CN102943564A - Flexible concrete rabbet connecting construction method - Google Patents

Flexible concrete rabbet connecting construction method Download PDF

Info

Publication number
CN102943564A
CN102943564A CN2012104071543A CN201210407154A CN102943564A CN 102943564 A CN102943564 A CN 102943564A CN 2012104071543 A CN2012104071543 A CN 2012104071543A CN 201210407154 A CN201210407154 A CN 201210407154A CN 102943564 A CN102943564 A CN 102943564A
Authority
CN
China
Prior art keywords
concrete
template
stubble
wood lath
strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104071543A
Other languages
Chinese (zh)
Inventor
江青海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Original Assignee
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd, North China Metallurgical Construction Engineering Construction Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN2012104071543A priority Critical patent/CN102943564A/en
Publication of CN102943564A publication Critical patent/CN102943564A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Sewage (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A flexible concrete rabbet connecting construction method mainly comprises the following steps: attaching a fixing wooden slat to the inner side of the top of a moulding plate so as to reserve an L-shaped rabbet at a connecting position of a bottom concrete component; sticking and nailing a through elastic sealing strip at the bottom of the moulding plate; rightly pressing the elastic sealing strip into the L-shaped rabbet reserved in the bottom concrete component; and the like. According to the flexible concrete rabbet connecting construction method, in construction, the problems of dislocation, slurry leakage, unsmooth and straight connection and the like of the connecting position can be effectively avoided and the pouring quality of concrete at the connecting position is ensured; and after the construction, a beautiful, unsmooth and straight protruding strip is formed at the connecting position.

Description

The flexible tongue and groove joint stubble of a kind of concrete job practices
Technical field
The present invention relates to a kind of concrete component construction method, particularly a kind of job practices of two-layer concrete member joint part.
Background technology
The concrete structure is that present China building engineering is used maximum form of structure, yet, faulting of slab ends, the spillage that concrete structure joint part exists, connect the problems such as stubble is not straight, it all is a weak part of concrete cast-in-place structural all the time, the joint part reason is bad, make not only that lines are not straight, stream slurry, affect the attractive in appearance of concrete structure, even can cause the quality problems such as concrete honeycomb, pitted skin, leakage muscle, hole.Therefore, the construction processing that concrete is connect stubble all is the problem that concrete construction is explored all the time.The job practices of conventional concrete structure joint part has template directly to be adjacent to method, later stage to smear the band method and paste sponge strip method etc. usually.Mainly there is following problem in this several method:
(1) template directly is adjacent to method:
The method is directly template to be touched the concrete face that has watered to reinforce, because the smooth deviation that exists of concrete face is easy to cause spillage, faulting of slab ends in casting process, connects stubble second-rate.The method is conventional construction method the earliest, seldom adopts now.
(2) later stage is smeared the band method:
The method is in order to remedy the mass defect of concrete joint part, at the concrete joint part of building, to smear out a band with cement mortar artificially, to cover the defective of joint part outside.Although the method has been covered the External Defect of joint part, can not guarantee the inherent quality of joint part, also consume simultaneously a large amount of artificial and materials, increased construction cost.
(3) paste the sponge strip method:
The method is present the most frequently used method, and it is sponge strip of stickup first artificial on the concrete face of bottom concrete joint part, and then installs upper former, to reaching the not purpose of spillage.But also there are a lot of drawbacks in the method: at first, owing on the concrete face floating dust being arranged, sponge strip generally is pasted not strongly, at formwork or when building concrete, and the easy local shedding of sponge strip, thus cause spillage, can not guarantee to connect a batch quality fully.Secondly, during the out-of-flatness of concrete face sponge strip be not easy to paste straight, thereby impact connects the attractive in appearance of stubble.Again, after concrete was built and finished, sponge strip is easy-clear not, simultaneously, pasted, removed sponge strip and need to expend certain artificial and material.
Summary of the invention
In order to solve faulting of slab ends, spillage that concrete structure joint part in the prior art exists, to connect the not straight technical problem of stubble, the purpose of this invention is to provide the flexible tongue and groove joint stubble of a kind of concrete job practices, utilize the method to carry out the concrete structure and connect the stubble construction, can effectively solve faulting of slab ends, spillage that concrete structure joint part exists, connect the not straight technical problem of stubble, guarantee the quality of concrete structure joint part.After construction is finished, form a beautiful recessed band at joint part, straight, attractive in appearance.
To achieve these goals, the invention provides the flexible tongue and groove joint stubble of a kind of concrete job practices, may further comprise the steps:
Step 1 installs bottom concrete component template, and fixes a wood lath the template inside top is additional;
Step 2 is carried out the bottom concrete and is built, build finish after, certain distance in the wood lath wedging bottom concrete member;
Step 3, bottom concrete are dismantled template after building and finishing certain hour, are formed the tongue and groove of " L " type by described wood lath at the joint part of bottom concrete member;
Step 4, the thicker elongated elastic sealing strip of thickness of an above-mentioned wood lath of Thickness Ratio of the sticking nail in the bottom of the template under dismounting;
Step 5, the template of sticking nail spring seal strip just in time are pressed into this elastic sealing strip in " L " type tongue and groove that bottom concrete member reserves when installing upper strata concrete component template turnover and use, then fixed form routinely;
Step 6 is carried out the upper strata concrete and is built, and finishes one and connects the stubble construction.
Preferably, described elastic sealing strip is rubber strip.
Preferably, the thickness of described wood lath is 3mm.
Preferably, the thickness of described rubber strip is 6mm.
Preferably, described wood lath is three-ply board.
The invention has the beneficial effects as follows:
1, bottom concrete member has been reserved tongue and groove, increased the spatial accommodation of elastic sealing strip, it is poorly sealed that the template that can avoid causing because of concrete face deviation is pressed onto the inclined to one side recess weather strip of elastic limit concrete face with weather strip, thereby cause the phenomenon of spillage, guaranteed the pouring quality of joint part concrete.
2, weather strip in advance sticking nail on template, both guaranteed the straight of weather strip, be unlikely to again partially recessed because of concrete face part, make template applying defective tightness and cause weather strip to come off.
3, the wood lath of the method and weather strip all are fixed on the template, can have enough to meet the need use, and be time saving and energy saving, saves cost.
4, after application the method is finished construction, form a beautiful recessed band at two-layer concrete face joint part, straight, attractive in appearance.
Description of drawings
Fig. 1 is the schematic diagram that the present invention carries out reserving when the bottom concrete is built tongue and groove;
Fig. 2 be bottom concrete of the present invention build finish after the partial enlarged drawing of reservation tongue and groove;
Fig. 3 is that the present invention carries out upper strata concrete tongue and groove joint stubble schematic diagram when building;
Fig. 4 is the partial enlarged drawing at A place among Fig. 3.
Reference numeral:
1: template 2: wood lath 3: elastic sealing strip
4: tongue and groove 5: split bolt 6: rough ground
7: concrete
The specific embodiment
In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention is described in further detail below in conjunction with accompanying drawing, and obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making all other embodiment that obtain under the creative work prerequisite.Therefore, accompanying drawing is illustrative with being described in essence, rather than is used for the protection domain of restriction claim.In addition, in this manual, accompanying drawing draws not in scale, and identical Reference numeral represents identical part.
When building bottom concrete member, install first bottom concrete component template, by rough ground 6 and split bolt 5 that template 1 is fixing as shown in Figure 1, and fix a wood lath 2 the inside top of template 1 is additional, then carry out the bottom concrete and build.Build finish after, certain distance in the wood lath 2 wedging bottom concrete members.The present embodiment wood lath 2 is preferably three-ply board, and is apparent, also can be the suitable planks of other thickness of job site.
According to execution conditions, the bottom concrete is dismantled template 1 after building and finishing certain hour, as shown in Figure 2, is formed the tongue and groove 4 of " L " type by described wood lath 2 at the joint part of bottom concrete member.
After template 1 was pulled down, as shown in Figure 3, at elongated elastic sealing strip 3 of the sticking nail in the bottom of template 1, the thickness of the above-mentioned wood lath 2 of the Thickness Ratio of this elastic sealing strip 3 was thicker.The thickness of the preferred wood lath 2 of the present embodiment is 3mm, and the thickness of elastic sealing strip is 6mm.
Then prepare to install upper strata concrete component template, the template 1 of sticking nail spring seal strip 3 can be had enough to meet the need use when installing upper strata concrete component template, template 1 when installing, as shown in Figure 4, described elastic sealing strip 3 just in time should be pressed in " L " type tongue and groove 4 that bottom concrete member reserves, thereby elastic sealing strip and the bottom concrete member of having built are fitted tightly, then routinely by rough ground 6 and split bolt 5 fixed forms 1.In the present embodiment, elastic sealing strip 3 is preferably rubber strip, and rubber strip had both had certain elasticity, has again certain degree of hardness, thereby is convenient to be fixed in the below of template 1.Obviously, elastic sealing strip 3 also can be other materials with certain elasticity and certain degree of hardness, such as sponge strip, Ethylene Propylene Terpolymer bar, polyurethane strip etc.
At last, carry out the upper strata concrete and build, under the effect of tongue and groove 4 and elastic sealing strip 3, effectively avoided joint part occurs in the casting process faulting of slab ends, spillage, connect the problems such as stubble is not straight.So far, finish one and connect the stubble construction.According to requirement of engineering, can repeat above step and finish and connect accordingly stubble construction.
As mentioned above, according to the flexible tongue and groove joint stubble of concrete of the present invention job practices, can use by the joint part on any direction of the normal temperature of concrete structure or similar concrete structure, non-corrosiveness injection-molded structure, in work progress, can effectively avoid faulting of slab ends, spillage that joint part occurs, connect the problems such as stubble is not straight, guarantee the pouring quality of joint part.After construction is finished, form a beautiful recessed band at joint part, straight, attractive in appearance.

Claims (5)

1. the flexible tongue and groove joint stubble of concrete job practices is characterized in that may further comprise the steps:
Step 1 installs bottom concrete component template, and fixes a wood lath the template inside top is additional;
Step 2 is carried out the bottom concrete and is built, build finish after, certain distance in the wood lath wedging bottom concrete member;
Step 3, bottom concrete are dismantled template after building and finishing certain hour, are formed the tongue and groove of " L " type by described wood lath at the joint part of bottom concrete member;
Step 4, the thicker elongated elastic sealing strip of thickness of an above-mentioned wood lath of Thickness Ratio of the sticking nail in the bottom of the template under dismounting;
Step 5, the template of sticking nail spring seal strip just in time are pressed into this elastic sealing strip in " L " type tongue and groove that bottom concrete member reserves when installing upper strata concrete component template turnover and use, then fixed form routinely;
Step 6 is carried out the upper strata concrete and is built, and finishes one and connects the stubble construction.
2. the flexible tongue and groove joint stubble of concrete according to claim 1 job practices, it is characterized in that: described elastic sealing strip is rubber strip.
3. the flexible tongue and groove joint stubble of concrete according to claim 1 job practices, it is characterized in that: the thickness of described wood lath is 3mm.
4. the flexible tongue and groove joint stubble of concrete according to claim 1 and 2 job practices, it is characterized in that: the thickness of described rubber strip is 6mm.
5. the flexible tongue and groove joint stubble of concrete according to claim 1 job practices, it is characterized in that: described wood lath is three-ply board.
CN2012104071543A 2012-10-23 2012-10-23 Flexible concrete rabbet connecting construction method Pending CN102943564A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104071543A CN102943564A (en) 2012-10-23 2012-10-23 Flexible concrete rabbet connecting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104071543A CN102943564A (en) 2012-10-23 2012-10-23 Flexible concrete rabbet connecting construction method

Publications (1)

Publication Number Publication Date
CN102943564A true CN102943564A (en) 2013-02-27

Family

ID=47726543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104071543A Pending CN102943564A (en) 2012-10-23 2012-10-23 Flexible concrete rabbet connecting construction method

Country Status (1)

Country Link
CN (1) CN102943564A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485418A (en) * 2013-09-26 2014-01-01 中国华冶科工集团有限公司 Concrete structure inter-layer indirect jointing method
CN105484498A (en) * 2016-01-04 2016-04-13 中国建筑第八工程局有限公司 Anti-slurry-leakage construction method of core tube wall
CN108425319A (en) * 2018-05-29 2018-08-21 上海宝冶集团有限公司 A kind of construction system and form of construction work of column
CN111894269A (en) * 2020-07-06 2020-11-06 五冶集团上海有限公司 Construction method for reinforcing structure of wall and column external mold

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101349106A (en) * 2008-08-26 2009-01-21 江苏南通二建集团有限公司 Dual-shear force wall deformation slit formwork
CN201268943Y (en) * 2008-08-26 2009-07-08 江苏南通二建集团有限公司 Novel dual-shearing force deformation joint template
CN101644079A (en) * 2009-06-08 2010-02-10 中铁建工集团有限公司 Construction method of reinforced concrete shear wall body
CN201486133U (en) * 2009-07-17 2010-05-26 中达建设集团股份有限公司 Reinforced concrete double-shear wall template
CN101876184A (en) * 2010-06-23 2010-11-03 河北省第二建筑工程公司 Construction method of expansion joint of pool
KR20110050898A (en) * 2009-11-09 2011-05-17 (주)시우에스티 Vertical joint frame for improving monolithic concrete
CN102650158A (en) * 2012-04-24 2012-08-29 中天建设集团有限公司 Connecting device used in casting of shear walls in upper and lower layers

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101349106A (en) * 2008-08-26 2009-01-21 江苏南通二建集团有限公司 Dual-shear force wall deformation slit formwork
CN201268943Y (en) * 2008-08-26 2009-07-08 江苏南通二建集团有限公司 Novel dual-shearing force deformation joint template
CN101644079A (en) * 2009-06-08 2010-02-10 中铁建工集团有限公司 Construction method of reinforced concrete shear wall body
CN201486133U (en) * 2009-07-17 2010-05-26 中达建设集团股份有限公司 Reinforced concrete double-shear wall template
KR20110050898A (en) * 2009-11-09 2011-05-17 (주)시우에스티 Vertical joint frame for improving monolithic concrete
CN101876184A (en) * 2010-06-23 2010-11-03 河北省第二建筑工程公司 Construction method of expansion joint of pool
CN102650158A (en) * 2012-04-24 2012-08-29 中天建设集团有限公司 Connecting device used in casting of shear walls in upper and lower layers

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
洪涛: "探讨钢筋混凝土剪力墙结构大模板施工工艺", 《建筑与装饰》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485418A (en) * 2013-09-26 2014-01-01 中国华冶科工集团有限公司 Concrete structure inter-layer indirect jointing method
CN103485418B (en) * 2013-09-26 2016-09-14 中国华冶科工集团有限公司 The method of the indirect stubble of concrete
CN105484498A (en) * 2016-01-04 2016-04-13 中国建筑第八工程局有限公司 Anti-slurry-leakage construction method of core tube wall
CN108425319A (en) * 2018-05-29 2018-08-21 上海宝冶集团有限公司 A kind of construction system and form of construction work of column
CN108425319B (en) * 2018-05-29 2024-04-05 上海宝冶集团有限公司 Construction system and construction mode of stand column
CN111894269A (en) * 2020-07-06 2020-11-06 五冶集团上海有限公司 Construction method for reinforcing structure of wall and column external mold

Similar Documents

Publication Publication Date Title
CN109267709B (en) Deformation joint anti-leakage structure and repairing method thereof
CN102644362B (en) Architectural decoration plastering construction method
CN103343655B (en) Wall window construction method
CN101487335B (en) External wall heat-preserving decoration wall and its construction process
CN102943564A (en) Flexible concrete rabbet connecting construction method
CN209942141U (en) Floor and stone or ceramic tile splicing structure
CN203160283U (en) Construction of horizontal construction joints of underground building waterproof outer walls
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN101761286A (en) Installation method of aluminum alloy door/window
CN104453011A (en) Light outer wall structure and construction method thereof
CN102677858B (en) Back hanging piece for installing decorative inorganic tetrafluoromethane veneer and construction method of back hanging piece
CN109881864A (en) A kind of joining method and structure on floor and stone material or ceramic tile
CN110080450B (en) Aluminum plate for outdoor piano keyboard type overhanging suspended ceiling and construction method thereof
JP6146244B2 (en) Waterproof structure and waterproofing method for external floor
CN205976290U (en) Compound incubation intergral template anchor is held in palm and is hung structure
CN214884349U (en) A protrusion structure that is used for window frame antiseep installation that wafts outward
CN213174595U (en) Closing-in system of assembled wall surface material seam area
CN110528912B (en) Construction method of integral bathroom
JP2007046444A (en) Externally thermal-insulated corner wall material
CN209603455U (en) A kind of precast facade ceramic tile is counter to beat lining mould
CN210289126U (en) A mould shell piece structure for close girt beam is pour
CN209443676U (en) The eave structure of Chinese style building roof
CN208518097U (en) Shower cabinet waterproof construction
CN205224539U (en) Sectional type is fallen from power rank and keep warm to be decorated stringcourse fixing device
CN204551288U (en) The fixed protection instrument of composite fiber plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130227