CN101806025A - 道岔组装方法 - Google Patents

道岔组装方法 Download PDF

Info

Publication number
CN101806025A
CN101806025A CN200910312574A CN200910312574A CN101806025A CN 101806025 A CN101806025 A CN 101806025A CN 200910312574 A CN200910312574 A CN 200910312574A CN 200910312574 A CN200910312574 A CN 200910312574A CN 101806025 A CN101806025 A CN 101806025A
Authority
CN
China
Prior art keywords
switch
assembling
railway switches
railway
track switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910312574A
Other languages
English (en)
Inventor
赵�智
谢录杲
秦瑞谦
王智勇
白昆华
龚斯昆
赵代强
梅红
肖肃宇
万轶
宋德佩
杜建武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN200910312574A priority Critical patent/CN101806025A/zh
Publication of CN101806025A publication Critical patent/CN101806025A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Train Traffic Observation, Control, And Security (AREA)
  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

本发明公开了一种道岔组装方法,包括以下步骤:将道岔组装平台在岔位上进行组装;将岔枕在平台上摆放方正;使用道岔专用吊具,将道岔长钢轨件吊卸至岔枕上,入槽并上紧扣件;联接道岔长钢轨件,并安装竖向支撑架;预埋横向调整件,并与岔枕桁架钢筋焊连;配合全站仪、电子水准仪及轨道几何状态测量仪,调整竖向、横向调整螺栓,使道岔直股中线与线路设计中线偏差控制在3mm以内,组装调整后的高程与设计高程的偏差控制在-5mm至0mm之间。本发明的积极效果是:通过本发明原位组装的道岔,整体平顺性好,保证道岔在组装过程中不变形,工效较以往有很大的提高。

Description

道岔组装方法
技术领域
本发明涉及铁路轨道,尤其是涉及无砟道岔原位组装方法。
背景技术
随着我国经济的发展,作业城市交通体系的铁路交通已成为大中城市连接的重要纽带。以无砟结构为主的轨道形式,已经成为现今国内轨道发展的主要的趋势,并大力的进行建设。轨枕埋入式无砟道岔是我国客运专线技术创新的最新研究成果,为此还成立了高速道岔课题组。无砟道岔是轨道结构中最为复杂的部分,铺设的好坏将直接影响到轨道结构的受力、平顺性、行车安全及舒适性,因而无砟道岔的铺设就成为无砟轨道关键施工技术之一。
道岔在厂内预组装调试合格后,拆截成散件运输到现场;现场将散件(扣件、轨枕、钢轨件等)进行组装、联接,并安装支撑调整***,进行初步定位;道岔组装是保证道岔铺设精度的关键过程,为此,专门研制出了一种道岔初步定位方法。
发明内容
基于上述实践的需要,本发明提供了一种道岔组装方法,使道岔散件在现场进行原位组装,且能保证道岔的整体平顺性好。
本发明解决其技术问题所采用的技术方案是:一种道岔组装方法,包括以下步骤:
第一步,根据定出的点位,以及测出的高程,将道岔组装平台在岔位上进行组装;
第二步,将岔枕在平台上摆放方正;
第三步,使用道岔专用吊具,将道岔长钢轨件吊卸至岔枕上,入槽并上紧扣件;
第四步,联接道岔长钢轨件,并安装竖向支撑架;
第五步,预埋横向调整件,并与岔枕桁架钢筋焊连;
第六步,配合全站仪、电子水准仪及轨道几何状态测量仪,调整竖向、横向调整螺栓,使道岔直股中线与线路设计中线偏差控制在3mm以内,组装调整后的高程与设计高程的偏差控制在-5mm至0mm之间。
本发明的积极效果是:通过本发明原位组装的道岔,整体平顺性好,保证道岔在组装过程中不变形,工效较以往有很大的提高。
具体实施方式
本说明书中公开的所有特征,或公开的所有方法或过程中的步骤,除了互相排斥的特征和/或步骤以外,均可以以任何方式组合。
本说明书(包括任何附加权利要求、摘要和附图)中公开的任一特征,除非特别叙述,均可被其他等效或具有类似目的的替代特征加以替换。即,除非特别叙述,每个特征只是一系列等效或类似特征中的一个例子而已。
一种道岔组装方法,包括如下步骤:
第一步,根据定出的点位,以及测出的高程,将道岔组装平台在岔位上进行组装;
第二步,将岔枕在平台上摆放方正;
第三步,使用道岔专用吊具,将道岔长钢轨件吊卸至岔枕上,入槽并上紧扣件;
第四步,联接道岔长钢轨件,并安装竖向支撑架;
第五步,预埋横向调整件,并与岔枕桁架钢筋焊连;
第六步,配合全站仪、电子水准仪及轨道几何状态测量仪,调整竖向、横向调整螺栓,使道岔直股中线与线路设计中线偏差不超过3mm,组装调整后的高程与设计高程偏差控制在-5mm至0mm之间,即不超过设计高程,但也不得低于设计高程5mm以下。
本发明组装道岔组装平台,是为了保证道岔散件能在现场组装时,在道岔方向和高程上进行比较精准的定位,保证了道岔组装的精度和便利性。
本发明将岔枕在平台上摆放方正,是为了保证岔枕的精准摆放,减少钢轨件吊卸后,岔枕的调整作业,提高了工效。
本发明使用道岔专用吊具吊卸道岔长钢轨件,是为了保证在吊卸过程中,不产生变形,保证了道岔组装质量。
本发明联接道岔长钢轨件及安装竖向调整架,是为了保证道岔长钢轨件联接平顺,便于后期调整;竖向调整架是为了调整道岔高程,也同时为后期拆除平台后,起到支撑道岔的作用。
本发明使用横向调整件,是为了调整道岔方向,同时控制道岔横向位移。
本发明使用全站仪、电子水准仪及轨道几何状态测量仪是为了调整道岔方向和高程,为后期道岔精调做好准备。
本发明并不局限于前述的具体实施方式。本发明扩展到任何在本说明书中披露的新特征或任何新的组合,以及披露的任一新的方法或过程的步骤或任何新的组合。

Claims (1)

1.一种道岔组装方法,其特征在于:包括以下步骤:
第一步,根据定出的点位,以及测出的高程,将道岔组装平台在岔位上进行组装;
第二步,将岔枕在平台上摆放方正;
第三步,使用道岔专用吊具,将道岔长钢轨件吊卸至岔枕上,入槽并上紧扣件;
第四步,联接道岔长钢轨件,并安装竖向支撑架;
第五步,预埋横向调整件,并与岔枕桁架钢筋焊连;
第六步,配合全站仪、电子水准仪及轨道几何状态测量仪,调整竖向、横向调整螺栓,使道岔直股中线与线路设计中线偏差控制在3mm以内,组装调整后的高程与设计高程的偏差控制在-5mm至0mm之间。
CN200910312574A 2009-12-30 2009-12-30 道岔组装方法 Pending CN101806025A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910312574A CN101806025A (zh) 2009-12-30 2009-12-30 道岔组装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910312574A CN101806025A (zh) 2009-12-30 2009-12-30 道岔组装方法

Publications (1)

Publication Number Publication Date
CN101806025A true CN101806025A (zh) 2010-08-18

Family

ID=42607969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910312574A Pending CN101806025A (zh) 2009-12-30 2009-12-30 道岔组装方法

Country Status (1)

Country Link
CN (1) CN101806025A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2451125C1 (ru) * 2010-12-28 2012-05-20 Открытое Акционерное Общество "Российские Железные Дороги" Поточная линия для сборки стрелочного перевода железнодорожного пути
CN102953304A (zh) * 2012-09-20 2013-03-06 中铁三局集团有限公司 地铁轨道结构施工的精密测量控制方法
CN111074698A (zh) * 2019-12-23 2020-04-28 中铁十七局集团第二工程有限公司 一种原位铺设法在隧道内道岔施工工艺
CN111074773A (zh) * 2019-12-23 2020-04-28 中铁十七局集团第二工程有限公司 一种桥上单开道岔的施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2451125C1 (ru) * 2010-12-28 2012-05-20 Открытое Акционерное Общество "Российские Железные Дороги" Поточная линия для сборки стрелочного перевода железнодорожного пути
CN102953304A (zh) * 2012-09-20 2013-03-06 中铁三局集团有限公司 地铁轨道结构施工的精密测量控制方法
CN102953304B (zh) * 2012-09-20 2015-04-08 中铁三局集团有限公司 地铁轨道结构施工的精密测量控制方法
CN111074698A (zh) * 2019-12-23 2020-04-28 中铁十七局集团第二工程有限公司 一种原位铺设法在隧道内道岔施工工艺
CN111074773A (zh) * 2019-12-23 2020-04-28 中铁十七局集团第二工程有限公司 一种桥上单开道岔的施工方法

Similar Documents

Publication Publication Date Title
CN101806025A (zh) 道岔组装方法
CN203080372U (zh) 下承式轨道调整支撑架
CN106049209A (zh) 一种用于铁路无砟轨道支撑层拆换的临时钢轨支撑装置
CN208869890U (zh) 一种吊装式钢轨精调装置
CN114086434B (zh) 一种纵向装配的预制板式轨道
CN201137021Y (zh) 一种道岔横向调整装置
CN109183530A (zh) 一种用于无砟轨道病害整治的线路临时架空装置及方法
CN110470193B (zh) 一种监测箱梁与桥墩相对位移的方法
CN201433334Y (zh) 框架梁式无砟轨道
KR101399839B1 (ko) 철도교량 단부 횡단 궤도 구조 및 그 시공 방법
CN201232141Y (zh) 一种抗疲劳弹条iv型扣件
KR101405468B1 (ko) 철도 궤도용 콘크리트 블록의 제조방법 및 이 방법에 의해 제조된 콘크리트 블록을 이용한 철도 궤도 부설방법
CN202194037U (zh) 高速铁路无砟道岔横向调整定位装置
CN203256551U (zh) 一种双块式无砟轨道排架装置
CN202705830U (zh) 双块式无砟轨道施工用互拉调整排架
CN205893837U (zh) 一种用于铁路无砟轨道支撑层拆换的临时钢轨支撑装置
CN213507844U (zh) 一种用于高架段套轨新型减振轨道结构
CN202658485U (zh) 用于双块式无碴轨道横向伸缩缝施工的模板装置
CN102758388B (zh) 双块式无碴轨道横向伸缩缝的模板装置及施工方法
CN210151488U (zh) 一种隔振支座
CN101768902A (zh) 道岔精调方法
CN102352585B (zh) 高速铁路无砟道岔横向调整定位装置
CN201671029U (zh) 一种无砟道床道岔组装平台
CN212983493U (zh) 一种适用于铁路小半径曲线段无砟轨道施工的轨排框架
CN111270573A (zh) 一种中低速磁浮轨排锚固装置及安装调整方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20100818