US2203978A - Means and method of shoring bell bottom pile holes - Google Patents

Means and method of shoring bell bottom pile holes Download PDF

Info

Publication number
US2203978A
US2203978A US235292A US23529238A US2203978A US 2203978 A US2203978 A US 2203978A US 235292 A US235292 A US 235292A US 23529238 A US23529238 A US 23529238A US 2203978 A US2203978 A US 2203978A
Authority
US
United States
Prior art keywords
shoring
members
template
hole
bell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US235292A
Inventor
Benjamin E Bertran
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JOSIE A BERTRAN
Original Assignee
JOSIE A BERTRAN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JOSIE A BERTRAN filed Critical JOSIE A BERTRAN
Priority to US235292A priority Critical patent/US2203978A/en
Application granted granted Critical
Publication of US2203978A publication Critical patent/US2203978A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Definitions

  • Josie Myjinvention relates to means and method of shoring bell bottom pile holes and the objects of my invention are:
  • Figure l is a vertical sectional view of a hole arranged preparatory for preparing the bell bottom in soft material taken from the line l-l 50 of Fig. 2 on a reduced scale and showing the templatein position in the lore-arranged hole and with one or the shoring members ready to be started;
  • Fig. 2 is atop or plan view taken from t the line 2-2 of Fig. 1 on anenlarged scale; Fig.
  • s 3 isa vertical sectional view showing the shoring ND METHOD oF snom BOTTOM PILE HOLES sand, gravel, or earth a part of this appli- N G BELL s ,Angeles, Calif., assign- A. Bertran, Los Angeles,
  • FIG. 4 is a similar view of that of Fig. 3 with the template removedand the shoring supporting ring shown in position ready to be placed against the upper ends of the shoring members;
  • Fig. 5 is an enlarged top view 6 taken. from the line 55 of Fig. 4;
  • Fig. 6 is a similar View showing more of the shoring in position and the ring secured at the top taken from the line 66 of Fig. 8 with the earth removed;
  • Fig. '7 is a vertical sectional view on a reduced 10 scale showing the supporting ringup in position and secured to the upper ends of the shoring 1 members ready for the removal of the earth;
  • Fig. 8 is a vertical sectional view of the hole ready for receiving the caisson or pile with the earth re- J moved, on a reduced scale taken from the line G--8 of Fig. 6; and Fig. 9 is a transverse sectional view of the hole complete with the plastic material piled therein.
  • the initial bore I, bell sha members 3, supporting ring 4, and template 5, constitute the principal elements of my means and the principal elements utilized in my novel method of shoring bell bottom pile holes for soft sandy material.
  • My means and method of shoring bell bottom pile holes enables the casting of hell bottom piling in soft sandy material whether the material is wet, or dry or dusty.
  • the first step consists in drilling a bore I which is the initial bore with any suitable drilling tool to approximately the depth of the stem of the caisson or pile and the position where the top of thebell shape starts. This is usually a short distance.
  • a template 5 ispositioned with its baseon the bottom of the additional hole I as shown best i of. the drawings.
  • This templatemember consists of a circular top member 5a, a circular base member 5b and a plurality of angularly positioned supporting members to connecting the members 5a and 5b.
  • the angle of these members 50 determine substantially-the angle of the slope of the bell shaped hole as the members 5a and 5b form the guide for driving the shoring members 3 into position.
  • This, base 519. is preferably supported on.
  • one of the shoring members 3 is posiped ,hole 2, shoring n Figs. 1, 2 and 3 40 2 tioned as shown best in Fig. 1 of the drawings and it is driven down so that it maintains sub,- stantially the angle between the top member 5a and base member 511 of the template 5.
  • This can be driven by an air hammer or any means desired for driving the shoring member 3.
  • These shoring members 3 are made of pipe which may be second grade or old pipe, or may be made of railroad ties or any scrap bar material that may be driven into the earth.
  • holes may be drilled using the template for supporting the drill instead of the shoring member and the holes may be drilled to the proper position. Then the shoring members 3 may be driven into these holes prepared for them. The shoring members 3 are driven relatively close to each other to form a shoring support for the sloping wall of the'bell shaped bottom hole. These shoringmembers 3 are driven some distance below the bottom of the finished bell shaped hole as shown. best in Fig. 8 of the drawings so that they are substantially supported at their lower ends after the materialis removed. As soon as the shoring is driven the template!
  • This ring is then raised by jacks or by other means so that it is pressed up against the inside of the upper ends of the shoring members 3 as shown best in Fig.
  • ring member 4 may be broken loose from the upper end of shoring members 3 and removed'and the shoring members 3 may be withdrawn as the filling of the cement is proceeded with.
  • Fig. 9 is shown the finished hole with the pile or caisson in position showing the shoring members 3' and ring 4 in reenforcing position.
  • the template 5 may conical in shape if desired, and the ring 4 may be made in two or more pieces as desired, and the shoring member 3 may be made of any drivable material that is strong enough to support the soft wall and prevent its caving.
  • a means for shoring bell bottom pile holes a plurality of spaced shoring members forming a bell shaped skeleton of frusto-conical shape forming a lining support for the bell bottom hole, a reenforcing member secured near the upper ends of said shoring members for supporting said shoring members at their upper ends, said reenforcing member including an annular member made in a plurality of pieces for placing and afterwards welded to form a single annular member.
  • a frustoconical template Ina means of the class described; a frustoconical template, a plurality of shoring members supported by said template while driving the same, and a ring member formed in several parts adapted to be drawn up against the inner end of from the bottom thereof adapted to rest'in grooves in the earth for stabilizing said template.
  • a method of sharing bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall and then driving shoring members using the outer side wall of said template as a guide for said shoring members.
  • a method of shoring bell bottom pile holes consisting in preparinga vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall, then driving shoring members using the outer sidewall of said template as a guide for said shoring members, then removing the template, then removing the earth some dis tance below the upper ends ofsaid driven shoring members, then placing a r'eenforcing ring made in' a plurality of pieces in said hole, then securing said plurality of pieces together, then raising said ring and securing it to the inner sides of said shoring members near their upper ends.
  • a method of shoring bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of saidhole provided with an angular outer side wall, then driving shoring members using the outer side wall of said template as a guide for said shoring members, then removing the template, then removing the earth some dis-- tance below the upper ends of said driven shoring members, then placing a reenforcing ring made in a plurality of pieces in said hole, then securing said plurality of pieces together, then raisingsaid ring and securing it to the inner sides of said shoring members near their upper ends, then removing the earth inside ofsaid shoring members.
  • a method of shoring bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall, then driving shoring members using the outerlside' wall of said template as a guide for said shoring members, then removing the template, then removing the earth some distance below the upper ends of said driven shoring members, then placing a reenforcing ring made in a plurality of pieces in said hole, then securing said plurality of pieces together, then raising said ring and securing it to the inner sides of said shoring members near their upper ends,
  • a method of preparing bell bottom pile holes in soft cavable material consisting of preparing a straight vertical initial hole, then placing an angularly Walled template in the bottom of said hole, then sinking shoring members into the earth on an angle with the wall of said template, then removing said template, then supporting the upper end of said shoring members, then removing the earth from the inside of said shorw ing members to near the bottom, ends thereof, then molding said shoring members and supporting means in plastic material filling said holes.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Description

June 11, 1940.v 2,203,978
mmusun uiawaon 0F snonme BELL BOTTOM FILE HOLES B. E. BERTRAN 2 Sheets-Sheet 1 Filed Oct. 15, 1958 INVENTOR. ganja/77m E. Barf/w June 11, 1940. B. s. BERTRAN 2,203,978
MEANS AND METHOD OF SHORING BELL BOTTOM FILE HOLES Filed Oct. 15, 1938 2 Sheets-Sheet 2 INVENTOR.
Ben/0mm E. Bern cm BY ATTORNEY.
20 or cavingwhile a Patented June 11, 19 10 PATENT oF icE MEANS A -Benjarnin E. Bertran, Lo
or of Calif Application October 15,
9 Claims.
one-half to Josie Myjinvention relates to means and method of shoring bell bottom pile holes and the objects of my invention are:
First, to provide a means of supporting the *5 tapering walls of a bell bottom pile hole where they are to be dug in soft ground, such as sand, gravel or the like;
Second, to provide a means of this class which is placed in position for supporting the sloping Wall before the dirt is removed for forming the bell shapedhole;
Third, to provide a means of this class in which a template is used for directing the positioning of the supporting shoring;
Fourth, to provide a means of this class which is applicable for use in connection with any kind of earth that is liable to cave from any cause;
Fifth, to provide a means of this class which reduces tofa minimum the liability and danger person is removing theearth in the bell bottomhole;
Sixth, to provide a novel method of supporting the roof or sides of a bell bottom hole for caisson or pile ofany size or diameter in soft sandy 25 earth;
Seventh, to provide a method of this class which is particularly adapted for that is liable to cave;
Eighth, to provide a method of this class in 30 which shoring is placed in position for supporting the wall before the earth is removed;
Ninth, to provide a means of this class which is very simple and economical of construction, easy to operate, efiicient in its action; and
Tenth, to provide a very economical and emcientxmethod of this class.
With these and other objects in view as will appearhereinafter, my invention consists of the novel features of construction,combination and 40 arrangement of parts andportions and the certain novel method as will be hereinafter described in detail and particularly set forth in the .appended claims, referencebeing had to the accompanying drawings and to the characters of 45 reference thereon which form cation in which:
Figure l is a vertical sectional view of a hole arranged preparatory for preparing the bell bottom in soft material taken from the line l-l 50 of Fig. 2 on a reduced scale and showing the templatein position in the lore-arranged hole and with one or the shoring members ready to be started; Fig. 2 is atop or plan view taken from t the line 2-2 of Fig. 1 on anenlarged scale; Fig.
s 3 isa vertical sectional view showing the shoring ND METHOD oF snom BOTTOM PILE HOLES sand, gravel, or earth a part of this appli- N G BELL s ,Angeles, Calif., assign- A. Bertran, Los Angeles,
1938, Serial No. 235,292
driven into position; Fig. 4 is a similar view of that of Fig. 3 with the template removedand the shoring supporting ring shown in position ready to be placed against the upper ends of the shoring members; Fig. 5 is an enlarged top view 6 taken. from the line 55 of Fig. 4; Fig. 6 is a similar View showing more of the shoring in position and the ring secured at the top taken from the line 66 of Fig. 8 with the earth removed; Fig. '7 is a vertical sectional view on a reduced 10 scale showing the supporting ringup in position and secured to the upper ends of the shoring 1 members ready for the removal of the earth; Fig.
8 is a vertical sectional view of the hole ready for receiving the caisson or pile with the earth re- J moved, on a reduced scale taken from the line G--8 of Fig. 6; and Fig. 9 is a transverse sectional view of the hole complete with the plastic material piled therein.
Similar characters of reference refer to similar parts and portions throughout the several views of the drawings:
The initial bore I, bell sha members 3, supporting ring 4, and template 5, constitute the principal elements of my means and the principal elements utilized in my novel method of shoring bell bottom pile holes for soft sandy material.
My means and method of shoring bell bottom pile holes enables the casting of hell bottom piling in soft sandy material whether the material is wet, or dry or dusty.
The first stepconsists in drilling a bore I which is the initial bore with any suitable drilling tool to approximately the depth of the stem of the caisson or pile and the position where the top of thebell shape starts. This is usually a short distance. After this is accomplished, a template 5 ispositioned with its baseon the bottom of the additional hole I as shown best i of. the drawings. This templatemember consists of a circular top member 5a, a circular base member 5b and a plurality of angularly positioned supporting members to connecting the members 5a and 5b. The angle of these members 50 determine substantially-the angle of the slope of the bell shaped hole as the members 5a and 5b form the guide for driving the shoring members 3 into position. This, base 519. is preferably supported on. two beams 5e'which rest in ditches in the earth in the bottom of the hole I tending to hold the template from shifting while the shoring members 3 are being driven. After the template 5is thus positioned in the bottom of the hole I, one of the shoring members 3 is posiped ,hole 2, shoring n Figs. 1, 2 and 3 40 2 tioned as shown best in Fig. 1 of the drawings and it is driven down so that it maintains sub,- stantially the angle between the top member 5a and base member 511 of the template 5. This can be driven by an air hammer or any means desired for driving the shoring member 3. These shoring members 3 are made of pipe which may be second grade or old pipe, or may be made of railroad ties or any scrap bar material that may be driven into the earth.
It will be here noted that in case there are too many relatively large stones to permit the driving of these members, holes may be drilled using the template for supporting the drill instead of the shoring member and the holes may be drilled to the proper position. Then the shoring members 3 may be driven into these holes prepared for them. The shoring members 3 are driven relatively close to each other to form a shoring support for the sloping wall of the'bell shaped bottom hole. These shoringmembers 3 are driven some distance below the bottom of the finished bell shaped hole as shown. best in Fig. 8 of the drawings so that they are substantially supported at their lower ends after the materialis removed. As soon as the shoring is driven the template! is removed and dirt is removed some distance below the upper end of the shoring 3 as shown in Fig. 4 of the drawings. Then a supporting ring 4 made in two halves 4a and 4b, is lowered into the hole inside of the upper endsof the shoring members 3, after which they are placed on the bottom of the hole and welded together at the reenforced point 40, thus forming a welded'single piece-ring out of the two separate pieces. This ring is then raised by jacks or by other means so that it is pressed up against the inside of the upper ends of the shoring members 3 as shown best in Fig. '7 of the drawings and it is then welded or otherwise rigidly secured to the upper ends of the shoring members 3 forming a rigid unit and supporting the upper ends of the shoring members, while the lower ends are supported in the earth in which they are driven. The earth is then removed inside of the shoring members 3 forming a bell shaped bottom for receiving cement, concrete or the like for forming the bell shaped bottom casing or pile.
It will be here noted that if there is any caving or running of the sand in the space between the pipe causing a space outside of the shoring members at or near thetop of the driven shoring members, cement grouting is placed therein, filling up all of the cavity, or sheet metal is laid back of the pipe to catch the sand. Then the earth material is removed inside of the shoring members 3 as shown best in Fig. 8 of the drawings. The bell shaped hole 2 is then ready to be filled with the plastic material forming the caisson or pile. The shoring members 3 and ring 4 are left in position and form reenforcing for the outer side of the caisson or pile. However, if desired, the ring member 4 may be broken loose from the upper end of shoring members 3 and removed'and the shoring members 3 may be withdrawn as the filling of the cement is proceeded with. In Fig. 9 is shown the finished hole with the pile or caisson in position showing the shoring members 3' and ring 4 in reenforcing position.
It will be here noted that the template 5 may conical in shape if desired, and the ring 4 may be made in two or more pieces as desired, and the shoring member 3 may be made of any drivable material that is strong enough to support the soft wall and prevent its caving.
Though I have shown and described a particular construction, combination and arrangement of parts and portions and a particular method, I do not wish to be limited to this particular construction, nor to the particular method, but desire to include in the scope of my invention the construction, combination and arrangement of parts and method substantially as set forth in the appended claims.
Having thus described my invention, what I claim as new and desire to secure by Letters Patent is:
1. In a means for shoring bell bottom pile holes, a plurality of spaced shoring members forming a bell shaped skeleton of frusto-conical shape forming a lining support for the bell bottom hole, a reenforcing member secured near the upper ends of said shoring members for supporting said shoring members at their upper ends, said reenforcing member including an annular member made in a plurality of pieces for placing and afterwards welded to form a single annular member.
2. In a means of the'class described, a frustoconical template and a plurality of shoring mem bers supported by said template while driving the same. I
3. Ina means of the class described; a frustoconical template, a plurality of shoring members supported by said template while driving the same, and a ring member formed in several parts adapted to be drawn up against the inner end of from the bottom thereof adapted to rest'in grooves in the earth for stabilizing said template.
5. A method of sharing bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall and then driving shoring members using the outer side wall of said template as a guide for said shoring members.
6. A method of shoring bell bottom pile holes consisting in preparinga vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall, then driving shoring members using the outer sidewall of said template as a guide for said shoring members, then removing the template, then removing the earth some dis tance below the upper ends ofsaid driven shoring members, then placing a r'eenforcing ring made in' a plurality of pieces in said hole, then securing said plurality of pieces together, then raising said ring and securing it to the inner sides of said shoring members near their upper ends.
7. A method of shoring bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of saidhole provided with an angular outer side wall, then driving shoring members using the outer side wall of said template as a guide for said shoring members, then removing the template, then removing the earth some dis-- tance below the upper ends of said driven shoring members, then placing a reenforcing ring made in a plurality of pieces in said hole, then securing said plurality of pieces together, then raisingsaid ring and securing it to the inner sides of said shoring members near their upper ends, then removing the earth inside ofsaid shoring members. 8. A method of shoring bell bottom pile holes consisting in preparing a vertical initial hole at the earth surface, then placing a template in the bottom of said hole provided with an angular outer side wall, then driving shoring members using the outerlside' wall of said template as a guide for said shoring members, then removing the template, then removing the earth some distance below the upper ends of said driven shoring members, then placing a reenforcing ring made in a plurality of pieces in said hole, then securing said plurality of pieces together, then raising said ring and securing it to the inner sides of said shoring members near their upper ends,
then removing the earth inside of said'shoring members, then filling said bell shaped hole and said initial hole with cement.
9. A method of preparing bell bottom pile holes in soft cavable material consisting of preparing a straight vertical initial hole, then placing an angularly Walled template in the bottom of said hole, then sinking shoring members into the earth on an angle with the wall of said template, then removing said template, then supporting the upper end of said shoring members, then removing the earth from the inside of said shorw ing members to near the bottom, ends thereof, then molding said shoring members and supporting means in plastic material filling said holes.
BENJAMIN E. BER'I'RAN.
US235292A 1938-10-15 1938-10-15 Means and method of shoring bell bottom pile holes Expired - Lifetime US2203978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US235292A US2203978A (en) 1938-10-15 1938-10-15 Means and method of shoring bell bottom pile holes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US235292A US2203978A (en) 1938-10-15 1938-10-15 Means and method of shoring bell bottom pile holes

Publications (1)

Publication Number Publication Date
US2203978A true US2203978A (en) 1940-06-11

Family

ID=22884892

Family Applications (1)

Application Number Title Priority Date Filing Date
US235292A Expired - Lifetime US2203978A (en) 1938-10-15 1938-10-15 Means and method of shoring bell bottom pile holes

Country Status (1)

Country Link
US (1) US2203978A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3330122A (en) * 1962-06-09 1967-07-11 Siemens Ag Method of forming underground nuclear reactor installation
US6435777B1 (en) * 1997-05-12 2002-08-20 Tokyo Electric Power Company Method of arranging reinforcement in forming foundation of ground reinforcing type and foundation body
WO2022096905A1 (en) 2020-11-05 2022-05-12 Winkler Lipot Peter Process and apparatus for producing elementary nanoparticulate mineral components and rare metal oxides therefrom using primary and secondary mineral resources as base materials

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3330122A (en) * 1962-06-09 1967-07-11 Siemens Ag Method of forming underground nuclear reactor installation
US6435777B1 (en) * 1997-05-12 2002-08-20 Tokyo Electric Power Company Method of arranging reinforcement in forming foundation of ground reinforcing type and foundation body
WO2022096905A1 (en) 2020-11-05 2022-05-12 Winkler Lipot Peter Process and apparatus for producing elementary nanoparticulate mineral components and rare metal oxides therefrom using primary and secondary mineral resources as base materials

Similar Documents

Publication Publication Date Title
JPS587765B2 (en) Method and apparatus for forming columns of underground fillings
US1681883A (en) Method of producing and placing piles
US2203978A (en) Means and method of shoring bell bottom pile holes
US1706002A (en) Method of producing and placing shafts, piles, and the like
US2875584A (en) Method for making structural foundations
CN104153355B (en) The constructing device of concrete-pile and construction method thereof
US2317016A (en) Bridge foundation and method of making same
CN109267575A (en) The construction method of pattern foundation pit supporting structure is cheated in the hole of Soft Soil Area
US3654767A (en) Method of forming a composite pile
US1296628A (en) Stabilizing foundation.
US2317017A (en) Pier and method of constructing the same
US785356A (en) Process of making concrete structures.
US1969229A (en) Apparatus for forming concrete structures
US1139384A (en) Apparatus for constructing concrete columns.
US1642213A (en) Construction of concrete piles or foundation elements
US2468265A (en) Foundation
US1665797A (en) Method of excavating and producing foundations
US1089573A (en) Method of lining shafts with concrete.
US1644572A (en) Ant ville
US1591165A (en) Piling
US1161512A (en) Water-supply system.
US933776A (en) Sinking shafts and the like.
US1607613A (en) Making concrete foundation piers and the like
GB256150A (en) Improvements in the construction of concrete piles
US1696421A (en) Method of and apparatus for supporting the side walls of excavations