SU704469A3 - Machine for continuous replacing of rails and sleepers of a railway - Google Patents

Machine for continuous replacing of rails and sleepers of a railway

Info

Publication number
SU704469A3
SU704469A3 SU701464751A SU1464751A SU704469A3 SU 704469 A3 SU704469 A3 SU 704469A3 SU 701464751 A SU701464751 A SU 701464751A SU 1464751 A SU1464751 A SU 1464751A SU 704469 A3 SU704469 A3 SU 704469A3
Authority
SU
USSR - Soviet Union
Prior art keywords
sleepers
rails
frame
machine
fasteners
Prior art date
Application number
SU701464751A
Other languages
Russian (ru)
Inventor
Плассер Франц
Тойрер Иозеф
Original Assignee
Франц Плассер Банбаумашинен -Индустригезельшафт М.Б.Х. (Фирма)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Франц Плассер Банбаумашинен -Индустригезельшафт М.Б.Х. (Фирма) filed Critical Франц Плассер Банбаумашинен -Индустригезельшафт М.Б.Х. (Фирма)
Application granted granted Critical
Publication of SU704469A3 publication Critical patent/SU704469A3/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/06Renewing or cleaning the ballast in situ, with or without concurrent work on the track
    • E01B27/11Renewing or cleaning the ballast in situ, with or without concurrent work on the track combined with concurrent renewal of track components
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/05Transporting, laying, removing, or renewing both rails and sleepers

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Claims (1)

дл  от тй  скреплений, устройство 15 дл  сн  ти  четарых шпал, направл ющее устройство 16 и роликовые захваты 17 дл  сн ти  старых и установки новых рельсов 18 и 19, а также устройство 20 дл  раскладки новых шпал Иг устройство 21 дл  установки скреплений. На транспортном средстве 13 установлено подвижное устройство 22 дл  транспортировки и погрз КИ новых шпал, а на транспортном средг стве; 23 - устройство 24 дл  транспортировки и nok-рузки старых шпал. Щ машине возможна устайовка запасного резервуара дл  шебн  с целью подсыпки его в нес бходимых случа х. После уплотнени  балласта: уплотнител ми 25 он может быть подсыпан 4 путь при помощи ленточных конвейеров 11 4 26. Положение пути контролируетс  устройством 27 при помощи образованной им базиснрй пр мой 23, например, в ввде инфракрасйых лучей или лучей лазера. Заслонка 29 служит дл  правильной установки исходной пр мой при помощи устройства 27. Машина перемещаетс  локомотивом 30. nfJH замене рельсов и шпал железнодорожно го машина перемещаетс  в направлении, пока нном стрелкой А. Производитс  сн тие скреплений и старых шпал, очистка и планировка балласта, замена рельсов и установка новых шпал и скреплений, при этом машина может работать как на пр мых участках, так и на криволинейных. Формула изобретени  Машина дл  нeпfгpывнoй замены рельсов и шпал железнодорожного пути, содержаща  раму , устройства дл  сн ти  и установки скреплений и закрепленные на раме устройства дл  сн ти  рельсов и шпал, устройство дл  распределени  и планировки балласта, расположенное в средней части рамы, и устройства дл  установки шпал и рельсов, отличающа с  тем, что, с делью повышени  эффективности ее использовани , она снабжена расположенным в средней части рамы устройством дл  очистки балласта и проход щим от ието к концу рамы ленточным конвейером дл  очшценното балласта, при этом рама выполнена из трех шарнирно соединенных между собой частей. Источники информации, прин тые во внимание при экспертизе 1. Патент Австрии N 273201, .л. 19а, 35, 1969 (прототип).for removing fasteners, a device 15 for removing sleepers, a guide device 16 and roller clamps 17 for removing old and installing new rails 18 and 19, as well as a device 20 for laying out new sleepers I for installing 21 fasteners. The vehicle 13 is equipped with a mobile device 22 for transporting and loading new sleepers, and on the vehicle; 23 is a device 24 for transporting and nok-ruzki old sleepers. In the machine, it is possible to install a storage tank for the shebna in order to add it in the carrying cases. After the ballast is compacted: with the seals 25, it can be poured in 4 ways using belt conveyors 11 4 26. The position of the path is controlled by the device 27 with the help of the basis 23 formed by it, for example, in infrared or laser beams. The shutter 29 serves to properly install the original straight with the device 27. The machine moves with locomotive 30. nfJH replacing rails and sleepers; the railway machine moves in the direction indicated by arrow A. rails and installation of new sleepers and fasteners, while the machine can work both on straight sections and on curvilinear ones. The invention The machine for non-continuous replacement of rails and railway sleepers, comprising a frame, devices for removing and installing fasteners and devices for removing rails and sleepers mounted on the frame, a device for distributing and leveling ballast, located in the middle part of the frame, and devices for installation of sleepers and rails, characterized in that, in order to increase the efficiency of its use, it is equipped with a device for cleaning ballast located in the middle part of the frame and a ribbon box running from one to the end of the frame A conveyor for very ballast, the frame is made of three parts hinged together. Sources of information taken into account during the examination 1. Austrian patent N 273201, l. 19a, 35, 1969 (prototype).
SU701464751A 1969-10-07 1970-08-17 Machine for continuous replacing of rails and sleepers of a railway SU704469A3 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT945369A AT316614B (en) 1969-10-07 1969-10-07 Mobile devices for the continuous replacement or renewal of rails and sleepers of a track

Publications (1)

Publication Number Publication Date
SU704469A3 true SU704469A3 (en) 1979-12-15

Family

ID=3614271

Family Applications (1)

Application Number Title Priority Date Filing Date
SU701464751A SU704469A3 (en) 1969-10-07 1970-08-17 Machine for continuous replacing of rails and sleepers of a railway

Country Status (13)

Country Link
US (1) US3685456A (en)
JP (1) JPS557481B1 (en)
AT (1) AT316614B (en)
CA (1) CA919993A (en)
CH (1) CH525330A (en)
DE (1) DE2023979C3 (en)
ES (1) ES384307A1 (en)
FR (1) FR2062824A5 (en)
GB (1) GB1322545A (en)
SE (1) SE365564B (en)
SU (1) SU704469A3 (en)
YU (1) YU34553B (en)
ZA (1) ZA706193B (en)

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH541028A (en) * 1971-07-07 1973-08-31 Matisa Materiel Ind Sa Method of jamming railways and device for its implementation
CH583822A5 (en) * 1974-07-11 1977-01-14 Scheuchzer Auguste Les Fils De
AT345878B (en) * 1975-07-11 1978-10-10 Plasser Bahnbaumasch Franz METHOD AND DEVICE FOR CHANGING A TRACK IN SECTIONS
DE2550391C2 (en) * 1975-11-10 1984-08-02 Fa. Max Knape, 8011 Kirchheim Method for removing bedding material from ballast bedding
AT353306B (en) * 1976-09-13 1979-11-12 Plasser Bahnbaumasch Franz SELF-PROPELLED BALL BED CLEANING MACHINE, IN PARTICULAR FOR THE AREA OF SWITCHES
AT358087B (en) * 1976-05-31 1980-08-25 Plasser Bahnbaumasch Franz SELF-DRIVING TRACK BUILDING MACHINE, IN PARTICULAR BOTTLE BED CLEANING MACHINE
AT346887B (en) * 1976-10-15 1978-04-15 Plasser Bahnbaumasch Franz MOBILE DEVICE FOR CONTINUOUSLY REPLACING A RAILWAY consisting of RAILS AND CROSS-SLEEPERS
JPS5819803B2 (en) * 1977-01-21 1983-04-20 日本国有鉄道 Paved track sleeper replacement device
AT350098B (en) * 1977-03-17 1979-05-10 Plasser Bahnbaumasch Franz TRACK CONSTRUCTION MACHINE, IN PARTICULAR TRACK COMPACTION MACHINE FOR NARROW GAUGE TRACKS
AT351069B (en) * 1977-09-02 1979-07-10 Plasser Bahnbaumasch Franz MOBILE DEVICE FOR CONTINUOUS REPLACEMENT OR RENEWING A TRACK COMPOSED OF RAILS AND SLEEPERS
AT359541B (en) * 1978-06-28 1980-11-10 Plasser Bahnbaumasch Franz DEVICE FOR REPLACING THE RAILS AND SLEEPERS OF A TRACK
AT366435B (en) * 1978-12-12 1982-04-13 Plasser Bahnbaumasch Franz EQUIPMENT FOR REPLACEMENT OR RENEWING THE RAILS OF A LAYED TRACK
US4250812A (en) * 1979-10-11 1981-02-17 Loram Maintenance Of Way Undertrack fabric applicator
AT370151B (en) * 1981-03-04 1983-03-10 Plasser Bahnbaumasch Franz BALLET CLEANING MACHINE AND HARD FOAM PANEL LAYING
AT384445B (en) * 1986-02-12 1987-11-10 Plasser Bahnbaumasch Franz MOBILE SYSTEM FOR RENEWING THE RAILS AND SILLS OF A TRACK
ATE44788T1 (en) * 1986-07-25 1989-08-15 Plasser Bahnbaumasch Franz MACHINE FOR EXCHANGE OR. REPLACING THE RAILS AND SLEEPERS OF A LAYED TRACK.
CH686144A5 (en) * 1991-10-30 1996-01-15 Matisa Materiel Ind Sa Renewal train a railway line.
IT1283554B1 (en) * 1995-04-18 1998-04-22 Plasser Bahnbaumasch Franz SYSTEM FOR THE CONTINUOUS RENEWAL OF A TRACK
FR2741640B1 (en) * 1995-11-27 1997-12-26 Sud Ouest Travaux RAILWAY RENEWAL PROCESS
DE10008986A1 (en) * 2000-02-25 2001-08-30 Gsg Knape Gleissanierung Gmbh Reconstruction/modification method for railway track uses appliance to remove/ regenerated old track materials and construct new track, in one single working phase and one direction only
AT3918U3 (en) * 2000-07-13 2001-08-27 Plasser Bahnbaumasch Franz MACHINE FOR RENEWING A TRACK
AT3917U3 (en) * 2000-07-13 2001-08-27 Plasser Bahnbaumasch Franz MACHINE FOR RENEWING A TRACK
US6981452B2 (en) * 2004-02-06 2006-01-03 Herzog Contracting Corp. Method and apparatus for unloading ribbon rails from rail cars
US7350467B2 (en) 2004-08-20 2008-04-01 Loram Maintenance Of Way, Inc. Long rail pick-up and delivery system
AT502438B1 (en) * 2005-08-25 2008-03-15 Oebb Infrastruktur Bau Ag PROCESS AND VEHICLE COMBINATION FOR WORKING IRONS
AT503019B1 (en) * 2006-03-07 2007-07-15 Plasser Bahnbaumasch Franz Track renovating method, involves raising rails with respect to working direction of cleaning machine, and moving rails outwards longitudinal side of cleaning machine with respect to transverse direction of cleaning machine
DE102008026873B4 (en) * 2008-06-05 2012-02-02 Ralf Zürcher trolley
ITGE20120055A1 (en) * 2012-05-30 2013-12-01 Enrico Valditerra "RAILWAY MASSIVE RAILWAY MACHINE WITH VARIABLE FRONT EXCAVATION CHAIN"
AT520387B1 (en) * 2017-08-25 2019-12-15 Plasser & Theurer Export Von Bahnbaumaschinen Gmbh Method and device for renewing sleepers of a track

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2997001A (en) * 1956-03-03 1961-08-22 Andre Scheuchzer Method of repairing railway tracks and an installation for carrying out the same
US3286648A (en) * 1963-08-30 1966-11-22 Brosnan Dennis William Rail renewal process
US3330219A (en) * 1963-09-23 1967-07-11 Plasser Franz Method and apparatus for replacing an old track by a new track
US3465687A (en) * 1966-11-18 1969-09-09 New York Central Railroad Co T Rail positioning system

Also Published As

Publication number Publication date
SE365564B (en) 1974-03-25
AT316614B (en) 1974-07-25
ES384307A1 (en) 1973-02-16
FR2062824A5 (en) 1971-06-25
JPS557481B1 (en) 1980-02-26
DE2023979B2 (en) 1978-04-20
CH525330A (en) 1972-07-15
GB1322545A (en) 1973-07-04
CA919993A (en) 1973-01-30
YU195570A (en) 1979-02-28
DE2023979C3 (en) 1978-12-07
DE2023979A1 (en) 1971-04-15
US3685456A (en) 1972-08-22
YU34553B (en) 1979-09-10
ZA706193B (en) 1971-05-27

Similar Documents

Publication Publication Date Title
SU704469A3 (en) Machine for continuous replacing of rails and sleepers of a railway
ES479737A1 (en) Train for the renewal of a railway track.
UA5581A1 (en) Machine for continuous laying layer of sand between earth sheet and layer of ballast of rail track
GB1523944A (en) Railway track laying
SE8700444D0 (en) SAVING PUMPING MACHINE WITH LIFTING, WITH STOPPING AND EVEN WITH DIRECTORY
SE7613821L (en) DEVICE FOR LAYOUT OR SECTIONAL REPLACEMENT OF RAILWAY SAVINGS
RU94033635A (en) Device for transportation and replacement of track rails
DE59200876D1 (en) Dolly.
SE9602136D0 (en) Storage trolley for storage of race goods
DE3372507D1 (en) Track renewal train
ES438386A1 (en) Method of renewal of a railroad track and train therefor
SE9100711D0 (en) DISTRIBUTING THE MACHINE AND PLANNING THE CONTROL SCOTTERS
DK0499018T3 (en) Cleaning machine
GB1278522A (en) Improvements relating to track maintenance vehicles
YU157390A (en) THRESHOLDING DEVICE
UA13001A (en) Ballast cleaning machine
FR2299459A1 (en) Renewal of old railway track - using lifting apparatus on end of train carrying new sleepers
GB1066498A (en) Apparatus for removing ballast from beneath the crossties of a railroad track
GB1278524A (en) Mobile apparatus for laying and/or taking up the sleepers of railway track
ES440332A1 (en) Shinkohokonitaishi yokohokonyodosuruyokenkasareteiru gondoratsukikensuitetsudo
SE8007800L (en) METHOD AND DEVICE FOR MACHINE HANDLING OF MATERIALS ON RAILWAY RAILWAYS, SPECIAL BALLAST MATERIAL
NL7315944A (en) Roof tile laying system - uses transverse slats as guide rails for truck carrying tile stock
GB1006639A (en) Apparatus for the clearing of railway track ballast
ES2110750T3 (en) TRAVERSE FOR RAILS OF A ROAD SUPERSTRUCTURE FOR RAILWAY VEHICLES.
GB316081A (en) Improved means for relaying railway tracks