merge with the credibility of this conclusion obtained.
A kind of concrete dam construction intelligent decision system of KBE using uncertain inference rule as Meta-knoeledge, is individually placed in reasoning module, is allowed to have automatic focusing properties, i.e. priority level the highest.This ensures that there two The rule (having different credibility) with same conclusions had been combined with before being triggered by other rules.
If Fig. 6 is reasoning pattern and the work of the concrete dam construction intelligent decision system of a kind of KBE Shown in flow process, the inference machine of the concrete dam construction intelligent decision system of a kind of KBE is according in data base Data, utilize the rule in knowledge base, by certain inference strategy, go Solve problems, the data explaining outside input and the fact, Derive conclusion and explain to user, the reason reached a conclusion is described as requested.
The concrete dam construction intelligent decision system of a kind of KBE belongs to design, the knowledge system of planning class System, solution space is very big, so selecting forward reasoning mode.
Forward reasoning is also referred to as data drive control, is from known data message, and forward uses rule, allows rule Former piece match with the record in data base and the fact, then enable rule conclusion part.
First forward reasoning is provided master data by user, leaves in data base, and then inference machine is operated, and it pushes away The key step of reason process is as follows:
(1) inference machine mates with the former piece of rule in rule base by this batch of fact.If the rule of only one coupling Then, then this rule is selected;If there being many rules to use, then select a rule therein according to Strategy of Conflict Resolution.
(2) the conclusion part fact of this rule is added in dynamic data base as new fact.
(3) with the fact that in the data base after renewal, (1), (2) step are repeated.So the most repeatedly until Resolving probiems or be given Till indeterminable reason.
So-called conflict refers to that a certain step in concrete dam construction solution formulation reasoning process has many rules can To use.Conflict resolution refers to select one from many rules that these are available for current reasoning;Strategy of Conflict Resolution It is how to select strategy or the method for best rule from many rules.
Feature according to concrete dam construction process: along with the increase of rule pre-condition, conclusion is currently Under the conditions of specific aim strengthen;Rules control is the highest, and conclusion is the most reliable.So at the concrete dam of KBE During pouring construction solution formulation, during rule-based uncertain inference, use following Strategy of Conflict Resolution.
Assume R1、R2For current spendable rule, then:
①GetNum(R1)、Num(R2)、CF(R1)、CF(R2)
②if Num(R1)Num(R2)then first_use_rule=R2goto⑤
③if Num(R2)Num(R1)then first_use_rule=R1goto⑤
④if CF(R1)≤CF(R2)then first_use_rule=R2else first_use_rule=R1
⑤end
Wherein Num (R1)、Num(R2) it is R1、R2Condition set, CF (R1)、CF(R2) it is R1、R2Credibility.When there being more than two Rule when can use, try to achieve first with this strategy and front two rules preferentially use rule, then this rule is advised with Article 3 Then compare, carry out successively, until finding best rule.

Claims (5)

1. utilize the method that the concrete dam construction intelligent decision system of KBE carries out decision-making, its feature Being: include the concrete dam construction intelligent decision system of KBE, this system includes engineering information storehouse, construction Rule base, intelligent inference system and functional module system;Engineering information storehouse includes arrangement and method for construction information, job site information and dam The data of three aspects of body Model information, the basic data support providing comprehensive is run in engineering information storehouse for system;Construction rule The expertise in the Its Relevant Technology Standards of storage and management concrete dam construction, technology requirement and industry is then responsible in storehouse And the rule knowledge of other concrete dam construction;The thinking process of the intelligent inference system simulation mankind, with rule base of constructing Interior rule is reasoning foundation, and according to the related data in engineering information storehouse, based on data, reasoning obtains the conclusion being correlated with Or constructing operation;Functional module system includes position in storehouse orchestration module, machinery scheduler module, plan-validation module, progress simulation mould Block, schedule module of getting the raw materials ready, grouting schedule module and water flowing scheme module;
The method of decision-making is as follows: comprise the steps:
(1) conventionally form represents the premise of knowledge and the extraction of conclusion,
In current concrete dam construction management with decision making process, it is full whether a certain position in storehouse concrete can pour needs Discrepancy in elevation restriction before and after foot, the left and right discrepancy in elevation limit, the interlayer intermittent time limits, meteorological condition limits, the construction of adjacent position in storehouse retrains this A little restrictions and constraints;When all of precondition meets, this position in storehouse can carry out pouring construction;From knowledge engineering Production rule angle understands, with constraints, these limit regards whether a certain position in storehouse can pour the premise bar of this rule as Part, " can pour " is then corresponding to the conclusion of this rule;
In the step for knowledge is extracted, it is that whether the concrete position in storehouse represented with conventionally form can be poured this is sentenced Disconnected work is converted into the premise part of rule, conclusion part, reliability form;The premise whether concrete position in storehouse can pour has The discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, 5 aspects of adjacent construction front and back;Conclusion maybe cannot be watered for pouring Build, for 0-1 variable;According to concrete dam construction specification, this rule is completely reliable;
(2) rule premise, conclusion, the quantization of reliability, classification,
On the basis of (one) step work, carry out quantifying, classifying or classification by the premise of rule, conclusion, reliability;
The discrepancy in elevation front and back: represent with absolute physical value, is i.e. represented with the actual discrepancy in elevation of front and back's position in storehouse, is represented by Formal Languages For Height_Diff-FB_Bin (x, y);The discrepancy in elevation before and after i.e. position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, otherwise It it is then negative value;
The left and right discrepancy in elevation: represent with absolute physical value, is i.e. represented with the actual discrepancy in elevation of left and right position in storehouse, is represented by Formal Languages For Height_Diff-LR_Bin (x, y);The i.e. left and right discrepancy in elevation of position in storehouse x and position in storehouse y, position in storehouse x higher than position in storehouse y be on the occasion of, otherwise It it is then negative value;
Intermittent time: represent with absolute physical value, both pouring the deadline with the bottom position in storehouse of current position in storehouse will plus specification Ask or on the basis of the intermittent time of current engineering setting, it is judged that whether current time had arrived in this time period;Pass through form Changing language table and be shown as Pause_time (x), its value is absolute calendar time, and its form is " MM/dd/yyyy hh:mm;ss”;
Meteorological condition: whether current position in storehouse is poured by meteorological condition is to consider from rainfall angle, by carrying out rainfall point Level;Being expressed as Rain (t) by Formal Languages, " t " is the time drafting moduling plan herein, the value root of Rain (t) According to the weather forecast parameter determination in data base;
Adjacent position in storehouse construction constraint: the construction constraint of adjacent position in storehouse refers to when certain position in storehouse casting concrete, adjacent thereto its Its position in storehouse is because draining, template erection and the cause of failures that puts in storage cannot carry out concrete pouring construction simultaneously;This is constrained to 0-1 and becomes Amount constraint, when there are adjacent position in storehouse just at casting concrete, this position in storehouse can not casting concrete, this binding occurrence is 0;Instead It, all positions in storehouse adjacent thereto are not the most at casting concrete, then current position in storehouse can carry out concrete pouring construction, this constraint Value is 1;It is expressed as Adjoin_Bin (x) by Formal Languages;Which position in storehouse is the adjacent position in storehouse of current position in storehouse, according to dam body The three-dimensional relationship of model parameter determines;
Conclusion: whether can pour the judgement of sets of conditions according to above current position in storehouse, conclusion maybe cannot be watered for pouring Build, for 0-1 variable;By Formal Languages, it is expressed as FitPour-Bin (x);
Reliability: according to concrete dam construction specification, this rule is completely reliable, i.e. reliability is 1:CF=1;
(3) formalization of production rule,
In the concrete dam construction intelligent decision system of KBE, by (two) step rule premise, Conclusion, the quantization of reliability, classification, and the statement of Formal Languages, " a certain during concrete dam construction Whether position in storehouse concrete can pour under current state " judgement of this event is expressed as following production rule:
The precondition of this rule is executed for the discrepancy in elevation, the left and right discrepancy in elevation, intermittent time, meteorological condition, adjacent position in storehouse before and after meeting simultaneously Work retrains, it may be assumed that P=Height_Diff-FB_Bin (x, y) ∧ Height_Diff-LR_Bin (x, y) ∧ Pause_time (x) ∧Rain(t)∧Adjoin_Bin(x);The conclusion of this rule is that current position in storehouse can be with casting concrete, it may be assumed that C=FitPour- Bin(x);The credibility of rule is 1;So, current rule can be expressed as:
Height_Diff-FB_Bin(x,y)∧Height_Diff-LR_Bin(x,y)∧Pause_time(x)∧Rain(t) ∧Adjoin_Bin(x)→FitPour-Bin(x)(1)
(4) rule inspection,
The inspection of rule is the important step of production rule acquisition work, is the examination to abovementioned steps gained knowledge and handle Close;In this step, major tasks are that by reflecting that this rule is verified by the example of various condition of construction, check The conclusion of its output is the most correct;For the output incorrect situation of conclusion, need check its reasoning process in detail and find former Cause;In rule inspection, verified adaptability and the correctness of this rule by some construction parameters in particular cases;If passed through After system test, do not find current rule existing problems, then this rule warehouse-in is preserved;If it find that existing problems, then need Current rule is extracted and formalization again, i.e. repeats step ()-step (three);
(5) again extract or formalization, for being found to have the rule of reasoning impropriety in checkout procedure, repeat step (1)-step (three), extracts or formalization again to this rule;
(6) warehouse-in, for rule qualified after inspection, is deposited in rule base, protects with the form of relational database Deposit.
The concrete dam construction intelligent decision system utilizing KBE the most according to claim 1 is carried out certainly The method of plan, it is characterised in that: the engineering letter of the concrete dam construction intelligent decision system of described KBE Breath storehouse specifically includes construction environment characteristic parameter, dam structure characteristic parameter, construction machinery characteristic parameter, construction technical requirement ginseng Number, material parameter, arrangement and method for construction parameter and engineering construction parameter.
The concrete dam construction intelligent decision system utilizing KBE the most according to claim 2 is carried out certainly The method of plan, it is characterised in that: described construction environment characteristic parameter includes rainfall, snowfall, water temperature and flow;Dam body is tied Structure characteristic parameter includes monolith structural parameters, position in storehouse spatial parameter, hollow spaces parameter and concrete performance parameter;Construction machinery Characteristic parameter includes the space orientation of concrete warehousing construction machinery, service behaviour, operation characteristic and working range;Construction technology The dam concrete pouring construction discrepancy in elevation limits, the intermittent time limits and temperature-controlled parameter to require parameter to include;Material parameter bag Include dam concrete match ratio, sandstone production and storage system and concrete storage system;Arrangement and method for construction parameter includes concrete Pour schedule requirement, mechanization and special technical requirement;Engineering construction parameter includes that concrete dam construction is on-the-spot Pour position in storehouse, be in the milk/water flowing position, respectively put in storage machinery current location.
The concrete dam construction intelligent decision system utilizing KBE the most according to claim 1 is carried out certainly The method of plan, it is characterised in that: described construction rule base specifically includes dam concrete and mixes and stirs technology requirement, concrete transportation Technology requires, dam concrete pours rule, concrete water flowing cooling is regular and dam body joint grouting rule.
The concrete dam construction intelligent decision system utilizing KBE the most according to claim 4 is carried out certainly The method of plan, it is characterised in that: described dam concrete mix technology requires to include concrete type, refrigeration requires and mix Time;Concrete transportation technology requires to include the free-electron model height in transportation, transhipment number of times and haulage time dam body and mixes Solidifying soil pours discrepancy in elevation restriction, intermittent time and the curing time that rule includes in concreting process;Concrete water flowing cools down Rule includes the beginning and ending time of dam concrete water flowing, trigger condition, water temperature and flow;Dam body joint grouting rule includes dam body The production of concrete mix, sandstone and storage system and concrete store system;Arrangement and method for construction parameter includes dam body joint grouting Time started, trigger condition and grouting region.
CN201310232318.8A 2013-06-13 2013-06-13 The concrete dam construction intelligent decision system of KBE and method thereof Active CN103337041B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310232318.8A CN103337041B (en) 2013-06-13 2013-06-13 The concrete dam construction intelligent decision system of KBE and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310232318.8A CN103337041B (en) 2013-06-13 2013-06-13 The concrete dam construction intelligent decision system of KBE and method thereof

Publications (2)

Publication Number Publication Date
CN103337041A CN103337041A (en) 2013-10-02
CN103337041B true CN103337041B (en) 2016-08-17

Family

ID=49245193

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310232318.8A Active CN103337041B (en) 2013-06-13 2013-06-13 The concrete dam construction intelligent decision system of KBE and method thereof

Country Status (1)

Country Link
CN (1) CN103337041B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104678954A (en) * 2015-01-23 2015-06-03 中国长江三峡集团公司 Dam safety intelligent monitoring and pre-warning system based on full life circle and method thereof
CN105332378B (en) * 2015-10-19 2017-03-22 中国水利水电科学研究院 Intelligent temperature control grouting system for concrete dam joint
CN105976273A (en) * 2016-04-29 2016-09-28 华能澜沧江水电股份有限公司 Highly roller compacted concrete dam construction procedure quality evaluation system and method
CN106251247A (en) * 2016-07-14 2016-12-21 长江三峡勘测研究院有限公司(武汉) A kind of aggregate quality evaluating method based on sandstone
JP6891039B2 (en) * 2017-05-17 2021-06-18 大和ハウス工業株式会社 Concrete construction management system
CN108304624B (en) * 2018-01-15 2021-08-13 北京航空航天大学 Inference decision method for artificial intelligence programmer to write digital aircraft source code
CN108596466B (en) * 2018-04-18 2019-05-31 河海大学 Concrete dam storehouse surface is vibrated mechanical Construction simulation method
CN109002674A (en) * 2018-10-09 2018-12-14 浙江省水利水电勘测设计院 A kind of tunnel group construction speed emulation mode and system
CN110512607B (en) * 2019-07-08 2021-03-09 中国三峡建设管理有限公司 Intelligent warehouse preparation method
CN110619186B (en) * 2019-09-25 2023-01-06 三峡大学 N-dimensional feature modeling method for concrete dam construction system
CN110619187B (en) * 2019-09-25 2022-12-16 三峡大学 Concrete dam construction scheme and resource conflict detection and adjustment method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102609774A (en) * 2012-01-31 2012-07-25 华中科技大学 System and method for identifying and reasoning security risks of metro construction
CN102693289A (en) * 2012-05-14 2012-09-26 中国水电顾问集团成都勘测设计研究院 Simulation method for high arch dam construction

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102609774A (en) * 2012-01-31 2012-07-25 华中科技大学 System and method for identifying and reasoning security risks of metro construction
CN102693289A (en) * 2012-05-14 2012-09-26 中国水电顾问集团成都勘测设计研究院 Simulation method for high arch dam construction

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
三峡大坝混凝土快速施工方案及工艺研究;戴会超等;《中国三峡建设》;20020731;第10页至12页 *
混凝土坝施工管理决策支持***;邱世明等;《天津大学学报》;20050531;第35卷(第3期);第392页至396页 *
混凝土坝施工***仿真理论方法与应用研究;练继亮;《中国博士学位论文电子期刊》;20041231;第102页第1段至108页第1段、图5-1,图5-2,图5-3 *

Also Published As

Publication number Publication date
CN103337041A (en) 2013-10-02

Similar Documents

Publication Publication Date Title
CN103337041B (en) The concrete dam construction intelligent decision system of KBE and method thereof
Ferrão et al. Sustainable urban metabolism
Chen et al. Forecasting container throughputs at ports using genetic programming
Li et al. Concepts, methodologies, and tools of an integrated geographical simulation and optimization system
Glover Tabu search—part I
Yang et al. The need for local adaptation of smart infrastructure for sustainable economic management
CN106997511A (en) Railway beam yard management system and railway beam yard management method based on BIM technology
Zamyatina et al. Single-industry towns of Russia: lock-in and drivers of innovative search
Dai et al. Agent-based model of land system: Theory, application and modelling framework
Xu et al. Environmental disaster risk reduction-oriented centralized treatment of hazardous wastes: A novel approach for production-distribution decision optimization in China
CN103628483B (en) The concrete dam pouring mechanically combining that puts in storage builds simulation and optimum method
Sjaifuddin Environmental management of industrial estate based on eco-industrial parks: a system dynamics modeling
Li Application of the BP neural network model of gray relational analysis in economic management
Russo et al. Emerging ICT in port operations: Case studies
Meng et al. CBR-RBR fusion based parametric rapid construction method of bridge BIM model
CN117057335A (en) Intelligent generation method for four pre-schemes of flood control in drainage basin
CN103824158B (en) A kind of villages and small towns space planning network system of flow guiding
CN109670746A (en) Chinese medicine Location Selection of Logistics Distribution Center method, readable storage medium storing program for executing and terminal
Huang et al. Modeling Agricultural Logistics Distribution Center Location Based on ISM.
Chen et al. Neural networked-assisted method for the nurse rostering problem
Mishchenko et al. Experience in the use of artificial intelligence in making managerial decisions in the construction of real estate
Huang Modeling and Planning on Urban Logistics Park Location Selection Based on the Artificial Neural Network.
Zhou Prediction of Urban and Rural Tourism Economic Forecast Based on Machine Learning
Yi Research on building material design in circular economy based on improved neural network
Hodková et al. Envimat. cz–Online database of environmental profiles of building materials and structures

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 430033 Hubei province in Qiaokou District of Wuhan City Jiefang Road Gezhouba Dam Building No. 558

Applicant after: CHINA GEZHOUBA GROUP Co.,Ltd.

Address before: 443002 Hubei Province in Qiaokou District of Wuhan City Jiefang Road Gezhouba Dam Building No. 558

Applicant before: CHINA GEZHOUBA GROUP Co.,Ltd.

Address after: 443002 Hubei Province in Qiaokou District of Wuhan City Jiefang Road Gezhouba Dam Building No. 558

Applicant after: CHINA GEZHOUBA GROUP Co.,Ltd.

Address before: 443002 Hubei province Yichang City Road No. 1

Applicant before: CHINA GEZHOUBA GROUP Co.,Ltd.

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171228

Address after: 830049 No. 918 Xinhua South Road, the Xinjiang Uygur Autonomous Region, Urumqi

Patentee after: Gezhouba Xinjiang Engineering Co.,Ltd.

Address before: 430033 Hubei province in Qiaokou District of Wuhan City Jiefang Road Gezhouba Dam Building No. 558

Patentee before: CHINA GEZHOUBA GROUP Co.,Ltd.