CN109681233A - City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure - Google Patents
City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure Download PDFInfo
- Publication number
- CN109681233A CN109681233A CN201910003212.8A CN201910003212A CN109681233A CN 109681233 A CN109681233 A CN 109681233A CN 201910003212 A CN201910003212 A CN 201910003212A CN 109681233 A CN109681233 A CN 109681233A
- Authority
- CN
- China
- Prior art keywords
- jurisdiction
- section
- interim
- cross
- vertical supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009412 basement excavation Methods 0.000 title claims abstract description 37
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000010276 construction Methods 0.000 claims description 40
- 230000008901 benefit Effects 0.000 abstract description 5
- 239000002689 soil Substances 0.000 abstract description 4
- 238000012407 engineering method Methods 0.000 abstract description 3
- 239000000243 solution Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000004062 sedimentation Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 238000007363 ring formation reaction Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 238000000844 transformation Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
- E21D11/083—Methods or devices for joining adjacent concrete segments
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D19/00—Provisional protective covers for working space
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention belongs to city underground engineering technical fields, the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure are used specifically related to a kind of city Shallow tunnel with large cross-section, including prefabricated interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction, the median septum of upper left step is set up by interim vertical supporting pipe sheet assembling, and the inverted arch of upper left step is set up by interim cross-brace pipe sheet assembling;The inverted arch of upper right step is set up by interim cross-brace pipe sheet assembling;Interim vertical supporting section of jurisdiction is equipped with injected hole.The present invention takes interim vertical supporting not bottomed, is closed with interim cross-brace, forms the inverse-T-shaped excavation method of innovation, and top bar is divided into upper left step and two step of upper right step is excavated, is reduced to the disposable perturbation area of the face soil body.Engineering method step of the present invention is simple, and strong operability is saved the area, and economic benefit and social benefit are significant.
Description
Technical field
The invention belongs to city underground engineering technical fields, and in particular to a kind of city Shallow tunnel with large cross-section using pre-
The inverse-T-shaped excavation method in system support section of jurisdiction and temporary support structure.
Background technique
With the development of the city, surface road is no longer satisfied growing vehicular traffic, has only and builds tube
Road is alleviated.How big in traffic pressure, ground space is narrow, the Downtown of surrounding enviroment complexity, safe and efficient to repair
Shallow tunnel with large cross-section is built, selects suitable excavation method particularly critical.There are benching tunnelling method, CD at present for excavating large cross-section tunnel
The excavation methods such as method, CRD method, two side-wall pilot tunnel, they respectively have an advantage and disadvantage, for example the construction of benching tunnelling method, CD method is more quick, still
In city, there are security risks in shallow embedding and stratum poor location;And CRD method and two side-wall pilot tunnel divide face is excavated
Portion is more, and construction space is smaller, and gib is constructed, and dismounting amount is larger, and construction efficiency reduces very much;Two side-wall pilot tunnel construction
Safety, but speed is slower, higher cost.In addition to this, above-mentioned existing engineering method especially will when building large cross-section tunnel
The interim vertical median septum of construction or interim inverted arch, when excavation supporting, shaped steel arch is installed in gib, hangs steel mesh, and injection is mixed
Solidifying soil is constructed, and also temporary support is all removed before later-stage secondary lining construction, not only construction efficiency is low, while causing tunnel
Road hole environment pollution, lot of materials waste, is not suitable for green construction section material, energy-efficient theory.
Summary of the invention
The present invention to solve the deficiencies in the prior art, in conjunction with city Shallow tunnel with large cross-section construction characteristic, is different from existing
Excavation method, innovation propose a kind of city Shallow tunnel with large cross-section use the inverse-T-shaped excavation method in precast support section of jurisdiction with
And temporary support structure.
The present invention is achieved by the following technical solutions: a kind of inverse-T-shaped excavation of city Shallow tunnel with large cross-section faces
When support construction, including prefabricated interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction, the median septum of upper left step is by facing
When vertical supporting pipe sheet assembling set up, the inverted arch of upper left step is set up by interim cross-brace pipe sheet assembling;Upper right
The inverted arch of step is set up by interim cross-brace pipe sheet assembling;Interim vertical supporting section of jurisdiction is equipped with injected hole.
Assembly is bolted in the assembly of the interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction.
2 injected holes are equipped between the interim vertical supporting section of jurisdiction connection bolt, injected hole is at a distance from bolt
30cm。
The width of the interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction is 1.5m, with a thickness of 20cm.
The invention also includes a kind of city Shallow tunnel with large cross-section to use the inverse-T-shaped excavation method in precast support section of jurisdiction, packet
Include following steps:
(1) upper left bench excavation: first carrying out advance support, then excavate, and carries out preliminary bracing construction, and assembling is prefabricated
Interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction are set up into interval wall construction with interim vertical supporting pipe sheet assembling, are used
Interim cross-brace pipe sheet assembling is set up into inverted arch structure;
(2) upper right bench excavation: first carrying out advance support, then excavate, and carries out preliminary bracing construction, and assembling is prefabricated
Interim cross-brace section of jurisdiction, is set up with interim cross-brace pipe sheet assembling into inverted arch structure;
(3) get out of a predicament or an embarrassing situation excavation: excavation of getting out of a predicament or an embarrassing situation, tunnel landing, construction tunnel inverted arch preliminary bracing form loopful closure;
(4) secondary lining inverted arch is constructed: after the completion of getting out of a predicament or an embarrassing situation construction, in the inverted arch that interim cross-brace pipe sheet assembling is set up
It constructs in time under structure secondary lining inverted arch;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps
Section of jurisdiction and interim cross-brace section of jurisdiction are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: utilizing the interim vertical supporting section of jurisdiction removed and interim cross-brace section of jurisdiction into next excavation branch
Shield circulation.
Beneficial effects of the present invention:
One, it takes interim vertical supporting not bottomed, is closed with interim cross-brace, forms the inverse-T-shaped excavation method of innovation,
Top bar is divided into upper left step and two step of upper right step is excavated, is reduced to the disposable perturbation area of the face soil body.This hair
Bright engineering method step is simple, and strong operability is saved the area, and economic benefit and social benefit are significant.
Two, a close ring is just formed after the completion of top bar is excavated, the inverted arch that interim cross-brace section of jurisdiction splicing is set up subtracts
The clearance convergence in tunnel is lacked, the median septum that interim vertical supporting section of jurisdiction splicing is set up reduces tunnel vault sedimentation, leaves office
Rank does not set up interim perpendicular support, not only increases efficiency while guaranteeing safe, has also speeded up tunnel landing and loopful closure
Time, while the construction speed of Tunnel Second Lining inverted arch can be accelerated, reduce tunnel safety hidden danger.
Three, interim cross-brace section of jurisdiction and interim vertical supporting section of jurisdiction can be recycled, and have saved a large amount of raw material, reached
Safe and efficient, green, factorial construction purpose is arrived.
Four, the present invention increases in the case where guarantee preliminary bracing safe stress and excavates space, reduce gib
Construction and the workload removed, had not only improved working efficiency but also had saved construction cost.Compared with the temporary support of existing site operation
Compared with, reduce construction time and concrete strength curing time, it is i.e. force-applied after prefabricated temporary support installation, reduce injection
Curing time needed for concrete strength is up to standard avoids the problem of sedimentation is with convergent deformation after tunnel excavation, especially interim cross
It to support (inverted arch), can pass through immediately after having set up, as construction road, machinery can pass through immediately, and existing conventional branch
Shield, can pass after waiting the concrete curing time to meet intensity requirement.The present invention reduces on-site construction times, reduce
Construction pollution in tunnel.
Detailed description of the invention
Fig. 1 is that inverted " t " of the present invention excavates structure chart.
Fig. 2 is the interim cross-brace section of jurisdiction plane drawing of the present invention.
Fig. 3 is the interim vertical supporting section of jurisdiction plane drawing of the present invention.
Fig. 4 is the facade drawing of the interim cross-brace section of jurisdiction of the present invention or interim vertical supporting section of jurisdiction.
In figure, 1 interim vertical supporting section of jurisdiction, 2 interim cross-brace sections of jurisdiction, 3 bolts, 4 injected holes, 5 upper left steps, 6 is right
Top bar, 7 get out of a predicament or an embarrassing situation.
Specific embodiment
Specific embodiments of the present invention are given below, it should be noted that the invention is not limited to implement in detail below
Example, all equivalent transformations made on the basis of the technical solutions of the present application each fall within protection scope of the present invention.
City Shallow tunnel with large cross-section of the invention using the inverse-T-shaped excavation method in precast support section of jurisdiction approximately as: will
Top bar is divided into two steps excavation, and left and right sides is separated certain distance, reduces to the disposable perturbation area of the face soil body, upper
Form a close ring after the completion of bench excavation, then carry out 7 excavations of getting out of a predicament or an embarrassing situation, get out of a predicament or an embarrassing situation 7 excavation when do not set up it is interim vertical
Support accelerates the time of tunnel landing and loopful closure for improving efficiency.
City Shallow tunnel with large cross-section of the invention use the inverse-T-shaped excavation method in precast support section of jurisdiction, specifically include as
Lower step:
(1) upper left step 5 excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated
Interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2, with interim 1 assembling of vertical supporting section of jurisdiction at median septum knot
Structure, with interim 2 assembling of cross-brace section of jurisdiction at inverted arch structure;
(2) upper right step 6 excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated
Interim cross-brace section of jurisdiction 2, with interim 2 assembling of cross-brace section of jurisdiction at inverted arch structure;
(3) get out of a predicament or an embarrassing situation 7 excavations: 7 excavations of getting out of a predicament or an embarrassing situation, tunnel landing, construction tunnel inverted arch preliminary bracing form loopful closure;
(4) secondary lining inverted arch construct: get out of a predicament or an embarrassing situation 7 constructions closing cyclization after, interim 2 assembling of cross-brace section of jurisdiction at
Inverted arch structure under construct in time secondary lining inverted arch, improve the safety coefficient of tunnel structure;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps
Section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: entering next excavation using the interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 removed
Supporting circulation.
Above-mentioned interim cross-brace section of jurisdiction 2 used and interim vertical supporting section of jurisdiction 1 shift to an earlier date prefabricated process in factory
At direct splicing use.
The assembled bolt 3 that passes through between above-mentioned interim vertical supporting section of jurisdiction 1, between interim cross-brace section of jurisdiction 2 carries out
Connection is assembled, and the width of interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 used is 1.5m, with a thickness of 20cm.
Injected hole 4 is equipped on above-mentioned interim vertical supporting section of jurisdiction 1, injected hole 4 is located at the connection bolt of interim vertical supporting section of jurisdiction 1
Between 3,2 injected holes 4 are equipped between connection bolt 3, as shown in Fig. 3, injected hole 4 is 30cm at a distance from bolt 3.
Under above-mentioned inverse-T-shaped excavation method, the present invention yet forms that a kind of city Shallow tunnel with large cross-section is inverse-T-shaped to be opened
The temporary support structure of digging, this temporary support structure include prefabricated interim vertical supporting section of jurisdiction 1 and interim cross-brace pipe
The median septum of piece 2, upper left step 5 is formed by interim 1 assembling of vertical supporting section of jurisdiction, and the inverted arch of upper left step 5 is by interim horizontal
It is formed to support 2 assembling of section of jurisdiction;The inverted arch of upper right step 6 is formed by interim 2 assembling of cross-brace section of jurisdiction.
Embodiment described above, only one kind of the present invention more preferably specific embodiment, those skilled in the art
The usual variations and alternatives that member carries out within the scope of technical solution of the present invention should be all included within the scope of the present invention.
Claims (5)
1. a kind of temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section, including prefabricated interim vertical supporting
Section of jurisdiction (1) and interim cross-brace section of jurisdiction (2), it is characterised in that: the median septum of upper left step (5) is by interim vertical supporting section of jurisdiction
(1) assembling forms, and the inverted arch of upper left step (5) is formed by interim cross-brace section of jurisdiction (2) assembling;Upper right step
(6) inverted arch is formed by interim cross-brace section of jurisdiction (2) assembling;Interim vertical supporting section of jurisdiction (1) is equipped with injected hole
(4).
2. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 1, it is characterised in that:
The interim vertical supporting section of jurisdiction (1) and the assembled of interim cross-brace section of jurisdiction (2) pass through bolt (3) connection assembly.
3. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 2, it is characterised in that:
Be equipped with 2 injected holes (4) between interim vertical supporting section of jurisdiction (1) connection bolt (3), injected hole (4) and bolt (3) away from
From for 30cm.
4. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 1, it is characterised in that:
The width of the interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) is 1.5m, with a thickness of 20cm.
5. a kind of city Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction, it is characterised in that: including such as
Lower step:
(1) upper left step (5) excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated
Good interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2), with interim vertical supporting section of jurisdiction (1) assembling at
Interval wall construction, with interim cross-brace section of jurisdiction (2) assembling at inverted arch structure;
(2) upper right step (6) excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated
Good interim cross-brace section of jurisdiction (2), with interim cross-brace section of jurisdiction (2) assembling at inverted arch structure;
(3) get out of a predicament or an embarrassing situation (7) excavation: get out of a predicament or an embarrassing situation (7) excavation, tunnel landing, construction tunnel inverted arch preliminary bracing, formed loopful close
It closes;
(4) secondary lining inverted arch construct: get out of a predicament or an embarrassing situation (7) construct after the completion of, interim cross-brace section of jurisdiction (2) assembling at
Inverted arch structure under construct in time secondary lining inverted arch;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps
Section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: being entered using the interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) removed next
Excavation supporting circulation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910003212.8A CN109681233B (en) | 2019-01-03 | 2019-01-03 | Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910003212.8A CN109681233B (en) | 2019-01-03 | 2019-01-03 | Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109681233A true CN109681233A (en) | 2019-04-26 |
CN109681233B CN109681233B (en) | 2024-06-04 |
Family
ID=66191834
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910003212.8A Active CN109681233B (en) | 2019-01-03 | 2019-01-03 | Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109681233B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111287764A (en) * | 2020-02-22 | 2020-06-16 | 北京泰德市政工程有限公司 | Tunnel secondary lining structure and construction method thereof |
CN111594233A (en) * | 2020-07-04 | 2020-08-28 | 四川路航建设工程有限责任公司 | Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall |
CN115110966A (en) * | 2022-08-30 | 2022-09-27 | 中铁十六局集团地铁工程有限公司 | Tunnel supporting structure and construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1490568A (en) * | 1973-12-05 | 1977-11-02 | Bochumer Eisen Heintzmann | Method of providing a support structure for a tunnel-like way and apparatus for performing the method |
CN102305077A (en) * | 2011-09-23 | 2012-01-04 | 中南大学 | Rapid construction method of large-section multi-arc tunnel |
CN103867210A (en) * | 2014-03-28 | 2014-06-18 | 西安建筑科技大学 | City subway single-cross undermining construction method |
CN104612713A (en) * | 2014-12-12 | 2015-05-13 | 中铁十九局集团有限公司 | Super-shallow-buried section tunnel construction method |
CN205400758U (en) * | 2016-02-25 | 2016-07-27 | 中铁四局集团有限公司 | Temporary support system convenient to undercut tunnel passes through fast and invades limit pipeline region |
CN106014424A (en) * | 2016-06-27 | 2016-10-12 | 中交公局第三工程有限公司 | Blasting excavation method for shallowly-overburdened and shallowly-buried bored tunnel |
CN107725064A (en) * | 2017-11-22 | 2018-02-23 | 北京市政建设集团有限责任公司 | Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method |
CN209586382U (en) * | 2019-01-03 | 2019-11-05 | 济南城建集团有限公司 | The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section |
-
2019
- 2019-01-03 CN CN201910003212.8A patent/CN109681233B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1490568A (en) * | 1973-12-05 | 1977-11-02 | Bochumer Eisen Heintzmann | Method of providing a support structure for a tunnel-like way and apparatus for performing the method |
CN102305077A (en) * | 2011-09-23 | 2012-01-04 | 中南大学 | Rapid construction method of large-section multi-arc tunnel |
CN103867210A (en) * | 2014-03-28 | 2014-06-18 | 西安建筑科技大学 | City subway single-cross undermining construction method |
CN104612713A (en) * | 2014-12-12 | 2015-05-13 | 中铁十九局集团有限公司 | Super-shallow-buried section tunnel construction method |
CN205400758U (en) * | 2016-02-25 | 2016-07-27 | 中铁四局集团有限公司 | Temporary support system convenient to undercut tunnel passes through fast and invades limit pipeline region |
CN106014424A (en) * | 2016-06-27 | 2016-10-12 | 中交公局第三工程有限公司 | Blasting excavation method for shallowly-overburdened and shallowly-buried bored tunnel |
CN107725064A (en) * | 2017-11-22 | 2018-02-23 | 北京市政建设集团有限责任公司 | Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method |
CN209586382U (en) * | 2019-01-03 | 2019-11-05 | 济南城建集团有限公司 | The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section |
Non-Patent Citations (1)
Title |
---|
涂平安;: "高速铁路膨胀土隧道CRD法施工技术", 石家庄铁路职业技术学院学报, no. 01, 15 March 2017 (2017-03-15) * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111287764A (en) * | 2020-02-22 | 2020-06-16 | 北京泰德市政工程有限公司 | Tunnel secondary lining structure and construction method thereof |
CN111594233A (en) * | 2020-07-04 | 2020-08-28 | 四川路航建设工程有限责任公司 | Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall |
CN111594233B (en) * | 2020-07-04 | 2022-01-14 | 四川路航建设工程有限责任公司 | Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall |
CN115110966A (en) * | 2022-08-30 | 2022-09-27 | 中铁十六局集团地铁工程有限公司 | Tunnel supporting structure and construction method |
CN115110966B (en) * | 2022-08-30 | 2022-11-08 | 中铁十六局集团地铁工程有限公司 | Tunnel supporting structure and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN109681233B (en) | 2024-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11319690B2 (en) | Assembled recyclable rectangular working well with preset detachable door opening and construction method thereof | |
CN108204240B (en) | Anti-floating reinforcement system and reinforcement method for newly-built tunnel to span existing tunnel in short distance | |
CN110821503B (en) | Construction method for main body of ultra-deep shield section air shaft after tunnel advance | |
CN101858222B (en) | Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction | |
CN110485470A (en) | A kind of default push pipe door opening of water rich strata and the sliding rear rectangle active well and its construction method for leaning on wall | |
CN109681233A (en) | City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure | |
CN109723085B (en) | Deep foundation pit division construction rib wall support replacing structure and construction method thereof | |
CN107190752B (en) | The design and construction method of rectangular section Row Piles Supporting Structure can be recycled in a kind of flexible compound antiseepage assembled | |
CN107130611B (en) | Design and construction method of flexible composite anti-seepage assembled recoverable round-section row pile supporting structure | |
CN112160755B (en) | Subway line construction method for expanding excavation station after shield tunnel construction in advance | |
CN105735322A (en) | Design and construction method of rigid-flexible composite anti-seepage recoverable supporting structure | |
CN110242305A (en) | A kind of inclined shaft applies the construction technique in main hole into single side heading method | |
CN209586382U (en) | The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section | |
CN102817621B (en) | Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions | |
CN103993885A (en) | Construction method for underground excavation tunnel side-direction hole opening supporting system | |
CN109457709A (en) | A kind of supporting construction and construction method of double-row pile combination wide-angle anchor cable | |
CN110485468A (en) | A kind of water rich strata presets the permanent round-seal reservoir and its construction method of push pipe door opening | |
CN209443459U (en) | Cut-pff wall assembled leads wall | |
CN111255462B (en) | Pipe curtain cover excavation top-down construction method for subway station construction | |
CN101871218A (en) | Trenchless construction method of underground station space and arc-shaped freezing pipe construction equipment thereof | |
CN105156130B (en) | A kind of constructing tunnel exempts from supporting safe construction method | |
CN109930610A (en) | Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete | |
CN209539357U (en) | One kind increasing vertical shaft hole of becoming a full member in inclined shaft end and post descends road construction structure | |
CN109681213B (en) | Construction method for accelerating urban underground road by adding vertical shaft turning positive hole at inclined shaft end | |
CN102392459A (en) | Construction method for straight manhole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |