SU699100A1 - Method of erecting prop in soil - Google Patents

Method of erecting prop in soil

Info

Publication number
SU699100A1
SU699100A1 SU782630424A SU2630424A SU699100A1 SU 699100 A1 SU699100 A1 SU 699100A1 SU 782630424 A SU782630424 A SU 782630424A SU 2630424 A SU2630424 A SU 2630424A SU 699100 A1 SU699100 A1 SU 699100A1
Authority
SU
USSR - Soviet Union
Prior art keywords
stand
well
soil
backfilling
drilling
Prior art date
Application number
SU782630424A
Other languages
Russian (ru)
Inventor
Арнольд Борисович Мясников
Александр Владимирович Романов
Сергей Александрович Шелементьев
Виктор Сергеевич Пименов
Original Assignee
Калининский Ордена Трудового Красного Знамени Политехнический Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Калининский Ордена Трудового Красного Знамени Политехнический Институт filed Critical Калининский Ордена Трудового Красного Знамени Политехнический Институт
Priority to SU782630424A priority Critical patent/SU699100A1/en
Application granted granted Critical
Publication of SU699100A1 publication Critical patent/SU699100A1/en

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

(54) СПОСОБ УСТАНОВКИ СТОЙКИ В ГРУНТЕ(54) METHOD FOR INSTALLATION OF STANDS IN GROUND

Claims (2)

Изобретение относитс  к области строительства , в основном дорожного, и касаетс  установки в грунте ограждающих тумб, светофоров, указателей, опор освещени  и низковольтных линий.. Известны способы установки стойки в грунте, включающие разработку котлованов, введение в них стоек и обратную засыпку полостей грунjOM 1. Однако несмотр  на механизацию земл ных работ, обратную засыпку выполн ют вручную, что делает эти способы малопроизводительными . Наиболее близким к изобретению  вл етс  способ установки стойки в грунте, предусматривающий бурение скважины, введение в нее стойки и обратную засыпку скважины 2. Этот способ реализуют с помощью специальных бурил но-крановых мащин. Засыпку полости между стойкой и стенками скважины производ т также вручную. В процессе бурени  в несв зных и насыпных грунтах происходит осыпание стенок скр жины. Недостаточное качество ручной обратной засыпки и наличие в основании стойки осыпавщегос  грунта снижает устойчивость стойки. Цель изобретени  - уменьшение трудоемкости путем механизации обратной засыпки скважины. Это достигаетс  тем, что бурение выполн ют с обсадной трубой, при зтом разбуренный грунт оставл ют у усть  скважины и производ т обратную засыпку этим грунтом- посредством подъема трубы возвратно-поступательными движени ми . Установку стойки в грунт производ т следующим образом. На обочине дороги бур т скважины и одновременно ввод т в нее обсадную трубу, предохран ющую стенки скважины от осыпани . Часть выбуренного грзоаа оставл ют у усть  скважины . После извлечени  бура из обсадной трубы в нее ввод т стойку. Затем вынимают обсадную трубу из скважины, придава  ей возвратно-поступательные движени . При этом происходит обсыпка стойки расположенным у скважины грунтом, который заполн ет воронку, образованную после уплотнени  грунта обсадной трубой вокруг стойки. Такой способ установки стойки в грунте позвол ет исключить ручной труд,обеспечить качествен369 HjTo обратную засыпку скважины и эффективно производить установку стоек в несв зных н насызных грунтах. Способ может быть осуществлг  с использованием известных бурильно-кран ых машин. Формула изобретени  Способ установки, стойки в грунте, включаю .ЩЕЙ бурение скважины, введение в нее стойки и обратную засыпку грунтом, отличающ 5 и с   тем, что, с целью уменьшени  трудоемкости путем механизации обратной засыпки , бурение выполн ют с -обсадной трубой. при этом разбуренный грунт оставл ют у усть  скважины и производ т обратную засыпку этим грунтом посредством подъема трубы возвратнопоступательными движени ми. Источники информации, прин тые во внимание при экспертизе 1.Бауман В. А. и Лапира Ф. А. Строительные машины, М., Машиностроение, 1976, т. 1, с, 140. The invention relates to the field of construction, mainly road, and concerns the installation of enclosing pedestals, traffic lights, signposts, lighting poles and low voltage lines in the ground. However, despite the mechanization of the earthworks, backfilling is done manually, which makes these methods inefficient. The closest to the invention is a method of installing a stand in the ground, which involves drilling a well, introducing a stand into it, and backfilling hole 2. This method is implemented using special drill-crane machines. The cavity between the stand and the walls of the well is also manually filled. In the process of drilling in groundless and loose soils, the walls of the skryina fall. Inadequate quality manual backfill and the presence in the base of the stand showered soil reduces the stability of the stand. The purpose of the invention is to reduce the labor intensity by mechanizing the backfilling of a well. This is achieved by drilling with a casing, whereby the drilled soil is left at the wellhead and backfilled with this soil by lifting the pipe with reciprocating movements. The rack is installed in the ground as follows. On the side of the road, a hole is drilled and at the same time a casing pipe is inserted into it, preventing the walls of the well from falling. A portion of the drilled hole was left at the wellhead. After the drill is removed from the casing, a rack is inserted into it. The casing is then removed from the well, giving it a reciprocating motion. When this occurs, the stand is sprayed with primer located at the well, which fills the funnel formed after compaction of the soil by the casing around the stand. This method of installing the stand in the ground eliminates manual labor, ensures high quality backfilling of the well and effectively installs the stands in non-bonded and saturable soils. The method can be carried out using well-known drilling machines. The Invention Method The method of installation, stand in the ground, includes drilling a well, inserting a stand into it and backfilling it with soil, differing from 5 and so that, in order to reduce labor intensity by mechanizing backfilling, drilling is done with a downhole. at the same time, the drilled soil is left at the well head and is backfilled with this soil by lifting the pipe with reciprocating movements. Sources of information taken into account during the examination 1.Bauman V.A. and Lapira F.A. Construction Machines, M., Mashinostroenie, 1976, V. 1, p. 140. 2.Каталог машин, механизмов, оборудовани , средств автоматизации и малой механизации, выпускаемых предпри ти ми Министерства транспортного строительства СССР, М., Орггрансстрой , 1975, с. 97-98 (прототип).2. Catalog of machines, mechanisms, equipment, automation and small-scale mechanization produced by enterprises of the Ministry of Transport Construction of the USSR, Moscow, Orggransstroy, 1975, p. 97-98 (prototype).
SU782630424A 1978-06-12 1978-06-12 Method of erecting prop in soil SU699100A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782630424A SU699100A1 (en) 1978-06-12 1978-06-12 Method of erecting prop in soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782630424A SU699100A1 (en) 1978-06-12 1978-06-12 Method of erecting prop in soil

Publications (1)

Publication Number Publication Date
SU699100A1 true SU699100A1 (en) 1979-11-25

Family

ID=20770890

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782630424A SU699100A1 (en) 1978-06-12 1978-06-12 Method of erecting prop in soil

Country Status (1)

Country Link
SU (1) SU699100A1 (en)

Similar Documents

Publication Publication Date Title
RU94029677A (en) Template and process for drilling and filling several boreholes
GB2017248B (en) Expansion shell assembly for the method of anchoring a bolt in a bore hole in a rock formation
SU699100A1 (en) Method of erecting prop in soil
US2450366A (en) Apparatus and method for seismographic exploration shooting
US2049236A (en) Surveying underground structures
RU2188948C1 (en) Method of constructing vertical mine shaft
JPS543344A (en) Method of excavating underground hole by tunnel boring machine
SU1076554A1 (en) Method of constructing a water intake well
SU756045A1 (en) Method of vertical mining in filling massif
GB1103097A (en) Improvements in methods of driving through subterranean rock strata in the production of vertical slots dug into the ground
SU724735A1 (en) Method of mining coal seams
RU94030130A (en) Method for recuperation of earth reservoirs
SU397867A1 (en) METHOD FOR ELIMINATING USED EXPLOSIVE DRILLS IN SEISMIC EXPLOSION
JPS57140424A (en) Construction work of reinforced soil
SU1027397A1 (en) Method of sinking a vertical mine working
SU514059A1 (en) The method of mounting land korea
SU767278A1 (en) Method of erecting wall in soil
SU1177500A1 (en) Method of protecting excavation workings
RU95106727A (en) Method for forming extended pits by excavation explosure
GB1340355A (en) Method and apparatus for making a bore hole in the ground
JPS5320634A (en) Method and apparatus for erecting electric light pole using lead pipe
SU1278394A1 (en) Method of determining sagging of loess body under own weight
DE59200866D1 (en) Process for limiting subsidence in the creation of underground cavities.
SU796441A1 (en) Method of securing preparatory workings of lower layers of thick coal beds
JPS56142913A (en) Method and apparatus for installing forcible insertion type borehole expansion loading tester