WO2019116451A1 - ショベル - Google Patents

ショベル Download PDF

Info

Publication number
WO2019116451A1
WO2019116451A1 PCT/JP2017/044610 JP2017044610W WO2019116451A1 WO 2019116451 A1 WO2019116451 A1 WO 2019116451A1 JP 2017044610 W JP2017044610 W JP 2017044610W WO 2019116451 A1 WO2019116451 A1 WO 2019116451A1
Authority
WO
WIPO (PCT)
Prior art keywords
digging
excavation
load
boom
cylinder
Prior art date
Application number
PCT/JP2017/044610
Other languages
English (en)
French (fr)
Inventor
春男 呉
Original Assignee
住友重機械工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 住友重機械工業株式会社 filed Critical 住友重機械工業株式会社
Priority to PCT/JP2017/044610 priority Critical patent/WO2019116451A1/ja
Priority to CN201780097670.1A priority patent/CN111511993B/zh
Priority to KR1020207016612A priority patent/KR102460502B1/ko
Priority to EP17934527.7A priority patent/EP3725959B1/en
Publication of WO2019116451A1 publication Critical patent/WO2019116451A1/ja
Priority to US16/896,396 priority patent/US11572676B2/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/24Safety devices, e.g. for preventing overload
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/30Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets with a dipper-arm pivoted on a cantilever beam, i.e. boom
    • E02F3/32Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets with a dipper-arm pivoted on a cantilever beam, i.e. boom working downwardly and towards the machine, e.g. with backhoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/2029Controlling the position of implements in function of its load, e.g. modifying the attitude of implements in accordance to vehicle speed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/2033Limiting the movement of frames or implements, e.g. to avoid collision between implements and the cabin
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/264Sensors and their calibration for indicating the position of the work tool
    • E02F9/265Sensors and their calibration for indicating the position of the work tool with follow-up actions (e.g. control signals sent to actuate the work tool)
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2203Arrangements for controlling the attitude of actuators, e.g. speed, floating function
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/226Safety arrangements, e.g. hydraulic driven fans, preventing cavitation, leakage, overheating

Definitions

  • the present disclosure relates to a shovel capable of detecting the posture of a digging attachment.
  • the digging reaction force may be increased.
  • the shovel of Patent Document 1 raises the boom regardless of whether deep excavation or normal excavation is performed if the calculated excavating reaction force is larger than a preset upper limit value. Therefore, the digging reaction force is increased in an attempt to reduce the digging reaction force at the time of the deep digging, and the digging reaction force may be increased, so that the digging can not be continued and the working efficiency may be reduced.
  • a shovel includes a lower traveling body, an upper revolving superstructure mounted on the lower traveling body, an excavating attachment attached to the upper revolving superstructure, and an attitude detecting device for detecting an attitude of the excavating attachment
  • a shovel having an unstable state detection device for detecting information on the unstable state of the upper swing body due to a digging load, and a control device for correcting the attitude of the digging attachment, the control device comprising: When it is determined that the digging load during deep digging is larger than a predetermined value based on the outputs of the posture detection device and the unstable state detecting device, the arm or the bucket configuring the digging attachment is opened.
  • a shovel is provided which can more appropriately control the drilling attachment during deep excavation.
  • FIG. 1 is a side view of a shovel according to an embodiment of the present invention.
  • An upper swing body 3 is rotatably mounted on the lower traveling body 1 of the shovel shown in FIG. 1 via a turning mechanism 2.
  • a boom 4 is attached to the upper swing body 3.
  • An arm 5 is attached to the tip of the boom 4, and a bucket 6 is attached to the tip of the arm 5.
  • the boom 4 as a working element, the arm 5 and the bucket 6 constitute a digging attachment which is an example of an attachment.
  • the boom 4, the arm 5 and the bucket 6 are hydraulically driven by the boom cylinder 7, the arm cylinder 8 and the bucket cylinder 9 respectively.
  • a cabin 10 is provided in the upper revolving superstructure 3 and a power source such as an engine 11 is mounted.
  • a posture detection device M1 is attached to the excavation attachment.
  • the posture detection device M1 is a device that detects the posture of the digging attachment.
  • the posture detection device M1 includes a boom angle sensor M1a, an arm angle sensor M1b, and a bucket angle sensor M1c.
  • the boom angle sensor M1a is a sensor that acquires a boom angle, and for example, a rotation angle sensor that detects a rotation angle of a boom foot pin, a stroke sensor that detects a stroke amount of the boom cylinder 7, and an inclination angle of the boom 4 Includes tilt (acceleration) sensor and so on.
  • the boom angle sensor M1a may be an inertial measurement device configured by a combination of a gyro sensor and an acceleration sensor. The same applies to the arm angle sensor M1b and the bucket angle sensor M1c.
  • FIG. 2 is a side view of the shovel showing various physical quantities related to the digging attachment.
  • the boom angle sensor M1a acquires, for example, a boom angle ( ⁇ 1).
  • the boom angle ( ⁇ 1) is an angle with respect to a horizontal line of a line segment P1-P2 connecting the boom foot pin position P1 and the arm connecting pin position P2 in the XZ plane.
  • the arm angle sensor M1b acquires, for example, an arm angle ( ⁇ 2).
  • the arm angle ( ⁇ 2) is an angle with respect to a horizontal line of a line segment P2-P3 connecting the arm connecting pin position P2 and the bucket connecting pin position P3 in the XZ plane.
  • the bucket angle sensor M1c acquires, for example, a bucket angle ( ⁇ 3).
  • the bucket angle ( ⁇ 3) is an angle with respect to a horizontal line of a line segment P3-P4 connecting the bucket connecting pin position P3 and the bucket toe position P4 in the XZ plane.
  • the basic system of the shovel mainly includes an engine 11, a main pump 14, a pilot pump 15, a control valve 17, an operating device 26, a controller 30, an engine control device 74, and the like.
  • the engine 11 is a driving source of a shovel, and is, for example, a diesel engine that operates to maintain a predetermined rotational speed.
  • the output shaft of the engine 11 is connected to the input shaft of the main pump 14 and the pilot pump 15.
  • the main pump 14 is a hydraulic pump that supplies hydraulic fluid to the control valve 17 via a hydraulic fluid line 16, and is, for example, a swash plate type variable displacement hydraulic pump.
  • the stroke length of the piston for determining the displacement volume is changed according to the change of the swash plate tilt angle, and the discharge flow rate per one rotation is changed.
  • the swash plate tilt angle is controlled by the regulator 14a.
  • the regulator 14 a changes the swash plate tilt angle according to the change of the control current from the controller 30. For example, the regulator 14a increases the swash plate tilting angle according to the increase of the control current to increase the discharge flow rate of the main pump 14.
  • the regulator 14a reduces the discharge flow rate of the main pump 14 by reducing the inclination angle of the swash plate in accordance with the decrease of the control current.
  • the discharge pressure sensor 14 b detects the discharge pressure of the main pump 14.
  • the oil temperature sensor 14 c detects the temperature of the hydraulic oil drawn by the main pump 14.
  • the pilot pump 15 is a hydraulic pump for supplying hydraulic fluid to various hydraulic control devices such as the operating device 26 via the pilot line 25 and is, for example, a fixed displacement hydraulic pump.
  • the control valve 17 is a set of flow control valves that control the flow of hydraulic fluid related to the hydraulic actuator.
  • the control valve 17 selectively supplies hydraulic oil received from the main pump 14 through the hydraulic oil line 16 to one or more hydraulic actuators in response to a change in pilot pressure corresponding to the operating direction and the operating amount of the operating device 26.
  • the hydraulic actuator includes, for example, a boom cylinder 7, an arm cylinder 8, a bucket cylinder 9, a left traveling hydraulic motor 1A, a right traveling hydraulic motor 1B, a turning hydraulic motor 2A, and the like.
  • the operating device 26 is a device used by the operator for operating the hydraulic actuator, and includes a lever 26A, a lever 26B, a pedal 26C, and the like.
  • the operating device 26 receives the supply of hydraulic fluid from the pilot pump 15 via the pilot line 25 to generate a pilot pressure. Then, the pilot pressure is applied to the pilot port of the corresponding flow control valve through the pilot line 25a. The pilot pressure changes in accordance with the operating direction and the operating amount of the operating device 26.
  • the operating device 26 may be operated remotely. In this case, the controller device 26 generates a pilot pressure in accordance with the information on the operation direction and the amount of operation received via wireless communication.
  • the controller 30 is a control device for controlling a shovel.
  • the controller 30 is configured by a computer provided with a CPU, a RAM, a ROM, and the like.
  • the CPU of the controller 30 reads out programs corresponding to various functions from the ROM, loads them into the RAM, and executes them, thereby realizing functions corresponding to the respective programs.
  • the controller 30 realizes a function of controlling the discharge flow rate of the main pump 14. Specifically, the controller 30 changes the control current to the regulator 14a according to the negative control pressure of the negative control valve, and controls the discharge flow rate of the main pump 14 via the regulator 14a.
  • the engine control device 74 is a device that controls the engine 11.
  • the engine control device 74 controls, for example, the fuel injection amount and the like so that the engine rotational speed set via the input device is realized.
  • the operation mode switching dial 75 is a dial for switching the operation mode of the shovel, and is provided in the cabin 10. In this embodiment, the operator can switch between the M (manual) mode and the SA (semi-automatic) mode.
  • the controller 30 switches the operating mode of the shovel, for example, according to the output of the operating mode switching dial 75.
  • FIG. 3 shows a state in which the SA mode is selected by the operation mode switching dial 75.
  • the M mode is a mode in which the shovel is operated according to the content of the operation input to the operation device 26 by the operator.
  • the mode is a mode in which the boom cylinder 7, the arm cylinder 8, the bucket cylinder 9, and the like are operated according to the content of the operation input to the operation device 26 by the operator.
  • the SA mode is a mode in which the shovel is automatically operated regardless of the content of the operation input to the operation device 26 when a predetermined condition is satisfied. For example, when a predetermined condition is satisfied, the boom cylinder 7, the arm cylinder 8, the bucket cylinder 9, etc. are automatically operated regardless of the content of the operation input to the operation device 26.
  • the operation mode switching dial 75 may be configured to switch between three or more operation modes.
  • the display device 40 is a device that displays various information, and is disposed in the vicinity of the driver's seat in the cabin 10.
  • the display device 40 has an image display unit 41 and an input unit 42.
  • An operator can input information and commands to the controller 30 using the input unit 42.
  • the operating condition and control information of the shovel can be grasped by looking at the image display unit 41.
  • the display device 40 is connected to the controller 30 via a communication network such as CAN. However, the display device 40 may be connected to the controller 30 via a dedicated line.
  • the display device 40 operates by receiving the supply of power from the storage battery 70.
  • the storage battery 70 is charged with the power generated by the alternator 11a.
  • the electric power of the storage battery 70 is supplied to components other than the controller 30 and the display device 40, such as the electrical component 72 of the shovel.
  • the starter 11 b of the engine 11 is driven by the power from the storage battery 70 to start the engine 11.
  • the engine 11 is controlled by an engine control device 74.
  • the engine control device 74 transmits various data indicating the state of the engine 11 (for example, data indicating the cooling water temperature (physical quantity) detected by the water temperature sensor 11 c) to the controller 30.
  • the controller 30 can store the data in the temporary storage unit (memory) 30 a and can transmit the data to the display device 40 as needed.
  • Data indicating the swash plate tilt angle output from the regulator 14a, data indicating the discharge pressure of the main pump 14 output from the discharge pressure sensor 14b, data indicating the hydraulic oil temperature output from the oil temperature sensor 14c, pilot pressure sensor 15a The same applies to data indicating the pilot pressure output by 15b.
  • the cylinder pressure sensor S1 is an example of an unstable state detection device that detects information related to the unstable state of the upper swing body 3 due to digging load, detects cylinder pressure of a hydraulic cylinder, and outputs detection data to the controller 30 Do.
  • the unstable state of the upper swing body 3 includes, for example, a state in which the rear end of the upper swing body 3 is easily lifted.
  • the cylinder pressure includes, for example, boom cylinder pressure, arm cylinder pressure and bucket cylinder pressure.
  • the cylinder pressure sensor S1 includes cylinder pressure sensors S11 to S16. Specifically, the cylinder pressure sensor S11 detects a boom bottom pressure which is the pressure of the hydraulic fluid in the bottom side oil chamber of the boom cylinder 7.
  • the cylinder pressure sensor S12 detects a boom rod pressure which is the pressure of the hydraulic fluid in the rod side oil chamber of the boom cylinder 7.
  • the cylinder pressure sensor S13 detects arm bottom pressure
  • the cylinder pressure sensor S14 detects arm rod pressure
  • the cylinder pressure sensor S15 detects bucket bottom pressure
  • the cylinder pressure sensor S16 detects bucket rod pressure .
  • Boom cylinder pressure includes boom rod pressure and boom bottom pressure.
  • Arm cylinder pressure includes arm rod pressure and arm bottom pressure.
  • Bucket cylinder pressure includes bucket rod pressure and bucket bottom pressure.
  • the control valve E1 is a valve that operates in response to a command from the controller 30.
  • the control valve E1 is used to forcibly operate the flow control valve for a predetermined hydraulic cylinder regardless of the content of the operation input to the operating device 26.
  • FIG. 4 is a diagram showing a configuration example of a digging control system mounted on the shovel of FIG.
  • the excavation control system mainly includes an attitude detection device M1, a cylinder pressure sensor S1, a controller 30, and a control valve E1.
  • the controller 30 includes a determination unit 31.
  • the determination unit 31 is a functional element that determines whether or not the posture of the digging attachment during digging should be corrected. For example, when it is determined that there is a possibility that the excavation load may become excessively large, the determination unit 31 determines that the posture of the excavation attachment being excavated should be corrected.
  • the determination unit 31 derives and records the digging load based on the output of the cylinder pressure sensor S1. Moreover, the empty excavation load corresponding to the attitude of the digging attachment detected by the attitude detection device M1 is derived. Then, the determination unit 31 subtracts the empty drilling load from the drilling load to calculate a net drilling load, and determines whether to correct the posture of the drilling attachment based on the net drilling load.
  • the determination unit 31 may take into consideration the inclination of the upper swing body 3 detected by the vehicle body inclination sensor S2, which is another example of the unstable state detection device, when the empty excavation load is derived.
  • the vehicle body inclination sensor S2 is configured of, for example, an acceleration sensor, a gyro sensor, an inertial measurement device, or the like.
  • Drilling means moving the drilling attachment while bringing the drilling attachment into contact with the drilling object such as earth and sand, and "empty drilling” means moving the drilling attachment without bringing the drilling attachment into contact with any feature.
  • Drilling load means the load when moving the drilling attachment while contacting with the drilling target
  • empty drilling load means the load when moving the drilling attachment without contacting any feature.
  • the “drilling load” is also referred to as “drilling resistance”.
  • the “drilling load”, the “empty drilling load”, and the “net drilling load” are respectively represented by arbitrary physical quantities such as cylinder pressure, cylinder thrust, drilling torque (moment of drilling force), drilling reaction force and the like.
  • a net cylinder pressure as a net excavation load is expressed as a value obtained by subtracting an empty excavation cylinder pressure as an empty excavation load from a cylinder pressure as an excavation load. The same applies to the case of using cylinder thrust, digging torque (moment of digging force), digging reaction force and the like.
  • a detection value of a cylinder pressure sensor S1 is used as the cylinder pressure.
  • the detection values of the cylinder pressure sensor S1 are, for example, boom bottom pressure (P11), boom rod pressure (P12), arm bottom pressure (P13), arm rod pressure (P14), bucket bottom pressure detected by the cylinder pressure sensors S11 to S16, bucket bottom Pressure (P15) and bucket rod pressure (P16).
  • the cylinder thrust is calculated based on, for example, the cylinder pressure and the pressure receiving area of the piston sliding in the cylinder.
  • the cylinder extension force (P11 ⁇ A11) which is the product of the boom bottom pressure (P11) and the pressure receiving area (A11) of the piston in the boom bottom side oil chamber is the boom cylinder thrust (f1). It is expressed by the difference (P11 ⁇ A11 ⁇ P12 ⁇ A12) of the cylinder contraction force which is the product (P12 ⁇ A12) of the boom rod pressure (P12) and the pressure receiving area (A12) of the piston in the boom rod side oil chamber Ru.
  • the arm cylinder thrust (f2) and the bucket cylinder thrust (f3) The same applies to the arm cylinder thrust (f2) and the bucket cylinder thrust (f3).
  • the digging torque is calculated based on, for example, the posture of the digging attachment and the cylinder thrust.
  • the magnitude of the bucket digging torque ( ⁇ 3) is equal to the magnitude of the bucket cylinder thrust (f3), and the distance between the operating line of the bucket cylinder thrust (f3) and the bucket connecting pin position P3. It is represented by a value multiplied by G3.
  • the distance G3 is a function of the bucket angle ( ⁇ 3), and is an example of the link gain. The same applies to the boom digging torque ( ⁇ 1) and the arm digging torque ( ⁇ 2).
  • the digging reaction force is calculated based on, for example, the posture of the digging attachment and the digging load.
  • the digging reaction force F is calculated based on a function (mechanistic function) having a physical quantity representing the posture of the digging attachment as an argument and a function having a physical quantity representing the digging load as an argument.
  • the digging reaction force F is a mechanical function having a boom angle ( ⁇ 1), an arm angle ( ⁇ 2) and a bucket angle ( ⁇ 3) as arguments, a boom digging torque ( ⁇ 1), an arm It is calculated as a product of a digging torque ( ⁇ 2) and a function with the bucket digging torque ( ⁇ 3) as arguments.
  • the functions with boom digging torque ( ⁇ 1), arm digging torque ( ⁇ 2) and bucket digging torque ( ⁇ 3) as arguments are boom cylinder thrust (f1), arm cylinder thrust (f2) and bucket cylinder thrust (f3) as arguments It may be a function that
  • boom angle ( ⁇ 1), arm angle ( ⁇ 2) and bucket angle ( ⁇ 3) may be based on force balance equation, may be based on Jacobian, or may be virtual work It may be based on the principle.
  • the digging load is derived based on the currently detected values of the various sensors.
  • the detection value of the cylinder pressure sensor S1 may be used as it is as a digging load.
  • the cylinder thrust calculated based on the detection value of the cylinder pressure sensor S1 may be used as the digging load.
  • the digging torque calculated from the cylinder thrust calculated on the basis of the detection value of the cylinder pressure sensor S1 and the posture of the digging attachment derived on the basis of the detection value of the posture detection device M1 may be used as a digging load Good. The same applies to the digging reaction force.
  • the empty excavation load may be stored in advance in association with the posture of the excavation attachment.
  • an empty drilling cylinder pressure table is used that stores empty drilling cylinder pressure as empty drilling load in a referential manner in association with the combination of boom angle ( ⁇ 1), arm angle ( ⁇ 2) and bucket angle ( ⁇ 3) Good.
  • an empty drilling cylinder thrust table is used that stores empty drill cylinder thrusts as empty drilling loads in association with combinations of boom angle ( ⁇ 1), arm angle ( ⁇ 2) and bucket angle ( ⁇ 3). Good.
  • the controller 30 It may be stored in advance in the ROM or the like. Or you may produce
  • the empty drilling cylinder pressure table, the empty drilling cylinder thrust table, the empty drilling torque table, and the empty drilling reaction force table may be prepared for each operation speed of the drilling attachment such as high speed, medium speed, and low speed. Also, it may be prepared for each operation content of the excavating attachment such as when the arm is closed, when the arm is opened, when the boom is raised, and when the boom is lowered.
  • the determination unit 31 determines that the excavating load may be excessive. For example, the determination unit 31 determines that the cylinder pressure as the digging load may become excessive when the net cylinder pressure as the net digging load becomes equal to or higher than a predetermined cylinder pressure.
  • the predetermined cylinder pressure may be a fluctuation value that changes according to a change in the attitude of the digging attachment, or may be a fixed value that does not change according to a change in the attitude of the digging attachment.
  • the determination unit 31 determines that the posture of the digging attachment under digging should be corrected, and the control valve E1. Output a command to
  • Control valve E1 receiving the command from determination unit 31 forcibly operates the flow control valve for a predetermined hydraulic cylinder regardless of the content of the operation input to operating device 26, and forcibly extends and contracts the predetermined hydraulic cylinder.
  • the control valve E1 forcibly extends the boom cylinder 7 by forcibly moving the flow control valve related to the boom cylinder 7.
  • the drilling depth can be made shallow by forcibly raising the boom 4.
  • the control valve E1 may forcibly extend the bucket cylinder 9 by forcibly moving the flow control valve related to the bucket cylinder 9.
  • the bucket toe angle can be adjusted to make the digging depth shallow.
  • the bucket toe angle is, for example, the angle of the toe of the bucket 6 with respect to the horizontal plane.
  • the control valve E1 can reduce the digging depth by forcibly expanding and / or contracting at least one of the boom cylinder 7 and the bucket cylinder 9.
  • the determination unit 31 makes the correction content of the posture of the excavation attachment in the case where the deep excavation is performed different from the correction content as described above in the case where the normal excavation is performed.
  • the determination unit 31 determines whether deep excavation or normal excavation is in progress based on the posture of the excavation attachment.
  • the determination unit 31 may determine whether deep digging or normal digging is in progress based on the attitude of the boom 4 or based on the attitude of the boom 4 and the attitude of the arm 5.
  • FIG. 5 is a side view of the shovel showing the transition of the posture of the digging attachment.
  • Fig. 5 (A1) to Fig. 5 (A3) show the transition of the posture of the excavating attachment when the normal excavation is performed
  • Fig. 5 (B1) to Fig. 5 (B3) shows the state when the deep excavation is performed. Indicates the transition of the attitude of the drilling attachment.
  • Normal excavating means excavating in the case where the moment of excavating reaction force to turn the shovel forward does not have to exceed the moment of self weight of the shovel to prevent the shovel from turning forward.
  • the excavation depth D1 is excavating below a predetermined depth (for example, 2 meters).
  • the digging depth means, for example, the depth of the point of application of the digging reaction force to the horizontal plane including the ground contact surface of the lower traveling body 1.
  • the digging depth has a negative value, which means the digging height.
  • “Deep excavation” means excavation where there is a possibility that the moment of the digging reaction force for turning the shovel forward may exceed the moment of self weight of the shovel preventing the shovel from turning forward.
  • the digging depth D2 is digging of a predetermined depth (eg, 2 meters) or more.
  • the determination unit 31 may determine “deep digging” when the boom angle ( ⁇ 1) is less than a predetermined value regardless of the position of the work site such as the bucket toe position P4.
  • the determination unit 31 determines whether or not the bucket 6 is in contact with the ground based on, for example, the outputs of the pilot pressure sensors 15a and 15b and the cylinder pressure sensors S11 to S16. It is for determining whether it is under excavation.
  • the determination unit 31 derives the bucket toe position P4 based on the detection value of the posture detection device M1, and sets the absolute value as the digging depth when the value of the Z coordinate of the bucket toe position P4 is a negative value. And if the excavation depth is more than predetermined depth, it will be judged as deep excavation and it will be judged as normal excavation if it is less than predetermined depth.
  • the determination unit 31 determines whether or not the digging load may become excessive. Then, when it is determined that the excavation load may become excessive during normal excavation, the determination unit 31 forcibly extends the boom cylinder 7 as described above and forcibly raises the boom 4.
  • the determination unit 31 forcibly contracts the arm cylinder 8 to forcibly move the arm 5 instead of forcibly raising the boom 4.
  • Force open Alternatively, the bucket cylinder 9 is forcibly contracted to forcibly open the bucket 6.
  • the arm 5 and the bucket 6 may be opened simultaneously. The reason is to reduce the digging reaction force, and if the boom 4 is forcedly raised to make the digging depth shallow when digging deeply, the digging reaction force may be increased.
  • the determination unit 31 determines whether the digging load may become excessive during deep excavation based on the output of the vehicle body inclination sensor S2 attached to the rear end of the upper swing body 3, ie, the upper swing body It may be determined whether or not 3 is likely to be unstable. Based on the inclination of the upper swing body 3, the determination unit 31 determines whether the moment of the digging reaction force for turning the shovel forward may exceed the moment of the weight of the shovel that prevents the shovel from turning forward. It is because it can be determined.
  • the determination unit 31 detects that the rear end of the upper swing body 3 has started to rise, for example, based on the output of the vehicle body inclination sensor S2, the digging load may become excessive, that is, It is determined that the upper swing body 3 may be in an unstable state.
  • the determination unit 31 may determine whether the excavation is a normal excavation or a deep excavation. Also, the determination as to whether or not excavation is in progress may be omitted. Alternatively, the determination as to whether or not the excavation is in progress, the determination as to the normal excavation or the deep excavation, and the determination as to whether or not the excavation load may become excessive may be performed simultaneously.
  • FIG. 6 is a flowchart of the determination process.
  • SA sin-automatic
  • the determination unit 31 of the controller 30 acquires data on the excavation attachment (step ST1).
  • the determining unit 31 acquires, for example, a boom angle ( ⁇ 1), an arm angle ( ⁇ 2), a bucket angle ( ⁇ 3), a cylinder pressure (P11 to P16), and the like.
  • the determination unit 31 performs a calculation process on the net digging load to calculate a net digging load (step ST2). Details of the calculation process will be described later.
  • the determination unit 31 determines whether or not the bucket 6 is in contact with the ground (step ST3). This is to determine whether or not the state is excavated.
  • the determination unit 31 determines whether or not the bucket 6 is in contact with the ground based on, for example, the outputs of the pilot pressure sensors 15a and 15b and the cylinder pressure sensors S11 to S16. For example, it is determined that the bucket 6 is in contact with the ground when the arm bottom pressure (P13), which is the pressure of hydraulic fluid in the extension side oil chamber during the arm closing operation, is equal to or higher than a predetermined value. Whether or not the arm closing operation is performed is determined based on the outputs of the pilot pressure sensors 15a and 15b.
  • the determination unit 31 determines whether there is a possibility that the digging load may become excessive (step ST4). For example, when the net excavation load calculated in the calculation process is equal to or more than a predetermined value (predetermined load), the determination unit 31 determines that the excavation load may be excessive. Even if it is determined based on the output of the vehicle body inclination sensor S2 whether digging load may become excessive during deep excavation, that is, it is determined whether the upper swing body 3 may become unstable. Good. Further, the predetermined load may be changed according to the output value of the vehicle body inclination sensor S2.
  • the determination unit 31 determines that there is a risk.
  • the fluctuation range of the output value of the vehicle body inclination sensor S2 is, for example, the difference between the output value of the vehicle body inclination sensor S2 and the current output value when it is determined that the bucket 6 has touched the ground.
  • the determination unit 31 may change the determination threshold based on the output value of the vehicle body inclination sensor S2 when it is determined that the bucket 6 has touched the ground. For example, even when the same load is applied to the work site, the shovel is more unstable when continuing work while tilting forward on a slope than when continuing work while tilting forward on a flat surface It is easy to become. For this reason, it is desirable to change the determination threshold based on the inclination of the upper swing body 3.
  • the determination unit 31 determines whether the digging is normal digging or deep digging (step ST5).
  • the determination unit 31 determines, for example, based on the posture of the digging attachment detected by the posture detection device M1, whether it is normal digging or deep digging. Specifically, the determination unit 31 determines, for example, that the excavation depth is a predetermined depth or more as deep excavation, and determines that the excavation depth is less than the predetermined depth as normal excavation.
  • the determining unit 31 performs adjustment processing during normal drilling because it is necessary to correct the posture of the drilling attachment during normal drilling (step ST6).
  • the determination unit 31 outputs a command to the control valve E1 and forcibly extends the boom cylinder 7 by forcibly moving the flow control valve related to the boom cylinder 7.
  • the digging depth can be made shallow by forcibly raising the boom 4 regardless of the presence or absence of the operation input to the boom control lever.
  • the determination unit 31 may forcibly extend the bucket cylinder 9 by forcibly moving the flow control valve related to the bucket cylinder 9.
  • the digging depth can be made shallow by forcibly closing the bucket 6 regardless of the presence or absence of the operation input to the bucket control lever.
  • the determination unit 31 performs adjustment processing during deep excavation because it is necessary to correct the posture of the excavation attachment during deep excavation ((4) Step ST7).
  • the determination unit 31 outputs a command to the control valve E1, and forcibly contracts the arm cylinder 8 by forcibly moving the flow control valve related to the arm cylinder 8.
  • the digging load can be reduced by forcibly opening the arm 5 regardless of the presence or absence of the operation input to the arm control lever.
  • the determination unit 31 may forcibly contract the bucket cylinder 9 by forcibly moving the flow control valve related to the bucket cylinder 9.
  • the digging load can be reduced by forcibly opening the bucket 6 regardless of the presence or absence of the operation input to the bucket operation lever.
  • the determination unit 31 performs the adjustment process. This determination processing is ended without executing.
  • the determining unit 31 determines whether there is a possibility that the digging load may become excessive, and further, the digging load may become excessive. After the decision is made, it is usually decided whether it is digging or deep digging. However, the determination unit 31 may determine whether the digging load may become excessive after determining whether the digging is normal digging or deep digging. In addition, the determination as to whether or not the bucket 6 has touched the ground may be omitted.
  • the determination unit 31 may determine whether the digging load may be excessively reduced.
  • the determination unit 31 may execute the adjustment processing as it is necessary to correct the posture of the digging attachment.
  • the determination unit 31 when it is determined that there is a possibility that the excavation load may become excessively small during normal excavation, the determination unit 31 outputs a command to the control valve E1 to forcibly move the flow control valve related to the boom cylinder 7
  • the boom cylinder 7 is forcibly contracted.
  • the digging depth can be increased by forcibly lowering the boom 4 regardless of the presence or absence of the operation input to the boom control lever.
  • the determination unit 31 may forcibly extend the bucket cylinder 9 by forcibly moving the flow control valve related to the bucket cylinder 9.
  • the digging depth can be made deeper by forcibly opening the bucket 6 regardless of the presence or absence of the operation input to the bucket operation lever.
  • FIG. 7 is a flowchart showing an example of the flow of calculation processing.
  • the determination unit 31 acquires a cylinder pressure as an excavation load at the present time (step ST11).
  • the cylinder pressure at the present time includes, for example, a boom bottom pressure (P11) detected by the cylinder pressure sensor S11. The same applies to boom rod pressure (P12), arm bottom pressure (P13), arm rod pressure (P14), bucket bottom pressure (P15) and bucket rod pressure (P16).
  • the determination unit 31 acquires an empty excavation cylinder pressure as an empty excavation load corresponding to the posture of the excavation attachment at the present time (step ST12).
  • the empty drilling cylinder pressure stored in advance is derived by referring to the empty drilling cylinder pressure table using the boom angle ( ⁇ 1), the arm angle ( ⁇ 2) and the bucket angle ( ⁇ 3) at the current time as search keys.
  • the empty drilling cylinder pressure may be, for example, at least one of an empty drilling boom bottom pressure, an empty drilling boom rod pressure, an empty drilling arm bottom pressure, an empty drilling arm rod pressure, an empty drilling bucket bottom pressure and an empty drilling bucket rod pressure Including.
  • the determination unit 31 subtracts the empty drilling cylinder pressure corresponding to the posture of the drilling attachment at the current time from the cylinder pressure at the current time to calculate a net cylinder pressure (step ST13).
  • the net cylinder pressure includes, for example, the net boom bottom pressure obtained by subtracting the air drilling boom bottom pressure from the boom bottom pressure (P11). The same applies to net boom rod pressure, net arm bottom pressure, net arm rod pressure, net bucket bottom pressure and net bucket rod pressure.
  • the determination unit 31 outputs the calculated net cylinder pressure as a net digging load (step ST14).
  • the determination unit 31 determines whether the excavation load may become excessive based on at least one of the six net cylinder pressures. .
  • the six net cylinder pressures are net boom bottom pressure, net boom rod pressure, net arm bottom pressure, net arm rod pressure, net bucket bottom pressure and net bucket rod pressure.
  • the determination unit 31 determines that the net arm bottom pressure is equal to or higher than the first predetermined pressure value and the net boom bottom pressure is equal to or higher than the second predetermined pressure value when combined operation of the arm closing operation and the boom raising operation is performed. In this case, it may be determined that the digging load may be excessive.
  • the determination unit 31 may determine that the digging load may be excessive when the net arm bottom pressure is equal to or more than the first predetermined pressure value when the arm closing operation is performed. Alternatively, the determination unit 31 may determine that the digging load may be excessive when the net boom bottom pressure is equal to or higher than the second predetermined pressure value while the boom raising operation is performed.
  • FIG. 8 is a flowchart showing another example of the flow of calculation processing.
  • the process of FIG. 8 is different from the process of FIG. 7 using cylinder pressure in that the cylinder thrust is used as the digging load at the present time.
  • the determination unit 31 calculates a cylinder thrust as a digging load from the cylinder pressure at the present time (step ST21).
  • the cylinder thrust at this time is, for example, a boom cylinder thrust (f1).
  • the boom cylinder thrust (f1) is a cylinder extension force (P11 ⁇ A11) which is the product of the boom bottom pressure (P11) and the pressure receiving area (A11) of the piston in the boom bottom side oil chamber, and the boom rod pressure (P12) This is the difference (P11 ⁇ A11 ⁇ P12 ⁇ A12) from the cylinder contraction force which is the product (P12 ⁇ A12) of the pressure receiving area (A12) of the piston in the boom rod side oil chamber.
  • the determination unit 31 acquires an empty excavation cylinder thrust as an empty excavation load corresponding to the posture of the excavation attachment at the current time (step ST22).
  • the empty drilling cylinder thrust stored in advance is derived by referring to the empty drilling cylinder thrust table with the boom angle ( ⁇ 1), the arm angle ( ⁇ 2) and the bucket angle ( ⁇ 3) at the current point as search keys.
  • the empty drilling cylinder thrust includes, for example, at least one of an empty drilling boom cylinder thrust, an empty drilling arm cylinder thrust and an empty drilling bucket cylinder thrust.
  • the determination unit 31 subtracts the empty drilling cylinder thrust from the cylinder thrust at the current time to calculate a net cylinder thrust (step ST23).
  • the net cylinder thrust includes, for example, the net boom cylinder thrust obtained by subtracting the empty drilling boom cylinder thrust from the current boom cylinder thrust (f1). The same applies to the net arm cylinder thrust and the net bucket cylinder thrust.
  • the determination unit 31 outputs the calculated net cylinder thrust as a net digging load (step ST24).
  • the determination unit 31 determines whether the excavation load may become excessive based on at least one of the three net cylinder thrusts. .
  • the three net cylinder thrusts are net boom cylinder thrust, net arm cylinder thrust and net bucket cylinder thrust. For example, when the net arm cylinder thrust is equal to or greater than the first predetermined thrust value and the net boom cylinder thrust is equal to or greater than the second predetermined thrust value, the determination unit 31 determines that the digging load may be excessive. It is also good. Alternatively, the determination unit 31 may determine that the digging load may be excessive when the net arm cylinder thrust is equal to or greater than the first predetermined thrust value.
  • the determination unit 31 determines whether the drilling load may become excessive based on at least one of the three net drilling torques when the three net drilling torques are derived as the net drilling loads. May be The three net drilling torques are net boom drilling torque, net arm drilling torque and net bucket drilling torque. For example, when the net arm digging torque is equal to or greater than the first predetermined torque value and the net boom digging torque is equal to or greater than the second predetermined torque value, the determining unit 31 determines that the digging load may be excessive. It is also good. Alternatively, the determination unit 31 may determine that the digging load may be excessive when the net arm digging torque is equal to or more than the first predetermined torque value.
  • FIG. 9 shows the temporal transition of the bucket angle ( ⁇ 3)
  • Fig. 9 (B) shows the temporal transition of the digging reaction force F.
  • the solid lines in FIG. 9A and FIG. 9B indicate the transition during deep excavation, and the broken lines indicate the transition during normal excavation.
  • the operator of the shovel brings the tip of the bucket 6 into contact with the ground at time t0 and performs excavation from time t0 to time t3 while closing the arm 5 and the bucket 6.
  • the bucket angle ( ⁇ 3) increases from time t0 to time t1 regardless of whether the normal digging or the deep digging is performed.
  • the digging reaction force F increases from time t0 to time t1 to reach the value F1 regardless of whether it is normal digging or deep digging.
  • the determination unit 31 determines that the bucket 6 contacts the ground at time t0 and determines that the digging load may become excessive at time t1, it determines whether normal digging or deep digging is performed.
  • the determination unit 31 forcibly extends the boom cylinder 7 and forcibly raises the boom 4 regardless of the content of the operation input to the operating device 26.
  • the bucket angle ( ⁇ 3) decreases from time t1 to time t2 as shown by the broken line in FIG. 9 (A).
  • the digging reaction force F decreases from time t1 to time t2 as indicated by the broken line in FIG. 9 (B). This is because the digging depth becomes shallow.
  • the determination unit 31 forcibly contracts the arm cylinder 8 and forcibly opens the arm 5 regardless of the content of the operation input to the operating device 26. This is because, if the boom 4 is forcibly raised as in the case of the normal excavation, the digging reaction force F may be rather increased.
  • the dashed-dotted line of FIG. 9 (B) shows transition of the digging reaction force F when forcedly raising the boom 4 when it determines with deep digging. In this case, the digging reaction force F increases from time t1 to time t11 and reaches the value F2.
  • the value F2 is, for example, a value of the digging reaction force F when the rear end of the shovel is lifted.
  • the bucket angle ( ⁇ 3) decreases from time t1 to time t2 as shown by the solid line in FIG. 9 (A).
  • the digging reaction force F decreases from time t1 to time t2 as indicated by the solid line in FIG. 9 (B).
  • the determination unit 31 stops the raising operation. Similarly, when the arm 5 is opened by a predetermined arm angle during deep excavation, the determination unit 31 stops the opening operation.
  • the bucket angle ( ⁇ 3) increases from time t2 to time t3 regardless of whether it is normal or deep excavation.
  • the digging reaction force F increases from time t2 to time t3 regardless of whether the normal digging or the deep digging is performed.
  • the controller 30 can determine with high accuracy whether or not the drilling load may become excessively large by deriving the net drilling load at the present time with high accuracy. Then, when it is determined that the digging load may become excessively large, the posture of the digging attachment can be automatically corrected so as to reduce the digging load. As a result, it is possible to prevent the movement of the digging attachment from stopping due to an overload during the digging operation, and an efficient digging operation can be realized.
  • the controller 30 can determine with high accuracy whether or not the drilling load may be excessively reduced by deriving the net drilling load at the present time with high accuracy. Then, when it is determined that the digging load may be excessively reduced, the posture of the digging attachment can be automatically corrected so that the digging load becomes large. As a result, it can prevent that the amount of excavation by one excavation operation becomes small too much, and can realize efficient excavation operation.
  • the controller 30 can automatically correct the attitude of the digging attachment during the digging operation so that the digging reaction force has an appropriate magnitude. Therefore, the posture, behavior and the like of the shovel can be prevented from becoming unstable, and accurate positioning control of the tip of the bucket 6 can be realized.
  • controller 30 can make the correction contents of the posture of the drilling attachment different between the normal drilling and the deep drilling. Therefore, by forcibly raising the boom 4 at the time of deep excavation, it is possible to prevent the digging reaction force from being increased.
  • the controller 30 can calculate the digging reaction force in consideration of the boom digging torque and the arm digging torque as well as the bucket digging torque. Therefore, the digging reaction force can be derived with higher accuracy.
  • a cylinder pressure sensor is employed as an example of the unstable state detection device, but another sensor such as a torque sensor may be employed as the unstable state detection device.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

本発明の実施例に係るショベルは、下部走行体(1)と、下部走行体(1)に搭載される上部旋回体(3)と、上部旋回体(3)に取り付けられる掘削アタッチメントと、掘削アタッチメントの姿勢を検出する姿勢検出装置(M1)と、掘削負荷による上部旋回体(3)の不安定状態に関する情報を検出するシリンダ圧センサ(S1)と、掘削アタッチメントの姿勢を修正するコントローラ(30)と、を有する。コントローラ(30)は、姿勢検出装置(M1)及びシリンダ圧センサ(S1)の出力に基づいて深掘掘削中の掘削負荷が所定値より大きいと判定した場合に、掘削アタッチメントを構成するアーム(5)又はバケット(6)を開くように構成される。

Description

ショベル
 本開示は、掘削アタッチメントの姿勢を検出可能なショベルに関する。
 ブーム、アーム及びバケット等の作業要素に荷重検出器を取り付けることなく作業要素の位置及び姿勢から掘削反力を求めることで掘削動作における過負荷の発生の有無を判定し、作業要素の動作を制御できるショベルが知られている(特許文献1参照。)。
 このショベルは、算出した掘削反力が予め設定した上限値より大きい場合、掘削動作の途中でブームを自動的に上昇させて掘削深さを浅くして掘削反力を低減させることで掘削動作が途中で停止してしまうのを防止している。
特開2011-252338号公報
 しかしながら、深掘掘削を行っている場合にブームを上昇させて掘削深さを浅くすると却って掘削反力を増大させてしまうおそれがある。この点に関し、特許文献1のショベルは、算出した掘削反力が予め設定した上限値より大きければ、深掘掘削を行っているか通常掘削を行っているかにかかわらずブームを上昇させてしまう。そのため、深掘掘削の際に掘削反力を低減させようとして却って掘削反力を増大させてしまい、深掘掘削を継続できないようにして作業効率を低下させてしまうおそれがある。
 上述に鑑み、深掘掘削の際に掘削アタッチメントをより適切に制御できるショベルを提供することが望まれる。
 本発明の実施例に係るショベルは、下部走行体と、前記下部走行体に搭載される上部旋回体と、前記上部旋回体に取り付けられる掘削アタッチメントと、前記掘削アタッチメントの姿勢を検出する姿勢検出装置と、掘削負荷による前記上部旋回体の不安定状態に関する情報を検出する不安定状態検出装置と、前記掘削アタッチメントの姿勢を修正する制御装置と、を有するショベルであって、前記制御装置は、前記姿勢検出装置及び前記不安定状態検出装置の出力に基づいて深掘掘削中の掘削負荷が所定値より大きいと判定した場合に、前記掘削アタッチメントを構成するアーム又はバケットを開くように構成される。
 上述の手段により、深掘掘削の際に掘削アタッチメントをより適切に制御できるショベルが提供される。
本発明の実施例に係るショベルの側面図である。 図1のショベルの掘削アタッチメントに関連する各種物理量を示すショベルの側面図である。 図1のショベルに搭載される基本システムの構成例を示す図である。 図1のショベルに搭載される掘削制御システムの構成例を示す図である。 掘削アタッチメントの姿勢の推移を示すショベルの側面図である。 判定処理のフローチャートである。 算出処理の流れの一例を示すフローチャートである。 算出処理の流れの別の一例を示すフローチャートである。 アーム閉じ操作及びブーム上げ操作の複合操作が行われているときのバケット角度及び掘削反力の時間的推移を示す図である。
 最初に、図1を参照し、本発明の実施例に係る建設機械としてのショベル(掘削機)について説明する。図1は、本発明の実施例に係るショベルの側面図である。図1に示すショベルの下部走行体1には旋回機構2を介して上部旋回体3が旋回可能に搭載されている。上部旋回体3にはブーム4が取り付けられている。ブーム4の先端にはアーム5が取り付けられ、アーム5の先端にはバケット6が取り付けられている。作業要素としてのブーム4、アーム5及びバケット6はアタッチメントの一例である掘削アタッチメントを構成する。ブーム4、アーム5、バケット6は、ブームシリンダ7、アームシリンダ8、バケットシリンダ9によりそれぞれ油圧駆動される。上部旋回体3にはキャビン10が設けられ、エンジン11等の動力源が搭載されている。
 掘削アタッチメントには姿勢検出装置M1が取り付けられている。姿勢検出装置M1は掘削アタッチメントの姿勢を検出する装置である。本実施例では、姿勢検出装置M1は、ブーム角度センサM1a、アーム角度センサM1b及びバケット角度センサM1cを含む。
 ブーム角度センサM1aは、ブーム角度を取得するセンサであり、例えば、ブームフートピンの回転角度を検出する回転角度センサ、ブームシリンダ7のストローク量を検出するストロークセンサ、ブーム4の傾斜角度を検出する傾斜(加速度)センサ等を含む。ブーム角度センサM1aは、ジャイロセンサと加速度センサの組み合わせで構成される慣性計測装置であってもよい。アーム角度センサM1b及びバケット角度センサM1cについても同様である。
 図2は、掘削アタッチメントに関連する各種物理量を示すショベルの側面図である。ブーム角度センサM1aは、例えば、ブーム角度(θ1)を取得する。ブーム角度(θ1)は、XZ平面において、ブームフートピン位置P1とアーム連結ピン位置P2とを結ぶ線分P1-P2の水平線に対する角度である。アーム角度センサM1bは、例えば、アーム角度(θ2)を取得する。アーム角度(θ2)は、XZ平面において、アーム連結ピン位置P2とバケット連結ピン位置P3とを結ぶ線分P2-P3の水平線に対する角度である。バケット角度センサM1cは、例えば、バケット角度(θ3)を取得する。バケット角度(θ3)は、XZ平面において、バケット連結ピン位置P3とバケット爪先位置P4とを結ぶ線分P3-P4の水平線に対する角度である。
 次に、図3を参照してショベルの基本システムについて説明する。ショベルの基本システムは、主に、エンジン11、メインポンプ14、パイロットポンプ15、コントロールバルブ17、操作装置26、コントローラ30、エンジン制御装置74等を含む。
 エンジン11はショベルの駆動源であり、例えば、所定の回転数を維持するように動作するディーゼルエンジンである。エンジン11の出力軸はメインポンプ14及びパイロットポンプ15の入力軸に接続されている。
 メインポンプ14は、作動油ライン16を介して作動油をコントロールバルブ17に供給する油圧ポンプであり、例えば、斜板式可変容量型油圧ポンプである。斜板式可変容量型油圧ポンプでは、斜板傾転角の変化に応じて押し退け容積を定めるピストンのストローク長が変化して1回転当たりの吐出流量が変化する。斜板傾転角はレギュレータ14aにより制御される。レギュレータ14aはコントローラ30からの制御電流の変化に応じて斜板傾転角を変化させる。例えば、レギュレータ14aは制御電流の増加に応じて斜板傾転角を大きくしてメインポンプ14の吐出流量を増大させる。或いは、レギュレータ14aは制御電流の減少に応じて斜板傾転角を小さくしてメインポンプ14の吐出流量を低減させる。吐出圧力センサ14bはメインポンプ14の吐出圧力を検出する。油温センサ14cはメインポンプ14が吸入する作動油の温度を検出する。
 パイロットポンプ15は、パイロットライン25を介して操作装置26等の各種油圧制御機器に作動油を供給するための油圧ポンプであり、例えば、固定容量型油圧ポンプである。
 コントロールバルブ17は油圧アクチュエータに関する作動油の流れを制御する流量制御弁のセットである。コントロールバルブ17は、操作装置26の操作方向及び操作量に対応するパイロット圧の変化に応じ、メインポンプ14から作動油ライン16を通じて受け入れた作動油を1又は複数の油圧アクチュエータに選択的に供給する。油圧アクチュエータは、例えば、ブームシリンダ7、アームシリンダ8、バケットシリンダ9、左走行用油圧モータ1A、右走行用油圧モータ1B、旋回用油圧モータ2A等を含む。
 操作装置26は、操作者が油圧アクチュエータの操作のために用いる装置であり、レバー26A、レバー26B、ペダル26C等を含む。操作装置26はパイロットライン25を介してパイロットポンプ15から作動油の供給を受けてパイロット圧を生成する。そして、パイロットライン25aを通じ、対応する流量制御弁のパイロットポートにそのパイロット圧を作用させる。パイロット圧は操作装置26の操作方向及び操作量に応じて変化する。操作装置26は遠隔操作されてもよい。この場合、操作装置26は、無線通信を介して受信した操作方向及び操作量に関する情報に応じてパイロット圧を生成する。
 コントローラ30は、ショベルを制御するための制御装置である。本実施例では、コントローラ30はCPU、RAM、ROM等を備えたコンピュータで構成されている。コントローラ30のCPUは、各種機能に対応するプログラムをROMから読み出してRAMにロードして実行することで、それらプログラムのそれぞれに対応する機能を実現させる。
 例えば、コントローラ30はメインポンプ14の吐出流量を制御する機能を実現させる。具体的には、コントローラ30はネガコン弁のネガコン圧に応じてレギュレータ14aに対する制御電流を変化させ、レギュレータ14aを介してメインポンプ14の吐出流量を制御する。
 エンジン制御装置74はエンジン11を制御する装置である。エンジン制御装置74は、例えば、入力装置を介して設定されたエンジン回転数が実現されるように燃料噴射量等を制御する。
 動作モード切替ダイヤル75は、ショベルの動作モードを切り替えるためのダイヤルであり、キャビン10内に設けられる。本実施例では、操作者はM(手動)モードとSA(半自動)モードとを切り換えることができる。コントローラ30は、例えば、動作モード切替ダイヤル75の出力に応じてショベルの動作モードを切り替える。図3は、動作モード切替ダイヤル75でSAモードが選択された状態を示す。
 Mモードは、操作者による操作装置26に対する操作入力の内容に応じてショベルを動作させるモードである。例えば、操作者による操作装置26に対する操作入力の内容に応じてブームシリンダ7、アームシリンダ8、バケットシリンダ9等を動作させるモードである。SAモードは、所定の条件が満たされた場合に、操作装置26に対する操作入力の内容にかかわらず、ショベルを自動的に動作させるモードである。例えば、所定の条件が満たされた場合に、操作装置26に対する操作入力の内容にかかわらず、ブームシリンダ7、アームシリンダ8、バケットシリンダ9等を自動的に動作させるモードである。動作モード切替ダイヤル75は3つ以上の動作モードを切り替えできるように構成されてもよい。
 表示装置40は、各種情報を表示する装置であり、キャビン10内の運転席の近傍に配置されている。本実施例では、表示装置40は画像表示部41及び入力部42を有する。操作者は入力部42を利用して情報や指令をコントローラ30に入力できる。また、画像表示部41を見てショベルの運転状況や制御情報を把握できる。表示装置40は、CAN等の通信ネットワークを介してコントローラ30に接続される。但し、表示装置40は専用線を介してコントローラ30に接続されてもよい。
 表示装置40は蓄電池70から電力の供給を受けて動作する。蓄電池70はオルタネータ11aで発電した電力で充電される。蓄電池70の電力は、ショベルの電装品72等、コントローラ30及び表示装置40以外にも供給される。エンジン11のスタータ11bは蓄電池70からの電力で駆動されてエンジン11を始動させる。
 エンジン11はエンジン制御装置74により制御される。エンジン制御装置74は、エンジン11の状態を示す各種データ(例えば、水温センサ11cで検出される冷却水温(物理量)を示すデータ)をコントローラ30に送信する。コントローラ30は一時記憶部(メモリ)30aにそれらデータを蓄積しておき、必要に応じて表示装置40に送信できる。レギュレータ14aが出力する斜板傾転角を示すデータ、吐出圧力センサ14bが出力するメインポンプ14の吐出圧力を示すデータ、油温センサ14cが出力する作動油温度を示すデータ、パイロット圧センサ15a、15bが出力するパイロット圧を示すデータ等についても同様である。
 シリンダ圧センサS1は、掘削負荷による上部旋回体3の不安定状態に関する情報を検出する不安定状態検出装置の一例であり、油圧シリンダのシリンダ圧を検出し、検出データをコントローラ30に対して出力する。上部旋回体3の不安定状態は、例えば、上部旋回体3の後端が浮き上がり易い状態を含む。シリンダ圧は、例えば、ブームシリンダ圧、アームシリンダ圧及びバケットシリンダ圧を含む。本実施例では、シリンダ圧センサS1は、シリンダ圧センサS11~S16を含む。具体的には、シリンダ圧センサS11は、ブームシリンダ7のボトム側油室における作動油の圧力であるブームボトム圧を検出する。また、シリンダ圧センサS12は、ブームシリンダ7のロッド側油室における作動油の圧力であるブームロッド圧を検出する。同様に、シリンダ圧センサS13はアームボトム圧を検出し、シリンダ圧センサS14はアームロッド圧を検出し、シリンダ圧センサS15はバケットボトム圧を検出し、シリンダ圧センサS16はバケットロッド圧を検出する。ブームシリンダ圧は、ブームロッド圧及びブームボトム圧を含む。アームシリンダ圧は、アームロッド圧及びアームボトム圧を含む。バケットシリンダ圧は、バケットロッド圧及びバケットボトム圧を含む。
 制御弁E1は、コントローラ30からの指令に応じて動作する弁である。本実施例では、制御弁E1は、操作装置26に対する操作入力の内容にかかわらず、所定の油圧シリンダに関する流量制御弁を強制的に動作させるために用いられる。
 図4は、図1のショベルに搭載される掘削制御システムの構成例を示す図である。掘削制御システムは、主に、姿勢検出装置M1、シリンダ圧センサS1、コントローラ30及び制御弁E1で構成される。コントローラ30は判定部31を含む。
 判定部31は、掘削中の掘削アタッチメントの姿勢を修正すべきか否かを判定する機能要素である。例えば、判定部31は、掘削負荷が過度に大きくなるおそれがあると判定した場合に、掘削中の掘削アタッチメントの姿勢を修正すべきと判定する。
 本実施例では、判定部31はシリンダ圧センサS1の出力に基づいて掘削負荷を導き出し、記録する。また、姿勢検出装置M1が検出した掘削アタッチメントの姿勢に対応する空掘削負荷を導き出す。そして、判定部31は、掘削負荷から空掘削負荷を差し引いて正味掘削負荷を算出し、正味掘削負荷に基づいて掘削アタッチメントの姿勢を修正すべきか否かを判定する。判定部31は、空掘削負荷を導き出すときに、不安定状態検出装置の別の一例である車体傾斜センサS2が検出した上部旋回体3の傾斜を考慮してもよい。車体傾斜センサS2は、例えば、加速度センサ、ジャイロセンサ、慣性計測装置等で構成される。
 「掘削」は掘削アタッチメントを土砂等の掘削対象に接触させながら掘削アタッチメントを動かすことを意味し、「空掘削」は掘削アタッチメントを何れの地物にも接触させることなく掘削アタッチメントを動かすことを意味する。
 「掘削負荷」は掘削対象に接触させながら掘削アタッチメントを動かす際の負荷を意味し、「空掘削負荷」は何れの地物にも接触させずに掘削アタッチメントを動かす際の負荷を意味する。「掘削負荷」は「掘削抵抗」とも称される。
 「掘削負荷」、「空掘削負荷」、及び「正味掘削負荷」はそれぞれ、シリンダ圧、シリンダ推力、掘削トルク(掘削力のモーメント)、掘削反力等の任意の物理量で表される。例えば、正味掘削負荷としての正味シリンダ圧は、掘削負荷としてのシリンダ圧から、空掘削負荷としての空掘削シリンダ圧を差し引いた値として表される。シリンダ推力、掘削トルク(掘削力のモーメント)、掘削反力等を利用する場合についても同様である。
 シリンダ圧としては、例えば、シリンダ圧センサS1の検出値が利用される。シリンダ圧センサS1の検出値は、例えば、シリンダ圧センサS11~S16が検出するブームボトム圧(P11)、ブームロッド圧(P12)、アームボトム圧(P13)、アームロッド圧(P14)、バケットボトム圧(P15)、バケットロッド圧(P16)である。
 シリンダ推力は、例えば、シリンダ圧とシリンダ内を摺動するピストンの受圧面積とに基づいて算出される。例えば、図2に示すように、ブームシリンダ推力(f1)は、ブームボトム圧(P11)とブームボトム側油室におけるピストンの受圧面積(A11)との積(P11×A11)であるシリンダ伸張力と、ブームロッド圧(P12)とブームロッド側油室におけるピストンの受圧面積(A12)との積(P12×A12)であるシリンダ収縮力との差(P11×A11-P12×A12)で表される。アームシリンダ推力(f2)、及び、バケットシリンダ推力(f3)についても同様である。
 掘削トルクは、例えば、掘削アタッチメントの姿勢とシリンダ推力とに基づいて算出される。例えば、図2に示すように、バケット掘削トルク(τ3)の大きさは、バケットシリンダ推力(f3)の大きさに、そのバケットシリンダ推力(f3)の作用線とバケット連結ピン位置P3との距離G3を乗じた値で表される。距離G3は、バケット角度(θ3)の関数であり、リンクゲインの一例とされる。ブーム掘削トルク(τ1)及びアーム掘削トルク(τ2)についても同様である。
 掘削反力は、例えば、掘削アタッチメントの姿勢と掘削負荷とに基づいて算出される。例えば、掘削反力Fは、掘削アタッチメントの姿勢を表す物理量を引数とする関数(機構関数)と、掘削負荷を表す物理量を引数とする関数とに基づいて算出される。具体的には、掘削反力Fは、図2に示すようにブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)を引数とする機構関数と、ブーム掘削トルク(τ1)、アーム掘削トルク(τ2)及びバケット掘削トルク(τ3)を引数とする関数との積として算出される。ブーム掘削トルク(τ1)、アーム掘削トルク(τ2)及びバケット掘削トルク(τ3)を引数とする関数は、ブームシリンダ推力(f1)、アームシリンダ推力(f2)及びバケットシリンダ推力(f3)を引数とする関数であってもよい。
 ブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)を引数とする関数は、力のつり合い式に基づくものであってもよく、ヤコビアンに基づくものであってもよく、仮想仕事の原理に基づくものであってもよい。
 このように、掘削負荷は各種センサの現時点における検出値に基づいて導き出される。例えば、シリンダ圧センサS1の検出値がそのまま掘削負荷として利用されてもよい。或いは、シリンダ圧センサS1の検出値に基づいて算出されるシリンダ推力が掘削負荷として利用されてもよい。或いは、シリンダ圧センサS1の検出値に基づいて算出されるシリンダ推力と、姿勢検出装置M1の検出値に基づいて導き出される掘削アタッチメントの姿勢とから算出される掘削トルクが掘削負荷として利用されてもよい。掘削反力についても同様である。
 一方、空掘削負荷は、掘削アタッチメントの姿勢に対応付けて予め記憶されていてもよい。例えば、ブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)の組み合わせに対応付けて空掘削負荷としての空掘削シリンダ圧を参照可能に記憶する空掘削シリンダ圧テーブルが利用されてもよい。或いは、ブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)の組み合わせに対応付けて空掘削負荷としての空掘削シリンダ推力を参照可能に記憶する空掘削シリンダ推力テーブルが利用されてもよい。空掘削トルクテーブル、空掘削反力テーブル等についても同様である。空掘削シリンダ圧テーブル、空掘削シリンダ推力テーブル、空掘削トルクテーブル、空掘削反力テーブル等は、例えば、実際のショベルで空掘削を行ったときに取得されたデータに基づいて生成され、コントローラ30のROM等に予め記憶されていてもよい。或いは、ショベルシミュレータ等のシミュレータ装置が導出したシミュレーション結果に基づいて生成されてもよい。また、参照テーブルの代わりに重回帰分析に基づく重回帰式等の計算式が用いられてもよい。重回帰式を用いる場合、空掘削負荷は、例えば、現時点におけるブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)の組み合わせに基づいてリアルタイムに算出される。
 また、空掘削シリンダ圧テーブル、空掘削シリンダ推力テーブル、空掘削トルクテーブル及び空掘削反力テーブルは、高速、中速、低速といった掘削アタッチメントの動作速度毎に用意されてもよい。また、アーム閉じ時、アーム開き時、ブーム上げ時、ブーム下げ時といった掘削アタッチメントの動作内容毎に用意されてもよい。
 現時点における正味掘削負荷が所定値(所定負荷)以上となった場合、判定部31は、掘削負荷が過大になるおそれがあると判定する。例えば、判定部31は、正味掘削負荷としての正味シリンダ圧が所定のシリンダ圧以上となった場合に、掘削負荷としてのシリンダ圧が過大になるおそれがあると判定する。所定のシリンダ圧は、掘削アタッチメントの姿勢の変化に応じて変化する変動値であってもよく、掘削アタッチメントの姿勢の変化に応じて変化しない固定値であってもよい。
 そして、動作モードがSA(半自動)モードのときに掘削負荷が過大になるおそれがあると判定した場合、判定部31は、掘削中の掘削アタッチメントの姿勢を修正すべきと判定し、制御弁E1に対して指令を出力する。
 判定部31からの指令を受けた制御弁E1は、操作装置26に対する操作入力の内容にかかわらず、所定の油圧シリンダに関する流量制御弁を強制的に動作させて所定の油圧シリンダを強制的に伸縮させる。本実施例では、制御弁E1は、例えば、ブーム操作レバーが操作されていない場合であっても、ブームシリンダ7に関する流量制御弁を強制的に動かすことでブームシリンダ7を強制的に伸張させる。その結果、ブーム4を強制的に上昇させることで掘削深さを浅くすることができる。或いは、制御弁E1は、バケット操作レバーが操作されていない場合であっても、バケットシリンダ9に関する流量制御弁を強制的に動かすことでバケットシリンダ9を強制的に伸張させてもよい。この場合、バケット6を強制的に閉じることでバケット爪先角度を調整して掘削深さを浅くすることができる。バケット爪先角度は、例えば、水平面に対するバケット6の爪先の角度である。このように、制御弁E1はブームシリンダ7及びバケットシリンダ9のうちの少なくとも1つを強制的に伸縮させることで掘削深さを浅くすることができる。
 しかしながら、深掘掘削を行っている場合に強制的にブーム4を上昇させ或いはバケット6を閉じて掘削深さを浅くすると却って掘削反力を増大させてしまうおそれがある。そこで、判定部31は、深掘掘削が行われている場合における掘削アタッチメントの姿勢の修正内容を、通常掘削が行われている場合における上述のような修正内容と異ならせる。
 例えば、判定部31は、掘削アタッチメントの姿勢に基づいて深掘掘削中であるか通常掘削中であるかを判定する。判定部31は、ブーム4の姿勢に基づいて、或いは、ブーム4の姿勢とアーム5の姿勢とに基づいて深掘掘削中であるか通常掘削中であるかを判定してもよい。
 ここで図5を参照し、通常掘削と深掘掘削の違いについて説明する。図5は掘削アタッチメントの姿勢の推移を示すショベルの側面図である。図5(A1)~図5(A3)は通常掘削が行われたときの掘削アタッチメントの姿勢の推移を示し、図5(B1)~図5(B3)は深掘掘削が行われたときの掘削アタッチメントの姿勢の推移を示す。
 「通常掘削」は、ショベルを前転させようとする掘削反力のモーメントがショベルを前転させないようにするショベルの自重のモーメントを上回るおそれがない場合の掘削を意味する。典型的には図5(A1)~図5(A3)に示すように、掘削深さD1が所定深さ(例えば2メートル)未満の掘削である。掘削深さは、例えば、下部走行体1の接地面を含む水平面に対する掘削反力の作用点の深さを意味する。なお、掘削反力の作用点が水平面より高い場合、掘削深さは負値となり、掘削高さを意味する。
 「深掘掘削」は、ショベルを前転させようとする掘削反力のモーメントがショベルを前転させないようにするショベルの自重のモーメントを上回るおそれがある場合の掘削を意味する。典型的には図5(B1)~図5(B3)に示すように、掘削深さD2が所定深さ(例えば2メートル)以上の掘削である。判定部31は、バケット爪先位置P4等の作業部位の位置にかかわらず、ブーム角度(θ1)が所定値未満の場合に「深掘掘削」であると判定してもよい。
 判定部31は、例えば、パイロット圧センサ15a、15b、シリンダ圧センサS11~S16等の出力に基づいてバケット6が地面に接触しているか否かを判定する。掘削中であるか否かを判定するためである。
 そして、判定部31は、姿勢検出装置M1の検出値に基づいてバケット爪先位置P4を導き出し、バケット爪先位置P4のZ座標の値が負値の場合、その絶対値を掘削深さとする。そして、その掘削深さが所定深さ以上であれば深掘掘削であると判定し、所定深さ未満であれば通常掘削であると判定する。
 その後、判定部31は、掘削負荷が過大になるおそれがあるか否かを判定する。そして、通常掘削中に掘削負荷が過大になるおそれがあると判定した場合、判定部31は、上述のようにブームシリンダ7を強制的に伸張させてブーム4を強制的に上昇させる。
 一方、深掘掘削中に掘削負荷が過大になるおそれがあると判定した場合、判定部31は、ブーム4を強制的に上昇させる代わりに、アームシリンダ8を強制的に収縮させてアーム5を強制的に開く。或いは、バケットシリンダ9を強制的に収縮させてバケット6を強制的に開く。アーム5とバケット6を同時に開いてもよい。掘削反力を低減させるためであり、深掘掘削を行っている場合に強制的にブーム4を上昇させて掘削深さを浅くすると却って掘削反力を増大させてしまうおそれがあるためである。
 なお、判定部31は、上部旋回体3の後端に取り付けられた車体傾斜センサS2の出力に基づいて深掘掘削中に掘削負荷が過大になるおそれがあるか否か、すなわち、上部旋回体3が不安定状態になるおそれがあるか否かを判定してもよい。判定部31は、上部旋回体3の傾斜に基づき、ショベルを前転させようとする掘削反力のモーメントがショベルを前転させないようにするショベルの自重のモーメントを上回るおそれがあるか否かを判定できるためである。具体的には、判定部31は、例えば、車体傾斜センサS2の出力に基づいて上部旋回体3の後端が浮き上がり始めたことを検知した場合に、掘削負荷が過大になるおそれがある、すなわち、上部旋回体3が不安定状態になるおそれがあると判定する。
 また、判定部31は、掘削負荷が過大になるおそれがあると判定した後で、通常掘削であるか深掘掘削であるかの判定を行うようにしてもよい。また、掘削中であるか否かの判定は省略されてもよい。或いは、掘削中であるか否かの判定、通常掘削であるか深掘掘削であるかの判定、及び、掘削負荷が過大になるおそれがあるか否かの判定は同時に行われてもよい。
 次に図6を参照し、アーム閉じ動作による掘削中に掘削アタッチメントの姿勢を修正する必要があるか否かをコントローラ30が判定する処理(以下、「判定処理」とする。)の流れについて説明する。図6は判定処理のフローチャートである。コントローラ30は、動作モードがSA(半自動)モードに設定されている場合にこの判定処理を所定の制御周期で繰り返し実行する。
 最初に、コントローラ30の判定部31は、掘削アタッチメントに関するデータを取得する(ステップST1)。判定部31は、例えば、ブーム角度(θ1)、アーム角度(θ2)、バケット角度(θ3)、シリンダ圧(P11~P16)等を取得する。
 その後、判定部31は、正味掘削負荷に関する算出処理を実行して正味掘削負荷を算出する(ステップST2)。算出処理の詳細については後述する。
 その後、判定部31は、バケット6が地面に接触しているか否かを判定する(ステップST3)。掘削状態であるか否かを判定するためである。判定部31は、例えば、パイロット圧センサ15a、15b、シリンダ圧センサS11~S16等の出力に基づいてバケット6が地面に接触しているか否かを判定する。例えば、アーム閉じ操作中の伸張側油室における作動油の圧力であるアームボトム圧(P13)が所定値以上となっている場合にバケット6が地面に接触していると判定する。アーム閉じ操作が行われているか否かはパイロット圧センサ15a、15bの出力に基づいて判定される。
 バケット6が地面に接触していると判定した場合(ステップST3のYES)、判定部31は、掘削負荷が過大になるおそれがあるか否かを判定する(ステップST4)。判定部31は、例えば、算出処理で算出した正味掘削負荷が所定値(所定負荷)以上の場合に掘削負荷が過大になるおそれがあると判定する。車体傾斜センサS2の出力に基づいて深掘掘削中に掘削負荷が過大になるおそれがあるか否か、すなわち、上部旋回体3が不安定状態になるおそれがあるか否かを判定してもよい。また、車体傾斜センサS2の出力値に応じて所定負荷を変更するように構成されていてもよい。更に、判定部31は、上部旋回体3のカウンタウェイトが浮き上がる方向に力が働いて車体傾斜センサS2の出力値の変動幅が所定の判定閾値以上となった場合に、掘削負荷が過大になるおそれがあると判定してもよい。車体傾斜センサS2の出力値の変動幅は、例えば、バケット6が地面に接触したと判定されたときの車体傾斜センサS2の出力値と現在の出力値との差である。
 また、判定部31は、バケット6が地面に接触したと判定されたときの車体傾斜センサS2の出力値に基づいて判定閾値を変更してもよい。例えば、作業部位に同じ負荷が掛かる場合であっても、平地において前方に傾きながら作業を継続するときよりも、傾斜地において前方に傾きながら作業を継続するときの方が、ショベルは不安定な状態になり易い。このため、上部旋回体3の傾きに基づいて判定閾値を変更する方が望ましい。
 掘削負荷が過大になるおそれがあると判定した場合(ステップST4のYES)、判定部31は、通常掘削であるか深掘掘削であるかを判定する(ステップST5)。判定部31は、例えば、姿勢検出装置M1が検出した掘削アタッチメントの姿勢に基づいて通常掘削であるか深掘掘削であるかを判定する。具体的には、判定部31は、例えば、掘削深さが所定深さ以上の場合に深掘掘削であると判定し、所定深さ未満の場合に通常掘削であると判定する。
 通常掘削であると判定した場合(ステップST5の通常掘削)、判定部31は、通常掘削中に掘削アタッチメントの姿勢を修正する必要があるとして通常掘削時の調整処理を実行する(ステップST6)。判定部31は、例えば、制御弁E1に対して指令を出力し、ブームシリンダ7に関する流量制御弁を強制的に動かすことでブームシリンダ7を強制的に伸張させる。その結果、ブーム操作レバーに対する操作入力の有無にかかわらず、ブーム4を強制的に上昇させることで掘削深さを浅くすることができる。或いは、判定部31は、バケットシリンダ9に関する流量制御弁を強制的に動かすことでバケットシリンダ9を強制的に伸張させてもよい。その結果、バケット操作レバーに対する操作入力の有無にかかわらず、バケット6を強制的に閉じることで掘削深さを浅くすることができる。
 深掘掘削であると判定した場合(ステップST5の深掘掘削)、判定部31は、深掘掘削中に掘削アタッチメントの姿勢を修正する必要があるとして深掘掘削時の調整処理を実行する(ステップST7)。判定部31は、例えば、制御弁E1に対して指令を出力し、アームシリンダ8に関する流量制御弁を強制的に動かすことでアームシリンダ8を強制的に収縮させる。その結果、アーム操作レバーに対する操作入力の有無にかかわらず、アーム5を強制的に開くことで掘削負荷を低減させることができる。或いは、判定部31は、バケットシリンダ9に関する流量制御弁を強制的に動かすことでバケットシリンダ9を強制的に収縮させてもよい。その結果、バケット操作レバーに対する操作入力の有無にかかわらず、バケット6を強制的に開くことで掘削負荷を低減させることができる。
 バケット6が地面に接触していないと判定した場合(ステップST3のNO)、或いは、掘削負荷が過大になるおそれがないと判定した場合(ステップST4のNO)、判定部31は、調整処理を実行することなく今回の判定処理を終了させる。
 図6の例では、判定部31は、バケット6が地面に接触したと判定した後で掘削負荷が過大になるおそれがあるか否かを判定し、更に、掘削負荷が過大になるおそれがあると判定した後で通常掘削か深掘掘削かを判定している。しかしながら、判定部31は、通常掘削か深掘掘削かを判定した後で掘削負荷が過大になるおそれがあるか否かを判定してもよい。また、バケット6が地面に接触したか否かの判定を省略してもよい。
 また、判定部31は、掘削負荷が過大になるおそれがあるか否かを判定したが、掘削負荷が過小になるおそれがあるか否かを判定してもよい。
 そして、掘削負荷が過小になるおそれがあると判定した場合にも、判定部31は、掘削アタッチメントの姿勢を修正する必要があるとして調整処理を実行してもよい。
 例えば、通常掘削中に掘削負荷が過小になるおそれがあると判定した場合、判定部31は、制御弁E1に対して指令を出力し、ブームシリンダ7に関する流量制御弁を強制的に動かすことでブームシリンダ7を強制的に収縮させる。その結果、ブーム操作レバーに対する操作入力の有無にかかわらず、ブーム4を強制的に下降させることで掘削深さを深くすることができる。或いは、判定部31は、バケットシリンダ9に関する流量制御弁を強制的に動かすことでバケットシリンダ9を強制的に伸張させてもよい。その結果、バケット操作レバーに対する操作入力の有無にかかわらず、バケット6を強制的に開くことで掘削深さを深くすることができる。
 次に図7を参照し、正味掘削負荷に関する算出処理の流れについて説明する。図7は算出処理の流れの一例を示すフローチャートである。
 最初に、判定部31は、現時点における掘削負荷としてのシリンダ圧を取得する(ステップST11)。現時点におけるシリンダ圧は、例えば、シリンダ圧センサS11が検出するブームボトム圧(P11)を含む。ブームロッド圧(P12)、アームボトム圧(P13)、アームロッド圧(P14)、バケットボトム圧(P15)及びバケットロッド圧(P16)についても同様である。
 その後、判定部31は、現時点における掘削アタッチメントの姿勢に対応する空掘削負荷としての空掘削シリンダ圧を取得する(ステップST12)。例えば、現時点におけるブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)を検索キーとして空掘削シリンダ圧テーブルを参照することで、予め記憶されている空掘削シリンダ圧を導き出す。空掘削シリンダ圧は、例えば、空掘削ブームボトム圧、空掘削ブームロッド圧、空掘削アームボトム圧、空掘削アームロッド圧、空掘削バケットボトム圧及び空掘削バケットロッド圧のうちの少なくとも1つを含む。
 その後、判定部31は、現時点におけるシリンダ圧から現時点における掘削アタッチメントの姿勢に対応する空掘削シリンダ圧を差し引いて正味シリンダ圧を算出する(ステップST13)。正味シリンダ圧は、例えば、ブームボトム圧(P11)から空掘削ブームボトム圧を差し引いた正味ブームボトム圧を含む。正味ブームロッド圧、正味アームボトム圧、正味アームロッド圧、正味バケットボトム圧及び正味バケットロッド圧についても同様である。
 その後、判定部31は、算出した正味シリンダ圧を正味掘削負荷として出力する(ステップST14)。
 判定部31は、例えば、6つの正味シリンダ圧を正味掘削負荷として導き出した場合、6つの正味シリンダ圧のうちの少なくとも1つに基づいて掘削負荷が過大になるおそれがあるか否かを判定する。6つの正味シリンダ圧は、正味ブームボトム圧、正味ブームロッド圧、正味アームボトム圧、正味アームロッド圧、正味バケットボトム圧及び正味バケットロッド圧である。例えば、判定部31は、アーム閉じ操作及びブーム上げ操作の複合操作が行われているときに正味アームボトム圧が第1所定圧力値以上で、且つ、正味ブームボトム圧が第2所定圧力値以上の場合に、掘削負荷が過大になるおそれがあると判定してもよい。或いは、判定部31は、アーム閉じ操作が行われているときに正味アームボトム圧が第1所定圧力値以上の場合に掘削負荷が過大になるおそれがあると判定してもよい。或いは、判定部31は、ブーム上げ操作が行われているときに正味ブームボトム圧が第2所定圧力値以上の場合に、掘削負荷が過大になるおそれがあると判定してもよい。
 次に図8を参照し、正味掘削負荷に関する算出処理の別の一例について説明する。図8は算出処理の流れの別の一例を示すフローチャートである。図8の処理は、現時点における掘削負荷としてシリンダ推力を利用する点で、シリンダ圧を利用する図7の処理と相違する。
 最初に、判定部31は、現時点におけるシリンダ圧から掘削負荷としてのシリンダ推力を算出する(ステップST21)。現時点におけるシリンダ推力は、例えば、ブームシリンダ推力(f1)である。ブームシリンダ推力(f1)は、ブームボトム圧(P11)とブームボトム側油室におけるピストンの受圧面積(A11)との積(P11×A11)であるシリンダ伸張力と、ブームロッド圧(P12)とブームロッド側油室におけるピストンの受圧面積(A12)との積(P12×A12)であるシリンダ収縮力との差(P11×A11-P12×A12)である。アームシリンダ推力(f2)及びバケットシリンダ推力(f3)についても同様である。
 その後、判定部31は、現時点における掘削アタッチメントの姿勢に対応する空掘削負荷としての空掘削シリンダ推力を取得する(ステップST22)。例えば、現時点におけるブーム角度(θ1)、アーム角度(θ2)及びバケット角度(θ3)を検索キーとして空掘削シリンダ推力テーブルを参照することで、予め記憶されている空掘削シリンダ推力を導き出す。空掘削シリンダ推力は、例えば、空掘削ブームシリンダ推力、空掘削アームシリンダ推力及び空掘削バケットシリンダ推力のうちの少なくとも1つを含む。
 その後、判定部31は、現時点におけるシリンダ推力から空掘削シリンダ推力を差し引いて正味シリンダ推力を算出する(ステップST23)。正味シリンダ推力は、例えば、現時点におけるブームシリンダ推力(f1)から空掘削ブームシリンダ推力を差し引いた正味ブームシリンダ推力を含む。正味アームシリンダ推力及び正味バケットシリンダ推力についても同様である。
 その後、判定部31は、算出した正味シリンダ推力を正味掘削負荷として出力する(ステップST24)。
 判定部31は、例えば、3つの正味シリンダ推力を正味掘削負荷として導き出した場合、3つの正味シリンダ推力のうちの少なくとも1つに基づいて掘削負荷が過大になるおそれがあるか否かを判定する。3つの正味シリンダ推力は、正味ブームシリンダ推力、正味アームシリンダ推力及び正味バケットシリンダ推力である。例えば、判定部31は、正味アームシリンダ推力が第1所定推力値以上で、且つ、正味ブームシリンダ推力が第2所定推力値以上の場合に、掘削負荷が過大になるおそれがあると判定してもよい。或いは、判定部31は、正味アームシリンダ推力が第1所定推力値以上の場合に掘削負荷が過大になるおそれがあると判定してもよい。
 或いは、判定部31は、3つの正味掘削トルクを正味掘削負荷として導き出した場合、3つの正味掘削トルクのうちの少なくとも1つに基づいて掘削負荷が過大になるおそれがあるか否かを判定してもよい。3つの正味掘削トルクは、正味ブーム掘削トルク、正味アーム掘削トルク及び正味バケット掘削トルクである。例えば、判定部31は、正味アーム掘削トルクが第1所定トルク値以上で、且つ、正味ブーム掘削トルクが第2所定トルク値以上の場合に、掘削負荷が過大になるおそれがあると判定してもよい。或いは、判定部31は、正味アーム掘削トルクが第1所定トルク値以上の場合に掘削負荷が過大になるおそれがあると判定してもよい。
 次に図9を参照し、アーム閉じ操作及びブーム上げ操作の複合操作が行われているときのバケット角度(θ3)及び掘削反力Fの時間的推移について説明する。図9(A)はバケット角度(θ3)の時間的推移を示し、図9(B)は掘削反力Fの時間的推移を示す。図9(A)及び図9(B)の実線は深掘掘削中の推移を示し、破線は通常掘削中の推移を示す。
 ショベルの操作者は、時刻t0においてバケット6の爪先を地面に接触させ、アーム5及びバケット6を閉じながら時刻t0から時刻t3にかけて掘削を行う。
 バケット角度(θ3)は、通常掘削であるか深掘掘削であるかにかかわらず、時刻t0から時刻t1にかけて増大する。同様に、掘削反力Fは、通常掘削であるか深掘掘削であるかにかかわらず、時刻t0から時刻t1にかけて増大して値F1に至る。
 判定部31は、時刻t0においてバケット6が地面に接触したと判定し、且つ、時刻t1において掘削負荷が過大になるおそれがあると判定すると、通常掘削か深掘掘削かを判定する。
 そして、時刻t1において通常掘削と判定した場合、判定部31は、操作装置26に対する操作入力の内容にかかわらず、ブームシリンダ7を強制的に伸張させてブーム4を強制的に上昇させる。
 ブーム4を強制的に上昇させると、バケット角度(θ3)は、図9(A)の破線で示すように時刻t1から時刻t2にかけて減少する。また、掘削反力Fは、図9(B)の破線で示すように時刻t1から時刻t2にかけて減少する。掘削深さが浅くなるためである。
 一方、時刻t1において深掘掘削と判定した場合、判定部31は、操作装置26に対する操作入力の内容にかかわらず、アームシリンダ8を強制的に収縮させてアーム5を強制的に開く。仮に通常掘削の場合と同様にブーム4を強制的に上昇させた場合、掘削反力Fが却って増大してしまうおそれがあるためである。図9(B)の一点鎖線は、深掘掘削と判定した場合にブーム4を強制的に上昇させたときの掘削反力Fの推移を示す。この場合、掘削反力Fは、時刻t1から時刻t11にかけて増大して値F2に至る。値F2は、例えば、ショベルの後端が浮き上がるときの掘削反力Fの値である。
 アーム5を強制的に開くと、バケット角度(θ3)は、図9(A)の実線で示すように時刻t1から時刻t2にかけて減少する。また、掘削反力Fは、図9(B)の実線で示すように時刻t1から時刻t2にかけて減少する。
 判定部31は、通常掘削中にブーム4を所定のブーム角度だけ上昇させると、その上昇動作を停止させる。同様に、判定部31は、深掘掘削中にアーム5を所定のアーム角度だけ開くと、その開き動作を停止させる。
 その後、操作者の複合操作に応じた掘削の継続に伴い、バケット角度(θ3)は、通常掘削であるか深掘掘削であるかにかかわらず、時刻t2から時刻t3にかけて増大する。同様に、掘削反力Fは、通常掘削であるか深掘掘削であるかにかかわらず、時刻t2から時刻t3にかけて増大する。
 上述の構成により、コントローラ30は、現時点における正味掘削負荷を高い精度で導き出すことで、掘削負荷が過度に大きくなるおそれがあるか否かを高い精度で判定できる。そして、掘削負荷が過度に大きくなるおそれがあると判定した場合には掘削負荷が小さくなるよう掘削アタッチメントの姿勢を自動的に修正できる。その結果、掘削動作中の過負荷により掘削アタッチメントの動きが止まってしまうのを防止でき、効率の良い掘削動作を実現できる。
 また、コントローラ30は、現時点における正味掘削負荷を高い精度で導き出すことで、掘削負荷が過度に小さくなるおそれがあるか否かを高い精度で判定できる。そして、掘削負荷が過度に小さくなるおそれがあると判定した場合には掘削負荷が大きくなるよう掘削アタッチメントの姿勢を自動的に修正できる。その結果、1回の掘削動作による掘削量が過度に小さくなってしまうのを防止でき、効率の良い掘削動作を実現できる。
 このように、コントローラ30は、掘削反力が適切な大きさとなるよう、掘削動作中に掘削アタッチメントの姿勢を自動的に修正できる。そのため、ショベルの姿勢、挙動等が不安定になるのを防止し、バケット6の爪先の正確な位置決め制御を実現できる。
 また、コントローラ30は、通常掘削のときと深掘掘削のときとで掘削アタッチメントの姿勢の修正内容を異ならせることができる。そのため、深掘掘削のときにブーム4を強制的に上昇させることで却って掘削反力を増大させてしまうのを防止できる。
 また、コントローラ30は、バケット掘削トルクばかりでなく、ブーム掘削トルク及びアーム掘削トルクを考慮して掘削反力を算出できる。そのため、掘削反力をより高精度に導き出すことができる。
 以上、本発明の好ましい実施例について詳説した。しかしながら、本発明は、上述した実施例に制限されることはない。上述した実施例は、本発明の範囲を逸脱することなしに、種々の変形、置換等が適用され得る。また、別々に説明された特徴は、技術的な矛盾が生じない限り、組み合わせが可能である。
 例えば、上述の実施例では、不安定状態検出装置の一例としてシリンダ圧センサが採用されているが、トルクセンサ等の他のセンサが不安定状態検出装置として採用されてもよい。
 1・・・下部走行体 1A・・・左走行用油圧モータ 1B・・・右走行用油圧モータ 2・・・旋回機構 2A・・・旋回用油圧モータ 3・・・上部旋回体 4・・・ブーム 5・・・アーム 6・・・バケット 7・・・ブームシリンダ 8・・・アームシリンダ 9・・・バケットシリンダ 10・・・キャビン 11・・・エンジン 11a・・・オルタネータ 11b・・・スタータ 11c・・・水温センサ 14・・・メインポンプ 14a・・・レギュレータ 14b・・・吐出圧力センサ 14c・・・油温センサ 15・・・パイロットポンプ 15a、15b・・・パイロット圧センサ 16・・・作動油ライン 17・・・コントロールバルブ 25、25a・・・パイロットライン 26・・・操作装置 26A、26B・・・レバー 26C・・・ペダル 30・・・コントローラ 30a・・・一時記憶部 31・・・判定部 40・・・表示装置 41・・・画像表示部 42・・・入力部 70・・・蓄電池 72・・・電装品 74・・・エンジン制御装置 75・・・動作モード切替ダイヤル E1・・・制御弁 M1・・・姿勢検出装置 M1a・・・ブーム角度センサ M1b・・・アーム角度センサ M1c・・・バケット角度センサ S1、S11~S16・・・シリンダ圧センサ S2・・・車体傾斜センサ

Claims (8)

  1.  下部走行体と、
     前記下部走行体に搭載される上部旋回体と、
     前記上部旋回体に取り付けられる掘削アタッチメントと、
     前記掘削アタッチメントの姿勢を検出する姿勢検出装置と、
     掘削負荷による前記上部旋回体の不安定状態に関する情報を検出する不安定状態検出装置と、
     前記掘削アタッチメントの姿勢を修正する制御装置と、を有するショベルであって、
     前記制御装置は、前記姿勢検出装置及び前記不安定状態検出装置の出力に基づいて深掘掘削中の掘削負荷が所定値より大きいと判定した場合に、前記掘削アタッチメントを構成するアーム又はバケットを開くように構成される、
     ショベル。
  2.  前記制御装置は、少なくとも前記掘削アタッチメントを構成するブームの姿勢に基づいて深掘掘削中であるか否かを判定する、
     請求項1に記載のショベル。
  3.  前記制御装置は、前記掘削アタッチメントの姿勢と掘削負荷とに基づいて掘削反力を算出し、算出した掘削反力に基づいて掘削負荷が前記所定値より大きいか否かを判定する、
     請求項1に記載のショベル。
  4.  前記制御装置は、ブームシリンダ圧に基づいて掘削負荷が前記所定値より大きいか否かを判定する、
     請求項1に記載のショベル。
  5.  前記制御装置は、アームシリンダ圧に基づいて掘削負荷が前記所定値より大きいか否かを判定する、
     請求項1に記載のショベル。
  6.  前記制御装置は、前記上部旋回体の傾斜に基づいて掘削負荷が前記所定値より大きいか否かを判定する、
     請求項1に記載のショベル。
  7.  前記不安定状態検出装置は、車体傾斜センサを含む、
     請求項1に記載のショベル。
  8.  前記制御装置は、車体傾斜センサの出力値に応じて前記所定値を変更するように構成されている、
     請求項1に記載のショベル。
PCT/JP2017/044610 2017-12-12 2017-12-12 ショベル WO2019116451A1 (ja)

Priority Applications (5)

Application Number Priority Date Filing Date Title
PCT/JP2017/044610 WO2019116451A1 (ja) 2017-12-12 2017-12-12 ショベル
CN201780097670.1A CN111511993B (zh) 2017-12-12 2017-12-12 挖土机
KR1020207016612A KR102460502B1 (ko) 2017-12-12 2017-12-12 쇼벨
EP17934527.7A EP3725959B1 (en) 2017-12-12 2017-12-12 Excavator
US16/896,396 US11572676B2 (en) 2017-12-12 2020-06-09 Shovel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2017/044610 WO2019116451A1 (ja) 2017-12-12 2017-12-12 ショベル

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US16/896,396 Continuation US11572676B2 (en) 2017-12-12 2020-06-09 Shovel

Publications (1)

Publication Number Publication Date
WO2019116451A1 true WO2019116451A1 (ja) 2019-06-20

Family

ID=66820114

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2017/044610 WO2019116451A1 (ja) 2017-12-12 2017-12-12 ショベル

Country Status (5)

Country Link
US (1) US11572676B2 (ja)
EP (1) EP3725959B1 (ja)
KR (1) KR102460502B1 (ja)
CN (1) CN111511993B (ja)
WO (1) WO2019116451A1 (ja)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395441A (zh) * 2020-04-27 2020-07-10 徐州徐工铁路装备有限公司 一种地下铲运机智能减阻控制***及控制方法

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12024173B2 (en) * 2020-11-04 2024-07-02 Deere & Company System and method for work state estimation and control of self-propelled work vehicles
CN112922078A (zh) * 2021-03-11 2021-06-08 天津工业大学 一种带有监测与维护铲车铲臂***的铲斗

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0673761A (ja) * 1992-08-24 1994-03-15 Yanmar Diesel Engine Co Ltd 建設機械の安全装置
JPH0849265A (ja) * 1994-06-15 1996-02-20 Caterpillar Inc 自動掘削制御装置および方法
JP2002304441A (ja) * 2001-04-05 2002-10-18 Shin Caterpillar Mitsubishi Ltd 工事進捗状況管理システム、工事進捗状況データ作成方法、工事進捗状況データおよび工事進捗状況データ提供方法
JP2011252338A (ja) 2010-06-03 2011-12-15 Sumitomo Heavy Ind Ltd 建設機械
JP2014122511A (ja) * 2012-12-21 2014-07-03 Sumitomo (Shi) Construction Machinery Co Ltd ショベル及びショベル制御方法
JP2016169572A (ja) * 2015-03-13 2016-09-23 住友重機械工業株式会社 ショベル

Family Cites Families (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3104072C2 (de) * 1981-02-06 1986-07-03 O & K Orenstein & Koppel Ag, 1000 Berlin Löffelbagger
JP2916957B2 (ja) 1991-05-28 1999-07-05 株式会社小松製作所 掘削作業機の自動制御方法
JP3147479B2 (ja) 1992-03-18 2001-03-19 コベルコ建機株式会社 建設機械の自動制御装置
CN1078287C (zh) * 1997-06-20 2002-01-23 日立建机株式会社 建筑机械的范围限制挖掘控制装置
US6568898B2 (en) * 2000-05-26 2003-05-27 Komatsu Limited Hydraulic shovel with hoisting hook
US8340872B2 (en) * 2005-12-12 2012-12-25 Caterpillar Inc. Control system and method for capturing partial bucket loads in automated loading cycle
JP5238181B2 (ja) * 2007-04-17 2013-07-17 カヤバ工業株式会社 油圧ショベル
CN101605954B (zh) * 2008-01-07 2012-11-07 日立建机株式会社 双臂工程机械
JP5143858B2 (ja) * 2010-04-20 2013-02-13 住友重機械工業株式会社 建設機械
US20150275469A1 (en) * 2014-03-28 2015-10-01 Caterpillar Inc. Lift Arm and Coupler Control System
EP3418455B1 (en) * 2014-06-20 2020-04-08 Sumitomo Heavy Industries, Ltd. Shovel and control method thereof
US20140320293A1 (en) * 2014-07-08 2014-10-30 Caterpillar Inc. Operator alert and height limitation system for load carrying machines
JP6393781B2 (ja) * 2014-12-26 2018-09-19 住友建機株式会社 ショベル
CN105971050A (zh) * 2015-03-13 2016-09-28 住友重机械工业株式会社 挖掘机
FR3041922B1 (fr) * 2015-10-01 2017-11-24 Manitou Bf Systeme de modification du rapport de direction pour vehicule a bras telescopique et vehicule correspondant

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0673761A (ja) * 1992-08-24 1994-03-15 Yanmar Diesel Engine Co Ltd 建設機械の安全装置
JPH0849265A (ja) * 1994-06-15 1996-02-20 Caterpillar Inc 自動掘削制御装置および方法
JP2002304441A (ja) * 2001-04-05 2002-10-18 Shin Caterpillar Mitsubishi Ltd 工事進捗状況管理システム、工事進捗状況データ作成方法、工事進捗状況データおよび工事進捗状況データ提供方法
JP2011252338A (ja) 2010-06-03 2011-12-15 Sumitomo Heavy Ind Ltd 建設機械
JP2014122511A (ja) * 2012-12-21 2014-07-03 Sumitomo (Shi) Construction Machinery Co Ltd ショベル及びショベル制御方法
JP2016169572A (ja) * 2015-03-13 2016-09-23 住友重機械工業株式会社 ショベル

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3725959A4

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395441A (zh) * 2020-04-27 2020-07-10 徐州徐工铁路装备有限公司 一种地下铲运机智能减阻控制***及控制方法

Also Published As

Publication number Publication date
CN111511993A (zh) 2020-08-07
KR20200090804A (ko) 2020-07-29
CN111511993B (zh) 2022-06-14
EP3725959B1 (en) 2022-01-26
US20200299933A1 (en) 2020-09-24
EP3725959A1 (en) 2020-10-21
EP3725959A4 (en) 2020-12-02
US11572676B2 (en) 2023-02-07
KR102460502B1 (ko) 2022-10-27

Similar Documents

Publication Publication Date Title
JP6740025B2 (ja) ショベル
JP7387795B2 (ja) ショベル及びショベル用のシステム
EP3126581B1 (en) Hydraulic system and method for controlling an implement of a working machine
JP6606103B2 (ja) 建設機械
US8887499B2 (en) Electronic high hydraulic pressure cutoff to improve system efficiency
US11572676B2 (en) Shovel
US20180328003A1 (en) Excavator
JP6959899B2 (ja) ホイールローダ
US10590623B2 (en) Construction machine
JP6605316B2 (ja) 作業機械の駆動装置
JP6710442B2 (ja) ショベル
US20240052595A1 (en) Shovel
JP6585012B2 (ja) ショベル
JP6707053B2 (ja) 作業機械
JP2022018504A (ja) 作業機械
US12049744B2 (en) Work machine
JPWO2020065915A1 (ja) ホイールローダ
CN109689982A (zh) 工程机械
US20240068203A1 (en) Work Machine
US20240150995A1 (en) Construction Machine
JPH11201108A (ja) 建設機械の制御装置

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17934527

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 20207016612

Country of ref document: KR

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2017934527

Country of ref document: EP

Effective date: 20200713

NENP Non-entry into the national phase

Ref country code: JP