CN109681233A - City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure - Google Patents

City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure Download PDF

Info

Publication number
CN109681233A
CN109681233A CN201910003212.8A CN201910003212A CN109681233A CN 109681233 A CN109681233 A CN 109681233A CN 201910003212 A CN201910003212 A CN 201910003212A CN 109681233 A CN109681233 A CN 109681233A
Authority
CN
China
Prior art keywords
jurisdiction
section
interim
cross
vertical supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910003212.8A
Other languages
Chinese (zh)
Other versions
CN109681233B (en
Inventor
金宝
聂进兴
修乃锐
张鵾
周平
石义
赵伟宏
潘冲根
刘沈吉
许吉刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pinghu City Landscape Management Office
Pinghu Municipal Public Utilities Administration Office
Jinan Urban Construction Group Co Ltd
Original Assignee
Pinghu City Landscape Management Office
Pinghu Municipal Public Utilities Administration Office
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pinghu City Landscape Management Office, Pinghu Municipal Public Utilities Administration Office, Jinan Urban Construction Group Co Ltd filed Critical Pinghu City Landscape Management Office
Priority to CN201910003212.8A priority Critical patent/CN109681233B/en
Publication of CN109681233A publication Critical patent/CN109681233A/en
Application granted granted Critical
Publication of CN109681233B publication Critical patent/CN109681233B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention belongs to city underground engineering technical fields, the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure are used specifically related to a kind of city Shallow tunnel with large cross-section, including prefabricated interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction, the median septum of upper left step is set up by interim vertical supporting pipe sheet assembling, and the inverted arch of upper left step is set up by interim cross-brace pipe sheet assembling;The inverted arch of upper right step is set up by interim cross-brace pipe sheet assembling;Interim vertical supporting section of jurisdiction is equipped with injected hole.The present invention takes interim vertical supporting not bottomed, is closed with interim cross-brace, forms the inverse-T-shaped excavation method of innovation, and top bar is divided into upper left step and two step of upper right step is excavated, is reduced to the disposable perturbation area of the face soil body.Engineering method step of the present invention is simple, and strong operability is saved the area, and economic benefit and social benefit are significant.

Description

City Shallow tunnel with large cross-section using the inverse-T-shaped excavation method in precast support section of jurisdiction and Temporary support structure
Technical field
The invention belongs to city underground engineering technical fields, and in particular to a kind of city Shallow tunnel with large cross-section using pre- The inverse-T-shaped excavation method in system support section of jurisdiction and temporary support structure.
Background technique
With the development of the city, surface road is no longer satisfied growing vehicular traffic, has only and builds tube Road is alleviated.How big in traffic pressure, ground space is narrow, the Downtown of surrounding enviroment complexity, safe and efficient to repair Shallow tunnel with large cross-section is built, selects suitable excavation method particularly critical.There are benching tunnelling method, CD at present for excavating large cross-section tunnel The excavation methods such as method, CRD method, two side-wall pilot tunnel, they respectively have an advantage and disadvantage, for example the construction of benching tunnelling method, CD method is more quick, still In city, there are security risks in shallow embedding and stratum poor location;And CRD method and two side-wall pilot tunnel divide face is excavated Portion is more, and construction space is smaller, and gib is constructed, and dismounting amount is larger, and construction efficiency reduces very much;Two side-wall pilot tunnel construction Safety, but speed is slower, higher cost.In addition to this, above-mentioned existing engineering method especially will when building large cross-section tunnel The interim vertical median septum of construction or interim inverted arch, when excavation supporting, shaped steel arch is installed in gib, hangs steel mesh, and injection is mixed Solidifying soil is constructed, and also temporary support is all removed before later-stage secondary lining construction, not only construction efficiency is low, while causing tunnel Road hole environment pollution, lot of materials waste, is not suitable for green construction section material, energy-efficient theory.
Summary of the invention
The present invention to solve the deficiencies in the prior art, in conjunction with city Shallow tunnel with large cross-section construction characteristic, is different from existing Excavation method, innovation propose a kind of city Shallow tunnel with large cross-section use the inverse-T-shaped excavation method in precast support section of jurisdiction with And temporary support structure.
The present invention is achieved by the following technical solutions: a kind of inverse-T-shaped excavation of city Shallow tunnel with large cross-section faces When support construction, including prefabricated interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction, the median septum of upper left step is by facing When vertical supporting pipe sheet assembling set up, the inverted arch of upper left step is set up by interim cross-brace pipe sheet assembling;Upper right The inverted arch of step is set up by interim cross-brace pipe sheet assembling;Interim vertical supporting section of jurisdiction is equipped with injected hole.
Assembly is bolted in the assembly of the interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction.
2 injected holes are equipped between the interim vertical supporting section of jurisdiction connection bolt, injected hole is at a distance from bolt 30cm。
The width of the interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction is 1.5m, with a thickness of 20cm.
The invention also includes a kind of city Shallow tunnel with large cross-section to use the inverse-T-shaped excavation method in precast support section of jurisdiction, packet Include following steps:
(1) upper left bench excavation: first carrying out advance support, then excavate, and carries out preliminary bracing construction, and assembling is prefabricated Interim vertical supporting section of jurisdiction and interim cross-brace section of jurisdiction are set up into interval wall construction with interim vertical supporting pipe sheet assembling, are used Interim cross-brace pipe sheet assembling is set up into inverted arch structure;
(2) upper right bench excavation: first carrying out advance support, then excavate, and carries out preliminary bracing construction, and assembling is prefabricated Interim cross-brace section of jurisdiction, is set up with interim cross-brace pipe sheet assembling into inverted arch structure;
(3) get out of a predicament or an embarrassing situation excavation: excavation of getting out of a predicament or an embarrassing situation, tunnel landing, construction tunnel inverted arch preliminary bracing form loopful closure;
(4) secondary lining inverted arch is constructed: after the completion of getting out of a predicament or an embarrassing situation construction, in the inverted arch that interim cross-brace pipe sheet assembling is set up It constructs in time under structure secondary lining inverted arch;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps Section of jurisdiction and interim cross-brace section of jurisdiction are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: utilizing the interim vertical supporting section of jurisdiction removed and interim cross-brace section of jurisdiction into next excavation branch Shield circulation.
Beneficial effects of the present invention:
One, it takes interim vertical supporting not bottomed, is closed with interim cross-brace, forms the inverse-T-shaped excavation method of innovation, Top bar is divided into upper left step and two step of upper right step is excavated, is reduced to the disposable perturbation area of the face soil body.This hair Bright engineering method step is simple, and strong operability is saved the area, and economic benefit and social benefit are significant.
Two, a close ring is just formed after the completion of top bar is excavated, the inverted arch that interim cross-brace section of jurisdiction splicing is set up subtracts The clearance convergence in tunnel is lacked, the median septum that interim vertical supporting section of jurisdiction splicing is set up reduces tunnel vault sedimentation, leaves office Rank does not set up interim perpendicular support, not only increases efficiency while guaranteeing safe, has also speeded up tunnel landing and loopful closure Time, while the construction speed of Tunnel Second Lining inverted arch can be accelerated, reduce tunnel safety hidden danger.
Three, interim cross-brace section of jurisdiction and interim vertical supporting section of jurisdiction can be recycled, and have saved a large amount of raw material, reached Safe and efficient, green, factorial construction purpose is arrived.
Four, the present invention increases in the case where guarantee preliminary bracing safe stress and excavates space, reduce gib Construction and the workload removed, had not only improved working efficiency but also had saved construction cost.Compared with the temporary support of existing site operation Compared with, reduce construction time and concrete strength curing time, it is i.e. force-applied after prefabricated temporary support installation, reduce injection Curing time needed for concrete strength is up to standard avoids the problem of sedimentation is with convergent deformation after tunnel excavation, especially interim cross It to support (inverted arch), can pass through immediately after having set up, as construction road, machinery can pass through immediately, and existing conventional branch Shield, can pass after waiting the concrete curing time to meet intensity requirement.The present invention reduces on-site construction times, reduce Construction pollution in tunnel.
Detailed description of the invention
Fig. 1 is that inverted " t " of the present invention excavates structure chart.
Fig. 2 is the interim cross-brace section of jurisdiction plane drawing of the present invention.
Fig. 3 is the interim vertical supporting section of jurisdiction plane drawing of the present invention.
Fig. 4 is the facade drawing of the interim cross-brace section of jurisdiction of the present invention or interim vertical supporting section of jurisdiction.
In figure, 1 interim vertical supporting section of jurisdiction, 2 interim cross-brace sections of jurisdiction, 3 bolts, 4 injected holes, 5 upper left steps, 6 is right Top bar, 7 get out of a predicament or an embarrassing situation.
Specific embodiment
Specific embodiments of the present invention are given below, it should be noted that the invention is not limited to implement in detail below Example, all equivalent transformations made on the basis of the technical solutions of the present application each fall within protection scope of the present invention.
City Shallow tunnel with large cross-section of the invention using the inverse-T-shaped excavation method in precast support section of jurisdiction approximately as: will Top bar is divided into two steps excavation, and left and right sides is separated certain distance, reduces to the disposable perturbation area of the face soil body, upper Form a close ring after the completion of bench excavation, then carry out 7 excavations of getting out of a predicament or an embarrassing situation, get out of a predicament or an embarrassing situation 7 excavation when do not set up it is interim vertical Support accelerates the time of tunnel landing and loopful closure for improving efficiency.
City Shallow tunnel with large cross-section of the invention use the inverse-T-shaped excavation method in precast support section of jurisdiction, specifically include as Lower step:
(1) upper left step 5 excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated Interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2, with interim 1 assembling of vertical supporting section of jurisdiction at median septum knot Structure, with interim 2 assembling of cross-brace section of jurisdiction at inverted arch structure;
(2) upper right step 6 excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated Interim cross-brace section of jurisdiction 2, with interim 2 assembling of cross-brace section of jurisdiction at inverted arch structure;
(3) get out of a predicament or an embarrassing situation 7 excavations: 7 excavations of getting out of a predicament or an embarrassing situation, tunnel landing, construction tunnel inverted arch preliminary bracing form loopful closure;
(4) secondary lining inverted arch construct: get out of a predicament or an embarrassing situation 7 constructions closing cyclization after, interim 2 assembling of cross-brace section of jurisdiction at Inverted arch structure under construct in time secondary lining inverted arch, improve the safety coefficient of tunnel structure;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps Section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: entering next excavation using the interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 removed Supporting circulation.
Above-mentioned interim cross-brace section of jurisdiction 2 used and interim vertical supporting section of jurisdiction 1 shift to an earlier date prefabricated process in factory At direct splicing use.
The assembled bolt 3 that passes through between above-mentioned interim vertical supporting section of jurisdiction 1, between interim cross-brace section of jurisdiction 2 carries out Connection is assembled, and the width of interim vertical supporting section of jurisdiction 1 and interim cross-brace section of jurisdiction 2 used is 1.5m, with a thickness of 20cm. Injected hole 4 is equipped on above-mentioned interim vertical supporting section of jurisdiction 1, injected hole 4 is located at the connection bolt of interim vertical supporting section of jurisdiction 1 Between 3,2 injected holes 4 are equipped between connection bolt 3, as shown in Fig. 3, injected hole 4 is 30cm at a distance from bolt 3.
Under above-mentioned inverse-T-shaped excavation method, the present invention yet forms that a kind of city Shallow tunnel with large cross-section is inverse-T-shaped to be opened The temporary support structure of digging, this temporary support structure include prefabricated interim vertical supporting section of jurisdiction 1 and interim cross-brace pipe The median septum of piece 2, upper left step 5 is formed by interim 1 assembling of vertical supporting section of jurisdiction, and the inverted arch of upper left step 5 is by interim horizontal It is formed to support 2 assembling of section of jurisdiction;The inverted arch of upper right step 6 is formed by interim 2 assembling of cross-brace section of jurisdiction.
Embodiment described above, only one kind of the present invention more preferably specific embodiment, those skilled in the art The usual variations and alternatives that member carries out within the scope of technical solution of the present invention should be all included within the scope of the present invention.

Claims (5)

1. a kind of temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section, including prefabricated interim vertical supporting Section of jurisdiction (1) and interim cross-brace section of jurisdiction (2), it is characterised in that: the median septum of upper left step (5) is by interim vertical supporting section of jurisdiction (1) assembling forms, and the inverted arch of upper left step (5) is formed by interim cross-brace section of jurisdiction (2) assembling;Upper right step (6) inverted arch is formed by interim cross-brace section of jurisdiction (2) assembling;Interim vertical supporting section of jurisdiction (1) is equipped with injected hole (4).
2. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 1, it is characterised in that: The interim vertical supporting section of jurisdiction (1) and the assembled of interim cross-brace section of jurisdiction (2) pass through bolt (3) connection assembly.
3. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 2, it is characterised in that: Be equipped with 2 injected holes (4) between interim vertical supporting section of jurisdiction (1) connection bolt (3), injected hole (4) and bolt (3) away from From for 30cm.
4. the support construction of Shallow tunnel with large cross-section inverse-T-shaped excavation in city according to claim 1, it is characterised in that: The width of the interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) is 1.5m, with a thickness of 20cm.
5. a kind of city Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction, it is characterised in that: including such as Lower step:
(1) upper left step (5) excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated Good interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2), with interim vertical supporting section of jurisdiction (1) assembling at Interval wall construction, with interim cross-brace section of jurisdiction (2) assembling at inverted arch structure;
(2) upper right step (6) excavates: first carrying out advance support, then excavates, carry out preliminary bracing construction, assembling is prefabricated Good interim cross-brace section of jurisdiction (2), with interim cross-brace section of jurisdiction (2) assembling at inverted arch structure;
(3) get out of a predicament or an embarrassing situation (7) excavation: get out of a predicament or an embarrassing situation (7) excavation, tunnel landing, construction tunnel inverted arch preliminary bracing, formed loopful close It closes;
(4) secondary lining inverted arch construct: get out of a predicament or an embarrassing situation (7) construct after the completion of, interim cross-brace section of jurisdiction (2) assembling at Inverted arch structure under construct in time secondary lining inverted arch;
(5) secondary lining side and roof arch is constructed: after the completion of the construction of Tunnel Second Lining inverted arch, removing the interim vertical of above-mentioned steps Section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) are supported, the lining construction of secondary lining side and roof arch two is carried out;
(6) circulation is excavated: being entered using the interim vertical supporting section of jurisdiction (1) and interim cross-brace section of jurisdiction (2) removed next Excavation supporting circulation.
CN201910003212.8A 2019-01-03 2019-01-03 Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces Active CN109681233B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910003212.8A CN109681233B (en) 2019-01-03 2019-01-03 Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910003212.8A CN109681233B (en) 2019-01-03 2019-01-03 Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces

Publications (2)

Publication Number Publication Date
CN109681233A true CN109681233A (en) 2019-04-26
CN109681233B CN109681233B (en) 2024-06-04

Family

ID=66191834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910003212.8A Active CN109681233B (en) 2019-01-03 2019-01-03 Inverted T-shaped excavation construction method and temporary support structure for urban shallow-buried large-section tunnel by adopting prefabricated support duct pieces

Country Status (1)

Country Link
CN (1) CN109681233B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111287764A (en) * 2020-02-22 2020-06-16 北京泰德市政工程有限公司 Tunnel secondary lining structure and construction method thereof
CN111594233A (en) * 2020-07-04 2020-08-28 四川路航建设工程有限责任公司 Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall
CN115110966A (en) * 2022-08-30 2022-09-27 中铁十六局集团地铁工程有限公司 Tunnel supporting structure and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1490568A (en) * 1973-12-05 1977-11-02 Bochumer Eisen Heintzmann Method of providing a support structure for a tunnel-like way and apparatus for performing the method
CN102305077A (en) * 2011-09-23 2012-01-04 中南大学 Rapid construction method of large-section multi-arc tunnel
CN103867210A (en) * 2014-03-28 2014-06-18 西安建筑科技大学 City subway single-cross undermining construction method
CN104612713A (en) * 2014-12-12 2015-05-13 中铁十九局集团有限公司 Super-shallow-buried section tunnel construction method
CN205400758U (en) * 2016-02-25 2016-07-27 中铁四局集团有限公司 Temporary support system convenient to undercut tunnel passes through fast and invades limit pipeline region
CN106014424A (en) * 2016-06-27 2016-10-12 中交公局第三工程有限公司 Blasting excavation method for shallowly-overburdened and shallowly-buried bored tunnel
CN107725064A (en) * 2017-11-22 2018-02-23 北京市政建设集团有限责任公司 Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN209586382U (en) * 2019-01-03 2019-11-05 济南城建集团有限公司 The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1490568A (en) * 1973-12-05 1977-11-02 Bochumer Eisen Heintzmann Method of providing a support structure for a tunnel-like way and apparatus for performing the method
CN102305077A (en) * 2011-09-23 2012-01-04 中南大学 Rapid construction method of large-section multi-arc tunnel
CN103867210A (en) * 2014-03-28 2014-06-18 西安建筑科技大学 City subway single-cross undermining construction method
CN104612713A (en) * 2014-12-12 2015-05-13 中铁十九局集团有限公司 Super-shallow-buried section tunnel construction method
CN205400758U (en) * 2016-02-25 2016-07-27 中铁四局集团有限公司 Temporary support system convenient to undercut tunnel passes through fast and invades limit pipeline region
CN106014424A (en) * 2016-06-27 2016-10-12 中交公局第三工程有限公司 Blasting excavation method for shallowly-overburdened and shallowly-buried bored tunnel
CN107725064A (en) * 2017-11-22 2018-02-23 北京市政建设集团有限责任公司 Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN209586382U (en) * 2019-01-03 2019-11-05 济南城建集团有限公司 The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
涂平安;: "高速铁路膨胀土隧道CRD法施工技术", 石家庄铁路职业技术学院学报, no. 01, 15 March 2017 (2017-03-15) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111287764A (en) * 2020-02-22 2020-06-16 北京泰德市政工程有限公司 Tunnel secondary lining structure and construction method thereof
CN111594233A (en) * 2020-07-04 2020-08-28 四川路航建设工程有限责任公司 Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall
CN111594233B (en) * 2020-07-04 2022-01-14 四川路航建设工程有限责任公司 Filling-free steel frame support subsection excavation construction method for tunnel lower-partition-free partition wall
CN115110966A (en) * 2022-08-30 2022-09-27 中铁十六局集团地铁工程有限公司 Tunnel supporting structure and construction method
CN115110966B (en) * 2022-08-30 2022-11-08 中铁十六局集团地铁工程有限公司 Tunnel supporting structure and construction method

Also Published As

Publication number Publication date
CN109681233B (en) 2024-06-04

Similar Documents

Publication Publication Date Title
US11319690B2 (en) Assembled recyclable rectangular working well with preset detachable door opening and construction method thereof
CN108204240B (en) Anti-floating reinforcement system and reinforcement method for newly-built tunnel to span existing tunnel in short distance
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN101858222B (en) Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
CN110485470A (en) A kind of default push pipe door opening of water rich strata and the sliding rear rectangle active well and its construction method for leaning on wall
CN109681233A (en) City Shallow tunnel with large cross-section uses the inverse-T-shaped excavation method in precast support section of jurisdiction and temporary support structure
CN109723085B (en) Deep foundation pit division construction rib wall support replacing structure and construction method thereof
CN107190752B (en) The design and construction method of rectangular section Row Piles Supporting Structure can be recycled in a kind of flexible compound antiseepage assembled
CN107130611B (en) Design and construction method of flexible composite anti-seepage assembled recoverable round-section row pile supporting structure
CN112160755B (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN105735322A (en) Design and construction method of rigid-flexible composite anti-seepage recoverable supporting structure
CN110242305A (en) A kind of inclined shaft applies the construction technique in main hole into single side heading method
CN209586382U (en) The temporary support structure of the inverse-T-shaped excavation of city Shallow tunnel with large cross-section
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN109457709A (en) A kind of supporting construction and construction method of double-row pile combination wide-angle anchor cable
CN110485468A (en) A kind of water rich strata presets the permanent round-seal reservoir and its construction method of push pipe door opening
CN209443459U (en) Cut-pff wall assembled leads wall
CN111255462B (en) Pipe curtain cover excavation top-down construction method for subway station construction
CN101871218A (en) Trenchless construction method of underground station space and arc-shaped freezing pipe construction equipment thereof
CN105156130B (en) A kind of constructing tunnel exempts from supporting safe construction method
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN209539357U (en) One kind increasing vertical shaft hole of becoming a full member in inclined shaft end and post descends road construction structure
CN109681213B (en) Construction method for accelerating urban underground road by adding vertical shaft turning positive hole at inclined shaft end
CN102392459A (en) Construction method for straight manhole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant