US3521565A US738475A US3521565DA US3521565A US 3521565 A US3521565 A US 3521565A US 738475 A US738475 A US 738475A US 3521565D A US3521565D A US 3521565DA US 3521565 A US3521565 A US 3521565A
Authority
US
United States
Prior art keywords
track
rails
new
ties
old
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US738475A
Other languages
English (en)
Inventor
Franz Plasser
Josef Theurer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Franz Plasser Bahnbaumaschinen Industrie GmbH
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US3521565A publication Critical patent/US3521565A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/05Transporting, laying, removing, or renewing both rails and sleepers

Definitions

  • the present invention relates to the continuously progressing replacement of old track by new track by means of a train moving along a right of way consisting of a section of old track, a section of new track and an intermediate section wherein the old track is replaced by the new track.
  • the replacement preferably includes not only the two track rails but also the ties whereon the rails are supported.
  • Track replacement trains running on the regular track gage are known, and such apparatus has been disclosed, for instance, in our US. Pat. No. 3,330,219.
  • the track rails are spread apart to permit the old ties to be removed and the new ties to be laid, and this has caused undesirable stresses in the rails, such stresses being particularly great in track curves where the outer rail is longer than the inner rail, and also due to temperature changes.
  • known methods and apparatus of this type involved considerable wear and tear on the rails due to the mechanical handling of the same during the operation.
  • the rails are supported on the train with a minimum of friction as the train moves in relation to the rails so that stresses are held to a minimum even when the course of the rails changes in relation to the track axis, for instance when the rails are spread, or in track curves or under conditions of temperature changes.
  • the new rails and the old rails are transported and supported on a plurality of cars in the forward and rear train section, respectively, the new rails being pulled off the forward train section in the intermediate section of the right of Way by the continuous forward movement of the train, and the old rails being pushed onto the rear section of the train behind the intermediate section.
  • the rails of the old and new track sections do not move in realtion to the ballast bed but only in relation to the moving train. If the friction of the rails on the supports is minimal, their wear and tear during the entire replacement operation is also minimal.
  • the rails of the old and new track are spread apart in the intermediate section on a horizontal plane to a lateral spacing at least equal to the length of the ties so that the old ties may be removed and the new ties replaced perpendicularly to the track axis between the spread rails.
  • the rails are spread apart for a distance beyond the intermediate section on the track cars in the forward and rear train sections adjacent the intermediate section.
  • this point is in front of the cars arranged to receive the old ties in the direction of movement of the train.
  • FIGS. 1 and 2 are schematic top views of the entire arrangement, the views being separated into two figures merely for the sake of convenience to avoid showing the various parts of the rather long arrangement on too small a scale, FIG. 1 showing the forward portion in the direction of movement of the apparatus, as indicated by the arrow, while FIG. 2 illustrates the rear portion, the two portions being contiguous along lines '1 and II of the figures;
  • FIGS. 3 and 5 are schematic side views, on an enlarged scale, of the track replacement section III-VI of FIG. 1, the views being separated into two figures merely for the sake of convenience, FIG. 3 showing the forward portion and FIG. 5 the rear portion, the two portions being contiguous along lines V and -III of the figures;
  • FIGS. 4 and 6 are respective top views of FIGS. 3 and 5, the two portions being contiguous along lines VI and IV of the figures;
  • FIG. 7 shows a detail of an apparatus for placing the ties.
  • the horizontal arrows indicate the direction of movement of the apparatus along the right of way during the track renewal operation.
  • This apparatus moves continuously in the direction of the arrows at an approximate speed of about three to five meters per minute, and consists of a train including a forward locomotive 1 and a rear locomotive 1' which pull, respectively push, the train along the track.
  • Seven flat freight cars 2 carry the rail sections for the new rails to be laid, followed by a work car 3 on which the rail sections are connected to form continuous rails.
  • rail sections are delivered in lengths of about 120 meters, and these sections are welded together on car 3 to form the two continuous rails of the new track.
  • the work car 3 is followed by six fiat freight cars 4 which carry the old ties previously removed from the right of way, and a loading car 5 for the old ties precedes the track replacement section IIIVI.
  • This section is about 60 to 70 meters long and constitutes the actual track renewal or replacement section wherein the old rails are removed and new rails are laid and, preferably, new ties are substituted for the old ties.
  • new rails 10 are shown in full lines while the old rails 11 are indicated in chain-dotted lines.
  • new rails or ties refers only to the fact that they form part of a newly laid track and that such replacement rails and/or ties may, in fact, be used and restored parts.
  • FIG. 3 shows the last car 4 of the train carrying the old ties, with the loading car 5 for the old ties being coupled thereto, the description proceeding opposite to the direction of movement of the apparatus as indicated by the horizontal arrows.
  • the locomotive 1, the freight cars 2 and 4, the work car 3 and the loading car 5 all run on wheels on the existing track rails 11 which are replaced in section IIIVI by the new track rails 10.
  • the loading cars 6, 6, the freight cars 7, work car 8, freight cars 9 and locomotive 1' run on wheels on the new track.
  • Track 13 for a trolley crane 14 are provided on the platforms of flat cars 4 and 5.
  • the crane has an outrigger or pivotal boom to take old ties collected and stacked in a bin 15, and to stack these old ties on the cars 4, loading first the front car and successive cars thereafter as the replacement operation proceeds.
  • the old ties are picked up from the ballast by a fork lift truck 16 which collects several ties at a time and places them on a conveyor 17 which continuously moves the old ties into the bin on car 5 whence the crane 14 removes them for subsequent storage on freight cars 4.
  • the conveyor has suitable entrainment elements for the ties and is mounted on a carrier 17' which is pivotally coupled to the loading car 5.
  • the free end of the conveyor carrier rests on a full-track vehicle 18 which moves on the ballast 22. No track is in position between cars 5 and 6 of the apparatus so that all vehicles operating in this section must be equipped with means for running on the ballast, such as full or half tracks, wheels with pneumatic tires, or the like.
  • each side of freight cars 4, loading car 5 and conveyor carrier 17 are a series of guide rollers 19 spaced apart along the right of way for support of the welded new track rails 10.
  • a series of such guide rollers 19 are similarly mounted on the conveyor carrier 17' and the succeeding vehicles including freight cars 7, the distance of these guide rollers from the ballast gradually increasing from carrier 17 backwards so that the guide rollers will pick up the old track rails 11 underneath the conveyor 17 (see FIG. 3) from old ties 12 and lift them to a desired height as the apparatus slowly and continuously moves along the right of 'way.
  • the permanent track bolts holding the rack rails on the ties are removed or loosened and the rails are provisionally held in position at points spaced about five to ten meters apart, which will. be perfectly safe since the apparatus moves at very slow speed during the track replacement. Lifting of the old rails from the support platelets on the ties will be facilitated by mounting a vibrator 20 on car 5, which will glide over the surface of the ties.
  • the guide rollers 19 on cars 4 and 5, conveyor carrier 17 and fork lift truck 16 will slowly move the welded new track rails 10 into thetrack renewal section IIIVI, the old rails 11 and the new rails 10 being at the same horizontal level or distance from the ballast at the guide rollers 19 on fork lift truck 16, as seen in FIG. 3.
  • the track rails do not move in relation to the ballast but only in relation to the continuously moving apparatus.
  • the old and new track rails actually remain stationary in the direction of track elongation during the entire renewal operation in section IIIVI. They are laterally spaced from the track rails on the ballast during the replacement operation. During this operation (see FIG.
  • the old and new track rails are spread apart by the guide rollers 19 to a distance equal at least to the length of the ties so that the old ties may be removed and new ties laid between the spread track rails perpendicularly to the elongation of the track.
  • the new rails are laid on new ties, the old ties as well as the old rails being removed.
  • a ballast leveling vehicle 21 follows the fork lift truck 16 to level the surface of the ballast and thus to prepare it properly for the new track. This may be followed further by a tamping vehicle 25 carrying surface tampers 24 for compacting the leveled ballast before the new ties are laid. Vehicles 21 and 25 also carry quide rollers 19 for the track rails, as do the succeeding cars 6, 6', 7 for guiding the old track rails 11 in a manner similar to the manner in which the guide rollers on the front portion of the apparatus carry new rails 10.
  • a track 13' for loading cranes 28 interconnects the flat cars 7 carrying the new ties with the loading cars 6, 6'.
  • the loading car 6 carries an outrigger 26 which is pivotally mounted above the section of the right of way where the new ties are to be laid and suspended by ropes or struts 26.
  • a trolley 27 runs on the outrigger and receives new ties 23 from cranes 28 which run on track 13' in the direction of the small arrows shown in FIG. 5. Groups of new ties 23- are transferred from trolley 27 to the small carriage 29 underneath the overhanging end of outrigger 26, whence the new ties are laid out on the ballast ready to receive the new track rails.
  • the carriage 29 is coupled to the preceding ballast tamping vehicle 25 by means of an hydraulically adjustable coupling 30 so that the distance between vehicle 25 and carriage 29 may be changed. While the apparatus is moved from one work location to another, the carriage 29 may be lifted by trolley 27 and transported on car 6. As shown in chaindotted lines in FIG. 6; the pivotal mounting of outrigger 26 makes it possible to proceed without difliculty in track curves with a radius up to 200 In.
  • the new track rails 10 carried by guide rollers 19 are gradually lowered ontothe new ties 23 under the outrigger 26 as best seen in FIG. 5, the new rails being released from the guide rollers at the outer end of the outrigger 26.
  • a gliding or rolling lining device 31 at the forward end of car 6 serves to align the new ties properly in respect of the track axis and the new track rails are first only provisionally secured to the new ties, at an approximate spacing of about 5 to 10 m.
  • the old track rails are guided upwardly 01f the ballast bed by a series of guide rollers 19 on cars 7 until they reach the work car 8 on which the rolled rails are cut into sections of about 120 m. lengths for transport on cars 9.
  • FIG. 7 schematically illustrates an apparatus on carriage 29 for placing the new ties on the ballast bed.
  • a suitable tie gripping implement 32 has a series of the tie gripping elements, which may be operated mechanically, pneumatically or magnetically, for instance, to seize a group of adjacent ties 23, for instance six, and to place three of these ties on the ballast bed 22, as shown in full lines at the right of FIG. 7, the lug 33 of gripping implement 32 automatically providing the proper spacing from the last-laid new tie 23' of the preceding group of ties.
  • the tie gripping implement is then raised with the remaining three ties of the group, as shown in full lines in FIG. 7, pushed forwardly in the direction of the arrow, and lowered onto the ballast bed, as shown in chaindotted lines.
  • a second stop 34 then provides the proper spacing from the forward tie 23 of the three ties just laid.
  • An apparatus for replacing an old track by a new track consisting of two rails supported on ties comprising a train including a plurality of cars for movement along a right of way consisting of a section of old track, a section of new track and an intermediate section wherein the old track is replaced by the new track, said train consisting of a forward section moving on the old track rails and a rear section moving on the new track rails, the cars of the forward train section transporting and supporting the rails of the new track and the rails of the new track being laid in said intermediate section as the train moves, and the cars of the rear train section transporting and supporting the rails of the old track and the rails of the old track being pushed onto the cars of the rear train section as the train moves.
  • the forward train section also includes cars receiving and transporting the ties of the old track section
  • the rear train section also includes cars transporting and placing the ties of the new track section in said intermediate section of the right of way, said tie transporting cars being between the intermediate section and the rail transport cars.
  • the apparatus of claim 2 further comprising means for loading and conveying the ties, as well as for positioning the new ties.
  • the positioning means for the new ties includes a car adjacent the intermediate section, and a laterally pivotal outrigger mounted on the latter car and extending over said intermediate section.
  • the apparatus of claim 4 further comprising a trolley running on said outrigger, crane means running on the cars transporting the new tie-s and delivering groups of said new ties to the trolley, and a carriage underneath the outrigger and receiving the groups of new ties from the trolley.
  • tie gripping implement is arranged to hold and lift said groups of ties closely adjacent each other, to position a partial group consisting of every other tie of said group on the ballast in a first operation, and to position the remaining ties of said group on the ballast forwardly of the first positioned partial group.
  • tie gripping implement has at least one lug cooperating with a next adjacent previously positioned tie for spacing the group of ties in relation to said previously positioned tie.
  • the forward train section includes a front section of said cars carrying new rails in discontinuous lengths and a work car coupled.
  • the rear train section includes a work car for cutting the continuous lengths of the rails of the old track section into discontinuous lengths, and a back section of said cars coupled to the latter work car for carrying the discontinuous lengths of the old rails.
  • the apparatus of claim 10 further comprising laterally extending guide means on at least most of the cars of the forward and rear train sections adjacent the intermediate section of the right of way for supporting the continuous lengths of the new and old rails with a minimum of friction whereby the rails are supported on said train cars for relative movement in respect to the train as the latter moves.
  • the apparatus of claim 11 further comprising mobile apparatus for leveling and tamping ballast in the intermediate section of the right of way, said apparatus also having said laterally extending guide means for the rails.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
US738475A 1967-06-29 1968-06-20 Apparatus for replacing an old track by a new track Expired - Lifetime US3521565A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT607667A AT305331B (de) 1967-06-29 1967-06-29 Vorrichtung zum kontinuierlich fortschreitenden Erneuern von Gleisen

Publications (1)

Publication Number Publication Date
US3521565A true US3521565A (en) 1970-07-21

Family

ID=3582607

Family Applications (2)

Application Number Title Priority Date Filing Date
US738475A Expired - Lifetime US3521565A (en) 1967-06-29 1968-06-20 Apparatus for replacing an old track by a new track
US8318A Expired - Lifetime US3633513A (en) 1967-06-29 1970-02-03 Method for replacing an old track by a new track

Family Applications After (1)

Application Number Title Priority Date Filing Date
US8318A Expired - Lifetime US3633513A (en) 1967-06-29 1970-02-03 Method for replacing an old track by a new track

Country Status (9)

Country Link
US (2) US3521565A (de)
AT (1) AT305331B (de)
CH (1) CH475423A (de)
DE (1) DE1658343C3 (de)
FR (1) FR1571796A (de)
GB (1) GB1237437A (de)
NL (1) NL159450B (de)
SE (1) SE332008B (de)
SU (2) SU443519A3 (de)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3972292A (en) * 1974-03-11 1976-08-03 Franz Plasser Bahnbaumaschinen-Industrie-Gesellschaft M.B.H. Track renewal apparatus
US4275659A (en) * 1978-09-14 1981-06-30 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Apparatus for operating transport vehicles movable on a track carried by a train of railroad cars
US5181472A (en) * 1990-07-13 1993-01-26 Les Fils D'auguste Scheuchzer S.A. Device for the substitution of the rails of railway tracks
US5237143A (en) * 1990-07-13 1993-08-17 Scheuchzer, S. A. Process and installation of on-track neutralization of the rails of a railway with high-frequency heating
DE4225788A1 (de) * 1992-08-01 1994-02-03 Stahlberg Roensch Gmbh & Co Kg Verfahren und Vorrichtung zum Herstellen eines lückenlosen Gleises
US5299504A (en) * 1992-06-30 1994-04-05 Technical Rail Products, Incorporated Self-propelled rail heater car with movable induction heating coils
US20060102042A1 (en) * 2004-08-20 2006-05-18 Martin Green Long rail pick-up and delivery system
US20140366767A1 (en) * 2013-06-13 2014-12-18 Tompkins Trucking & Excavating Railroad Tie Setting Apparatus and Method
US9121140B2 (en) 2011-02-09 2015-09-01 Robert B. Conner, Jr. Low profile material handling system

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5243918A (en) * 1991-08-12 1993-09-14 Herzog Contracting Company Railroad track laying system with multiple railroad tie handling
US5361704A (en) * 1989-03-30 1994-11-08 Herzog Contracting Corp. Railroad track laying system with multiple railroad tie handling
IT1232099B (it) * 1989-05-23 1992-01-23 Valditerra S P A Procedimento per la saldatura continua di tronchi di rotaia, e rotabile attrezzato per la sua attuazione
AT400339B (de) * 1991-09-10 1995-12-27 Plasser Bahnbaumasch Franz Maschinenanordnung zur erneuerung eines gleises
DE4418376B4 (de) * 1994-05-26 2004-02-19 Robel Bahnbaumaschinen Gmbh Schienenverladezug zum Transport sowie zum Auf- und Abladen von Langschienen
FR2897326B1 (fr) * 2006-02-16 2008-04-18 Europ De Travaux Ferroviaires Procede et dispositif pour l'optimisation de l'agencement des elements constitutifs de trains dits de "travaux"
CN102817290B (zh) * 2012-08-20 2014-04-30 中铁重工有限公司 铁路铺轨机的导轨自动化回送***
FR3021674A1 (fr) * 2014-05-27 2015-12-04 Eiffage Rail Ensemble de renovation de voie ferree
CN105155370B (zh) * 2015-09-30 2017-08-11 株洲时代电子技术有限公司 一种连续换轨作业列车及其作业方法
CN112850302B (zh) * 2021-01-04 2022-07-05 中铁四局集团有限公司 一种在自动铺轨***中使钢轨落枕的滚筒回收车及方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2997001A (en) * 1956-03-03 1961-08-22 Andre Scheuchzer Method of repairing railway tracks and an installation for carrying out the same
US3286648A (en) * 1963-08-30 1966-11-22 Brosnan Dennis William Rail renewal process
US3288082A (en) * 1965-02-10 1966-11-29 Brosnan Dennis William Rail handling apparatus

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2997001A (en) * 1956-03-03 1961-08-22 Andre Scheuchzer Method of repairing railway tracks and an installation for carrying out the same
US3286648A (en) * 1963-08-30 1966-11-22 Brosnan Dennis William Rail renewal process
US3288082A (en) * 1965-02-10 1966-11-29 Brosnan Dennis William Rail handling apparatus

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3972292A (en) * 1974-03-11 1976-08-03 Franz Plasser Bahnbaumaschinen-Industrie-Gesellschaft M.B.H. Track renewal apparatus
US4275659A (en) * 1978-09-14 1981-06-30 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Apparatus for operating transport vehicles movable on a track carried by a train of railroad cars
US5181472A (en) * 1990-07-13 1993-01-26 Les Fils D'auguste Scheuchzer S.A. Device for the substitution of the rails of railway tracks
US5237143A (en) * 1990-07-13 1993-08-17 Scheuchzer, S. A. Process and installation of on-track neutralization of the rails of a railway with high-frequency heating
US5299504A (en) * 1992-06-30 1994-04-05 Technical Rail Products, Incorporated Self-propelled rail heater car with movable induction heating coils
DE4225788C2 (de) * 1992-08-01 1999-11-04 Stahlberg, Roensch Gmbh & Co Kg Verfahren und Vorrichtung zum Herstellen eines lückenlosen Gleises
DE4225788A1 (de) * 1992-08-01 1994-02-03 Stahlberg Roensch Gmbh & Co Kg Verfahren und Vorrichtung zum Herstellen eines lückenlosen Gleises
US20060102042A1 (en) * 2004-08-20 2006-05-18 Martin Green Long rail pick-up and delivery system
US7350467B2 (en) 2004-08-20 2008-04-01 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
US20080163781A1 (en) * 2004-08-20 2008-07-10 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
US7895950B2 (en) 2004-08-20 2011-03-01 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
US9121140B2 (en) 2011-02-09 2015-09-01 Robert B. Conner, Jr. Low profile material handling system
US20140366767A1 (en) * 2013-06-13 2014-12-18 Tompkins Trucking & Excavating Railroad Tie Setting Apparatus and Method

Also Published As

Publication number Publication date
CH475423A (de) 1969-07-15
DE1658343A1 (de) 1970-11-05
US3633513A (en) 1972-01-11
AT305331B (de) 1973-02-26
DE1658343B2 (de) 1977-12-29
SE332008B (de) 1971-01-25
SU441717A3 (ru) 1974-08-30
GB1237437A (en) 1971-06-30
NL159450B (nl) 1979-02-15
NL6809139A (de) 1968-12-30
SU443519A3 (ru) 1974-09-15
FR1571796A (de) 1969-06-20
DE1658343C3 (de) 1978-08-24

Similar Documents

Publication Publication Date Title
US3521565A (en) Apparatus for replacing an old track by a new track
AU595647B2 (en) Tie exchange method
US4253398A (en) Mobile apparatus for the continuous replacement of ties
CA1130653A (en) Mobile apparatus for continuously renewing track
CA1046846A (en) Track renewal method and apparatus
US3330219A (en) Method and apparatus for replacing an old track by a new track
US4809614A (en) Mobile tie gang apparatus
CA1312784C (en) Tie exchange machine
US4000699A (en) Apparatus for replacement of rail tracks
US5193461A (en) Tie exchange machine with a tie exchange device which both removes old ties and inserts new ties
US4211170A (en) Mobile apparatus for the continuous replacement of an old track by a new track
US5467717A (en) Work train for exchanging old ties for new ties
US5067412A (en) Tie plate inserting machine
US4911599A (en) Mobile installation for loading, transporting and unloading
US4261264A (en) Mobile track tie transport apparatus with traveling gantry
US4878435A (en) Mobile tie exchange machine arrangement
CA1295514C (en) Mobile tie gang apparatus
CZ273487A3 (en) Mobile device for removing or lying, as well as transport of track panels
US4862806A (en) Mobile tie gang apparatus and tie exchange method
US2696791A (en) Equipment for the laying ahead of railroad tracks by means of completely assembled sections
GB805075A (en) Improvements in or relating to methods of and means for railway track replacement
US3683816A (en) Curving chute apparatus and method for positioning railroad ties
CS212409B1 (cs) Zařízení pro kontinuální výměnu starých kolejnic za nové