RU2694662C1 - Erection method of lined building - Google Patents

Erection method of lined building Download PDF

Info

Publication number
RU2694662C1
RU2694662C1 RU2018137735A RU2018137735A RU2694662C1 RU 2694662 C1 RU2694662 C1 RU 2694662C1 RU 2018137735 A RU2018137735 A RU 2018137735A RU 2018137735 A RU2018137735 A RU 2018137735A RU 2694662 C1 RU2694662 C1 RU 2694662C1
Authority
RU
Russia
Prior art keywords
elements
anchors
concrete
formwork
facing
Prior art date
Application number
RU2018137735A
Other languages
Russian (ru)
Inventor
Владимир Владимирович Большаков
Original Assignee
Владимир Владимирович Большаков
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Владимир Владимирович Большаков filed Critical Владимир Владимирович Большаков
Priority to RU2018137735A priority Critical patent/RU2694662C1/en
Application granted granted Critical
Publication of RU2694662C1 publication Critical patent/RU2694662C1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

FIELD: construction.
SUBSTANCE: invention relates to construction. Method of erected lined building includes installation of external facing and heat-insulating materials with subsequent floor erection of reinforced concrete bearing walls of building. Facing elements are installed in design position, placing end elements of their anchors, available on reverse side of each facing element, in inter-formwork space, and fixing the position of the installed facing element in space by means of links arranged in their upper part, after which the end parts of anchors placed in it are embedded by concrete supply into the shelling space. Quality of facing elements is represented by large-size elements of architectural concrete of factory fabrication, which are installed on bearing surface in design position, after which the formwork and carcass structure is erected with arrangement of end elements of anchors of facing elements in inter-formwork space. Top part of facing elements is fixed by means of temporary bonds, which are removed after hardening of concrete.
EFFECT: technical result is providing high accuracy of installation using simple means, reducing time and labour costs for erection of buildings, avoiding the need for special, high-altitude and steep-running works, use of forests, as well as possibility of increasing bearing capacity of its external walls due to the fact that facing elements will take part of load from superposed structural elements of structure.
8 cl

Description

Изобретение относится к области строительства и может быть использовано при облицовке монолитных железобетонных стен жилых домов, зданий и сооружений.The invention relates to the field of construction and can be used when facing monolithic reinforced concrete walls of residential buildings, buildings and structures.

Известен способ возведения монолитных стен зданий и сооружений в несъемной опалубке бетона, включающий установку одновременно внешних и внутренних отдельных щитов опалубки из древесно-минеральных материалов и фиксацию их снизу и поверху гибкими связями в виде монтажных хомутов (первый ряд устанавливается на захватку по всему периметру стен и перегородок). Бетонную смесь укладывают в несъемную опалубку, смесь равномерно распирает щиты каждого ряда до упора по гибким связям и фиксирует плоскости панелей в проектном положении при одинаковой толщине стены. Арматура устанавливается до установки щитов опалубки (C1, RU, №2198988, 2003).There is a method of erecting monolithic walls of buildings and structures in permanent concrete formwork, including the installation of both external and internal separate formwork boards made of wood-mineral materials and their fixation from the bottom and top by flexible connections in the form of mounting clamps (the first row is installed on the hook around the perimeter of the walls and partitions). The concrete mixture is placed in a permanent formwork, the mixture evenly spreads the shields of each row until it stops through flexible connections and fixes the planes of the panels in the design position with the same thickness of the wall. The reinforcement is installed before the installation of formwork panels (C1, RU, No. 21898988, 2003).

Недостатками известного способа является то, что при заливке бетоном не предусмотрена жесткая фиксация по вертикали, так как: гибкие связи при заливке все равно дадут отклонения, и требуются другие приспособления для удержания строгой вертикальности при заливке. Помимо этого, известная технология не позволяет устанавливать крупногабаритный облицовочный материал. The disadvantages of this method are that, when concrete is poured, rigid fixation along the vertical is not provided, as: flexible connections will give deflections when pouring, and other devices are required to maintain strict verticality during pouring. In addition, the well-known technology does not allow to install large-sized cladding material.

Наиболее близким к заявленному изобретению является способ возведения облицованного здания, предусматривающий установку внешнего и внутреннего облицовочного материала, а также теплоизолирующего материала одновременно с циклическим возведением несущих стен здания, для чего до их возведения устанавливают облицовочные элементы, размещают концевые элементы их анкеров, установленных на оборотной стороне каждого облицовочного элемента, в межопалубочном пространстве и фиксируют положение установленного облицовочного элемента в пространстве посредством связей, размещаемых в верхней их части, после чего в изолированное пространство подают бетонную смесь (C1, RU, № 2387762, 2010).The closest to the claimed invention is a method of erecting a lined building, providing for the installation of external and internal lining material, as well as thermal insulation material simultaneously with the cyclic erection of the bearing walls of the building, for which, prior to their erection, lining elements are installed, end elements of their anchors are installed on the back side each facing element in the inter-deck space and fix the position of the installed facing element in the space Constance through links placed in their upper part, after which a concrete mix is supplied to the isolated space (C1, RU, No. 2387762, 2010).

Недостатками известного решения являются значительные временные и трудовые затраты на возведение облицовки, необходимость возведения строительных лесов.The disadvantages of the known solutions are significant time and labor costs for the construction of cladding, the need for the construction of scaffolding.

Техническим результатом, достигаемым при реализации заявленного изобретения, является возможность использования крупноразмерных облицовочных элементов, обеспечение высокой точности монтажа простыми средствами, снижение затрат времени и труда на возведение здания, отсутствие необходимости в специальных, высотных и верхолазных работах, использования лесов, а также возможность повышения несущей способности внешних его стен за счет того, что облицовочные элементы будут воспринимать часть нагрузки от вышерасположенных конструктивных элементов сооружения.The technical result achieved in the implementation of the claimed invention is the possibility of using large-sized cladding elements, ensuring high accuracy of installation with simple means, reducing the time and labor costs for erecting a building, no need for special, high-rise and climbing works, the use of scaffolding, and the possibility of increasing the carrier the ability of its outer walls due to the fact that the cladding elements will take part of the load from the upstream structural elements of construction.

Указанный технический результат достигается тем, что в способе возведения облицованного здания, предусматривающим установку внешнего облицовочного и теплоизолирующего материалов и последующее поэтажное возведение железобетонных несущих стен здания, для чего облицовочные элементы устанавливают в проектное положение, размещая концевые элементы их анкеров, замоноличенных на оборотной стороне каждого облицовочного элемента, в межопалубочном пространстве и фиксируют положение установленного облицовочного элемента в пространстве посредством связей, размещаемых в верхней их части, после чего подачей бетона в межопалубочное пространство замоноличивают размещенные в нем концевые части анкеров, в качестве облицовочных элементов используют крупноразмерные элементы архитектурного бетона заводского изготовления с анкерами на оборотной стороне, которые устанавливают на опорную поверхность в проектном положении, после чего возводят конструкцию опалубки и арматурного каркаса, фиксируют верхнюю часть облицовочных элементов посредством временных связей, которые удаляют после твердения бетона.This technical result is achieved in that in the method of erection of the lined building, providing for the installation of external facing and thermal insulation materials and the subsequent floor-by-floor construction of reinforced concrete bearing walls of the building, for which the facing elements are installed in the design position, placing the terminal elements of their anchors embedded in the back side of each facing element in the inter-deck space and fix the position of the installed facing element in space by The radios of connections placed in the upper part of them, after which the end parts of the anchors placed in it are monolithic into the inter-decking space, large-sized elements of factory-made architectural concrete with anchors on the reverse side that are installed on the supporting surface in the design position are used as facing elements, then build the formwork and reinforcement cage, fix the upper part of the facing elements by means of temporary connections, which remove t after hardening of concrete.

Возводят железобетонные несущие стены, анкера элементов архитектурного бетона размещают в межопалубочном пространстве, пропуская их через отверстия в неизвлекаемой опалубке. Reinforced concrete bearing walls are erected, anchors of elements of architectural concrete are placed in the inter-deck space, passing them through the holes in the non-removable formwork.

Возводят железобетонные несущие стены, анкера элементов архитектурного бетона размещают в межопалубочном пространстве, пропуская их через зазоры между секциями извлекаемой разрезной опалубки.Reinforced concrete bearing walls are erected, anchors of architectural concrete elements are placed in the interdepartmental space, passing them through the gaps between the sections of the recoverable split formwork.

Теплоизолирующий материал прикрепляют к неизвлекаемой опалубке.Thermal insulation material is attached to a non-removable formwork.

Теплоизолирующий материал прикрепляют к несущей стене после снятия опалубки.Thermal insulation material is attached to the supporting wall after removing the formwork.

В качестве временных связей и используют струбцины.Clamps are used as temporary connections.

В качестве анкеров используют стержневые элементы, приваренные к закладным деталям облицовочных элементов. As anchors use core elements, welded to the mortgage details facing elements.

В качестве крупноразмерных элементов архитектурного бетона заводского изготовления используют секции самонесущей рамы.As large-sized elements of architectural concrete factory made use of self-supporting frame sections.

Заявленное изобретение отличает от известного ряд существенных признаков, - таким образом, оно соответствует условию патентоспособности «новизна».The claimed invention differs from the known number of essential features, - thus, it meets the condition of patentability "novelty."

Заявленный способ не противоречит известным законам физики механики, что позволяет утверждать о его соответствии условию патентоспособности «промышленная применимость». The claimed method does not contradict the known laws of physics of mechanics, which allows to assert its compliance with the condition of patentability "industrial applicability".

Поскольку из уровня техники не известен способ облицовки здания крупноразмерными облицовочными материалами одновременно с возведением железобетонных стен, следует сделать вывод о его соответствии условию патентоспособности «изобретательский уровень».Since the prior art does not know the method of facing a building with large-sized facing materials simultaneously with the erection of reinforced concrete walls, it should be concluded that it meets the patentability requirement of "inventive step".

Способ реализуют следующим образом.The method is implemented as follows.

В качестве облицовочных элементов используют крупноразмерные элементы архитектурного бетона заводского изготовления, которые до возведения несущих конструкций текущего этажа первоначально устанавливают на опорную поверхность (на перекрытие, либо на нижележащий элемент через извлекаемые прокладки) и фиксируют в проектном положении посредством временных связей от верхней части крупноразмерных элементов к перекрытию текущего этажа. Монтаж облицовочных элементов по этой схеме происходит с контролем положения по разметочной линии и вертикальности элемента. Одновременно происходит дефектование крупноразмерных элементов по соответствию их геометрии проекту. Все работы выполняются на перекрытии на любой высоте без привлечения рабочих с высотной специализацией. Определение проектного положения элемента и разбивка монтажных осей выполняется линейными методами без привлечения геодезиста с тахеометром что обеспечивает повышенную точность монтажа вплоть до 0,25% от линейного размера облицовочного элемента.As the cladding elements, large-sized elements of prefabricated architectural concrete are used, which, prior to the construction of the supporting structures of the current floor, are initially installed on the supporting surface (on the floor, or on the underlying element through removable gaskets) and fixed in the design position by temporary connections from the top of the large-size elements to overlap the current floor. The installation of facing elements according to this scheme occurs with the control of the position along the marking line and the verticality of the element. At the same time, there is a flaw detection of large-sized elements in accordance with their geometry to the project. All work is performed on the floor at any height without the involvement of workers with high-rise specialization. The determination of the design position of the element and the breakdown of the mounting axes is performed by linear methods without involving a surveyor with a total station that provides increased installation accuracy of up to 0.25% of the linear size of the cladding element.

Элементы архитектурного бетона имеют замоноличенные или приваренные к закладным деталям анкеры из стандартного проката, не требующие поэтому отдельной сертификации. Количество и профиль анкеров определяется расчетом, из условия несения двойной нагрузки, когда последующий ярус элементов опирается на предыдущий, до замоноличивания анкеров. Положению этих анкеров соответствуют отверстия в наружной несъемной опалубке. Щиты опалубки с закрепленным на них с наружной стороны утеплителем надевают на анкеры и приступают к монтажу арматурного каркаса несущей конструкции и оставшейся части опалубки. При необходимости, производят новое крепление струбцинами верха облицовочных элементов к опалубке, удаляя старое крепление. В случаях, когда применение несъемной опалубки нежелательно, анкеры пропускают в вырезах стыков между отдельными секциями извлекаемой опалубки. В случае с извлекаемой опалубкой, после твердения залитого бетона, извлекают съемную опалубку, а зазоре между облицовочным элементом и несущей стеной размещают утеплительный материал, закрепляя его на поверхности стены любым известным способом. После набора бетоном прочности верхняя часть облицовочного элемента освобождают от временных связей и удаляют дистонцирующие прокладки, которые обеспечивают деформационные швы фасада.Elements of architectural concrete have anchors from standard rolled products that are embedded in monolithic or welded to embedded parts, and therefore do not require separate certification. The number and profile of the anchors is determined by calculation, from the condition of carrying a double load, when the next tier of elements is based on the previous one, before the monoliths of the anchors. The position of these anchors correspond to the holes in the external fixed formwork. The formwork panels with insulator fixed to them from the outside are put on anchors and proceed to the installation of the reinforcement cage of the supporting structure and the remaining part of the formwork. If necessary, make a new fastening clamps top cladding elements to the formwork, removing the old mount. In cases where the use of fixed formwork is undesirable, anchors are passed in the cut-outs of the joints between the individual sections of the formwork to be removed. In the case of removable formwork, after hardening the poured concrete, remove the removable formwork, and the gap between the cladding element and the supporting wall is placed insulating material, fixing it on the wall surface by any known method. After the concrete gains strength, the upper part of the cladding element is freed from temporary connections and the distonation pads are removed, which provide the deformation seams of the facade.

В качестве крупноразмерных элементов архитектурного бетона могут использоваться секции самонесущей металлической рамы, высотой в один этаж, образующей подсистему вентилируемого фасада. В этом случае анкера приваривают к раме и пропускают через опалубку. Крепление утеплителя к стене выполняют через решетку рамы. Далее работы по фасаду выполняются в соответствии с типовой технологической картой, например: ТК-23 «ТИПОВАЯ ТЕХНОЛОГИЧЕСКАЯ КАРТА НА МОНТАЖ ВЕНТИЛИРУЕМОГО ФАСАДА С ОБЛИЦОВКОЙ КОМПОЗИТНЫМИ ПАНЕЛЯМИ» М. 2006.As a large-sized elements of architectural concrete can be used sections of the self-supporting metal frame, the height of one floor, forming a subsystem of the ventilated facade. In this case, the anchor is welded to the frame and passed through the formwork. Fastening insulation to the wall perform through the lattice of the frame. Further, works on the facade are carried out in accordance with a typical technological map, for example: TK-23 “TYPICAL TECHNOLOGICAL CARD FOR INSTALLATION OF VENTILATED FACADE WITH FACING WITH COMPOSITE PANELS” M. 2006.

Claims (8)

1. Способ возведения облицованного здания, предусматривающий установку внешнего облицовочного и теплоизолирующего материалов и последующее поэтажное возведение железобетонных несущих стен здания, для чего облицовочные элементы устанавливают в проектное положение, размещая концевые элементы их анкеров, замоноличенных на оборотной стороне каждого облицовочного элемента, в межопалубочном пространстве, и фиксируют положение установленного облицовочного элемента в пространстве посредством связей, размещаемых в верхней их части, после чего подачей бетона в межопалубочное пространство замоноличивают размещенные в нем концевые части анкеров, отличающийся тем, что в качестве облицовочных элементов используют крупноразмерные элементы архитектурного бетона заводского изготовления с анкерами на оборотной стороне, которые устанавливают на опорную поверхность в проектном положении, после чего возводят конструкцию опалубки и арматурного каркаса с размещением анкеров облицовочных элементов в межопалубочном пространстве, фиксируют верхнюю часть облицовочных элементов посредством временных связей, которые удаляют после твердения бетона.1. The method of erection of the lined building, providing for the installation of external cladding and heat insulating materials and the subsequent floor-by-floor construction of reinforced concrete bearing walls of the building. and fix the position of the installed facing element in space by means of links placed in their upper part, after the end parts of the anchors placed in it are monolithic by feeding concrete into the inter-deck space, characterized in that large-sized elements of factory-made architectural concrete with anchors on the reverse side, which are installed on the supporting surface in the design position, after which they construct the formwork and reinforcement cage with the placement of anchors of the cladding elements in the inter-deck space, fix the upper part of the cladding elements by temporary bonds that are removed after hardening of the concrete. 2. Способ по п. 1, отличающийся тем, что возводят железобетонные несущие стены, анкеры элементов архитектурного бетона размещают в межопалубочном пространстве, пропуская их через отверстия в неизвлекаемой опалубке.2. The method according to p. 1, characterized in that the reinforced concrete load-bearing walls are erected, the anchors of the elements of architectural concrete are placed in the inter-deck space, passing them through the holes in the non-removable formwork. 3. Способ по п. 1, отличающийся тем, что возводят железобетонные несущие стены, анкеры элементов архитектурного бетона размещают в межопалубочном пространстве, пропуская их через зазоры между секциями извлекаемой разрезной опалубки.3. The method according to p. 1, characterized in that the reinforced concrete load-bearing walls are erected, the anchors of the architectural concrete elements are placed in the inter-deck space, passing them through the gaps between the sections of the removable split formwork. 4. Способ по п. 2, отличающийся тем, что теплоизолирующий материал прикрепляют к неизвлекаемой опалубке.4. The method according to p. 2, characterized in that the insulating material is attached to non-removable formwork. 5. Способ по п. 3, отличающийся тем, что теплоизолирующий материал прикрепляют к несущей стене после снятия опалубки.5. The method according to p. 3, characterized in that the insulating material is attached to the supporting wall after removing the formwork. 6. Способ по п. 1 отличающийся тем, что в качестве временных связей используют струбцины.6. The method according to claim 1, characterized in that clamps are used as temporary connections. 7. Способ по п. 1, отличающийся тем, что в качестве анкеров используют стержневые элементы, приваренные к закладным деталям облицовочных элементов.7. The method according to p. 1, characterized in that as anchors use core elements, welded to the embedded parts of the facing elements. 8. Способ по п. 1, отличающийся тем, что в качестве крупноразмерных элементов архитектурного бетона заводского изготовления используют секции самонесущей рамы.8. The method according to claim 1, characterized in that the self-supporting frame sections are used as large-sized elements of architectural concrete of factory production.
RU2018137735A 2018-10-26 2018-10-26 Erection method of lined building RU2694662C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2018137735A RU2694662C1 (en) 2018-10-26 2018-10-26 Erection method of lined building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2018137735A RU2694662C1 (en) 2018-10-26 2018-10-26 Erection method of lined building

Publications (1)

Publication Number Publication Date
RU2694662C1 true RU2694662C1 (en) 2019-07-16

Family

ID=67309370

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2018137735A RU2694662C1 (en) 2018-10-26 2018-10-26 Erection method of lined building

Country Status (1)

Country Link
RU (1) RU2694662C1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3466825A (en) * 1963-08-27 1969-09-16 Karl Guddal Wall structure
DE1683433A1 (en) * 1967-07-01 1971-08-19 Richter Reinhold Fastening element set for ventilated facade panels
SU1590522A1 (en) * 1988-03-31 1990-09-07 Предприятие П/Я М-5835 External face of building and structures
RU2387763C1 (en) * 2008-09-18 2010-04-27 Николай Стефанович Чернов Method for erection of monolithic walls of residential buildings, housings and structures in combined curb
RU2387762C1 (en) * 2008-12-22 2010-04-27 Николай Стефанович Чернов Method for erection of monolithic walls of residential buildings, housings and structures in non-removable curb

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3466825A (en) * 1963-08-27 1969-09-16 Karl Guddal Wall structure
DE1683433A1 (en) * 1967-07-01 1971-08-19 Richter Reinhold Fastening element set for ventilated facade panels
SU1590522A1 (en) * 1988-03-31 1990-09-07 Предприятие П/Я М-5835 External face of building and structures
RU2387763C1 (en) * 2008-09-18 2010-04-27 Николай Стефанович Чернов Method for erection of monolithic walls of residential buildings, housings and structures in combined curb
RU2387762C1 (en) * 2008-12-22 2010-04-27 Николай Стефанович Чернов Method for erection of monolithic walls of residential buildings, housings and structures in non-removable curb

Similar Documents

Publication Publication Date Title
US10837166B2 (en) Building structure and construction method for same
EA010805B1 (en) Insulated concrete form system with variable length wall ties
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN205242706U (en) Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window
RU2335606C1 (en) External sandwich wall of building and method of its erection
RU2598664C1 (en) Method of mounting support masonry formwork profile
EA013175B1 (en) Outer multi-story frame building wall of arcos system and method of erection thereof
RU2552506C1 (en) Method for construction of monolithic structures of buildings and non-removable universal modular formwork system
WO2011127522A1 (en) A method of forming a structural element and a method of building a structure
RU94245U1 (en) LARGE-PANEL MULTI-STOREY RESIDENTIAL BUILDING WITH COMBINED WALLS SERIES 93
RU158675U1 (en) Masonry support formwork profile
RU2459913C2 (en) Set of leave-in-place form by vv podsevalov
RU2694662C1 (en) Erection method of lined building
RU2399731C1 (en) Method for erection of multilayer building wall, which is self-bearing within floor
US20180112388A1 (en) Precast thermally separated cantilevered balcony system and method of using same
RU2385998C1 (en) Wall
RU2363820C1 (en) Method for erection of self-bearing external walls of frame-monolithic houses
RU2706288C1 (en) Construction method
RU2678750C1 (en) Buildings and structures with bearing monolithic reinforced concrete structures construction method using the reinforced concrete wall panels
RU2369697C1 (en) Wall panel by mr av kotov
RU2387763C1 (en) Method for erection of monolithic walls of residential buildings, housings and structures in combined curb
RU2634139C1 (en) Framework universal prefabricated architectural and construction system
RU2338843C1 (en) Method of multistorey building carcassing
RU2353735C2 (en) Method for erection of solid-cast frame buildings
CN114961174B (en) Post-installation process and auxiliary positioning device for smoke exhaust pipe of vertical shaft