CN102587405A - 海上风机导管架基础安装方法及分离式导管架装置 - Google Patents

海上风机导管架基础安装方法及分离式导管架装置 Download PDF

Info

Publication number
CN102587405A
CN102587405A CN2012100451399A CN201210045139A CN102587405A CN 102587405 A CN102587405 A CN 102587405A CN 2012100451399 A CN2012100451399 A CN 2012100451399A CN 201210045139 A CN201210045139 A CN 201210045139A CN 102587405 A CN102587405 A CN 102587405A
Authority
CN
China
Prior art keywords
jacket
guide pipe
pipe frame
sea bed
pile tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100451399A
Other languages
English (en)
Inventor
朱荣华
傅强
张康
崔靓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Mingyang Wind Power Group Co Ltd
Original Assignee
Guangdong Mingyang Wind Power Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Mingyang Wind Power Group Co Ltd filed Critical Guangdong Mingyang Wind Power Group Co Ltd
Priority to CN2012100451399A priority Critical patent/CN102587405A/zh
Publication of CN102587405A publication Critical patent/CN102587405A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

本发明公开了分离式导管架装置,包括有水平设置在海床面上的导管架体,该导管架体包括有多根导管架腿,在各根导管架腿中***有固定在海床面上的管桩,导管架体的顶部设置有可安装风机榙筒的导管架平台,所述各根管桩上端平齐切断后并通过焊接方式与导管架平台连接在一起。另外公开了海上风机导管架基础安装方法,包括如下步骤:A、安放导管架体,将导管架体放置到海床上,调整导管架体,使导管架体水平放置在海床上。B、打桩,将管桩相应地从各根导管架腿中***,并使管桩进入海床,之后利用打桩机将管桩打入海床中并使管桩牢固地置于海床中,而管桩上端则露出导管架腿一部分。C、灌浆,管桩与导管架腿之间的间隙之间灌入水泥砂浆。

Description

海上风机导管架基础安装方法及分离式导管架装置
【技术领域】
本发明涉及一种海上风机导管架基础安装方法及分离式导管架安装装置。
【背景技术】
由于陆上风资源有限、且陆上风机日趋饱和,海洋已成为风力发电的新场地。国内外传统的海上风机导管架基础,一般将管桩通过打桩机打到海床面上,然后放置导管架,最后在导管架桩腿和钢管桩之间灌浆固定。
传统的这种导管架结构施工在操作上比较困难,譬如水下打桩,管桩定位,管桩内部的杂质清除,水下灌浆以及风机榙筒基座调平等诸多问题。
本发明就是在此种情况下作出的。
【发明内容】
本发明目的是克服了现有技术中的不足而提供一种使用效果好、定位容易的海上风机安装装置。
本发明的另一目的是提供一种使用效果好、定位容易、操作简单的海上风机导管架基础安装方法。
为了解决上述存在的技术问题,本发明采用下列技术方案:
分离式导管架装置,其特征在于包括有水平设置在海床面3上的导管架体1,该导管架体1包括有多根导管架腿2,在各根导管架腿2中***有固定在海床面3上的管桩4,导管架体1的顶部设置有可安装风机榙筒的导管架平台5,所述各根管桩4上端平齐切断后并通过焊接方式与导管架平台5连接在一起。
如上所述的分离式导管架装置,其特征在于在导管架腿2与管桩4之间的间隙灌有砂浆。
如上所述的分离式导管架装置,其特征在于在各根导管架腿2底部设有挡泥板7。
一种海上风机导管架基础安装方法,其特征在于包括有如下步骤:
A、安放导管架体,将具有多根导管架腿2和横杆8连接起来形成的导管架体1放置到海床上,并调整导管架体1,使导管架体1水平放置在海床上;
B、打桩,将管桩4相应地从各根导管架腿2中***,并使管桩4下端伸出导管架腿2,从而进入海床,之后利用打桩机将管桩4打入海床中并使管桩4牢固地置于海床中,而管桩4上端则露出导管架腿2一部分;
C、灌浆,打好管桩后,管桩与导管架腿2之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿2的底部并固定在海床上,而管桩与导管架腿2之间的间隙也会被充满。
如上所述的海上风机导管架基础安装方法,其特征在于还包括有安装导管架平台,在B步骤之后,将各根管桩4上端露出导管架腿2一部分平齐切断后,使各根管桩4的上端处于同一水平面,之后再将导管架平台5焊接固定在各根管桩4上,最终使导管架平台5处于水平位置,之后再进行灌浆步骤。
如上所述的海上风机导管架基础安装方法,其特征在于在各根导管架腿2底部设有挡泥板7。
本发明与现有技术相比有如下优点:
本发明的装置利用一个导管架体,先将其放置到海床上,之后再将管桩***导管架腿中并从导管架腿底部伸出并进入到海床中,之后利用打桩机将管桩打到海床中实现固定。
由于有导管架腿的定位,所以管桩的定位十分准确,同时导管架平台可以借助打入的钢桩调平。
而本发明的方法,利用了导管架装置,从而使该海上风机导管架基础安装方法具有使用效果好、定位容易、操作简单、安装高效、成本低等优点。
【附图说明】
图1是实施例一的立体图。
图2是实施例一的立体图。
图3是另一实施例的立体图。
【具体实施方式】
下面结合附图对本发明进行详细描述:
如图所示,分离式导管架装置,包括有水平设置在海床面3上的导管架体1。该导管架体1包括有多根导管架腿2。在各根导管架腿2中***有固定在海床面3上的管桩4。其安装方式为:先将管桩4***导管架腿2中并从导管架腿底部伸出并进入到海床中,之后利用打桩机将管桩打到海床中实现固定。有导管架腿的定位,所以管桩的定位十分准确。而导管架体1一部分浸泡在海水6中,另一部分则置于海平面上方。
导管架体1的顶部设置有可安装风机榙筒的导管架平台5。设置的导管架平台5有两种实施方式。
其中一种方式是:所述导管架平台5与导管架体1连为一体。即在将导管架体1放置到海床之前,导管架平台5就设置好在导管架体1上。
另一种方式是:所述各根管桩4上端平齐切断后并通过焊接方式与导管架平台5连接在一起。即,先将导管架体1放置到海床上,并将管桩打好在海床上之后,将管桩上部露出导管架腿的部分进行平齐切断后,再通过焊接方式与导管架平台5连接在一起。而本实施例就是采用此种实施方式。
作为本实施例的优选方式,在导管架腿2与管桩4之间的间隙灌有粘合料。所述的粘合料为砂浆。即,打好管桩之后,就需要灌浆,完成导管架体1的固定安装。
作为本实施例的优选方式,所述管桩4为钢桩。
作为本实施例的优选方式,所述导管架腿2的个数有四根,各个导管架腿2之间通过横杆8连接。
作为本实施例的优选方式,在各根导管架腿2底部设有挡泥板7,挡泥板7的作用主要是防止导管架沉入淤泥。
一种海上风机导管架基础安装方法,包括有如下步骤:
A、安放导管架体,将具有多根导管架腿2和横杆8连接起来形成的导管架体1放置到海床上,并调整导管架体1,使导管架体1水平放置在海床上。
B、打桩,将管桩4相应地从各根导管架腿2中***,并使管桩4下端伸出导管架腿2,从而进入海床,之后利用打桩机将管桩4打入海床中并使管桩4牢固地置于海床中,而管桩4上端则露出导管架腿2一部分。
C、灌浆,打好管桩后,管桩与导管架腿2之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿2的底部并固定在海床上,而管桩与导管架腿2之间的间隙也会被充满。
此外,本方法还包括有安装导管架平台,其中安装导管架平台的方式是:在B步骤之后,将各根管桩4上端露出导管架腿2一部分平齐切断后,使各根管桩4的上端处于同一水平面,之后再将导管架平台5焊接固定在各根管桩4上,最终使导管架平台5处于水平位置,之后再进行灌浆步骤。

Claims (6)

1.分离式导管架装置,其特征在于包括有水平设置在海床面(3)上的导管架体(1),该导管架体(1)包括有多根导管架腿(2),在各根导管架腿(2)中***有固定在海床面(3)上的管桩(4),导管架体(1)的顶部设置有可安装风机榙筒的导管架平台(5),所述各根管桩(4)上端平齐切断后并通过焊接方式与导管架平台(5)连接在一起。
2.根据权利要求1所述的分离式导管架装置,其特征在于在导管架腿(2)与管桩(4)之间的间隙灌有砂浆。
3.根据权利要求1或2所述的分离式导管架装置,其特征在于在各根导管架腿(2)底部设有挡泥板(7)。
4.一种海上风机导管架基础安装方法,其特征在于包括有如下步骤:
A、安放导管架体,将具有多根导管架腿(2)和横杆(8)连接起来形成的导管架体(1)放置到海床上,并调整导管架体(1),使导管架体(1)水平放置在海床上;
B、打桩,将管桩(4)相应地从各根导管架腿(2)中***,并使管桩(4)下端伸出导管架腿(2),从而进入海床,之后利用打桩机将管桩(4)打入海床中并使管桩(4)牢固地置于海床中,而管桩(4)上端则露出导管架腿(2)一部分;
C、灌浆,打好管桩后,管桩与导管架腿(2)之间会留有间隙,从间隙之间灌入水泥砂浆,并使水泥砂浆流入到导管架腿(2)的底部并固定在海床上,而管桩与导管架腿(2)之间的间隙也会被充满。
5.根据权利要求4所述的海上风机导管架基础安装方法,其特征在于还包括有安装导管架平台,在B步骤之后,将各根管桩(4)上端露出导管架腿(2)一部分平齐切断后,使各根管桩(4)的上端处于同一水平面,之后再将导管架平台(5)焊接固定在各根管桩(4)上,最终使导管架平台(5)处于水平位置,之后再进行灌浆步骤。
6.根据权利要求5所述的海上风机导管架基础安装方法,其特征在于在各根导管架腿(2)底部设有挡泥板(7)。
CN2012100451399A 2012-02-27 2012-02-27 海上风机导管架基础安装方法及分离式导管架装置 Pending CN102587405A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100451399A CN102587405A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及分离式导管架装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100451399A CN102587405A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及分离式导管架装置

Publications (1)

Publication Number Publication Date
CN102587405A true CN102587405A (zh) 2012-07-18

Family

ID=46476596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100451399A Pending CN102587405A (zh) 2012-02-27 2012-02-27 海上风机导管架基础安装方法及分离式导管架装置

Country Status (1)

Country Link
CN (1) CN102587405A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103225304A (zh) * 2013-04-28 2013-07-31 国电联合动力技术有限公司 一种海上基础支撑结构及其施工方法
CN103953055A (zh) * 2014-04-21 2014-07-30 广东明阳风电产业集团有限公司 一种海上风电机组水上四桩基础
CN104812963A (zh) * 2012-10-03 2015-07-29 技术项目有限公司 用于海上风力涡轮机的安装的基于重力的地基***和用于海上风力涡轮机地基***的安装的方法
CN105155569A (zh) * 2015-08-03 2015-12-16 浙江华蕴海洋工程技术服务有限公司 一种后打桩海上风机基础的施工装置及施工方法
CN105971000A (zh) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 一种海上风机嵌岩单桩基础临时施工平台
CN109853609A (zh) * 2018-12-25 2019-06-07 长江勘测规划设计研究有限责任公司 一种海上风电组合基础
CN112411603A (zh) * 2020-11-21 2021-02-26 南通泰胜蓝岛海洋工程有限公司 一种海上风电升压站的安装施工工艺
CN113638441A (zh) * 2020-04-27 2021-11-12 中国电建集团华东勘测设计研究院有限公司 一种桩桶组合式导管架支撑结构及其施工方法
CN114991148A (zh) * 2022-06-30 2022-09-02 福建永福电力设计股份有限公司 一种分体式吸力桩导管架安装定位架及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5551804A (en) * 1995-04-24 1996-09-03 Mcdermott International, Inc. Method of driving a pile
DE10109040C1 (de) * 2001-02-24 2002-07-11 Conrad Hansen Gründung für eine Windkraftanlage
CN201506979U (zh) * 2009-09-14 2010-06-16 中国水利水电科学研究院 一种海上风机桩基础与导管架腿柱的灌浆连接结构
CN101838997A (zh) * 2010-05-18 2010-09-22 江苏海力风电设备科技有限公司 潮间带风电场风机基础及其生产方法
CN201649118U (zh) * 2010-04-07 2010-11-24 中国水电顾问集团华东勘测设计研究院 导管架式海上风电机组基础结构
CN202440828U (zh) * 2012-02-27 2012-09-19 广东明阳风电产业集团有限公司 分离式导管架装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5551804A (en) * 1995-04-24 1996-09-03 Mcdermott International, Inc. Method of driving a pile
DE10109040C1 (de) * 2001-02-24 2002-07-11 Conrad Hansen Gründung für eine Windkraftanlage
CN201506979U (zh) * 2009-09-14 2010-06-16 中国水利水电科学研究院 一种海上风机桩基础与导管架腿柱的灌浆连接结构
CN201649118U (zh) * 2010-04-07 2010-11-24 中国水电顾问集团华东勘测设计研究院 导管架式海上风电机组基础结构
CN101838997A (zh) * 2010-05-18 2010-09-22 江苏海力风电设备科技有限公司 潮间带风电场风机基础及其生产方法
CN202440828U (zh) * 2012-02-27 2012-09-19 广东明阳风电产业集团有限公司 分离式导管架装置

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104812963A (zh) * 2012-10-03 2015-07-29 技术项目有限公司 用于海上风力涡轮机的安装的基于重力的地基***和用于海上风力涡轮机地基***的安装的方法
CN104812963B (zh) * 2012-10-03 2017-10-13 技术项目有限公司 用于海上风力涡轮机的安装的基于重力的地基***和用于海上风力涡轮机地基***的安装的方法
CN103225304A (zh) * 2013-04-28 2013-07-31 国电联合动力技术有限公司 一种海上基础支撑结构及其施工方法
CN103225304B (zh) * 2013-04-28 2016-09-14 国电联合动力技术有限公司 一种海上基础支撑结构及其施工方法
CN103953055A (zh) * 2014-04-21 2014-07-30 广东明阳风电产业集团有限公司 一种海上风电机组水上四桩基础
WO2017020697A1 (zh) * 2015-08-03 2017-02-09 广东明阳风电产业集团有限公司 一种后打桩海上风机基础的施工装置及施工方法
CN105155569B (zh) * 2015-08-03 2017-05-31 浙江华蕴海洋工程技术服务有限公司 一种后打桩海上风机基础的施工装置及施工方法
CN105155569A (zh) * 2015-08-03 2015-12-16 浙江华蕴海洋工程技术服务有限公司 一种后打桩海上风机基础的施工装置及施工方法
US10253475B2 (en) 2015-08-03 2019-04-09 Ming Yang Smart Energy Group., Ltd. Construction device and method for offshore wind turbine foundation with piling performed later
CN105971000A (zh) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 一种海上风机嵌岩单桩基础临时施工平台
CN109853609A (zh) * 2018-12-25 2019-06-07 长江勘测规划设计研究有限责任公司 一种海上风电组合基础
CN113638441A (zh) * 2020-04-27 2021-11-12 中国电建集团华东勘测设计研究院有限公司 一种桩桶组合式导管架支撑结构及其施工方法
CN112411603A (zh) * 2020-11-21 2021-02-26 南通泰胜蓝岛海洋工程有限公司 一种海上风电升压站的安装施工工艺
CN114991148A (zh) * 2022-06-30 2022-09-02 福建永福电力设计股份有限公司 一种分体式吸力桩导管架安装定位架及其施工方法

Similar Documents

Publication Publication Date Title
CN102587405A (zh) 海上风机导管架基础安装方法及分离式导管架装置
CN102535510A (zh) 海上风机导管架基础安装方法及一体化导管架装置
AU2007202274B2 (en) Method and apparatus for wind power foundation
KR101559472B1 (ko) 수중 지지구조물용 기초부 시공방법
CN206034408U (zh) 用于海上升压站的后插桩式导管架结构
CN103225304B (zh) 一种海上基础支撑结构及其施工方法
KR101595490B1 (ko) 지지구조물용 기초부 시공방법
JP3764643B2 (ja) 洋上風力発電装置の基礎構造
CN102777333A (zh) 桁架式风力发电机组结构
CN103423093B (zh) 用于深海海面的带吸力式沉箱的平台浮式风电机
CN202440828U (zh) 分离式导管架装置
JP5356482B2 (ja) 太陽電池モジュール又は太陽電池アレイ用架台の基礎構造
JP2013091923A (ja) 仮締切り構造体および仮締切り構造体の施工方法
CN103088801A (zh) 海上风力发电机及桩基一次整体安装平台
KR101383159B1 (ko) 암반 설치용 중력식 해상풍력 기초 슬래브
CN103669383B (zh) 一种在海底地面上安装和调平沉箱的方法
CN202466618U (zh) 一体化导管架装置
CN106049520A (zh) 海上支撑结构的混凝土基底和钢管桩之间的结合方法
CN113550345A (zh) 一种风机基础与塔筒的连接结构及施工方法
CN103410677A (zh) 带吸力式沉箱的单桩固定式垂直轴风电机
KR101384168B1 (ko) 위치센서를 이용한 해상풍력 발전기의 기초슬래브 설치 방법
CN114215093B (zh) 一种承台基础施工方法
JP2009209577A (ja) 海洋構造物及び海洋構造物の施工方法
CN105672317A (zh) 水下导管架打桩内插式定位装置
CN210066790U (zh) 套箱施工***

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120718