CN101265704B - Underground cast-in-place concrete structure outer wall neck construction method - Google Patents

Underground cast-in-place concrete structure outer wall neck construction method Download PDF

Info

Publication number
CN101265704B
CN101265704B CN2008100529217A CN200810052921A CN101265704B CN 101265704 B CN101265704 B CN 101265704B CN 2008100529217 A CN2008100529217 A CN 2008100529217A CN 200810052921 A CN200810052921 A CN 200810052921A CN 101265704 B CN101265704 B CN 101265704B
Authority
CN
China
Prior art keywords
wall
reinforcing bar
steel bars
wall body
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008100529217A
Other languages
Chinese (zh)
Other versions
CN101265704A (en
Inventor
***
杨建国
李忠雨
翟树起
娄维萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JIANGONG CONSTRUCTION CO Ltd
Original Assignee
TIANJIN JIANGONG CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JIANGONG CONSTRUCTION CO Ltd filed Critical TIANJIN JIANGONG CONSTRUCTION CO Ltd
Priority to CN2008100529217A priority Critical patent/CN101265704B/en
Publication of CN101265704A publication Critical patent/CN101265704A/en
Application granted granted Critical
Publication of CN101265704B publication Critical patent/CN101265704B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses an external wall neck construction method of the underground cast-in-situ concrete structure, which includes the following steps: (1) arranging reinforced bars, wall body external steel bars and wall body internal steel bars on a bedding course, arranging a first exterior sheathing composed of a multilayer board and a square timber outside the wall body external steel bars in the method of external suspended form supporting formwork; (2) arranging the first exterior sheathing composed of the multilayer board and the square timber inside and fixedly connecting with the wall body internal steel bars, arranging a water-stopping steel plate between the wall body external steel bars and the wall body internal steel bars; (3) casting the concrete and finishing the underground cast-in-situ concrete structure external wall neck construction. The method enables a calendering operation of the upper surface of a foundation plate through surface rolling mechanically or manually, and enables the wall foot of the wall neck to be conveniently rolled to achieve the process requirement of one-step operation of casting and rolling together and the effect of exposed concrete. The method is easy, practical and economic, and the flatness can be controlled.

Description

Underground cast-in-place concrete structure outer wall neck construction method
Technical field
The invention belongs to building engineering field, particularly relate to a kind of underground cast-in-place concrete structure outer wall neck construction method.
Background technology
Underground cast-in-place concrete structure outer in construction owing to require between the operation and the requirement of waterproof, when carrying out the construction of underground foundation base plate, adopt following method by the current specifications requirement: the upper surface at sole plate is kept somewhere the high wall neck (Fig. 1) of 300mm, the upper surface of wall neck is a horizontal construction joint, mould mold method (Fig. 2) is hung in the employing that is provided with of wall neck, promptly the template of forming by composite board, the lumps of wood by scaffold tubes prop up be located at base plate reinforcing bar top after, fluid concrete makes underground foundation base plate and the one-shot forming of wall neck.
The method of keeping somewhere the wall neck by prior art, because template need support with scaffold tubes in inner side of outer wall, template and scaffold tubes occupy certain space, the upper surface that makes sole plate is during by mechanical or manual floating calendering operation, the foot of a wall portion of wall neck can't be floating, can't accomplish the technological requirement that once survives with smearing with building.Since more and more higher to the concrete wall surface standard-required in recent years, reach the clear-water concrete effect.So very high to its impression planeness requirement, particularly ground, the metope to large-scale basement requires one-shot forming, reach the clear-water concrete standard, and ground flat degree is not more than the 2mm accuracy standard.Existing formwork support process by code requirement is difficult to reach designing requirement.
Summary of the invention:
The objective of the invention is to overcome deficiency of the prior art, a kind of underground cast-in-place concrete structure outer wall neck construction method is provided.
Technical scheme of the present invention is summarized as follows:
A kind of underground cast-in-place concrete structure outer wall neck construction method comprises the steps:
(1) the inboard reinforcing bar of reinforcement foundation, wall outer side reinforcing bar and body of wall is set on bed course, hangs first exterior sheathing that the method setting of mould formwork is made up of composite board, the lumps of wood with external application at the wall outer side reinforcing bar;
(2) will be arranged on by first inner formword that composite board, the lumps of wood are formed in the inboard reinforcing bar of body of wall, and fixedly connected, between outside reinforcing bar and the inboard reinforcing bar of body of wall, steel plate for sealing water will be set with the inboard reinforcing bar of body of wall;
(3) concreting is finished the underground cast-in-place concrete structure outer wall neck construction.
Method of the present invention can make the upper surface of sole plate by mechanical or manual floating calendering operation, and the foot of a wall of wall neck can be convenient floating, accomplishes the technological requirement that once survives with smearing with building.Reach the clear-water concrete effect.Method of the present invention is simple, practical, and economy, planeness reach controlled.
Description of drawings
Sole plate and outer wall neck schematic diagram that Fig. 1 builds for existing method;
Fig. 2 installs concrete exterior wall wall neck template method schematic diagram for existing method;
Fig. 3 installs concrete exterior wall wall neck template schematic diagram for method of the present invention;
Fig. 4 is a formwork erection method schematic diagram for the inventive method pouring concrete exterior wall;
Sole plate and concrete exterior wall overall schematic that Fig. 5 builds for the inventive method.
The specific embodiment
The present invention is further illustrated below in conjunction with accompanying drawing.
Sole plate that existing method shown in Figure 1 is built and outer wall neck schematic diagram are among the figure: wall outer side reinforcing bar 1; The inboard reinforcing bar 2 of body of wall; Steel plate for sealing water 3; Outer wall neck 4; Sole plate 5; Bed course 6.
Make underground foundation base plate and the one-shot forming of wall neck, prior art adopts the method for hanging the mould formwork, sees Fig. 2, among the figure: reinforcement foundation 10, scaffold tubes 9, the first inner formwords 16, the first exterior sheathings 17, inside and outside template is made up of composite board, the lumps of wood.
A kind of underground cast-in-place concrete structure outer wall neck construction method of the present invention comprises the steps: (see figure 3)
(1) the inboard reinforcing bar 2 of reinforcement foundation 10, wall outer side reinforcing bar 1 and body of wall is set on bed course 6, hangs first exterior sheathing 17 that the method setting of mould formwork is made up of composite board, the lumps of wood (external application hang the mould formwork method be to support first exterior sheathing 17) at the wall outer side reinforcing bar with external application by scaffold tubes 9;
(2) will be arranged on by first inner formword 16 that composite board, the lumps of wood are formed in the inboard reinforcing bar of body of wall, and fixedly connected, between outside reinforcing bar and the inboard reinforcing bar of body of wall, steel plate for sealing water 3 will be set with the inboard reinforcing bar of body of wall;
(3) concreting is finished the underground cast-in-place concrete structure outer wall neck construction.Because first inner formword is arranged in the inboard reinforcing bar of body of wall, makes the sole plate upper surface not have any supporter, when building, sole plate upper surface mechanical trowelling machine easy to use carries out floating press polish, has improved operating efficiency.
After finishing the underground cast-in-place concrete structure outer wall neck construction, remove first inner formword and first exterior sheathing, carry out the top wall construction, the method of its formwork is seen Fig. 4, second inner formword 12 is directly upright to the sole plate upper surface by the inside wall line, second inner formword, second exterior sheathing 13 are fixed by scaffold tubes 9 and through-wall bolt 14, build again.After removing the second inside and outside template, the anhydrous flat constuction joint of inboard metope (existing method has inboard metope that horizontal construction joint is arranged), the surface is the impression unanimity up and down.See Fig. 5, among Fig. 5, build sole plate 15 and wall neck for the first time, for the second time concreting wall 18.

Claims (1)

1. a underground cast-in-place concrete structure outer wall neck construction method is characterized in that comprising the steps:
(1) the inboard reinforcing bar of reinforcement foundation, wall outer side reinforcing bar and body of wall is set on bed course, hangs first exterior sheathing that the method setting of mould formwork is made up of composite board, the lumps of wood with external application at the wall outer side reinforcing bar;
(2) will be arranged on by first inner formword that composite board, the lumps of wood are formed in the inboard reinforcing bar of body of wall, and fixedly connected, between outside reinforcing bar and the inboard reinforcing bar of body of wall, steel plate for sealing water will be set with the inboard reinforcing bar of body of wall;
(3) concreting is finished the underground cast-in-place concrete structure outer wall neck construction, and described wall neck is to keep somewhere the high wall of 300mm at the upper surface of sole plate.
CN2008100529217A 2008-04-28 2008-04-28 Underground cast-in-place concrete structure outer wall neck construction method Expired - Fee Related CN101265704B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100529217A CN101265704B (en) 2008-04-28 2008-04-28 Underground cast-in-place concrete structure outer wall neck construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100529217A CN101265704B (en) 2008-04-28 2008-04-28 Underground cast-in-place concrete structure outer wall neck construction method

Publications (2)

Publication Number Publication Date
CN101265704A CN101265704A (en) 2008-09-17
CN101265704B true CN101265704B (en) 2010-06-09

Family

ID=39988370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100529217A Expired - Fee Related CN101265704B (en) 2008-04-28 2008-04-28 Underground cast-in-place concrete structure outer wall neck construction method

Country Status (1)

Country Link
CN (1) CN101265704B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102352607A (en) * 2011-10-28 2012-02-15 中铁四局集团第四工程有限公司 Full water stopping side wall template system
CN109025290A (en) * 2018-07-24 2018-12-18 北京首钢建设集团有限公司 A kind of water-proof concrete exterior wall and basic intersection setting-up of construction joint construction method
CN112814369A (en) * 2020-12-30 2021-05-18 中国建筑第八工程局有限公司 Horizontal construction joint formwork device for cast-in-place reinforced concrete wall and construction method
CN115929040A (en) * 2022-12-19 2023-04-07 中铁四局集团第三建设有限公司 Side wall construction method for improving horizontal construction joint

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2658247Y (en) * 2003-09-30 2004-11-24 张在东 Thermal insulation water-proof structure of underground exposed wall of building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2658247Y (en) * 2003-09-30 2004-11-24 张在东 Thermal insulation water-proof structure of underground exposed wall of building

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴杰平.钢筋混凝土外墙施工缝接缝处理.建筑工人 3.2005,(3),27.
吴杰平.钢筋混凝土外墙施工缝接缝处理.建筑工人 3.2005,(3),27. *

Also Published As

Publication number Publication date
CN101265704A (en) 2008-09-17

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN105908777A (en) Comprehensive pipe gallery sliding mold and application method thereof
EP3670774A1 (en) Prefabricated bathroom and methods for constructing and installing the same
CN101265704B (en) Underground cast-in-place concrete structure outer wall neck construction method
CN211007032U (en) Concrete bay window plastering-free construction structure
CN109797969B (en) Construction method of post-cast strip tool type advanced formwork lifting system
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN204456428U (en) A kind of entirety being installed on composite wallboard is waftd window
CN211597707U (en) A design built-up plate for expansion joint department shear force wall
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN202509764U (en) Template bracing structure for constructional column
CN101886470B (en) Construction method of exposed concrete ribbed beams
CN209854976U (en) Assembled heat preservation brickwork wall
CN204850078U (en) Short wall structure of leading of basement outer wall
CN103056957A (en) Reinforced concrete precast column vertical type prefabrication method
CN109914476A (en) Construction process of cast-in-place urban comprehensive pipe gallery
CN206267520U (en) A kind of self-supporting post-cast strip is poured with hanging mould
CN204510688U (en) A kind of temporary fixing structure of precast wall panel
CN208686067U (en) Plate sizing arc mould drops in toilet
CN209244257U (en) A kind of removable superstructure formwork
CN207392583U (en) A kind of 3D printing wall having across structure
CN109235709B (en) Full cast-in-place outer wall structure of building
CN207525964U (en) A kind of prefabricated composite wallboard pitched roof system
CN112609979A (en) Wall connecting piece erecting method for connecting ultrahigh external frame of external wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant