US20080313906A1 - Method of forming heat exchanger tubes - Google Patents

Method of forming heat exchanger tubes Download PDF

Info

Publication number
US20080313906A1
US20080313906A1 US12/140,524 US14052408A US2008313906A1 US 20080313906 A1 US20080313906 A1 US 20080313906A1 US 14052408 A US14052408 A US 14052408A US 2008313906 A1 US2008313906 A1 US 2008313906A1
Authority
US
United States
Prior art keywords
ribbons
tubes
perforations
perforation
ribbon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US12/140,524
Inventor
Siegfried Eisele
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Modine Manufacturing Co
Original Assignee
Modine Manufacturing Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Modine Manufacturing Co filed Critical Modine Manufacturing Co
Assigned to MODINE MANUFACTURING COMPANY reassignment MODINE MANUFACTURING COMPANY ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: EISELE, SIEGFRIED
Publication of US20080313906A1 publication Critical patent/US20080313906A1/en
Priority to US13/206,080 priority Critical patent/US8434227B2/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D53/00Making other particular articles
    • B21D53/02Making other particular articles heat exchangers or parts thereof, e.g. radiators, condensers fins, headers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes
    • B21C37/08Making tubes with welded or soldered seams
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes
    • B21C37/08Making tubes with welded or soldered seams
    • B21C37/0807Tube treating or manipulating combined with, or specially adapted for use in connection with tube making machines, e.g. drawing-off devices, cutting-off
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes
    • B21C37/15Making tubes of special shape; Making tube fittings
    • B21C37/151Making tubes with multiple passages
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes
    • B21C37/15Making tubes of special shape; Making tube fittings
    • B21C37/156Making tubes with wall irregularities
    • B21C37/157Perforations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes
    • B21C37/15Making tubes of special shape; Making tube fittings
    • B21C37/22Making finned or ribbed tubes by fixing strip or like material to tubes
    • B21C37/225Making finned or ribbed tubes by fixing strip or like material to tubes longitudinally-ribbed tubes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10TTECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
    • Y10T29/00Metal working
    • Y10T29/49Method of mechanical manufacture
    • Y10T29/4935Heat exchanger or boiler making
    • Y10T29/49377Tube with heat transfer means
    • Y10T29/49378Finned tube

Definitions

  • the present invention relates to a method of forming tubes, and more particularly to a method of forming heat exchanger tubes on a roller mill.
  • the present invention provides a method for manufacturing tubes, in particular for heat exchangers, composed of endless ribbon material on a roller mill.
  • Tubes can be formed from at least two parts or ribbon strips which are subjected to a shaping process on a roller mill. Perforations or predetermined break points are introduced into the ribbon material at predetermined locations. A step of making the perforations in the parts or ribbon strips is carried out, after which the parts are combined to form the tube and after which individual tubes are separated off from the tube at predetermined locations.
  • DE-AS 10 25 821 describes the manufacture of flat tubes from just one ribbon strip.
  • a central part of the ribbon strip is provided with a corrugation and the two edge parts are positioned as wall parts of the flat tube around the central, corrugated part.
  • slots and webs are made in the ribbon strips at intervals corresponding to the desired tube lengths. After this, the shaping of the flat tube is continued by the already mentioned folding over of the lateral edge parts in order to close the flat tube and finally separate it off at the perforation.
  • the method of the present invention has the advantage that the method steps of making the perforations from two or even three sheet metal strips correspond and combine the sheet metal strips to form the tube which steps are extremely difficult at least on first sight, are not required because the known flat tube is, as mentioned, manufactured from only a single sheet metal strip.
  • One independent object of the invention is to develop a manufacturing method for tubes presented at the beginning in such a way that, inter alia, the investment in the roller mill can be reduced.
  • the perforations are provided within the shaping process it is advantageous to construct the perforations just before the end of the shaping process. It has been found that with this measure the undesired tearing of the ribbon strip can be prevented. It is therefore not necessary to provide all the shaping rollers with a drive, for which reason it has been possible to reduce the investment for the roller mill.
  • the present invention also provides a roller mill with which the manufacturing method is carried out.
  • the roller mill can include a perforation station arranged inside or, viewed in the running direction of the ribbon strip, downstream of the shaping station.
  • the flat tubes which run from the roller mill are combined with and soldered to corrugation fins to form a heat exchanger system.
  • all the flat tubes are permanently connected to one another and also to the air-side corrugation fins.
  • the perforations can either be slots with webs or else linear ribbon thinning lines which constitute predetermined break points, preferably in a straight line.
  • a third part, which constitutes a later internal insert of the tubes, is preferably provided.
  • the perforation or the manufacture of the predetermined break lines is preferably carried out by means of rollers. In some embodiments, there is at least one pair of rollers in this context.
  • FIG. 1 is a schematic illustration of a roller mill for manufacturing tubes according to some embodiments of the present invention.
  • FIG. 2 is an enlarged view of a perforation station which can be located in the roller mill shown in FIG. 1 .
  • FIGS. 3 a, b and c show perforations or optionally predetermined break points in sheet metal ribbons.
  • FIG. 4 shows a perspective view of a roller mill.
  • FIG. 5 shows a flat tube being manufactured on a roller mill in accordance with some embodiments of the method of the present invention.
  • FIG. 6 is an enlarged view of a part of a flat tube during its manufacture.
  • FIGS. 7 and 8 show cross-sectional views of a flat heat exchanger tube according to some embodiments of the present invention.
  • tubes 1 which are composed of three parts a, b, c are manufactured.
  • the parts a and b are respectively the upper and lower wall parts of the flat tube, and the part c is a corrugated internal insert of the flat tube.
  • a cross section of the finished, preferred tube can be seen in FIG. 7 .
  • An embodiment of the preferred flat tube 1 which is slightly modified with respect to the corrugated internal insert c can be found in FIG. 8 , which shows merely one of the edges of the flat tube 1 .
  • the parts a and b are identical but laterally inverted with respect to one another, in which case one of the relatively large edge arcs of the parts a, b engages around the other relatively small edge arc of the respective other part.
  • the part c is also shaped at its two longitudinal edges and they advantageously reinforce the narrow sides 12 of the tube 1 by virtue of the fact that the longitudinal edges come to rest there.
  • the preferred thickness of the parts is in the range of, for example, 0.03-0.09 mm for the internal insert c and of 0.03-0.15 mm or somewhat more for the wall parts a, b.
  • the dimensions of the tubes can vary from a clear width d of approximately 1.0 mm or less and up to 10 mm or more.
  • the tube width D can be selected over wide ranges by virtue of the fact that a correspondingly wide sheet metal ribbon is used.
  • roller ribbons R 1 , R 2 , R 3 are present as the starting material.
  • This material is sheet aluminum.
  • the roller ribbon R 1 produces the part a
  • the roller ribbon R 2 produces the part c
  • the corrugated internal insert and finally the roller ribbon R 3 gives rise to the part b of the flat tube 1 .
  • an extremely large loop is present in the ribbons just downstream of the roller ribbons R 1 , R 2 , R 3 , and said loops can be used to compensate different speeds or else stoppages of the ribbons.
  • the perforation stations P 1 , P 2 , P 3 are located at the end of the shaping station U.
  • perforations 3 it is also possible, for example, to provide ribbon thinning lines 3 b as the predetermined break points (see FIGS. 3 b and 3 c ).
  • the roller ribbons R 1 (part a) and R 3 (part b) simply also run along without being already significantly shaped there.
  • the upper roller ribbon R 1 then reaches the perforation station P 2 .
  • the perforation station P 3 Just after this there is the perforation station P 3 through which the lower roller ribbon R 3 runs in order to be perforated.
  • the edge shaping is then constructed on the parts a and b, and the part c is threaded in between the parts a and b, which cannot be seen in detail.
  • the perforation station P 1 for the part c, the corrugated internal insert lies at the end of the shaping station U. There, the perforations 3 are made in the already finally shaped corrugated internal insert c. Because in the exemplary embodiment shown the formation of the perforations 3 by means of the pair P of rollers leads to flattening of the corrugations in the area near to the perforations 3 , a pair W of rollers is located downstream of the perforation station P 1 and is used to manufacture again the corrugated shape in the nearby area. This is represented in FIG. 6 , said figure showing the state after the perforation cutting has been carried out and before the corrugated internal insert c enters the pair W of rollers. It could also be advantageous to equip at least the pair W of rollers with a drive (not shown in the basic illustrations).
  • the perforations 3 in the three parts a, b, c are made to correspond, for which purpose known open-loop and closed-loop control means (not shown) are used.
  • This section Ü should, as a person skilled in the art certainly knows, be located upstream of the area in which the parts a, b, c are already connected to one another or are in secure physical contact because an individual speed adaptation could be necessary in order to make the perforations 3 correspond.
  • the three parts a, b, c have been indicated in a situation such as occurs approximately between the pair W of rollers and the station Ü. At said location the parts already have the perforations 3 which, as described, have to be made to correspond. If the parts a, b, c have subsequently been joined to form the tube 1 , an endless tube 1 is then obtained and the individual tubes 1 are then to be separated off from it. In this exemplary embodiment subsequent to the section Ü there is a further shaping section U in which the parts a and b have been shaped at the longitudinal edges and joined to the third part c to form the tube.
  • FIG. 5 the state of the endless tube is shown in this situation.
  • the upper wall part a has been broken off at the end in order to be able to show a piece of the corrugated internal insert c.
  • the manufacturing method has been used to produce flat tubes whose large diameter D is approximately 55 mm ( FIG. 7 ). Accordingly, the width of the sheet metal ribbon for manufacturing the wall parts a and b respectively is approximately 59 mm.
  • the width of the sheet metal ribbon of the part c is significantly larger, perhaps 70-80 mm, which can be clearly seen in FIG. 4 . With these dimensions it has become apparent that in each case only one web 30 is sufficient, for example at the two longitudinal edges of the sheet metal strips a, b. Intermediate webs 30 are therefore not necessary there.
  • the webs 30 it has proven particularly advantageous for them not to be constructed as far as the outermost longitudinal edge of the sheet metal ribbons a, b, c. It is better to form a slot 3 c which is perhaps 2 mm long and is adjoined by the web 30 which itself could for example have a length of 2 to 8 mm depending on the dimension of the tubes, and after this the long slot 3 c which extends as far as the web 30 which is also constructed on the other longitudinal edge of the sheet metal strip a and b respectively (see FIG. 3 b , left-hand side). Furthermore, it may also be advantageous to reduce the thickness of the sheet metal in the vicinity of the webs 30 somewhat, as a result of which the later separation is made easier (not shown clearly).
  • FIGS. 6 and 7 The above situation has been indicated in FIGS. 6 and 7 by hatching on the narrow sides 12 of the flat tube 1 .
  • the hatching shows in practice the webs 30 on which individual flat tubes 1 are still firstly connected to one another and are to be separated off later. The separation occurs at the separating station A ( FIGS. 1 and 4 ).
  • the third sheet metal strip c also has a configuration which is similar in terms of the construction of the webs 30 and slots 3 c , and this has also been indicated in FIGS. 7 and 8 .
  • the three perforation stations P 1 , P 2 and P 3 which have already been mentioned may in principle be identical in construction.
  • the perforation stations P 1 , P 2 , P 3 are composed in the exemplary embodiment of a pair PP of rollers.
  • One (upper) roller P preferably runs along and conveys the part a, b or c which is transported between the rollers P.
  • the other (lower) roller P is constructed with a protruding perforation dye PS.
  • the other roller P with the perforation dye PS is held in a waiting position in which the perforation dye PS is not in engagement. In this position, the perforation dye PS is on the left in FIG. 2 , in a horizontal position on the roller P.
  • the aforementioned means then ensure that the roller P is suddenly moved at a high rotational speed in order to arrive at the action position which is also shown in FIG. 2 and in which the perforation dye PS is in engagement and the perforations 3 are manufactured.
  • the rotational speed or the circumferential speed of the rollers P is preferably higher than the transportation speed of the ribbon in order to ensure that the ribbon does not curl up. It must be remembered that the inventors have envisaged a ribbon speed of 100 to 200 m/min.
  • the perforations 3 are not cutouts, as FIG. 3 may be presumed to indicate, but merely quite fine indents which have webs 30 which are arranged at intervals and which are separated off later, as is customary per se with perforations in other fields.
  • the significantly enlarged illustration in FIG. 3 b serves merely to allow the webs 30 to be seen.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Shaping Metal By Deep-Drawing, Or The Like (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
  • Metal Rolling (AREA)

Abstract

The invention relates to a method for manufacturing tubes, in particular for heat exchangers, composed of endless ribbons on a roller mill, wherein the tubes are composed of at least two ribbons which are subjected to a shaping process on the roller mill, wherein perforations or predetermined break points are introduced into the ribbons at predetermined locations, wherein a step of making the perforations in the ribbons is carried out, after which the ribbons are combined to form the tube and after which individual tubes are separated off at the predetermined locations. The formation of the perforations or the predetermined break points in at least one of the two ribbons is performed within or at the end of the shaping process of the corresponding ribbon so that some of the pairs of rollers do not require a drive.

Description

    CROSS-REFERENCE TO RELATED APPLICATIONS
  • Priority is hereby claimed to German Patent Application No. DE 10 2007 028710.2, filed Jun. 21, 2007, the entire contents of which is incorporated herein by reference.
  • FIELD OF THE INVENTION
  • The present invention relates to a method of forming tubes, and more particularly to a method of forming heat exchanger tubes on a roller mill.
  • SUMMARY
  • In some embodiments, the present invention provides a method for manufacturing tubes, in particular for heat exchangers, composed of endless ribbon material on a roller mill. Tubes can be formed from at least two parts or ribbon strips which are subjected to a shaping process on a roller mill. Perforations or predetermined break points are introduced into the ribbon material at predetermined locations. A step of making the perforations in the parts or ribbon strips is carried out, after which the parts are combined to form the tube and after which individual tubes are separated off from the tube at predetermined locations.
  • Published German Patent Application Nos. DE 10 2006 033 568.6 and DE 10 2006 059 609.9 disclose prior art systems. It has become apparent that the formation of perforations or of predetermined break points in the not yet shaped sheet metal strips that was envisaged in the earlier applications can lead to tearing off of the ribbon strips in the course of their shaping unless all, or at least a large number of, the shaping rollers of the roller mill have a drive. The result of such a system is that the sheet metal strips have to be pulled through non-driven shaping rollers, during which process the aforementioned tearing off can occur. However, equipping all the shaping rollers with a drive entails a relatively high level of investment in the roller mill. It is also possible for excessive and undesirable stretching to occur in the webs which are associated with the perforations.
  • DE-AS 10 25 821 describes the manufacture of flat tubes from just one ribbon strip. A central part of the ribbon strip is provided with a corrugation and the two edge parts are positioned as wall parts of the flat tube around the central, corrugated part. In order to be able to separate off individual flat tubes from the endless flat tube, slots and webs are made in the ribbon strips at intervals corresponding to the desired tube lengths. After this, the shaping of the flat tube is continued by the already mentioned folding over of the lateral edge parts in order to close the flat tube and finally separate it off at the perforation.
  • Compared to the method mentioned above, the method of the present invention has the advantage that the method steps of making the perforations from two or even three sheet metal strips correspond and combine the sheet metal strips to form the tube which steps are extremely difficult at least on first sight, are not required because the known flat tube is, as mentioned, manufactured from only a single sheet metal strip. However, it is disadvantageous that with the known method it is not possible to provide heat exchangers with extremely thin wall thicknesses of the tubes or with a significant improvement in terms of performance per unit of weight because the wall thickness of the tube usually has to be the same as the wall thickness of the corrugated central part.
  • One independent object of the invention is to develop a manufacturing method for tubes presented at the beginning in such a way that, inter alia, the investment in the roller mill can be reduced. There is provision for the formation of the perforations or of the predetermined break points in at least one of the two ribbon strips or the two parts to be performed within the shaping process or subsequent to the shaping process of the corresponding ribbon strip. In such cases in which the perforations are provided within the shaping process it is advantageous to construct the perforations just before the end of the shaping process. It has been found that with this measure the undesired tearing of the ribbon strip can be prevented. It is therefore not necessary to provide all the shaping rollers with a drive, for which reason it has been possible to reduce the investment for the roller mill. Furthermore, it has been found that the stretching of the ribbon strip at the webs of the perforations occurs to a significantly smaller degree or is even negligible, as a result of which the perforations in the preferably three ribbon strips can be made to correspond with a higher degree of precision.
  • The present invention also provides a roller mill with which the manufacturing method is carried out. The roller mill can include a perforation station arranged inside or, viewed in the running direction of the ribbon strip, downstream of the shaping station. The flat tubes which run from the roller mill are combined with and soldered to corrugation fins to form a heat exchanger system. In this context, all the flat tubes are permanently connected to one another and also to the air-side corrugation fins.
  • The perforations can either be slots with webs or else linear ribbon thinning lines which constitute predetermined break points, preferably in a straight line.
  • A third part, which constitutes a later internal insert of the tubes, is preferably provided.
  • The perforation or the manufacture of the predetermined break lines is preferably carried out by means of rollers. In some embodiments, there is at least one pair of rollers in this context.
  • Other aspects of the invention will become apparent by consideration of the detailed description and accompanying drawings.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 is a schematic illustration of a roller mill for manufacturing tubes according to some embodiments of the present invention.
  • FIG. 2 is an enlarged view of a perforation station which can be located in the roller mill shown in FIG. 1.
  • FIGS. 3 a, b and c show perforations or optionally predetermined break points in sheet metal ribbons.
  • FIG. 4 shows a perspective view of a roller mill.
  • FIG. 5 shows a flat tube being manufactured on a roller mill in accordance with some embodiments of the method of the present invention.
  • FIG. 6 is an enlarged view of a part of a flat tube during its manufacture.
  • FIGS. 7 and 8 show cross-sectional views of a flat heat exchanger tube according to some embodiments of the present invention.
  • DETAILED DESCRIPTION
  • Before any embodiments of the invention are explained in detail, it is to be understood that the invention is not limited in its application to the details of construction and the arrangement of components set forth in the following description or illustrated in the following drawings. The invention is capable of other embodiments and of being practiced or of being carried out in various ways. Also, it is to be understood that the phraseology and terminology used herein is for the purpose of description and should not be regarded as limiting. The use of “including,” “comprising,” or “having” and variations thereof herein is meant to encompass the items listed thereafter and equivalents thereof as well as additional items. Unless specified or limited otherwise, the terms “mounted,” “connected,” “supported,” and “coupled” and variations thereof are used broadly and encompass both direct and indirect mountings, connections, supports, and couplings. Further, “connected” and “coupled” are not restricted to physical or mechanical connections or couplings.
  • In the exemplary embodiment shown, tubes 1 which are composed of three parts a, b, c are manufactured. The parts a and b are respectively the upper and lower wall parts of the flat tube, and the part c is a corrugated internal insert of the flat tube. A cross section of the finished, preferred tube can be seen in FIG. 7. An embodiment of the preferred flat tube 1 which is slightly modified with respect to the corrugated internal insert c can be found in FIG. 8, which shows merely one of the edges of the flat tube 1. The parts a and b are identical but laterally inverted with respect to one another, in which case one of the relatively large edge arcs of the parts a, b engages around the other relatively small edge arc of the respective other part. The part c is also shaped at its two longitudinal edges and they advantageously reinforce the narrow sides 12 of the tube 1 by virtue of the fact that the longitudinal edges come to rest there. The preferred thickness of the parts is in the range of, for example, 0.03-0.09 mm for the internal insert c and of 0.03-0.15 mm or somewhat more for the wall parts a, b. The dimensions of the tubes can vary from a clear width d of approximately 1.0 mm or less and up to 10 mm or more. The tube width D can be selected over wide ranges by virtue of the fact that a correspondingly wide sheet metal ribbon is used.
  • Because, as stated above, the preferred exemplary embodiment refers to three-part tubes, it is clear in FIGS. 1 and 4 that three roller ribbons R1, R2, R3 are present as the starting material. This material is sheet aluminum. The roller ribbon R1 produces the part a, the roller ribbon R2 produces the part c, the corrugated internal insert, and finally the roller ribbon R3 gives rise to the part b of the flat tube 1. As is shown in the illustration, in each case an extremely large loop is present in the ribbons just downstream of the roller ribbons R1, R2, R3, and said loops can be used to compensate different speeds or else stoppages of the ribbons. Depending on requirements it is also possible to provide a plurality of loops, which is also certain in the case in practice. The perforation stations P1, P2, P3 are located at the end of the shaping station U. Instead of perforations 3 it is also possible, for example, to provide ribbon thinning lines 3 b as the predetermined break points (see FIGS. 3 b and 3 c).
  • In this exemplary embodiment on the first section of the shaping station U the roller ribbons R1 (part a) and R3 (part b) simply also run along without being already significantly shaped there. The upper roller ribbon R1 then reaches the perforation station P2. Just after this there is the perforation station P3 through which the lower roller ribbon R3 runs in order to be perforated. The edge shaping is then constructed on the parts a and b, and the part c is threaded in between the parts a and b, which cannot be seen in detail. However, a reference can be made in this regard to the older patent application DE 10-2006-029 378.9. In the case of doubt, the entire content of said document should be considered as being disclosed at this point and is hereby incorporated herein by reference. The perforation station P1 for the part c, the corrugated internal insert, lies at the end of the shaping station U. There, the perforations 3 are made in the already finally shaped corrugated internal insert c. Because in the exemplary embodiment shown the formation of the perforations 3 by means of the pair P of rollers leads to flattening of the corrugations in the area near to the perforations 3, a pair W of rollers is located downstream of the perforation station P1 and is used to manufacture again the corrugated shape in the nearby area. This is represented in FIG. 6, said figure showing the state after the perforation cutting has been carried out and before the corrugated internal insert c enters the pair W of rollers. It could also be advantageous to equip at least the pair W of rollers with a drive (not shown in the basic illustrations).
  • Approximately in the section Ü, the perforations 3 in the three parts a, b, c are made to correspond, for which purpose known open-loop and closed-loop control means (not shown) are used. This section Ü should, as a person skilled in the art certainly knows, be located upstream of the area in which the parts a, b, c are already connected to one another or are in secure physical contact because an individual speed adaptation could be necessary in order to make the perforations 3 correspond.
  • In the illustration in FIG. 4 a, the three parts a, b, c have been indicated in a situation such as occurs approximately between the pair W of rollers and the station Ü. At said location the parts already have the perforations 3 which, as described, have to be made to correspond. If the parts a, b, c have subsequently been joined to form the tube 1, an endless tube 1 is then obtained and the individual tubes 1 are then to be separated off from it. In this exemplary embodiment subsequent to the section Ü there is a further shaping section U in which the parts a and b have been shaped at the longitudinal edges and joined to the third part c to form the tube.
  • In FIG. 5 the state of the endless tube is shown in this situation. The upper wall part a has been broken off at the end in order to be able to show a piece of the corrugated internal insert c. In first trial series, the manufacturing method has been used to produce flat tubes whose large diameter D is approximately 55 mm (FIG. 7). Accordingly, the width of the sheet metal ribbon for manufacturing the wall parts a and b respectively is approximately 59 mm. The width of the sheet metal ribbon of the part c is significantly larger, perhaps 70-80 mm, which can be clearly seen in FIG. 4. With these dimensions it has become apparent that in each case only one web 30 is sufficient, for example at the two longitudinal edges of the sheet metal strips a, b. Intermediate webs 30 are therefore not necessary there.
  • With respect to the webs 30 it has proven particularly advantageous for them not to be constructed as far as the outermost longitudinal edge of the sheet metal ribbons a, b, c. It is better to form a slot 3 c which is perhaps 2 mm long and is adjoined by the web 30 which itself could for example have a length of 2 to 8 mm depending on the dimension of the tubes, and after this the long slot 3 c which extends as far as the web 30 which is also constructed on the other longitudinal edge of the sheet metal strip a and b respectively (see FIG. 3 b, left-hand side). Furthermore, it may also be advantageous to reduce the thickness of the sheet metal in the vicinity of the webs 30 somewhat, as a result of which the later separation is made easier (not shown clearly). The above situation has been indicated in FIGS. 6 and 7 by hatching on the narrow sides 12 of the flat tube 1. The hatching shows in practice the webs 30 on which individual flat tubes 1 are still firstly connected to one another and are to be separated off later. The separation occurs at the separating station A (FIGS. 1 and 4). Furthermore, the third sheet metal strip c also has a configuration which is similar in terms of the construction of the webs 30 and slots 3 c, and this has also been indicated in FIGS. 7 and 8. The three perforation stations P1, P2 and P3 which have already been mentioned may in principle be identical in construction. The perforation stations P1, P2, P3 are composed in the exemplary embodiment of a pair PP of rollers. One (upper) roller P preferably runs along and conveys the part a, b or c which is transported between the rollers P. The other (lower) roller P is constructed with a protruding perforation dye PS. Using conventional open-loop and closed-loop control means, the other roller P with the perforation dye PS is held in a waiting position in which the perforation dye PS is not in engagement. In this position, the perforation dye PS is on the left in FIG. 2, in a horizontal position on the roller P. The aforementioned means then ensure that the roller P is suddenly moved at a high rotational speed in order to arrive at the action position which is also shown in FIG. 2 and in which the perforation dye PS is in engagement and the perforations 3 are manufactured. The rotational speed or the circumferential speed of the rollers P is preferably higher than the transportation speed of the ribbon in order to ensure that the ribbon does not curl up. It must be remembered that the inventors have envisaged a ribbon speed of 100 to 200 m/min.
  • The perforations 3 are not cutouts, as FIG. 3 may be presumed to indicate, but merely quite fine indents which have webs 30 which are arranged at intervals and which are separated off later, as is customary per se with perforations in other fields. In particular, the significantly enlarged illustration in FIG. 3 b serves merely to allow the webs 30 to be seen.
  • In order to carry out the separating process for the individual tubes 1, identical open-loop and closed-loop control means to those at the perforation stations P can be used.
  • Various features and advantages of the invention are set forth in the following claims.

Claims (14)

1. A method of manufacturing heat exchanger tubes, the method comprising the acts of:
subjecting at least two endless ribbons to a shaping process on a roller mill;
perforating or forming predetermined break portions on at least one of the ribbons at a predetermined location before the at least two ribbons are combined to form a tube; and
separating individual tubes from the tube after the tube is formed;
wherein the perforations or predetermined break portions are formed during or subsequent to the shaping process of the at least one of the ribbons.
2. The method of claim 1, wherein the shaping of the ribbons is, if necessary, performed again in an area near to the perforation or the predetermined break portions after it has been formed.
3. The method of claim 1, wherein one of the at least two ribbons in which the perforations or the break portions are formed after the shaping is a corrugated internal insert of the flat tube.
4. The method of claim 1, wherein the perforations are either at least one slot with two webs or can be linear ribbon thinning lines which constitute the predetermined break points.
5. The method of claim 4, wherein the webs are constructed on two longitudinal edges of a corrugated internal insert.
6. The method of claim 4, wherein further webs can be constructed depending on a width of a corrugated internal insert or of the ribbons.
7. The method of claim 1, wherein a third ribbon is provided which constitutes the corrugated internal insert of the tubes, wherein the third ribbon is perforated after the construction of the corrugations, in that the perforations of the third ribbon are also made to correspond to the perforations of the two ribbons, and that the three ribbons are joined to form the tube.
8. The method of claim 1, wherein the separating is performed by one of breaking, cutting, and tearing.
9. The method of claim 1, wherein the perforation or the breaking of the ribbons is performed by rollers.
10. A roller mill for manufacturing tubes from at least two endless ribbons, the mill comprising:
at least one perforation station;
a section for shaping the ribbons to form the tubes;
a separating station for tubes; and
a section for perforating the ribbons;
wherein the perforation station is arranged behind or inside the shaping station.
11. The roller mill of claim 10, wherein the perforation station is adjoined by at least one pair of rollers in order to shape of the ribbons again.
12. The roller mill of claim 10, wherein a number of perforation stations corresponds to a number of the at least two endless ribbons.
13. A flat heat exchanger manufactured according to claim 1.
14. A heat exchanger including flat tubes manufactured according to claim 1.
US12/140,524 2006-01-19 2008-06-17 Method of forming heat exchanger tubes Abandoned US20080313906A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/206,080 US8434227B2 (en) 2006-01-19 2011-08-09 Method of forming heat exchanger tubes

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102007028710A DE102007028710B4 (en) 2007-06-21 2007-06-21 Manufacturing process for pipes, rolling mill for carrying out the process, flat tube and heat exchangers with such flat tubes
DE102007028710.2 2007-06-21

Related Parent Applications (3)

Application Number Title Priority Date Filing Date
US12/063,744 Continuation-In-Part US20090218085A1 (en) 2006-01-19 2007-01-19 Flat tube, flat tube heat exchanger, and method of manufacturing same
PCT/US2007/060790 Continuation-In-Part WO2007084997A2 (en) 2006-01-19 2007-01-19 Flat tube, flat tube heat exchanger, and method of manufacturing same
US6374408A Continuation-In-Part 2006-01-19 2008-06-06

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US13/206,080 Continuation-In-Part US8434227B2 (en) 2006-01-19 2011-08-09 Method of forming heat exchanger tubes

Publications (1)

Publication Number Publication Date
US20080313906A1 true US20080313906A1 (en) 2008-12-25

Family

ID=40030752

Family Applications (1)

Application Number Title Priority Date Filing Date
US12/140,524 Abandoned US20080313906A1 (en) 2006-01-19 2008-06-17 Method of forming heat exchanger tubes

Country Status (2)

Country Link
US (1) US20080313906A1 (en)
DE (1) DE102007028710B4 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120297850A1 (en) * 2011-04-06 2012-11-29 Chauncey Edward W Method of preparing a metallic tape for use on a joint
US8434227B2 (en) 2006-01-19 2013-05-07 Modine Manufacturing Company Method of forming heat exchanger tubes
US20140123720A1 (en) * 2011-07-11 2014-05-08 Wisco Lasertechnik Gmbh Method and apparatus for producing tailored sheet-metal strips
US20210333055A1 (en) * 2020-04-28 2021-10-28 Hamilton Sundstrand Corporation Stress relieving additively manufactured heat exchanger fin design
CN117920907A (en) * 2024-03-21 2024-04-26 张家港三丰机电开发有限公司 Intelligent temperature control wire stretcher special for copper wire production and control system thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010022713A1 (en) 2010-06-04 2011-12-08 Modine Manufacturing Co. Apparatus and method for producing pipes
JP5861549B2 (en) 2012-04-04 2016-02-16 株式会社デンソー Tube and heat exchanger provided with the tube

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3021804A (en) * 1955-02-18 1962-02-20 Modine Mfg Co Method of fabricating heat exchangers
US5271754A (en) * 1988-03-24 1993-12-21 Sigurd Bauerecker Process for producing fluorescent or phosphorescent pigments coated with glass
US20040108305A1 (en) * 2002-09-28 2004-06-10 Gunter Harnisch Method and apparatus for laser cutting sheet metal parts

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2757628A (en) 1952-09-17 1956-08-07 Gen Motors Corp Method of making a multiple passage heat exchanger tube
JPS63264218A (en) * 1987-04-21 1988-11-01 Calsonic Corp Manufacture of heat exchanger tube and its apparatus
US5201117A (en) * 1991-11-04 1993-04-13 General Motors Corporation Method and apparatus for sizing and cutting tubing
DE19641144A1 (en) * 1996-10-05 1998-04-16 Fischer Edelstahl Rohre Gmbh Method for manufacturing tubular component
DE102006033568B4 (en) 2006-07-20 2010-08-05 Modine Manufacturing Co., Racine Manufacturing process for pipes and rolling mill for carrying out this process
DE102006029378B4 (en) 2006-06-27 2014-02-13 Modine Manufacturing Co. Flat tube for heat exchangers and manufacturing process

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3021804A (en) * 1955-02-18 1962-02-20 Modine Mfg Co Method of fabricating heat exchangers
US5271754A (en) * 1988-03-24 1993-12-21 Sigurd Bauerecker Process for producing fluorescent or phosphorescent pigments coated with glass
US20040108305A1 (en) * 2002-09-28 2004-06-10 Gunter Harnisch Method and apparatus for laser cutting sheet metal parts

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8434227B2 (en) 2006-01-19 2013-05-07 Modine Manufacturing Company Method of forming heat exchanger tubes
US20120297850A1 (en) * 2011-04-06 2012-11-29 Chauncey Edward W Method of preparing a metallic tape for use on a joint
US8800342B2 (en) * 2011-04-06 2014-08-12 Edward W. Chauncey Method of preparing a metallic tape for use on a joint
US20140123720A1 (en) * 2011-07-11 2014-05-08 Wisco Lasertechnik Gmbh Method and apparatus for producing tailored sheet-metal strips
US9789530B2 (en) * 2011-07-11 2017-10-17 Wisco Lasertechnik Gmbh Method and apparatus for producing tailored sheet-metal strips
US20210333055A1 (en) * 2020-04-28 2021-10-28 Hamilton Sundstrand Corporation Stress relieving additively manufactured heat exchanger fin design
CN117920907A (en) * 2024-03-21 2024-04-26 张家港三丰机电开发有限公司 Intelligent temperature control wire stretcher special for copper wire production and control system thereof

Also Published As

Publication number Publication date
DE102007028710A1 (en) 2008-12-24
DE102007028710B4 (en) 2013-08-08

Similar Documents

Publication Publication Date Title
US8434227B2 (en) Method of forming heat exchanger tubes
US20080313906A1 (en) Method of forming heat exchanger tubes
US8561451B2 (en) Tubes and method and apparatus for producing tubes
US2757628A (en) Method of making a multiple passage heat exchanger tube
KR100227209B1 (en) Heat transfer tube having grooved inner surface and production method therefor
EP0617250B1 (en) A method of producing a refrigerant tube for heat exchangers
US7140107B2 (en) Stacking-type, multi-flow, heat exchangers and methods for manufacturing such heat exchangers
US20080078541A1 (en) Roll formed manifold with integral distributor tube
JP2006329578A (en) Method and device for manufacturing inner finned tube
GB2268260A (en) Heat exchange tubes formed from a unitary portion of sheet or strip material
US20120247600A1 (en) Rotary die forming process and apparatus for fabricating multi-port tubes
EP3043137A1 (en) Heat transfer pipe, method for manufacturing heat transfer pipe, and heat exchanger
JP2005177921A (en) Tube manufacturing method, heat exchanging tube, and heat exchanger
CN1873361B (en) Tube for heat exchanger and manufacture method thereof
US9702598B2 (en) Evaporator
CN104995476A (en) Heat exchanger and production method therefor
WO1995017985A1 (en) Method and apparatus for producing header tank of heat exchanger
EP3108980A1 (en) Method of fabricating a tube for an evaporator and device for fabricating a tube for an evaporator
KR19980071026A (en) Sheet for manufacturing fins for heat exchanger and fins for heat exchanger
JP6435347B2 (en) Manufacturing method of heat exchanger fins
WO2019131377A1 (en) Device for manufacturing fins and method for manufacturing fins
JP3779447B2 (en) Manufacturing equipment for heat exchanger tubes
KR100906295B1 (en) Piping of air conditioner, and apparatus and method for manufacturing the same
CN110998211A (en) Heat exchanger tube
JP7221918B2 (en) Electrode sheet manufacturing method

Legal Events

Date Code Title Description
AS Assignment

Owner name: MODINE MANUFACTURING COMPANY, WISCONSIN

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:EISELE, SIEGFRIED;REEL/FRAME:021326/0490

Effective date: 20080703

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION