WO2023005126A1 - 钢箱梁提运架***及其施工方法 - Google Patents

钢箱梁提运架***及其施工方法 Download PDF

Info

Publication number
WO2023005126A1
WO2023005126A1 PCT/CN2021/140989 CN2021140989W WO2023005126A1 WO 2023005126 A1 WO2023005126 A1 WO 2023005126A1 CN 2021140989 W CN2021140989 W CN 2021140989W WO 2023005126 A1 WO2023005126 A1 WO 2023005126A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel box
box girder
track
pier
transporting
Prior art date
Application number
PCT/CN2021/140989
Other languages
English (en)
French (fr)
Inventor
赵立财
Original Assignee
中铁十九局集团第五工程有限公司
中铁十九局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁十九局集团第五工程有限公司, 中铁十九局集团有限公司 filed Critical 中铁十九局集团第五工程有限公司
Publication of WO2023005126A1 publication Critical patent/WO2023005126A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Definitions

  • the present disclosure relates to the technical field of beam transport and erection, in particular to a steel box girder lifting and transporting system and a construction method thereof.
  • the technical problem to be solved in the present disclosure is to solve the existing problem that the girder slab cannot be transported to the vicinity of the bridge pier for subsequent lifting of the steel box girder transported below the bridge pier for beam erection above the steep slope on the mountain side.
  • an embodiment of the present disclosure provides a steel box girder lifting frame system, including a beam transporting track, a traction mechanism, a floating suspension mechanism and a suspension beam mechanism;
  • the beam transport track is set on the slope of the bank side of the water surface, and extends along the direction of the slope to the first bridge pier provided on the bank side;
  • the traction mechanism is located on the beam transport track and arranged close to the first pier;
  • the floating crane mechanism floats on the water surface, and is used to hoist the steel box girder to the end of the beam transportation track away from the first pier, so that the steel box girder is pulled by the traction mechanism Move to the preset hoisting position along the beam transportation track;
  • the hanging beam mechanism is located above the water surface and corresponds to the preset lifting position, and is used for lifting and erecting the steel box girder transported below the hanging beam mechanism.
  • the steel box girder lifting and transporting frame system further includes a beam transporting vehicle, the beam transporting vehicle is arranged on the beam transporting track and connected with the traction mechanism, so that the floating The crane mechanism lifts the steel box girder to the beam transport vehicle, and the traction mechanism pulls the beam transport vehicle to move along the beam transport track to the preset lifting position.
  • the traction mechanism includes two, and the two traction mechanisms are arranged at intervals along the direction perpendicular to the length extension of the beam transportation track, and the two traction mechanisms are respectively connected to the The two sides of the beam transport vehicle are connected.
  • the floating crane mechanism includes a floating seat floating on the water surface and a floating crane assembly arranged on the floating seat, and the floating crane assembly is used to lift the steel box
  • the beam is placed on the beam transporting track and can rotate relative to the floating seat.
  • the suspension beam mechanism includes a suspension beam assembly and a traveling wheel arranged at the bottom of the suspension beam assembly, and the suspension beam assembly is used to lift the steel box girder for erection and can pass through The traveling wheels move to a position corresponding to the preset hoisting position.
  • a construction method including the following steps:
  • the beam transport track on the slope of the bank side of the water surface; wherein, the beam transport track extends along the direction of the slope to the first pier provided on the bank side;
  • the assembled steel box girder is welded and fixed by stay cables to complete the erection.
  • the construction method before the step of laying the beam transport track on the slope on the bank side, the construction method further includes:
  • a support is provided on the side of the first pier away from the water surface, and a beam storage platform is erected between the support and the first pier.
  • the step of hoisting and assembling the steel box girder at the preset hoisting position through the hoisting beam mechanism includes:
  • the steel box girder is hoisted by the lifting beam mechanism and moved along the beam storage platform to a preset erection position for assembling respectively.
  • the method for transporting and erecting girders further includes:
  • the disclosure provides a steel box girder lifting frame system and its construction method.
  • the steel box girder lifting frame system includes a beam transporting track, a traction mechanism, a floating crane mechanism, and a hanging beam mechanism; on the slope, and extend along the direction of the slope to the first bridge pier set on the shore; the traction mechanism is located on the beam transport track and is set close to the first bridge pier; the floating crane mechanism floats on the water surface and is used to move the steel box Hoist to the end of the beam transport track away from the first pier, so that the steel box girder moves to the preset hoisting position along the beam transport track under the traction of the traction mechanism; the hoisting beam mechanism is located above the water surface and corresponds to the preset hoisting position Correspondingly, it is used to lift and erect the steel box girder transported to the lower part of the lifting beam mechanism.
  • the steel box girder lifting and transporting frame system of the present disclosure can set the beam transporting track on the steep slope, so that the steel box girder can be hoisted to the end of the beam transporting track close to the water surface through the floating crane mechanism, and then pass the beam transporting track set on the water surface.
  • the traction mechanism pulls the steel box girder to the preset hoisting position along the beam transporting track, and the beam transporting track extends from the water surface toward the first bridge pier, so that the steel box girder can be transported to the vicinity of the first bridge pier for subsequent erection.
  • FIG. 1 is a schematic structural view of a pier provided on a bank slope according to an embodiment of the present disclosure
  • Fig. 2 is a structural schematic diagram of a beam transporting and erecting device according to an embodiment of the present disclosure
  • Fig. 3 is a schematic diagram of the position and structure of the beam transporting and erecting device when the beam transporting and erecting method of the embodiment of the present disclosure is in process one;
  • FIG. 4 is a schematic diagram of the position and structure of the beam transporting and erecting device when the beam transporting and erecting method of the embodiment of the present disclosure is in the second process;
  • FIG. 5 is a schematic diagram of the position and structure of the beam transporting and erecting device when the beam transporting and erecting method of the embodiment of the present disclosure is in process three;
  • FIG. 6 is a schematic diagram of the position and structure of the beam transporting and erecting device when the beam transporting and erecting method of the embodiment of the present disclosure is in process four;
  • FIG. 7 is a schematic diagram of the position and structure of the beam transporting and erecting device when the beam transporting and erecting method of the embodiment of the present disclosure is in process five;
  • Fig. 8 is a side view of a beam transporting and erecting device according to an embodiment of the present disclosure
  • FIG. 9 is a schematic flow chart of a method for transporting and erecting beams according to an embodiment of the present disclosure.
  • the present disclosure provides a steel box girder lifting frame system.
  • the steel box girder lifting frame system includes a beam transporting track 1, a traction mechanism 2, a floating suspension mechanism 3 and a suspension beam mechanism 4;
  • the beam transport track 1 is arranged on the bank side 51 of the water surface 5, where the bank side 51 can also refer to the beach of a lake or a river, etc.; and the beam transport track 1 extends along the direction of the slope of the bank side 51 to the bank side 51 on the first pier 52;
  • the traction mechanism 2 is located on the beam transport track 1 and is set close to the first bridge pier 52;
  • the floating crane mechanism 3 floats on the water surface 5, and is used to hoist the steel box girder 6 to the beam transport track 1
  • the hoisting beam mechanism 4 is located above the water surface 5 and corresponds to the
  • the steel box girder lifting and transporting frame system of the present disclosure can lift the steel box girder 6 to the end of the beam transporting track 1 close to the water surface 5 by setting the beam transporting track 1 on the shore side 51 of the water surface 5 through the floating crane mechanism 3 Finally, the steel box girder 6 is pulled to the preset hoisting position along the beam transporting track 1 through the traction mechanism 2 provided on the beam transporting track 1, and the end of the beam transporting track 1 away from the water surface 5 is provided with a
  • the block 11 that blocks, the bottom of the beam transporting track 11 has a concrete foundation 12 for supporting the beam transporting track 1; and the beam transporting track extends from the water surface 5 towards the first pier 52, so that the steel box girder 6 can be Transport to the first pier 52 to facilitate subsequent erection between the 0# pier (ie the second pier 53 ) and the 1# pier (ie the first pier 52 ) above the steep slope 8 on the mountain side.
  • the beam transport track 1 is arranged on the bank side 51 of the water surface 5 , and extends along the slope of the bank side 51 to the first bridge pier 52 provided on the bank side 51 . Since the ships transporting the steel box girder 6 may not be able to approach the first bridge pier 52 placed on the slope of the bank during the dry season or the wet season, the steel box girder 6 needs to be transported by the beam transport track 1 at this time. Transport to the first pier 52 or near the first pier 52 for subsequent erection operations.
  • the beam transporting track 1 is set to extend along the bank side 51 to the first pier 52, so that the beam transporting ship can approach the side of the beam transporting track 1 away from the first pier 52 to place the steel box girder 6 on
  • it is transported along the beam transport track 1 to any preset hoisting position at the first pier 52 or near the first bridge pier 52, where the preset hoisting position refers to its position above the water surface 5
  • the preset erection position for example, the steel box girder 6 needs to be erected at a certain position, at this time, a hanging beam mechanism 4 can be set near a certain position, so that the steel box girder 6 directly below a certain position can be hoisted for erection .
  • the traction mechanism 2 is located on the beam transport track 1 and is set close to the first pier 52, so that the floating crane mechanism 3 lifts the steel box girder 6 to the end of the beam transport track 1 close to the water surface 5, so that the steel box Under the traction of the traction mechanism 2, the beam 6 moves along the beam transportation track 1 to a preset hoisting position for subsequent erection.
  • a cross support 73 is arranged above the support 7 , a longitudinal beam 74 is arranged on the cross support 73 , and a moving track 75 is formed on the longitudinal beam 74 for the movement of the suspension beam mechanism 4 .
  • the erection bridge among the present embodiment is with 0# bridge pier (being the second bridge pier 53) to 1# bridge pier (being the first bridge pier 52), the steel between 1# bridge pier to 2# bridge pier
  • the erection of the box girder is taken as an example for specific introduction: as shown in Figure 1, the 0# bridge pier to the 1# bridge pier are located on the steep slope 8 of the slope of the bank side 51, and the 1# bridge pier to the 2# bridge pier are located in the beach area.
  • the steel box girder 6 can be transported by using the slope-shaped beam transport track 1, and then the steel box girder 6 can be hoisted by the suspension beam mechanism 4 provided on the bridge deck for erection.
  • the beam transport track 1 adopts two 2m-wide strips of concrete to expand the foundation, and a double track and a wedge-shaped beam transport vehicle are set above the strip foundation as the beam transport vehicle 21.
  • the beam transport vehicle 21 can be pulled by the traction mechanism 2 to move Beam track 1 moves.
  • the length of the beam transport vehicle 21 should be greater than the length of the steel box girder 6, and the wedge angle of the wedge-shaped beam transport vehicle 21 is the same as the maximum gradient of the beam transport track 1.
  • a Anti-slip stoppers to prevent slipping during ascents.
  • the traction mechanism 2 can specifically be a winch 22, and the winch 22 includes two, and the two winches 22 are arranged at intervals along the extending direction perpendicular to the length of the beam transport rail 1, and the two winches 22 are respectively connected to the transporting beam track 1. Both sides of the beam vehicle 21 are connected and the strokes of the two winches 22 are synchronized, so that both sides of the beam transport vehicle 21 can move in a balanced manner under the joint traction of the two winches 22 to prevent one-sided rollover.
  • the winch 22 For the model selection of the winch 22, it can be calculated based on the heaviest steel box girder 6 on the steepest point on the beam transport track 1 with the static friction force starting, and the calculation traction force will retain a surplus coefficient of more than three times, the winch 22
  • the selection of wire rope and walking wheel set should meet the requirements of corresponding hoisting specifications.
  • the hoist 22 is fixed by driving in I-steel anchors. The anchors are excavated around the hoist 22, and a three-meter-long I-20 section steel is each driven in and concrete is poured.
  • the anchoring safety factor calculated by each winch 22 according to the characteristics of the bottom layer is greater than 5.
  • the suspension beam mechanism 4 includes a suspension beam assembly 41 and a traveling wheel 42 disposed at the bottom of the suspension beam assembly 41 , and the suspension beam assembly 41 may include a suspension beam truss 41 and a hanger 412 .
  • the hanging beam assembly 41 is used to lift the steel box girder 6 for erection and can be moved to a position corresponding to the preset lifting position by the traveling wheels 42, so that the hanging beam assembly 41 can lift the steel box girder 6 higher than 1
  • the steel box girder 6 is placed across the top of the 1# pier through the luffing mechanism of the suspension beam assembly 41, placed on the beam storage platform 71 between the 0# pier and the 1# pier, and then placed by sliding in the default position.
  • the floating crane mechanism 3 includes a floating seat 32 floating on the water surface, a floating crane assembly 31 and a counterweight device 33 arranged on the floating seat 32, and the floating crane assembly 31 includes a floating crane truss 311 and a hook 312 , the floating crane component 31 is used to lift the steel box girder 6 onto the beam transporting track 1 and can rotate relative to the floating seat 32, so that the floating crane component 31 can lift the steel box girder 6 and then rotate to the top of the beam transporting track 1
  • the beam mechanism 4 lifts the steel box girder 6 and crosses the top of the 1# pier and places it on the beam storage platform 71 between the 0# pier and the 1# pier, and then erects the stored steel box girder 6 in order to complete the
  • the present disclosure also provides a method for transporting and erecting beams, including the following steps:
  • the minimum thickness of the foundation concrete of the beam transport track is not less than 2m, according to the slope of the water level fluctuation zone of the water surface (that is, the slope of the bank side) Sets the slope of the beam track.
  • the water level recedes After the water level recedes, first measure the elevation of the river beach on the bank, and use the principle of low burial and high excavation to select a reasonable comprehensive slope, and the slope change points should not be too many.
  • the bearing capacity of the foundation shall be measured on site, and the minimum bearing capacity shall not be less than 150Kpa.
  • the bearing capacity is too small, it can be constructed by replacing fill, squeezing silt or driving into pine piles.
  • the elevation of the vertical formwork is fixed after passing the strategic lofting test, and the rail steel plate is pre-embedded according to the lofting elevation. Secure broken track ends.
  • the stakeout is carried out by measurement, and the center line of the track is released at intervals of 5m in the same cross section, and the intensive stakeout is carried out at the cross section of the slope change point.
  • the beam transport and erection method also includes: setting a support on the side of the bridge pier away from the water surface, and erecting a beam storage platform between the support and the bridge pier for storing The steel box girder lifted by the suspension beam mechanism.
  • the step of hoisting the steel box girder at the preset hoisting position above the bridge pier through the hoisting beam mechanism and erecting it includes: hoisting a plurality of steel box girders sequentially onto the beam storage platform above the bridge pier; The beam mechanism lifts the steel box girder and moves along the beam storage platform to the preset erection position for erection respectively.
  • the method of transporting the beam and erecting the girder also includes: erecting the steel box girder and other adjacent steel box girders steel box girder connection.
  • the beam transporting and erecting method further includes: fixing the steel box girder through stay cables.
  • Process 1 As shown in Figure 3 and Figure 4, the beam transport track and the bracket on the left side of the 1# pier are erected first, and then the steel box girder numbered I-numbered L is hoisted to the transport beam by using a floating crane mechanism On the vehicle, the girder truck is pulled by the traction mechanism and transported to the right below the suspension beam mechanism on the bridge deck. The suspension beam mechanism slowly lifts the steel box girders, and then erects the steel box girders in sequence and connects them together and passes The stay cable is fixed.
  • Process 2 As shown in Figure 5, the floating crane mechanism is used to hoist the steel box girders numbered V-O to the beam transporting vehicle in sequence, and the beam transporting vehicle is transported to the top of the beam transporting track under the traction of the traction mechanism , that is, at the 1# pier. At this time, the suspension beam mechanism on the bridge deck lifts the steel box girder numbered V-numbered O to the top of the 1# pier, and moves it on the bracket to be erected.
  • Process 3 As shown in Figure 6, the steel box girder numbered N is hoisted by the suspension beam mechanism on the bridge deck to the top of the 1# pier, and pre-deflection is carried out.
  • the hanging beam mechanism has a luffing mechanism, which can hoist the steel box girder numbered M for erection, and then pull the steel box girder numbered N for closing construction.
  • Process five As shown in Figure 7, the suspension beam mechanism of the bridge deck is followed by installation and construction, and the closing construction is carried out.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种钢箱梁提运架***及其施工方法。该钢箱梁提运架***包括运梁轨道(1)、牵引机构(2)、浮吊机构(3)以及吊梁机构(4);运梁轨道(1)设于岸边的坡面上,且沿坡面的方向延伸至岸边上设置的第一桥墩(52)处;牵引机构(2)位于运梁轨道(1)上且靠近第一桥墩(52)设置;浮吊机构(3)将钢箱梁(6)吊送至运梁轨道(1)上;吊梁机构(4)位于水面上方且与预设吊起位置相对应。该钢箱梁提运架***通过岸侧的坡面上设置运梁轨道(1),从而通过浮吊机构(3)将钢箱梁(6)吊送至运梁轨道(1)靠近水面的一端后,再通过运梁轨道(1)上设置的牵引机构(2)将钢箱梁(6)沿着运梁轨道(1)牵引至预设吊起位置,且运梁轨道(1)自水面朝向第一桥墩(52)延伸,从而使得钢箱梁(6)能够被运送至桥墩处从而便于后续架设。

Description

钢箱梁提运架***及其施工方法
本公开要求于2021年7月30日提交中国专利局、申请号为202110873109.6、发明名称为“钢箱梁提运架***及其施工方法”的中国专利申请的优先权,其全部内容通过引用结合在本公开中。
技术领域
本公开涉及运梁架梁技术领域,尤其涉及一种钢箱梁提运架***及其施工方法。
背景技术
随着我国基础建设的发展,桥梁建设日新月异,特别是山区的桥梁的建成,不但解决了交通问题,更是带动了沿线经济的飞速发展。
由于山区地形复杂,水面的岸侧的坡面存在陡坡等地形,在对该地形条件下的水面上方进行架桥时,通常会在岸侧的坡面处设立用于架设钢箱梁的桥墩。然而,当水面处于枯水期的时候,运梁船舶无法靠近岸侧处设置的桥墩,因而无法将梁板运输到该桥墩附近以便后续将运输至桥墩下方的钢箱梁吊起以在山侧陡坡上方进行架梁操作。
发明内容
(一)要解决的技术问题
本公开要解决的技术问题是解决现有的无法将梁板运输到该桥墩附近以便后续将运输至桥墩下方的钢箱梁吊起以在山侧陡坡上方进行架梁操作的问题。
(二)技术方案
为了解决上述技术问题,本公开实施例提供了一种钢箱梁提运架***,包括运梁轨道、牵引机构、浮吊机构以及吊梁机构;
所述运梁轨道设于水面的岸侧的坡面上,且沿所述坡面方向延伸至所述岸侧上设置的第一桥墩处;
所述牵引机构位于所述运梁轨道上且靠近所述第一桥墩设置;
所述浮吊机构漂浮在所述水面上,用于将钢箱梁吊送至所述运梁轨道远离所述第一桥墩的一端,以使得所述钢箱梁在所述牵引机构的牵引下沿所述运梁轨道移动至预设吊起位置;
所述吊梁机构位于所述水面上方且与所述预设吊起位置相对应,用于将运送至所述吊梁机构下方的所述钢箱梁吊起并进行架设。
根据本公开的一种实施例,所述钢箱梁提运架***还包括运梁车,所述运梁车设于所述运梁轨道上且与所述牵引机构连接,以使得所述浮吊机构将所述钢箱梁吊送至所述运梁车上,所述牵引机构牵引所述运梁车沿着所述运梁轨道移动至所述预设吊起位置。
根据本公开的一种实施例,所述牵引机构包括两个,两个所述牵引几个沿垂直于所述运梁轨道的长度延伸方向间隔设置,且两个所述牵引机构分别与所述运梁车的两侧连接。
根据本公开的一种实施例,所述浮吊机构包括漂浮在所述水面上的浮座以及设于所述浮座上的浮吊组件,所述浮吊组件用于吊取所述钢箱梁至所述运梁轨道上且可相对于所述浮座旋转。
根据本公开的一种实施例,所述吊梁机构包括吊梁组件以及设于所述吊梁组件底部的行走轮,所述吊梁组件用于吊取所述钢箱梁进行架设且可通过所述行走轮移动至与所述预设吊起位置相对应的位置。
第二方面,还提供一种施工方法,包括如下步骤:
将运梁轨道铺设在水面的岸侧的坡面上;其中,所述运梁轨道沿所述坡面方向延伸至所述岸侧上设置的第一桥墩处;
将钢箱梁通过浮吊机构运送至所述运梁轨道上;
将所述运梁轨道上的所述钢箱梁通过牵引机构牵引至预设吊起位置;
将牵引至所述预设吊起位置处的所述钢箱梁通过吊梁机构吊起并进行拼装;
将拼装好的所述钢箱梁通过斜拉索焊接固定以完成架设。
根据本公开的一种实施例,在所述将运梁轨道铺设在岸侧的坡面上的步骤之前,所述施工方法还包括:
在所述第一桥墩远离所述水面的一侧设置支架,并在所述支架和所述第一桥墩之间架设存梁平台。
根据本公开的一种实施例,所述将所述预设吊起位置处的所述钢箱梁通过所述吊梁机构吊起并进行拼装的步骤包括:
将多个所述钢箱梁依次吊起至所述第一桥墩上方的所述存梁平台上;
通过所述吊梁机构吊起所述钢箱梁并沿所述存梁平台移动至预设架设位置分别进行拼装。
根据本公开的一种实施例,在将运送至所述预设吊起位置处的所述钢箱梁通过吊梁机构吊起进行拼装的步骤之后,所述运梁架梁的方法还包括:
将所述钢箱梁和与所述钢箱梁相邻的其他架设好的钢箱梁连接。
(三)有益效果
本公开实施例提供的上述技术方案与现有技术相比具有如下优点:
本公开提供了一种钢箱梁提运架***及其施工方法,该钢箱梁提运架***包括运梁轨道、牵引机构、浮吊机构以及吊梁机构;运梁轨道设于岸侧的坡面上,且沿坡面的方向延伸至岸侧上设置的第一桥墩处;牵引机构位于运梁轨道上且靠近第一桥墩设置;浮吊机构漂浮在水面上,用于将钢箱梁吊送至运梁轨道远离第一桥墩的一端,以使得钢箱梁在牵引机构的牵引下沿运梁轨道移动至预设吊起位置;吊梁机构位于水面上方且与预设吊起位置相对应,用于将运送至吊梁机构下方的钢箱梁吊起并进行架设。本公开的钢箱梁提运架***,可以通过在陡坡上设置运梁轨道,从而通过浮吊机构将钢箱梁吊送至运梁轨道靠近水面的一端后,再通过运梁轨道上设置的牵引机构将钢箱梁沿着运梁轨道牵引至预设吊起位置,且运梁轨道自水面朝向第一桥墩延伸,从而可以使得钢箱梁能够被运送至第一桥墩附近从而便于后续架设。
应当理解的是,以上的一般描述和后文的细节描述仅是示例性和解释性的,并不能限制本公开。
附图说明
此处的附图被并入说明书中并构成本说明书的一部分,示出了符 合本公开的实施例,并与说明书一起用于解释本公开的原理。
为了更清楚地说明本公开实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,对于本领域普通技术人员而言,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。
图1为本公开实施例的岸侧的坡面设置桥墩的结构示意图;
图2为本公开实施例的运梁架梁装置的结构示意图;
图3为本公开实施例的运梁架梁方法处于流程一时的运梁架梁装置的位置结构示意图;
图4为本公开实施例的运梁架梁方法处于流程二时的运梁架梁装置的位置结构示意图;
图5为本公开实施例的运梁架梁方法处于流程三时的运梁架梁装置的位置结构示意图;
图6为本公开实施例的运梁架梁方法处于流程四时的运梁架梁装置的位置结构示意图;
图7为本公开实施例的运梁架梁方法处于流程五时的运梁架梁装置的位置结构示意图;
图8为本公开实施例的运梁架梁装置的侧视图;
图9为本公开实施例的运梁架梁的方法的方法流程示意图。
其中,1、运梁轨道;11、挡块;12、混凝土基础;2、牵引机构;21、运梁车;22、卷扬机;3、浮吊机构;31、浮吊组件;311、浮吊桁架;312、吊钩;32、浮座;33、配重装置;4、吊梁机构;41、吊梁组件;411、吊梁桁架;412、吊具;42、行走轮;5、水面;51、岸侧;52、第一桥墩;53、第二桥墩;6、钢箱梁;7、支架;71、存梁平台;72、系梁;73、横梁;74、纵梁;75、移动轨道;8、陡坡;9、斜拉索。
具体实施方式
为使本公开实施例的目的、技术方案和优点更加清楚,下面将对 本公开实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本公开的一部分实施例,而不是全部的实施例。基于本公开中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本公开保护的范围。
如图1至图8所示,本公开提供了一种钢箱梁提运架***,钢箱梁提运架***包括运梁轨道1、牵引机构2、浮吊机构3以及吊梁机构4;运梁轨道1设于水面5的岸侧51上,此处的岸侧51也可以指的是湖泊或者江河等的河滩处;且运梁轨道1沿岸侧51的坡面的方向延伸至岸侧51上设置的第一桥墩52处;牵引机构2位于运梁轨道1上且靠近第一桥墩52设置;浮吊机构3漂浮在水面5上,用于将钢箱梁6吊送至运梁轨道1靠近水面5的一端,以使得钢箱梁5在牵引机构2的牵引下沿运梁轨道1移动至预设吊起位置;吊梁机构4位于水面5上方且与预设吊起位置相对应,用于将运送至吊梁机构4下方的钢箱梁6吊起并进行架设。本公开的钢箱梁提运架***,可以通过在水面5的岸侧51上设置运梁轨道1,从而通过浮吊机构3将钢箱梁6吊送至运梁轨道1靠近水面5的一端后,再通过运梁轨道1上设置的牵引机构2将钢箱梁6沿着运梁轨道1牵引至预设吊起位置,运梁轨道1远离水面5的一端设置有用于对钢箱梁6进行阻挡的挡块11,运梁轨道11的底部具有混凝土基础12用于对运梁轨道1进行支撑;且运梁轨道自水面5朝向第一桥墩52延伸,从而可以使得钢箱梁6能够被运送至第一桥墩52处从而便于后续架设在山侧陡坡8的上方的0#桥墩(即第二桥墩53)与1#桥墩(即第一桥墩52)之间。
具体的,如图1所示,运梁轨道1设于水面5的岸侧51上,且沿岸侧51的坡面的方向延伸至岸侧51上设置的第一桥墩52处。由于运输钢箱梁6的船舶在枯水期或者丰水期的时候均可能发生无法靠近岸边的坡面上设置的第一桥墩52处的情况,此时需要通过运梁轨道1将钢箱梁6运输到第一桥墩52处或者第一桥墩52附近以便进行后续架设操作。因此,本实施例中,设置运梁轨道1沿着岸侧51延伸至第一桥墩52处,使得运梁船舶可以靠近运梁轨道1远离第一桥墩52的一侧以将钢箱梁6放置在运梁轨道1上后沿着运梁轨道1运输至第一桥 墩52处或者第一桥墩52附近的任意预设吊起位置,此处的预设吊起位置指的是其在水面5上方的预设架设位置,比如说,钢箱梁6需要被架设在某一位置,此时某一位置处附近可以设置吊梁机构4,从而将某一位置正下方的钢箱梁6吊起进行架设。
如图2所示,牵引机构2位于运梁轨道1上且靠近第一桥墩52设置,使得浮吊机构3将钢箱梁6吊送至运梁轨道1靠近水面5的一端,以使得钢箱梁6在牵引机构2的牵引下沿运梁轨道1移动至预设吊起位置从而进行后续架设。
如图8所示,支架7上方设置有横支撑73,横支撑73上设置有纵梁74,纵梁74上形成有移动轨道75,以供吊梁机构4移动。
如图1至图2所示,本实施例中的架设桥梁以0#桥墩(即第二桥墩53)至1#桥墩(即第一桥墩52),1#桥墩至2#桥墩之间的钢箱梁的架设为例进行具体介绍:如图1所示,0#桥墩至1#桥墩位于岸侧51的坡面的陡坡8上,1#桥墩至2#桥墩位于岸滩区,由于水面蓄水影响,使得水面的施工区域的最低水位为143.3m,最高水位为173.3m,使得即便在丰水期运输船舶也无法靠近1#桥墩。为了使得在最低水位时也能够进行0#桥墩至1#桥墩、1#桥墩至2#桥墩的钢箱梁的吊装施工,又不需要引入超大型浮吊和搭设超长高大支架,本实施例中,可以采用斜坡状的运梁轨道1进行钢箱梁6运输,然后采用桥面设置的吊梁机构4吊起钢箱梁6进行架设。具体的,运梁轨道1采用两个2m宽的条形混凝土扩大基础,条形基础上方设置双轨道及楔形运梁车作为运梁车21,运梁车21通过牵引机构2的牵引可以在运梁轨道上1移动。运梁车21的长度应大于钢箱梁6的长度,并且楔形的运梁车21的楔形角度与运梁轨道1的最大坡度相同,在运梁车21放在运梁轨道1上后设置有防滑落挡块,用于防止上坡过程中滑落。
示例性的,本实施例中,牵引机构2具体可以为卷扬机22,卷扬机22包括两个,两个卷扬机22沿垂直于运梁轨道1的长度延伸方向间隔设置,且两个卷扬机22分别与运梁车21的两侧连接且两个卷扬机22的行程同步,以使得运梁车21的两侧可以在两个卷扬机22的共同牵引作用下平衡地移动,以防止单侧侧翻。对于卷扬机22的型号选 取,具体可以以最重的钢箱梁6在运梁轨道1上的最陡处上以静摩擦力启动为计算依据,计算牵引力要保留三倍以上的富余系数,卷扬机22的钢丝绳和行走轮组的选取要符合相应的吊装规范要求。另外,卷扬机22采用打入工钢锚的方法进行固定,在卷扬机22的四周挖掘锚根,各打入一根三米长的工20型钢并浇筑混凝土。每台卷扬机22根据底层特点计算的锚固安全系数大于5。
如图1、图2所示,0#桥墩至1#桥墩位于山侧陡坡8,需存梁八片(具体参照图1),由于钢箱梁6无法运输至0#桥墩至1#桥墩之间,只能依靠吊梁机构4跨越1#桥墩存放至1#桥墩上方搭设的存梁平台71上。因此,吊梁机构4包括吊梁组件41以及设于吊梁组件41底部的行走轮42,吊梁组件41可以包括吊梁桁架41以及吊具412。吊梁组件41用于吊取钢箱梁6进行架设且可通过行走轮42移动至与预设吊起位置相对应的位置,以使得吊梁组件41可以将钢箱梁6吊起高于1#桥墩的顶部,通过吊梁组件41的变幅机构,将钢箱梁6跨过1#桥墩的顶部,放置在0#桥墩至1#桥墩之间的存梁平台71上,然后通过滑动放置在预设位置。
如图2所示,浮吊机构3包括漂浮在水面上的浮座32以及设于浮座32上的浮吊组件31和配重装置33,浮吊组件31包括浮吊桁架311以及吊钩312,浮吊组件31用于吊取钢箱梁6至运梁轨道1上且可相对于浮座32旋转,进而使得浮吊组件31可以吊起钢箱梁6后转动至运梁轨道1的上方以将钢箱梁6放置在运梁轨道1上的运梁车21上,使得卷扬机22牵引运梁车21沿着运梁轨道1移动至第一桥墩52处,使得第一桥墩52上方的吊梁机构4吊起钢箱梁6并跨过1#桥墩的顶部放置在0#桥墩和1#桥墩之间的存梁平台71上,然后将该存放的钢箱梁6依次架设好完成0#桥墩至1#桥墩的钢箱梁6的架设。此外,1#桥墩的左侧设置有支架7,支架7和第一桥墩52的上方设置存梁平台71,且存量平台71横跨于0#桥墩和1#桥墩之间。
参照图1所示,0#桥墩至1#桥墩之间需八片钢箱梁6,即如图1所示的编号为O至编号为V的钢箱梁6,因此可以重复上述过程八次以吊起存放八片钢箱梁以便架设在0#桥墩和1#桥墩之间架设钢箱梁6, 架设好后可以通过斜拉索9固定。
如图9所示,本公开还提供一种运梁架梁方法,包括如下步骤:
S101:将运梁轨道铺设在水面的岸侧的坡面上;其中,运梁轨道沿岸侧的延伸方向延伸至岸侧上设置的第一桥墩处;
S102:将钢箱梁通过浮吊机构运送至运梁轨道上;
S103:将运梁轨道上的钢箱梁通过牵引机构牵引至预设吊起位置;
S104:将牵引至预设吊起位置处的钢箱梁通过吊梁机构吊起并进行拼装;
S105:将拼装好的钢箱梁通过斜拉索焊接固定以完成架设。
具体的,对于运梁轨道的施工,为了减少工程量,在保证运梁轨道的基础混凝土的最小厚度不小于2m的前提下,依照水面的水位涨落区的坡度(也就是岸侧的坡度)设置运梁轨道的坡度。水位退落后,先测量岸侧河滩的高程,采用低埋高挖的原则选择合理的综合坡度,变坡点不宜过多。运梁轨道的地基开挖后,要现场实测地基承载力,最小承载力要求不低于150Kpa。如果承载力过小,可以采用换填、挤淤或者打入松木桩的方法施工。运梁轨道在浇筑前,立模标高由策略放样检测合格后固定,并根据放样标高拉线预埋轨道钢板,在边坡点处两侧不同坡度的基础内预埋一块轨道固定预埋板,以固定断开的轨道端部。运梁轨道安装前由测量放样,在同一横截面内每间隔5m放出轨道中心线,并在变坡点横断面进行加密放样。运梁轨道安装时不仅要保证单根轨道的顺直,而且要保证四根轨道两两间距偏差不超过5mm,高程差小于3mm。
进一步的,在将运梁轨道铺设在岸侧上的步骤之前,运梁架梁方法还包括:在桥墩远离水面的一侧设置支架,并在支架和桥墩之间架设存梁平台,用于存放吊梁机构吊起的钢箱梁。
进一步的,将预设吊起位置处的钢箱梁通过吊梁机构吊起至桥墩上方并进行架设的步骤包括:将多个钢箱梁依次吊起至桥墩上方的存梁平台上;通过吊梁机构吊起钢箱梁并沿存梁平台移动至预设架设位置分别进行架设。
进一步的,在将运送至预设吊起位置处的钢箱梁通过吊梁机构吊 起进行架设的步骤之后,运梁架梁方法还包括:将钢箱梁和与钢箱梁相邻的其他架设好的钢箱梁连接。
进一步的,在将钢箱梁和与钢箱梁相邻的其他架设好的钢箱梁连接的步骤之后,运梁架梁方法还包括:将钢箱梁通过斜拉索固定。
如图3至图7所示,1#桥墩(即上述实施例所指的第一桥墩52)至2#桥墩之间需要架设9片钢箱梁,即如图1中所示的编号D至编号N的钢箱梁。具体的整个钢箱梁(编号为H-编号为V的共计15片的钢箱梁)的架设过程为:
流程一:如图3、图4所示,先将运梁轨道和1#桥墩左侧的支架搭设完成,然后采用浮吊机构将编号为I-编号为L的钢箱梁吊起至运梁车上,运梁车在牵引机构的牵引下运至桥面的吊梁机构的正下方,吊梁机构将钢箱梁缓缓吊起,然后再将钢箱梁依次架设好连接在一起并通过斜拉索固定。
流程二:如图5所示,采用浮吊机构依次将编号为V-编号为O的钢箱梁吊起至运梁车上,运梁车在牵引机构的牵引下运至运梁轨道的顶端,即1#桥墩处,此时桥面上的吊梁机构依次吊装编号为V-编号为O的钢箱梁至1#桥墩的顶部,并在支架上移动就位后进行架设。
流程三:如图6所示,桥面上的吊梁机构吊装编号为N的钢箱梁至1#桥墩的顶部,并进行预偏。
流程四:如图7所示,吊梁机构具有变幅机构,可以吊装编号为M的钢箱梁进行架设,然后牵引编号为N的钢箱梁进行合拢施工。
流程五:如图7所示,桥面的吊梁机构进行后续的安装施工,并且进行合拢施工。
需要说明的是,在本文中,诸如“第一”和“第二”等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有 更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。
以上所述仅是本公开的具体实施方式,使本领域技术人员能够理解或实现本公开。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本公开的精神或范围的情况下,在其它实施例中实现。因此,本公开将不会被限制于本文所述的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。

Claims (9)

  1. 一种钢箱梁提运架***,其特征在于,包括运梁轨道(1)、牵引机构(2)、浮吊机构(3)以及吊梁机构(4);
    所述运梁轨道(1)设于水面(5)岸侧(51)的坡面上,且沿所述坡面的倾斜方向延伸至所述岸侧(51)上设置的第一桥墩(52)处;
    所述牵引机构(2)位于所述运梁轨道(1)上且靠近所述第一桥墩(52)设置;
    所述浮吊机构(3)漂浮在所述水面(5)上,用于将钢箱梁(6)吊送至所述运梁轨道(1)远离所述第一桥墩(52)的一端,以使得所述钢箱梁(6)在所述牵引机构(2)的牵引下沿所述运梁轨道(1)移动至预设吊起位置;
    所述吊梁机构(4)位于所述水面(5)上方且与所述预设吊起位置相对应,用于将运送至所述吊梁机构(4)下方的所述钢箱梁(6)吊起并进行架设。
  2. 根据权利要求1所述的钢箱梁提运架***,其特征在于,所述钢箱梁提运架***还包括运梁车(21),所述运梁车(21)设于所述运梁轨道(1)上且与所述牵引机构(2)连接,以使得所述浮吊机构(3)将所述钢箱梁(6)吊送至所述运梁车(21)上,所述牵引机构(2)牵引所述运梁车(21)沿着所述运梁轨道(1)移动至所述预设吊起位置。
  3. 根据权利要求2所述的钢箱梁提运架***,其特征在于,所述牵引机构(2)包括两个,两个所述牵引机构(2)沿垂直于所述运梁轨道(1)的长度延伸方向间隔设置,且两个所述牵引机构(2)分别与所述运梁车(21)的两侧连接。
  4. 根据权利要求1所述的钢箱梁提运架***,其特征在于,所述浮吊机构(3)包括漂浮在所述水面(5)上的浮座(31)以及设于所述浮座(32)上的浮吊组件(31),所述浮吊组件(31)用于吊取所述钢箱梁(6)至所述运梁轨道(1)上且可相对于所述浮座(32)旋转。
  5. 根据权利要求1所述的钢箱梁提运架***,其特征在于,所述 吊梁机构(4)包括吊梁组件(41)以及设于所述吊梁组件(41)底部的行走轮(42),所述吊梁组件(41)用于吊取所述钢箱梁(6)进行架设且可通过所述行走轮(42)移动至与所述预设吊起位置相对应的位置。
  6. 一种利用如权利要求1至5任一项所述的钢箱梁提运架***进行钢箱梁的提运架的施工方法,其特征在于,包括如下步骤:
    将运梁轨道铺设在水面的岸侧的坡面上;其中,所述运梁轨道沿所述坡面的方向延伸至所述岸侧上设置的第一桥墩处;
    将钢箱梁通过浮吊机构运送至所述运梁轨道上;
    将所述运梁轨道上的所述钢箱梁通过牵引机构牵引至预设吊起位置;
    将牵引至所述预设吊起位置处的所述钢箱梁通过吊梁机构吊起并进行拼装;
    将拼装好的所述钢箱梁通过斜拉索焊接固定以完成架设。
  7. 根据权利要求6所述的施工方法,其特征在于,在所述将运梁轨道铺设在岸侧的坡面上的步骤之前,所述方法还包括:
    在所述第一桥墩远离所述水面的一侧设置支架,并在所述支架和所述第一桥墩之间架设存梁平台。
  8. 根据权利要求7所述的施工方法,其特征在于,所述将所述预设吊起位置处的所述钢箱梁通过所述吊梁机构吊起并进行拼装的步骤包括:
    将多个所述钢箱梁依次吊起至所述第一桥墩上方的所述存梁平台上;
    通过所述吊梁机构吊起所述钢箱梁并沿所述存梁平台移动至预设架设位置分别进行架拼装。
  9. 根据权利要求6所述的施工方法,其特征在于,在将运送至所述预设吊起位置处的所述钢箱梁通过吊梁机构吊起进行拼装的步骤之后,所述方法还包括:
    将所述钢箱梁和与所述钢箱梁相邻的其他架设好的钢箱梁连接。
PCT/CN2021/140989 2021-07-30 2021-12-23 钢箱梁提运架***及其施工方法 WO2023005126A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110873109.6A CN113585080A (zh) 2021-07-30 2021-07-30 钢箱梁提运架***及其施工方法
CN202110873109.6 2021-07-30

Publications (1)

Publication Number Publication Date
WO2023005126A1 true WO2023005126A1 (zh) 2023-02-02

Family

ID=78252759

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/140989 WO2023005126A1 (zh) 2021-07-30 2021-12-23 钢箱梁提运架***及其施工方法

Country Status (2)

Country Link
CN (1) CN113585080A (zh)
WO (1) WO2023005126A1 (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113585080A (zh) * 2021-07-30 2021-11-02 中铁十九局集团第五工程有限公司 钢箱梁提运架***及其施工方法
CN115123936B (zh) * 2022-06-22 2023-12-08 中铁二十四局集团桥梁建设有限公司 一种单臂架桥机及其使用方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102127899A (zh) * 2010-12-30 2011-07-20 中铁大桥局集团第二工程有限公司 大吨位钢箱梁在陆域及浅滩区的提升滑移***及施工方法
WO2013002641A1 (en) * 2011-06-30 2013-01-03 Cargotec Netherlands B.V. Ship to shore crane installation with main support girder
CN106400693A (zh) * 2016-11-13 2017-02-15 中交路桥建设有限公司 一种斜坡道钢箱梁运梁车及运梁方法
CN113585080A (zh) * 2021-07-30 2021-11-02 中铁十九局集团第五工程有限公司 钢箱梁提运架***及其施工方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012854B (zh) * 2016-06-22 2017-07-28 青岛蓝天创先科技服务有限公司 预制装配式高架桥桥板的运输设备
KR101872265B1 (ko) * 2018-02-01 2018-06-28 주식회사 에코메가리프팅 교량의 해체방법
CN111236085A (zh) * 2020-03-16 2020-06-05 浙江省交通规划设计研究院有限公司 山区节段梁运输装置以及山区预制节段梁的运输方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102127899A (zh) * 2010-12-30 2011-07-20 中铁大桥局集团第二工程有限公司 大吨位钢箱梁在陆域及浅滩区的提升滑移***及施工方法
WO2013002641A1 (en) * 2011-06-30 2013-01-03 Cargotec Netherlands B.V. Ship to shore crane installation with main support girder
CN106400693A (zh) * 2016-11-13 2017-02-15 中交路桥建设有限公司 一种斜坡道钢箱梁运梁车及运梁方法
CN113585080A (zh) * 2021-07-30 2021-11-02 中铁十九局集团第五工程有限公司 钢箱梁提运架***及其施工方法

Also Published As

Publication number Publication date
CN113585080A (zh) 2021-11-02

Similar Documents

Publication Publication Date Title
WO2023005126A1 (zh) 钢箱梁提运架***及其施工方法
CN110042769B (zh) 一种组合梁斜拉桥辅助跨全悬臂拼装施工方法
CN105565176B (zh) 一种单塔不对称缆索吊机
CN110552296B (zh) 斜拉桥拆除施工方法
CN208167539U (zh) 一种叠合梁斜拉桥主梁吊装施工缆索吊机***
CN110747752A (zh) 一种用于大跨距钢结构拱桥浮拖法安装工艺
CN111172882A (zh) 一种桥梁主梁悬臂拼装的梁段运输方法
CN110886187B (zh) 缆索吊***安装体系及其施工方法
CN102367650A (zh) 一种钢管拱桥的施工方法
WO2023016573A1 (zh) 一种斜拉桥钢混主梁的施工方法
CN111350135B (zh) 大跨度钢桁梁浮拖架设施工方法
CN112160246B (zh) 组合梁安装方法
WO2022233226A1 (zh) 用于斜拉桥主梁安装的三跨缆索吊机及其施工方法
CN102535344A (zh) 一种用于沟壑地区高墩桥梁梁体混凝土运输的方法
CN216891994U (zh) 用于斜拉桥主梁安装的三跨缆索吊机
CN110616638A (zh) 悬索桥浅滩区钢箱梁无支架吊装方法
CN217325062U (zh) 斜拉桥索塔大吨位钢横梁的拼装滑移支架
CN113802461B (zh) 一种钢箱梁架设方法
CN115961549A (zh) 一种斜拉桥大吨位整节段钢梁后喂梁式架设施工方法
CN115387207A (zh) 一种浅覆盖层钢混组合桩桥墩结构及施工方法
CN212895958U (zh) 下挂移动式桥面吊机
CN112520578A (zh) 一种大跨度超重钢桁架梁浮船驳运的吊装施工方法
CN211310620U (zh) 交通应急保障缆索输送装置
CN110510526B (zh) 一种用于交通应急保障的缆索输送机
CN111519538A (zh) 一种大跨度连续钢桁梁逐孔架设方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21951698

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE