WO2011144776A1 - Incremental tunnel - Google Patents

Incremental tunnel Download PDF

Info

Publication number
WO2011144776A1
WO2011144776A1 PCT/ES2011/070099 ES2011070099W WO2011144776A1 WO 2011144776 A1 WO2011144776 A1 WO 2011144776A1 ES 2011070099 W ES2011070099 W ES 2011070099W WO 2011144776 A1 WO2011144776 A1 WO 2011144776A1
Authority
WO
WIPO (PCT)
Prior art keywords
tunnel
sections
section
pushed
successive sections
Prior art date
Application number
PCT/ES2011/070099
Other languages
Spanish (es)
French (fr)
Inventor
Fernando CARREÑO MARTINEZ
Oscar DIÉGUEZ LÓPEZ
Original Assignee
Obras Y Proyectos, Ecología Y Medio Ambiente, S.L. (Opema)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obras Y Proyectos, Ecología Y Medio Ambiente, S.L. (Opema) filed Critical Obras Y Proyectos, Ecología Y Medio Ambiente, S.L. (Opema)
Publication of WO2011144776A1 publication Critical patent/WO2011144776A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Definitions

  • the invention is comprised within the public works sector. STATE OF THE TECHNIQUE
  • tunnels are being executed by means of the so-called conventional methods, this is excavation and execution in situ of the tunnel, or by tunneling machines, machines that are excavating and at the same time placing the segments or interior cladding of reinforced concrete of the tunnel.
  • the invention is based on the execution of tunnel sections, (pieces of reinforced concrete with the appropriate shape so that once introduced into the ground, they will be the concrete lining of said tunnel) in the immediate vicinity of the final area, so that once built, by means of an oleodynamic thrust, that is to say with hydraulic cylinders, with dimensions of 200 x 350 x 500 (0 rod x 0 piston x stroke), which will work with a force of 250 t / cylinder and up to a maximum working pressure of 260 bar, operated by an electrical equipment equipped with all the necessary safety components, will be moved to their final location until the total length is completed. As we move forward it becomes necessary, logically, that with the appropriate machinery we will extract the earth or rock that is in the space that the new tunnel will occupy.
  • the invention is based on the construction of tunnel sections, which will be moved successively by means of thrust with hydraulic cylinders placed between them until reaching the total execution of the work, for which it will be necessary, to arrange between every two sections, in the area of the cylinders, of plates anchored to the section that goes ahead and that will slide over the one behind, at the time of the advance, that close this space and prevent landslides (see Figure 7: SECTIONS I or , 2 or and 3 or TUNNEL. PLANT IN ADVANCE).
  • the first vain will be different from the rest of those that will later be moved, in that the front part of it will not be straight, but will have an inclination in its gables or walls so that as the excavation occurs, the spill of the land is in line with the shape of the structure.
  • the first section will be finished off in the edge of the front part with suitable steel endings (see Figure 3: FRONT SECTIONS OF SECTION I or TUNNEL)
  • the hydraulic cylinders can suffer damages as a result of the transmitted reaction due to the push of those who immediately precede it, pieces in the form of metal cylinders with a 30 mm wall that absorb these forces will be placed between sections (see Figure 8: LAST TUNNEL SECTION. PLANT).
  • MODE OF REALIZATION The invention is that to make tunnels of moderate dimensions, it will be carried out by pushing successive sections of tunnel that will lead to the final work.
  • the tunnels tend to be made, as already mentioned above, by means of the so-called conventional methods, this is excavation and on-site execution of the tunnel, or by tunneling machines, machines that are excavating and at the same time placing the segments or interior cladding of reinforced concrete from the tunnel

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to an incremental tunnel that is built with successive tunnel sections that can vary from 10 to 30 meters in length and have the shape required by the project, and that once inserted in the ground, will form the cement liner making it possible for trains or vehicles to move easily through the tunnel. Said sections will be inserted into the ground as the cutting wheel bores through the ground with the required section.

Description

DESCRIPCIÓN  DESCRIPTION
TITULO  TITLE
Túnel empujado mediante tramos sucesivos. Tunnel pushed through successive sections.
SECTOR DE LA TÉCNICA AL QUE SE REFIERE LA INVENCIÓN:  SECTOR OF THE TECHNIQUE TO WHICH THE INVENTION REFERS:
La invención esta comprendida dentro del sector de la obra pública. ESTADO DE LA TÉCNICA  The invention is comprised within the public works sector. STATE OF THE TECHNIQUE
En la actualidad se están ejecutando túneles mediante los llamados métodos convencionales, esto es excavación y ejecución in situ del túnel, o mediante tuneladoras, máquinas que van excavando y a la vez colocando las dovelas o revestimiento interior de hormigón armado del túnel.  At present, tunnels are being executed by means of the so-called conventional methods, this is excavation and execution in situ of the tunnel, or by tunneling machines, machines that are excavating and at the same time placing the segments or interior cladding of reinforced concrete of the tunnel.
Este tipo de tareas, sobre todo en el caso de tuneladoras, tienen una aplicación interesante para grandes longitudes debido al elevado coste de la maquinaria requerida.  These types of tasks, especially in the case of TBMs, have an interesting application for large lengths due to the high cost of the required machinery.
Es por esto que se inventa una nueva forma de construir túneles, que no requiera inversiones tan altas y que sea mas eficaz y eficiente para la ejecución de estas obras con dimensiones moderadas, y que denominaremos túnel empujado mediante tramos sucesivos.  That is why a new way of building tunnels is invented, which does not require such high investments and is more efficient and efficient for the execution of these works with moderate dimensions, and which we will call a tunnel pushed through successive sections.
EXPLICACIÓN DE LA INVENCIÓN EXPLANATION OF THE INVENTION
La invención se basa en la ejecución de tramos de túnel, (piezas de hormigón armado con la forma apropiada para que una vez introducidos en el terreno, serán el revestimiento de hormigón de dicho túnel) en las inmediaciones de la zona definitiva, de manera que una vez construidos, mediante empuje oleodinámico, es decir con cilindros hidráulicos, con dimensiones de 200 x 350 x 500 (0 vástago x 0 pistón x carrera), que trabajarán con una fuerza de 250 t/cilindro y hasta una presión máxima de trabajo de 260 bar, maniobrados por un equipo eléctrico dotado de todos los componentes de seguridad necesarios, se trasladarán hasta su ubicación final hasta completar la longitud total. A medida que avanzamos se hace preciso, lógicamente, que con la maquinaria apropiada vayamos extrayendo las tierras o roca que se hayan en el espacio que va a ocupar el nuevo túnel. Para esto se construyen uno a continuación de otro, los tramos que se pueda dependiendo del espacio que en cada caso se disponga, con una separación entre ellos que permita la interposición de baterías de cilindros hidráulicos que serán los que empujen para la traslación de los mismos (ver Figura n° 4: TRAMOS Io, 2o Y 3o DE TUNEL. SECCIÓN LONGITUDINAL y Figura n° 5: TRAMOS Io, 2o Y 3o DE TUNEL. PLANTA). The invention is based on the execution of tunnel sections, (pieces of reinforced concrete with the appropriate shape so that once introduced into the ground, they will be the concrete lining of said tunnel) in the immediate vicinity of the final area, so that once built, by means of an oleodynamic thrust, that is to say with hydraulic cylinders, with dimensions of 200 x 350 x 500 (0 rod x 0 piston x stroke), which will work with a force of 250 t / cylinder and up to a maximum working pressure of 260 bar, operated by an electrical equipment equipped with all the necessary safety components, will be moved to their final location until the total length is completed. As we move forward it becomes necessary, logically, that with the appropriate machinery we will extract the earth or rock that is in the space that the new tunnel will occupy. For this purpose, the following sections are constructed, depending on the space that is available in each case, with a separation between them that allows the interposition of hydraulic cylinder batteries that will be the ones that push them to move them (See Figure 4: SECTIONS I o , 2 o Y 3 o OF TUNNEL. LONGITUDINAL SECTION and Figure n ° 5: SECTIONS I o , 2 o Y 3 o OF TUNNEL. PLANT).
Cuando se ha agotado todo el espacio disponible para construir tramos seguidos, y al lado del último, se ejecutará otro tramo paralelo a este, de tal manera que cuando los anteriores avancen, se desplace lateralmente hasta ocupar la posición que en su ubicación inicial ocupaba el ultimo construido de forma seguida, dejando sitio para ejecutar otro y así de forma sucesiva hasta que se realicen los necesarios para completar la longitud del túnel a (ver Figura n° 5: TRAMOS Io, 2o Y 3o DE TUNEL. PLANTA). When all the available space to build consecutive sections has been exhausted, and next to the last one, another section parallel to it will be executed, so that when the previous ones advance, it moves laterally until it occupies the position that in its initial location occupied the The last one was built in a row, leaving room to execute another and so on until the necessary ones are completed to complete the length of the tunnel a (see Figure 5: SECTIONS I o , 2 o Y 3 o DE TUNEL. PLANT) .
Como decimos, la invención se basa en la construcción de tramos de túnel, que se desplazarán sucesivamente mediante empuje con cilindros hidráulicos colocados entre ellos hasta llegar a la ejecución total de la obra, para lo que será necesario, disponer entre cada dos tramos, en la zona de los cilindros, de chapas ancladas al tramo que va delante y que deslizarán sobre el de detrás, en el momento del avance, que cierren este espacio e impidan desmoronamientos del terreno (ver Figura n° 7: TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA EN AVANCE). As we say, the invention is based on the construction of tunnel sections, which will be moved successively by means of thrust with hydraulic cylinders placed between them until reaching the total execution of the work, for which it will be necessary, to arrange between every two sections, in the area of the cylinders, of plates anchored to the section that goes ahead and that will slide over the one behind, at the time of the advance, that close this space and prevent landslides (see Figure 7: SECTIONS I or , 2 or and 3 or TUNNEL. PLANT IN ADVANCE).
Asimismo destacar que el vano primero se diferenciará del resto de los que posteriormente se trasladarán, en que la parte frontal del mismo no será recta, sino que tendrá una inclinación en sus hastíales o paredes para que a medida que se produzca la excavación, el derrame del terreno esté en consonancia con la forma de la estructura. Also note that the first vain will be different from the rest of those that will later be moved, in that the front part of it will not be straight, but will have an inclination in its gables or walls so that as the excavation occurs, the spill of the land is in line with the shape of the structure.
(ver Figura n° 1 : TRAMO Io DE TUNEL. SECCIÓN LONGITUDINAL y Figura n° 2: TRAMO Io DE TUNEL. PLANTA). (See Figure 1: SECTION I or TUNNEL. LONGITUDINAL SECTION and Figure 2: SECTION I or TUNNEL. PLANT).
A su vez y para controlar que los desplazamientos horizontales y verticales sean los deseados, el primer tramo estará rematado en el borde de la parte frontal con terminaciones adecuadas en acero (ver Figura n° 3: REMATES FRONTALES DE TRAMO Io DE TUNEL) Por otro lado, y para evitar que en la traslación, los cilindros hidráulicos puedan sufrir daños como consecuencia de la reacción transmitida por el empuje de los que inmediatamente le preceden, se colocarán entre tramos piezas con forma de cilindros metálicos con pared de 30 mm que absorban estos esfuerzos (ver Figura n° 8: TRAMO ÚLTIMO DE TÚNEL. PLANTA). In turn and to control that the horizontal and vertical displacements are the desired ones, the first section will be finished off in the edge of the front part with suitable steel endings (see Figure 3: FRONT SECTIONS OF SECTION I or TUNNEL) On the other hand, and to avoid that in the translation, the hydraulic cylinders can suffer damages as a result of the transmitted reaction due to the push of those who immediately precede it, pieces in the form of metal cylinders with a 30 mm wall that absorb these forces will be placed between sections (see Figure 8: LAST TUNNEL SECTION. PLANT).
Para empujar el ultimo de los tramos que se ha construido de forma seguida, así como los que se desplazarán lateralmente, se dispondrá, para absorber la reacción ejercida en el empuje de los mismos, de sendos muros de reacción de hormigón armado a los que se trasladarán los esfuerzos (ver Figura n° 4: TRAMOS Io, 2o Y 3o DE TUNEL. SECCIÓN LONGITUDINAL y Figura n° 5: TRAMOS Io, 2o Y 3o DE TUNEL. PLANTA) To push the last of the sections that have been built in a row, as well as those that will move laterally, it will be arranged, to absorb the reaction exerted in the thrust thereof, of two concrete reaction walls of reinforced concrete to which efforts will be taken (see Figure 4: TRAMOS I or 2 or 3 or TUNNEL aND longitudinal section and Figure 5. TRAMOS I or 2 or 3 or TUNNEL aND PLANT.)
DESCRIPCIÓN DE LOS DIBUJOS DESCRIPTION OF THE DRAWINGS
Para complementar la descripción que se está realizando y al objeto de ayudar a una mejor comprensión de las características del invento, acompaña a la presente memoria descriptiva, como parte integrante de la misma ocho hojas de planos en las cuales con carácter ilustrativo y no limitativo, se ha representado lo siguiente:  To complement the description that is being made and in order to help a better understanding of the characteristics of the invention, it accompanies this descriptive report, as an integral part of it, eight sheets of plans in which with an illustrative and non-limiting nature, The following has been represented:
Figura n° l TRAMO Io DE TÚNEL. SECCIÓN LONGITUDINAL Figure n ° SECTION I or TUNNEL. LONGITUDINAL SECTION
Figura n° 2 TRAMO Io DE TÚNEL. PLANTA Figure 2 SECTION I or TUNNEL. PLANT
Figura n° 3 REMATES FRONTALES DE TRAMO Io DE TÚNEL Figura n° 4 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL Figure n ° 3 FRONT REMITTES OF SECTION I or TUNNEL Figure n ° 4 SECTIONS I o , 2 or Y 3 or TUNNEL. LONGITUDINAL SECTION
Figura n0 5 TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA Figure n 0 5 SECTIONS I o , 2 o Y 3 o DE TUNNEL. PLANT
Figura n° 6 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL EN AVANCE Figure 6 SECTIONS I o , 2 o Y 3 o DE TUNNEL. LONGITUDINAL SECTION IN PROGRESS
Figura n° 7 TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA EN AVANCE Figure n ° 7 SECTIONS I o , 2 o Y 3 o DE TUNNEL. PLANT IN PROGRESS
Figura n° 8 TRAMO ÚLTIMO DE TÚNEL. PLANTA  Figure n ° 8 LAST TUNNEL SECTION. PLANT
MODO DE REALIZACIÓN La invención consiste en que para realizar túneles de dimensiones moderadas, se llevará a cabo mediante el empuje de sucesivos tramos de túnel que darán lugar a la obra final. MODE OF REALIZATION The invention is that to make tunnels of moderate dimensions, it will be carried out by pushing successive sections of tunnel that will lead to the final work.
El procedimiento de ejecución será como sigue: The execution procedure will be as follows:
Fase A Phase A
Ejecución del primer tramo de túnel sobre una solera de hormigón armado que servirá de apoyo y entre unos muretes guía que impedirán los desplazamientos transversales indeseados en el avance, en las inmediaciones de la ladera o montaña donde se va a ejecutar la obra, que será diferente, según se ha mencionado, al resto de los tramos (ver Figura n° 1 TRAMO Io DE TÚNEL. SECCIÓN LONGITUDINAL y Figura n° 2 TRAMO Io DE TÚNEL. PLANTA). Fase B Execution of the first section of tunnel over a reinforced concrete slab that will serve as support and between some guide walls that will prevent unwanted transverse displacements in the advance, in the immediate vicinity of the slope or mountain where the work will be executed, which will be different , as mentioned, to the rest of the sections (see Figure 1 SECTION I or TUNNEL. LONGITUDINAL SECTION and Figure 2 SECTION I or TUNNEL. PLANT). Phase B
Ejecución de los tramos de túnel seguidos al primero sobre solera de hormigón armado y entre muretes guía al igual que este, que la zona de trabajo permita, con una separación entre ellos para la interposición de una batería de cilindros hidráulicos que se encargará de transmitir los esfuerzos necesarios para el desplazamiento de los tramos (ver Figura n° 4 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL y Figura n° 5 TRAMOS Io, 2o Y 3o Execution of the tunnel sections followed by the first on reinforced concrete floor and between guide walls as well as this one, that the work area allows, with a separation between them for the interposition of a battery of hydraulic cylinders that will be responsible for transmitting the effort required for moving the sections (see Figure 4 RUNS I or 2 or 3 or Y TUNNEL. LONGITUDINAL SECTION and Figure 5 RUNS I or 2 or 3 or Y
DE TÚNEL. PLANTA). OF TUNNEL. PLANT).
Fase C C phase
Ejecución del muro de reacción detrás del último tramo, que permita absorber los esfuerzos transmitidos por la batería de cilindros hidráulicos de este último tramo (ver Figura n° 4 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL y Figura n° 5 TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA). Execution of the reaction wall behind the last section, which allows the forces transmitted by the battery of hydraulic cylinders of this last section to be absorbed (see Figure 4 SECTIONS I o , 2 or Y 3 or TUNNEL. LONGITUDINAL SECTION and Figure n ° 5 SECTIONS I o , 2 o Y 3 o TUNNEL. PLANT).
Fase D Phase D
Ejecución de un tramo de túnel paralelo al ultimo seguido con su muro de reacción correspondiente, en caso de ser necesario, para que una vez trasladados todos los anteriores que están enfrentados entre si, pueda desplazarse este lateralmente hasta ocupar el sitio del ultimo seguido, y así continuar empujando tramos (ver Figura n° 5 TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA). Fase E Execution of a tunnel section parallel to the last one followed with its corresponding reaction wall, if necessary, so that once all the previous ones that are facing each other have been moved, it can move laterally until it occupies the site of the last one followed, and thus continue pushing sections (see Figure n ° 5 SECTIONS I o , 2 o Y 3 o TUNNEL. PLANT). E phase
Colocación de las baterías de cilindros hidráulicos entre tramos y de las piezas cilindricas que aguantarán la reacción del empuje del tramo que le precede (ver Figura n° 4 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL, Figura n° 5 TRAMOS Io, 2o Y 3o DE TÚNEL. PLANTA y Figura n° 6 TRAMOS Io, 2o Y 3o DE TÚNEL. SECCIÓN LONGITUDINAL EN AVANCE). Inserting batteries hydraulic cylinders between sections and the cylindrical parts that will endure the reaction thrust portion preceding it (see Figure 4 RUNS I or 2 or Y 3 or TUNNEL. SECTION LONGITUDINAL, Fig.5 SECTIONS I o , 2 o Y 3 o TUNNEL PLANT and Figure n ° 6 SECTIONS I o , 2 o Y 3 o TUNNEL. LONGITUDINAL SECTION IN PROGRESS).
Fase F Phase F
Empuje del primer tamo de túnel el recorrido de los cilindros hidráulicos, recogerlos y empuje del que le sigue repitiendo la operación en todos los tramos seguidos.  Push the route of the hydraulic cylinders from the first tunnel tunnel, pick them up and push the one that continues to repeat the operation in all the sections in a row.
Fase G G phase
Interposición entre el último tramo y el muro de reacción construido detrás de este, de vigas fabricadas a tal efecto (ver Figura n° 0 8 TRAMO ÚLTIMO DE TÚNEL. PLANTA), que permitan cubrir el hueco que a medida que se avanza va quedando entre estos, y sirvan de apoyo de los cilindros para el avance. Esta operación se realizará hasta que este avance sea el suficiente para que quede hueco a fin de trasladar lateralmente el tramo paralelo al último y que previamente ya se había ejecutado, para lo que se retirarán estas vigas que habían ido colocando. Interposition between the last section and the reaction wall built behind it, of beams manufactured for this purpose (see Figure 0 8 LAST TUNNEL SECTION. PLANT), which allow to cover the gap that as it progresses between these, and serve as support of the cylinders for the advance. This operation will be carried out until this advance is sufficient so that it is hollow in order to laterally move the section parallel to the last one and which had previously been executed, for which these beams that had been placed will be removed.
Fase H H phase
Fabricar otro tramo en la zona que ha quedado libre al desplazar el tramo lateral hasta colocarlo alineado con los anteriores.  Make another section in the area that has been free when moving the side section until it is aligned with the previous ones.
Fase I Phase I
Repetir estas operaciones las veces que sean necesarias hasta cubrir con tramos la longitud de túnel que se necesite en cada caso.  Repeat these operations as many times as necessary to cover the length of tunnel needed in each case.
APLICACIÓN INDUSTRIAL INDUSTRIAL APPLICATION
La necesidad de cruzar mediante un túnel una montaña, montículo o cordillera para construcción de nuevas carreteras o ferrocarriles, ha planteado desde un principio problemas que a lo largo del tiempo se han resuelto de acuerdo al desarrollo técnico.  The need to cross through a tunnel a mountain, mound or mountain range for the construction of new roads or railways, has raised from the outset problems that over time have been resolved according to technical development.
La premisa fundamental ha sido y es, la necesidad de ejecutar los trabajos con seguridad y fiabilidad, y de ahí han partido todas las soluciones. The fundamental premise has been and is the need to carry out the work safely and reliably, and from there all the solutions
Actualmente se tiende a realizar los túneles, como ya se mencionó anteriormente, mediante los llamados métodos convencionales, esto es excavación y ejecución in situ del túnel, o mediante tuneladoras, máquinas que van excavando y a la vez colocando las dovelas o revestimiento interior de hormigón armado del túnel.  Currently, the tunnels tend to be made, as already mentioned above, by means of the so-called conventional methods, this is excavation and on-site execution of the tunnel, or by tunneling machines, machines that are excavating and at the same time placing the segments or interior cladding of reinforced concrete from the tunnel
Nuestra invención trata de ejecutar estos trabajos de una forma mas eficaz y eficiente para túneles con dimensiones moderadas reduciendo costes. Our invention tries to execute these works in a more effective and efficient way for tunnels with moderate dimensions reducing costs.

Claims

REIVINDICACIONES
Túnel empujado mediante tramos sucesivos se caracteriza en la ejecución de tramos de túnel en las inmediaciones de la zona definitiva, de manera que una vez construidos, mediante empuje oleodinámico, es decir con cilindros hidráulicos, con dimensiones de 200 x 350 x 500 (0 vástago x 0 pistón x carrera), que trabajarán con una fuerza de 250 t/cilindro y hasta una presión máxima de trabajo de 260 bar, maniobrados por un equipo eléctrico, se empujarán trasladarán a su ubicación final hasta completar la totalidad del túnel a llevar a cabo.  Tunnel pushed by successive sections is characterized in the execution of tunnel sections in the immediate vicinity of the definitive area, so that once built, by means of an oleodynamic thrust, that is, with hydraulic cylinders, with dimensions of 200 x 350 x 500 (0 rod x 0 piston x stroke), which will work with a force of 250 t / cylinder and up to a maximum working pressure of 260 bar, maneuvered by an electrical equipment, will be moved to its final location until the entire tunnel to be taken is completed. cape.
Túnel empujado mediante tramos sucesivos, según reivindicación 1 se caracteriza en se construyen uno a continuación de otro, los tramos de túnel que se pueda dependiendo del espacio que en cada caso se disponga, con una separación entre ellos que permita la interposición de baterías de cilindros hidráulicos que serán los que empujen para la traslación de los mismos.  Tunnel pushed by successive sections, according to claim 1, is characterized in that one builds next to each other, the tunnel sections that can be depending on the space that is available in each case, with a separation between them that allows the interposition of cylinder batteries hydraulics that will be the ones that push for the translation of the same.
Túnel empujado mediante tramos sucesivos, según reivindicaciones 1 y 2 se caracteriza en que cuando se ha agotado todo el espacio disponible para construir tramos seguidos, y al lado del último, se ejecutará otro tramo paralelo a este, de tal manera que cuando los anteriores avancen, se desplace lateralmente hasta ocupar la posición que en su ubicación inicial ocupaba el ultimo construido de forma seguida, dejando sitio para ejecutar otro y así de forma sucesiva hasta que se realicen los necesarios para completar la longitud del túnel.  Tunnel pushed by successive sections, according to claims 1 and 2, is characterized in that when all the available space to build consecutive sections has been exhausted, and next to the last one, another section parallel to this one will be executed, so that when the previous ones advance , move laterally until occupying the position that in its initial location occupied the last one built in a row, leaving room to execute another and so on until the necessary ones are completed to complete the length of the tunnel.
Túnel empujado mediante tramos sucesivos, según reivindicaciones 1 , 2 y 3 se caracteriza en que entre cada dos tramos, en la zona de los cilindros, se dispondrá de chapas ancladas al tramo que va delante y que deslizarán sobre el de detrás, en el momento del avance, que cierren este espacio e impidan desmoronamientos del terreno.  Tunnel pushed by successive sections, according to claims 1, 2 and 3, is characterized in that between each two sections, in the area of the cylinders, there will be sheets anchored to the section that goes ahead and that will slide over the one behind, at the moment of the advance, to close this space and prevent landslides.
Túnel empujado mediante tramos sucesivos, según reivindicaciones 1 , 2, 3 y 4 se caracteriza en que el vano primero se diferenciará del resto de los que posteriormente se trasladarán, en que la parte frontal  Tunnel pushed by successive sections, according to claims 1, 2, 3 and 4, is characterized in that the first opening will be different from the rest of those that will later be moved, in that the front part
HOJA DE REEMPLAZO (REGLA 26) del mismo no será recta, sino que tendrá una inclinación en sus hastíales o paredes para que a medida que se produzca la excavación, el derrame del terreno esté en consonancia con la forma de la estructura. REPLACEMENT SHEET (RULE 26) it will not be straight, but it will have an inclination in its gables or walls so that as the excavation occurs, the spill of the land is in line with the shape of the structure.
6. Túnel empujado mediante tramos sucesivos, según reivindicaciones 1 , 2, 3, 4 y 5 se caracteriza en que para controlar que los desplazamientos horizontales y verticales sean los deseados, el primer tramo estará rematado en el borde de la parte frontal con terminaciones adecuadas en acero.  6. Tunnel pushed by successive sections, according to claims 1, 2, 3, 4 and 5, characterized in that in order to control that the horizontal and vertical displacements are the desired ones, the first section will be finished off at the edge of the front part with suitable terminations in steel
HOJA DE REEMPLAZO (REGLA 26) REPLACEMENT SHEET (RULE 26)
PCT/ES2011/070099 2010-05-19 2011-02-14 Incremental tunnel WO2011144776A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
ESP201000645 2010-05-19
ES201000645A ES2370621B1 (en) 2010-05-19 2010-05-19 TUNNEL PUSHED BY SUCCESSIVE SECTIONS.

Publications (1)

Publication Number Publication Date
WO2011144776A1 true WO2011144776A1 (en) 2011-11-24

Family

ID=44991222

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/ES2011/070099 WO2011144776A1 (en) 2010-05-19 2011-02-14 Incremental tunnel

Country Status (2)

Country Link
ES (1) ES2370621B1 (en)
WO (1) WO2011144776A1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1463632A (en) * 1975-01-10 1977-02-02 Genton J C Method of positioning and underpass below another roadway by hydraulic drive-through and the constructive work obtained thereby
US4095435A (en) * 1975-04-08 1978-06-20 Koichi Uemura Method of advancing a plurality of longitudinally arranged movable constructional units forwardly successively in a self-running manner and apparatus for performing same
GB2185277A (en) * 1985-12-04 1987-07-15 Barrett Jack Eric Improvements in and relating to inserting tubular members into the ground
WO1998049425A1 (en) * 1997-04-30 1998-11-05 Bilfinger + Berger Bauaktiengesellschaft Method for building a tunnel under an existing construction
EP1712734A1 (en) * 2005-04-11 2006-10-18 P&P Patent Development SA Method and apparatus for the construction of underpasses to cross railway lines with one or more tracks

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1463632A (en) * 1975-01-10 1977-02-02 Genton J C Method of positioning and underpass below another roadway by hydraulic drive-through and the constructive work obtained thereby
US4095435A (en) * 1975-04-08 1978-06-20 Koichi Uemura Method of advancing a plurality of longitudinally arranged movable constructional units forwardly successively in a self-running manner and apparatus for performing same
GB2185277A (en) * 1985-12-04 1987-07-15 Barrett Jack Eric Improvements in and relating to inserting tubular members into the ground
WO1998049425A1 (en) * 1997-04-30 1998-11-05 Bilfinger + Berger Bauaktiengesellschaft Method for building a tunnel under an existing construction
EP1712734A1 (en) * 2005-04-11 2006-10-18 P&P Patent Development SA Method and apparatus for the construction of underpasses to cross railway lines with one or more tracks

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
DATABASE WPI Derwent World Patents Index; AN 1977-A9615Y *
DATABASE WPI Derwent World Patents Index; AN 1998-584706 *

Also Published As

Publication number Publication date
ES2370621A1 (en) 2011-12-21
ES2370621B1 (en) 2012-10-26

Similar Documents

Publication Publication Date Title
US11739639B2 (en) Composite support structure, construction system, and method
ES2742818T3 (en) Procedure for the construction of cross passages in double duct tunnels
JP4958035B2 (en) Shield roof construction method
US7766579B2 (en) Process and device for building a tunnel immersed on a sub-sea soil
CN104863597A (en) Transverse tunnel cover method for shallow-buried underground excavation large underground space construction
JP2006322222A (en) Construction method of large-sectional tunnel
RU2012140916A (en) THREE-WATER COLUMN TYPE METRO STATION AND METHODS OF ITS ESTABLISHMENT (DEVICE AND METHODS OF YURKEVICH P.B.)
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
CN104929649A (en) Tunnel transverse cave-to-master cave top brushing construction method and top brushing structure
CN104712342A (en) Method of providing working plane for station expanding excavation construction in large-diameter shield tunnel
ES2253794T3 (en) PROCEDURE TO WIDEN ROADS, HIGHWAYS OR TUNNELS OF VIA FERREA, WITHOUT NEED TO INTERRUPT THE TRAFFIC.
KR20130058193A (en) Method for constructing largesection tunnel and largesection tunnel
WO2011144776A1 (en) Incremental tunnel
DE102007014104B4 (en) Method for expanding a tunnel and apparatus for carrying out the method
CN202192411U (en) Quick timbering type reinforcing mesh installation device for tunnel boring machine
ES2393760B1 (en) TUNNEL PUSHED BY SUCCESSIVE SECTIONS.
EP0257652B1 (en) Method of and device for driving a coal winning gallery partly in the footwall of a seam
CN108979641B (en) Construction method for underground structure
CN110145314A (en) A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed
WO2012017314A4 (en) Closed trench tunnels
JP6307119B2 (en) Installation method of lining plate or protective work with square steel pipe
Lunardi Widening the load at Nazzano.(Focus On Refurbishment)
TW201239188A (en) A method and equipment for tunnelling
KR101181094B1 (en) The lead container to build the tunnel which uses the container
KR102608601B1 (en) Sheet non excavation method for drilling a tunnel having a file reinforcing structure

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11783109

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 11783109

Country of ref document: EP

Kind code of ref document: A1