CN102305077A - Rapid construction method of large-section multi-arc tunnel - Google Patents

Rapid construction method of large-section multi-arc tunnel Download PDF

Info

Publication number
CN102305077A
CN102305077A CN201110285869A CN201110285869A CN102305077A CN 102305077 A CN102305077 A CN 102305077A CN 201110285869 A CN201110285869 A CN 201110285869A CN 201110285869 A CN201110285869 A CN 201110285869A CN 102305077 A CN102305077 A CN 102305077A
Authority
CN
China
Prior art keywords
tunnel
mid
board
positive hole
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110285869A
Other languages
Chinese (zh)
Inventor
施成华
彭立敏
杨伟超
雷明锋
丁祖德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201110285869A priority Critical patent/CN102305077A/en
Publication of CN102305077A publication Critical patent/CN102305077A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a rapid construction method of a large-section multi-arc tunnel. In the method, a middle pilot tunnel is not arranged; in the tunnel construction process, the places of a main tunnel and a mid-board on one side of the multi-arc tunnel are synchronously excavated, wherein the tunnel excavation is performed by CD or CRD method; primary support and mid-board are constructed, then secondary lining of the tunnel follows; and finally, the main tunnel on the other side of the multi-arc tunnel is excavated by a step method or CD method, and corresponding support structure is built. Compared with the traditional multi-arc tunnel construction method, the construction method disclosed by the invention does not need to communicate the middle pilot tunnel and build a mid-board before excavating the main tunnels on the two sides, thereby greatly increasing the construction speed of multi-arc tunnel, shortening the construction time and properly reducing the engineering cost.

Description

A kind of rapid constructing method of big section multiple-arch tunnel
Technical field
The present invention relates to a kind of job practices of tunnel, be specifically related to a kind of rapid constructing method of big section multiple-arch tunnel.
Background technology
Multiple-arch tunnel has openings position and selects degree of freedom big, the lead-in wire floor space is little, be convenient to the bridge tunnel continuous, handsome in appearance, be convenient to plurality of advantages such as operation management, the multiple-arch tunnel structure is widely used in the engineering practice in recent years.Its main construction method has:
(1) the pilot tunnel excavation method of going ahead of the rest in [1,2]This method is the middle pilot tunnel excavation perforation earlier with position, multiple-arch tunnel mid-board place; Then therefrom mid-board is built to hole, two ends, tunnel in the pilot tunnel middle part; After treating that mid-board can carry, carry out the excavation in positive hole, multiple-arch tunnel both sides again and carry out the work of executing of corresponding supporting and protection structure.This method can guarantee the construction safety in tunnel, but because excavation branch is many, speed of application is slower.Most at present multiple-arch tunnels all is to adopt this method to construct.
(2) mid-board job-hopping excavation method [3]This method is the first positive hole of a side of excavation multiple-arch tunnel, executes and does preliminary bracing, and the country rock at the tunneling mid-board position of then job-hoping is also built mid-board, excavates the positive hole of opposite side at last and executes and make corresponding supporting and protection structure.This method has reduced working procedure, has accelerated construction speed.But arch, tunnel supporting and protection structure was in vacant state when mid-board position country rock excavated in this method construction; Very easily cause whole sinking of structure generation of arch, tunnel even whole tunnel to cave in; There is bigger construction safety hidden danger, can only could using under the wall rock condition preferably; And adopt the vertical constuction joint of this method more, also influenced the quality and the durability of tunnel structure.Only there are indivedual multiple-arch tunnels to adopt this method to construct at present both at home and abroad.
(3) no pilot tunnel method [4,5]This method is that full section or benching tunnelling method excavation is adopted at position, the positive hole of multiple-arch tunnel one side and mid-board place synchronously, executes and does preliminary bracing, then excavates the positive hole of opposite side and executes and make corresponding supporting and protection structure.This method has reduced working procedure, has accelerated construction speed greatly.But in this method construction full section or benching tunnelling method excavation are adopted as a cavern in positive hole of a side and position, mid-board place; This cavern span is big; Risk is high in the construction; Cause the landslide in tunnel easily; There is very big potential safety hazard, therefore generally only could uses when perhaps the positive hole of multiple-arch tunnel span is very little down at wall rock condition preferably.Also only there are several multiple-arch tunnels of only a few to adopt this method to construct at present both at home and abroad.
On the whole; At present in the Multi-arch Tunnel Construction; Pilot tunnel excavation perforation earlier in also main the employing; Build mid-board again, then excavate the job practices in positive hole, its excavation piecemeal is many; Speed of application is slow; Had a strong impact on the construction speed of multiple-arch tunnel, can't satisfy the requirement of multiple-arch tunnel rapid construction, caused present multiple-arch tunnel generally to be only applicable to the short tunnel of length less than 500m.
List of references
[1] Tang Liang. Double Multi-Arch Tunnel Construction method [J]. Traffic Institutes Of Chongqing's journal, 2004,23 (2): 31-35.
[2] Wang Hansheng. soft rock shallow embedding section Double Multi-Arch highway tunnel construction technology [J]. railway type design, 2004, (8): 41-43.
[3] Li Leyang, the section grandson its, Wang Qiu comes. the instance [J] of single hole method construction multiple-arch tunnel. construction technology, 2008, (11): 107-111.
[4] Shu Lei. no pilot tunnel method construction multiple-arch tunnel technology [J]. railway type design, 2008, (6): 76-79.
[5] Liu Sheng, Li Ningjun, Liu Hongping. based on the multiple-arch tunnel structure design and the Construction Study [J] of no pilot tunnel method. water conservancy and construction work journal, 2010,8 (4): 107-110.
Summary of the invention
Technical problem to be solved by this invention provide a kind of can guarantee construction safety, again can accelerating construction progress and reduce the rapid constructing method of the big section multiple-arch tunnel of construction costs.
In order to solve the problems of the technologies described above; The rapid constructing method of big section multiple-arch tunnel provided by the invention; Middle pilot tunnel is not set; The positive hole of one side of multiple-arch tunnel mid-board position, place and multiple-arch tunnel is excavated synchronously; Then excavate the positive hole of opposite side; Multiple-arch tunnel adopts mid-board method (CD method) or intersection mid-board method (CRD method) elder generation excavation to comprise the side cavern at positive hole of multiple-arch tunnel one side and position, mid-board place; Execute the preliminary bracing of doing this cavern immediately, then execute secondary lining and the mid-board of doing this positive hole; The positive hole of the opposite side of multiple-arch tunnel adopts benching tunnelling method or mid-board method (CD method) to excavate, and executes the preliminary bracing of doing this positive hole immediately, and then executes the secondary lining of doing this positive hole again.
The mid-board of described multiple-arch tunnel is executed work, one-time cast-forming simultaneously with the secondary lining that excavates the positive hole of side earlier.
In the process of the big section multiple-arch tunnel rapid constructing method of research and development; Carried out deep theoretical analysis and calculation; The key influence factor and pass key control operation of job practices of the present invention have been confirmed on this basis; Therefore; The present invention has sufficient theory analysis research basis and foundation, can guarantee the construction safety and the accelerating construction progress in tunnel better.
Adopt the rapid constructing method of the big section multiple-arch tunnel of technique scheme, compare with existing Multi-arch Tunnel Construction method, its advantage is:
(1) need not connect in the construction in advance in pilot tunnel and execute and make mid-board, mid-board can progressively be executed work with the excavation in the positive hole of a side, has accelerated the construction speed of multiple-arch tunnel greatly, has shortened the construction period in multiple-arch tunnel tunnel;
(2) reduced excavation branch and working procedure in the Multi-arch Tunnel Construction process, the corresponding disturbance that has reduced the tunnel perimeter country rock simultaneously, has been shortened the closed time of whole tunnel support structure, has guaranteed the construction safety in tunnel;
(3) reduce engineering quantity and the excavation at middle pilot tunnel top and the engineering quantity of backfill of pilot tunnel temporary lining in the part in the construction, reduced the construction costs of multiple-arch tunnel to a certain extent.
(4) tunnel mid-board and the positive hole of side secondary lining integral body are executed work, have reduced constuction joint, are beneficial to the assurance construction quality.
(5) owing to the reduction of duration and cost, job practices of the present invention can be expanded the range of application of multiple-arch tunnel greatly, and the above medium tunnel of 500m also can adopt the multiple-arch tunnel structural shape.
Description of drawings
Fig. 1 is the concrete working procedure sketch map of the embodiment of the invention
Among the figure: the excavation of topping bar on the left of the positive hole, an I-left side; Left side, positive hole, the II-left side excavation of getting out of a predicament or an embarrassing situation; Zheng Dong right side, the III-left side excavation of topping bar; Zheng Dong right side, the IV-left side excavation of getting out of a predicament or an embarrassing situation; The right Zheng Dong of the V-excavation of topping bar on the right side; The right Zheng Dong of the VI-excavation of getting out of a predicament or an embarrassing situation on the right side; Left side, the right positive hole of the VII-excavation of topping bar; Left side, the right positive hole of the VIII-excavation of getting out of a predicament or an embarrassing situation; The A-preliminary bracing; The B-secondary lining; The C-interim mid-board of constructing; The permanent mid-board of D-multiple-arch tunnel; Zheng Dong arch, 1-left side advance support; Left side, positive hole, a 2-left side top bar preliminary bracing and temporary lining; Left side, positive hole, a 3-left side get out of a predicament or an embarrassing situation preliminary bracing and temporary lining; The preliminary bracing of topping bar of Zheng Dong right side, a 4-left side; The preliminary bracing of getting out of a predicament or an embarrassing situation of Zheng Dong right side, a 5-left side, the positive hole temporary lining of a 6-left side is removed, positive hole, a 7-left side and mid-board secondary lining; Arch, the right Zheng Dong arch of 8-advance support; The right Zheng Dong of 9-top bar on the right side preliminary bracing and temporary lining, the right Zheng Dong of 10-get out of a predicament or an embarrassing situation on the right side preliminary bracing and temporary lining, the preliminary bracing of topping bar of left side, the right positive hole of 11-; The right positive hole temporary lining of 12-is removed, the right positive hole of 13-secondary lining.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the present invention is further specified.
Referring to Fig. 1, the rapid constructing method of big section multiple-arch tunnel provided by the invention, its concrete working procedure is following:
(1) adopting method such as leading grouting with small pipe to carry out left Zheng Dong arch pays in advance and protects 1;
(2) carry out left side, positive hole, a left side top bar (I portion) bore to pop and dig;
(3) execute and do left side, positive hole, a left side top bar spray anchor preliminary bracing (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) and mid-board temporary lining 2 (the steel bow member is installed, is hung steel mesh reinforcement, sprayed mortar);
(4) carry out left side, positive hole, a left side get out of a predicament or an embarrassing situation (II portion) bore to pop and dig;
(5) execute and do left side, positive hole, a left side get out of a predicament or an embarrassing situation spray anchor preliminary bracing (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) and mid-board temporary lining 3 (the steel bow member is installed, is hung steel mesh reinforcement, sprayed mortar);
(6) carry out left Zheng Dong right side top bar (III portion) bore to pop and dig;
(7) execute and do the spray anchor preliminary bracing 4 (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) of topping bar of left Zheng Dong right side;
(8) carry out left Zheng Dong right side get out of a predicament or an embarrassing situation (IV portion) bore to pop and dig;
(9) execute and do the spray anchor preliminary bracing 5 (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) of getting out of a predicament or an embarrassing situation of left Zheng Dong right side;
(10) remove the positive hole temporary lining 6 in a left side;
(11) lay splash guard, positive hole secondary lining in a cast left side and steel concrete mid-board, positive hole secondary lining in a left side and tunnel mid-board one-time cast-forming 7;
(12) adopting method such as leading grouting with small pipe to carry out right Zheng Dong arch pays in advance and protects 8;
(13) carry out right Zheng Dong right side top bar (V portion) bore to pop and dig;
(14) execute and do right Zheng Dong right side top bar spray anchor preliminary bracing (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) and mid-board temporary lining 9 (the steel bow member is installed, is hung steel mesh reinforcement, sprayed mortar);
(15) carry out right Zheng Dong right side get out of a predicament or an embarrassing situation (VI portion) bore to pop and dig;
(16) execute and do right Zheng Dong right side get out of a predicament or an embarrassing situation spray anchor preliminary bracing (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) and mid-board temporary lining 10 (the steel bow member is installed, is hung steel mesh reinforcement, sprayed mortar);
(17) carry out left side, positive hole, the right side top bar (VII portion) bore to pop and dig;
(18) execute and do the spray anchor preliminary bracing 11 (the steel bow member is installed, is hung steel mesh reinforcement, skyhook, sprayed mortar) of topping bar of left side, right positive hole;
(19) carry out left side, positive hole, the right side get out of a predicament or an embarrassing situation (VIII portion) bore to pop and dig;
(20) remove right positive hole temporary lining 12;
(21) lay splash guard, the right positive hole of cast secondary lining 13.

Claims (2)

1. the rapid constructing method of a big section multiple-arch tunnel; The positive hole of one side of multiple-arch tunnel mid-board position, place and multiple-arch tunnel is excavated synchronously; Then excavate the positive hole of opposite side; It is characterized in that: multiple-arch tunnel adopts mid-board method or intersection mid-board method to excavate the side cavern that comprises positive hole of multiple-arch tunnel one side and position, mid-board place earlier; Execute the preliminary bracing of doing this cavern immediately, then execute secondary lining and the mid-board of doing this positive hole; The positive hole of the opposite side of multiple-arch tunnel adopts benching tunnelling method or mid-board method to excavate, and executes the preliminary bracing of doing this positive hole immediately, and then executes the secondary lining of doing this positive hole again.
2. the rapid constructing method of big section multiple-arch tunnel according to claim 1 is characterized in that: the mid-board of described multiple-arch tunnel is executed work, one-time cast-forming simultaneously with the secondary lining that excavates the positive hole of side earlier.
CN201110285869A 2011-09-23 2011-09-23 Rapid construction method of large-section multi-arc tunnel Pending CN102305077A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110285869A CN102305077A (en) 2011-09-23 2011-09-23 Rapid construction method of large-section multi-arc tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110285869A CN102305077A (en) 2011-09-23 2011-09-23 Rapid construction method of large-section multi-arc tunnel

Publications (1)

Publication Number Publication Date
CN102305077A true CN102305077A (en) 2012-01-04

Family

ID=45378975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110285869A Pending CN102305077A (en) 2011-09-23 2011-09-23 Rapid construction method of large-section multi-arc tunnel

Country Status (1)

Country Link
CN (1) CN102305077A (en)

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102562075A (en) * 2012-03-09 2012-07-11 中交第二公路工程局有限公司 Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103195455A (en) * 2013-03-11 2013-07-10 中铁二院工程集团有限责任公司 Large section tunnel construction support and protection system and construction method under flabby geological environment
CN103334761A (en) * 2013-06-28 2013-10-02 中国一冶集团有限公司 Method of constructing shallow tunnel underground passage variable-cross section cross mid-partition wall
CN103670423A (en) * 2013-11-14 2014-03-26 中铁隧道集团有限公司 Method for excavating tunnel in layered phyllite body
CN103670427A (en) * 2013-12-24 2014-03-26 中铁十九局集团第三工程有限公司 Cross excavation support late-dismantling type tunnel construction method
CN103758530A (en) * 2014-01-22 2014-04-30 北京市市政工程设计研究总院有限公司 Primary support multiple-arch dual-liner independent underground excavation subway interval structure and construction method
CN104314571A (en) * 2014-08-19 2015-01-28 西安建筑科技大学 Construction method for three-step six-step ultrashort step for large-section tunnel
CN104405419A (en) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 Parallel middle separation wall construction method for hidden type middle wall multi-arch tunnel
CN104405402A (en) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 Symmetric middle separation wall construction method for hidden type middle wall multi-arch tunnel
CN104533465A (en) * 2015-01-14 2015-04-22 中南大学 Temporary supporting structure for tunnel construction
CN104594913A (en) * 2015-01-16 2015-05-06 中交一公局第一工程有限公司 Tunnel longitudinal ventilation connection duct and main tunnel zero-clear-distance three-dimensional crossing structure and construction method thereof
CN104912559A (en) * 2015-06-02 2015-09-16 北车建设工程有限责任公司 Rapid construction method for long and large double-multiple arch tunnel
CN105386779A (en) * 2015-10-19 2016-03-09 北京城建设计发展集团股份有限公司 Arch column method for building large-scale underground structure in shallow buried rock stratums
CN105909279A (en) * 2016-06-30 2016-08-31 中铁隧道集团有限公司 Construction method for preventing primary support of tunnel in water-rich stratum from water permeation through drilling and blasting method
CN106437724A (en) * 2016-08-31 2017-02-22 济南轨道交通集团有限公司 Subway station constructed by adopting rectangular jacking pipes combined with interval shields and construction method
CN107490336A (en) * 2017-08-22 2017-12-19 浙江工业大学 A kind of experimental provision and test method of simulation CRD method constructing tunnels
CN108678779A (en) * 2018-05-11 2018-10-19 云南省建设投资控股集团有限公司 Multi-arch Tunnel Construction method is led without in
CN109190190A (en) * 2018-08-13 2019-01-11 中国铁建大桥工程局集团有限公司 Numerical analysis method for influence of double-side-wall pilot tunnel construction on stress and displacement of surrounding rock
CN109681233A (en) * 2019-01-03 2019-04-26 济南城建集团有限公司 City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure
CN109707399A (en) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 Tunnel outlet support structure and its construction method
CN111022060A (en) * 2019-12-26 2020-04-17 中交三公局第二工程有限公司 Single-hole excavation construction method of double-arch tunnel
CN111535818A (en) * 2020-04-21 2020-08-14 中铁广州工程局集团有限公司 Rapid construction method for large-section tunnel of high-speed railway
CN111594185A (en) * 2020-05-29 2020-08-28 中铁一局集团有限公司 Construction method for mechanically excavating CRD (cross section) of tunnel under loess stratum condition
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method
CN112112669A (en) * 2020-08-21 2020-12-22 贵州大学 Method for laying middle wall steel frame of multi-arch tunnel
CN112177616A (en) * 2020-11-13 2021-01-05 贵州大学 Method for laying steel frame of multi-arch tunnel without middle pilot tunnel
CN112943260A (en) * 2020-11-13 2021-06-11 上海宝冶集团有限公司 Tunnel middle partition wall step excavation method
CN113250705A (en) * 2021-06-28 2021-08-13 重庆工程职业技术学院 Multi-arch tunnel construction method
CN114263467A (en) * 2021-11-17 2022-04-01 湖南省交通规划勘察设计院有限公司 Excavation design construction method for four-arch tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100752285B1 (en) * 2006-01-11 2007-08-29 주식회사 케이투기술단 Construction method for two arches tunnel
JP2008025305A (en) * 2006-07-25 2008-02-07 Ihi Corp Tunnel construction method and tunnel structure
KR20100003061A (en) * 2008-06-30 2010-01-07 (주)엘티엠 Tunneling method and apparatus for blasting of enlargement and construction of concrete lining carried out simultaneously during excavation of pilot tunnel by tbm
CN201696056U (en) * 2010-03-04 2011-01-05 湖南省交通规划勘察设计院 Improved structure of twin-arch tunnel with composite middle partition wall
CN102155232A (en) * 2011-04-02 2011-08-17 中铁二院工程集团有限责任公司 Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100752285B1 (en) * 2006-01-11 2007-08-29 주식회사 케이투기술단 Construction method for two arches tunnel
JP2008025305A (en) * 2006-07-25 2008-02-07 Ihi Corp Tunnel construction method and tunnel structure
KR20100003061A (en) * 2008-06-30 2010-01-07 (주)엘티엠 Tunneling method and apparatus for blasting of enlargement and construction of concrete lining carried out simultaneously during excavation of pilot tunnel by tbm
CN201696056U (en) * 2010-03-04 2011-01-05 湖南省交通规划勘察设计院 Improved structure of twin-arch tunnel with composite middle partition wall
CN102155232A (en) * 2011-04-02 2011-08-17 中铁二院工程集团有限责任公司 Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
舒磊等: "多断面组合形成的铁路车站隧道施工技术", 《建设机械技术与管理》, no. 11, 28 November 2006 (2006-11-28) *
资斌全等: "双连拱隧道双洞施工工法", 《市政技术》, no. 03, 31 May 2011 (2011-05-31) *
赖金星等: "连拱隧道无中导洞施工技术探讨", 《铁道建筑》, no. 04, 20 April 2006 (2006-04-20) *

Cited By (43)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102562075B (en) * 2012-03-09 2014-06-11 中交第二公路工程局有限公司 Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN102562075A (en) * 2012-03-09 2012-07-11 中交第二公路工程局有限公司 Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN102704939B (en) * 2012-06-26 2014-10-01 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section
CN103195455B (en) * 2013-03-11 2016-05-11 中铁二院工程集团有限责任公司 Weak geological environment large cross-section tunnel construction supporting system and construction method
CN103195455A (en) * 2013-03-11 2013-07-10 中铁二院工程集团有限责任公司 Large section tunnel construction support and protection system and construction method under flabby geological environment
CN103334761A (en) * 2013-06-28 2013-10-02 中国一冶集团有限公司 Method of constructing shallow tunnel underground passage variable-cross section cross mid-partition wall
CN103334761B (en) * 2013-06-28 2015-06-24 中国一冶集团有限公司 Method of constructing shallow tunnel underground passage variable-cross section cross mid-partition wall
CN103670423A (en) * 2013-11-14 2014-03-26 中铁隧道集团有限公司 Method for excavating tunnel in layered phyllite body
CN103670423B (en) * 2013-11-14 2016-04-06 中铁隧道集团有限公司 A kind of method of tunneling on stratiform phyllite rock mass
CN103670427A (en) * 2013-12-24 2014-03-26 中铁十九局集团第三工程有限公司 Cross excavation support late-dismantling type tunnel construction method
CN103758530A (en) * 2014-01-22 2014-04-30 北京市市政工程设计研究总院有限公司 Primary support multiple-arch dual-liner independent underground excavation subway interval structure and construction method
CN104314571A (en) * 2014-08-19 2015-01-28 西安建筑科技大学 Construction method for three-step six-step ultrashort step for large-section tunnel
CN104405419A (en) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 Parallel middle separation wall construction method for hidden type middle wall multi-arch tunnel
CN104405402A (en) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 Symmetric middle separation wall construction method for hidden type middle wall multi-arch tunnel
CN104533465A (en) * 2015-01-14 2015-04-22 中南大学 Temporary supporting structure for tunnel construction
CN104594913A (en) * 2015-01-16 2015-05-06 中交一公局第一工程有限公司 Tunnel longitudinal ventilation connection duct and main tunnel zero-clear-distance three-dimensional crossing structure and construction method thereof
CN104594913B (en) * 2015-01-16 2016-08-17 中交一公局第一工程有限公司 Tunnel longitudinal ventilation contact air channel and positive hole zero net are away from grade separation structure and construction method
CN104912559A (en) * 2015-06-02 2015-09-16 北车建设工程有限责任公司 Rapid construction method for long and large double-multiple arch tunnel
CN104912559B (en) * 2015-06-02 2017-02-01 中车建设工程有限公司 Rapid construction method for long and large double-multiple arch tunnel
CN105386779A (en) * 2015-10-19 2016-03-09 北京城建设计发展集团股份有限公司 Arch column method for building large-scale underground structure in shallow buried rock stratums
CN105909279A (en) * 2016-06-30 2016-08-31 中铁隧道集团有限公司 Construction method for preventing primary support of tunnel in water-rich stratum from water permeation through drilling and blasting method
CN106437724A (en) * 2016-08-31 2017-02-22 济南轨道交通集团有限公司 Subway station constructed by adopting rectangular jacking pipes combined with interval shields and construction method
CN107490336A (en) * 2017-08-22 2017-12-19 浙江工业大学 A kind of experimental provision and test method of simulation CRD method constructing tunnels
CN107490336B (en) * 2017-08-22 2019-04-09 浙江工业大学 A kind of experimental provision and test method for simulating CRD method constructing tunnel
CN108678779A (en) * 2018-05-11 2018-10-19 云南省建设投资控股集团有限公司 Multi-arch Tunnel Construction method is led without in
CN109190190A (en) * 2018-08-13 2019-01-11 中国铁建大桥工程局集团有限公司 Numerical analysis method for influence of double-side-wall pilot tunnel construction on stress and displacement of surrounding rock
CN109681233A (en) * 2019-01-03 2019-04-26 济南城建集团有限公司 City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure
CN109681233B (en) * 2019-01-03 2024-06-04 济南城建集团有限公司 Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces
CN109707399A (en) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 Tunnel outlet support structure and its construction method
CN109707399B (en) * 2019-02-21 2024-01-30 中铁二院工程集团有限责任公司 Tunnel exit supporting structure and construction method thereof
CN111022060A (en) * 2019-12-26 2020-04-17 中交三公局第二工程有限公司 Single-hole excavation construction method of double-arch tunnel
CN111022060B (en) * 2019-12-26 2021-03-23 中交三公局第二工程有限公司 Single-hole excavation construction method of double-arch tunnel
CN111535818A (en) * 2020-04-21 2020-08-14 中铁广州工程局集团有限公司 Rapid construction method for large-section tunnel of high-speed railway
CN111594185A (en) * 2020-05-29 2020-08-28 中铁一局集团有限公司 Construction method for mechanically excavating CRD (cross section) of tunnel under loess stratum condition
CN111594185B (en) * 2020-05-29 2021-11-26 中铁一局集团有限公司 Construction method for mechanically excavating CRD (cross section) of tunnel under loess stratum condition
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method
CN112112669A (en) * 2020-08-21 2020-12-22 贵州大学 Method for laying middle wall steel frame of multi-arch tunnel
CN112943260A (en) * 2020-11-13 2021-06-11 上海宝冶集团有限公司 Tunnel middle partition wall step excavation method
CN112177616A (en) * 2020-11-13 2021-01-05 贵州大学 Method for laying steel frame of multi-arch tunnel without middle pilot tunnel
CN113250705A (en) * 2021-06-28 2021-08-13 重庆工程职业技术学院 Multi-arch tunnel construction method
CN113250705B (en) * 2021-06-28 2023-10-20 重庆工程职业技术学院 Multi-arch tunnel construction method
CN114263467A (en) * 2021-11-17 2022-04-01 湖南省交通规划勘察设计院有限公司 Excavation design construction method for four-arch tunnel

Similar Documents

Publication Publication Date Title
CN102305077A (en) Rapid construction method of large-section multi-arc tunnel
CN102373930A (en) Rapid construction method of weak surrounding rock large-section multi-arc tunnel
CN102644466B (en) Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN101775988B (en) Construction method for inclined shaft to main tunnel of weak surrounding rock
CN101864963B (en) Large-section loess tunnel construction method
CN103775092B (en) Tunnels in Shallow Buried tunneling remaining core soil in advance improvement CRD construction
CN102155232B (en) Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN102926757A (en) Construction method of two-sidestep and four-step excavation support of weak large-span tunnel of mountain ridge
CN102268993B (en) Method for excavating tunnel in high liquid limit soil
CN105804760B (en) Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN104074524B (en) A kind of construction method of shallow embedding underpass of freeways large cross-section tunnel
CN105003272A (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN104653197A (en) Method for constructing extra-large variable cross section tunnel
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN201412163Y (en) Circular tunnel lining structure for construction of open-type tunnel boring machine
CN103306680A (en) Construction method for extending single-track tunnel to multi-track tunnel
CN204457792U (en) A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building
CN207934910U (en) A kind of newly built tunnels closely on across existing tunnel anti-floating reinforcement system
CN101539021A (en) Road tunnel excavation method
CN102305091A (en) Support structure for hard rock large-section tunnel construction, and construction method for support structure
CN109056810A (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120104