RU2189936C2 - Automatically mountable tower lifting crane with boom sidewise folded for transportation - Google Patents

Automatically mountable tower lifting crane with boom sidewise folded for transportation Download PDF

Info

Publication number
RU2189936C2
RU2189936C2 RU98106852A RU98106852A RU2189936C2 RU 2189936 C2 RU2189936 C2 RU 2189936C2 RU 98106852 A RU98106852 A RU 98106852A RU 98106852 A RU98106852 A RU 98106852A RU 2189936 C2 RU2189936 C2 RU 2189936C2
Authority
RU
Russia
Prior art keywords
boom
folding
intermediate element
hinge
base
Prior art date
Application number
RU98106852A
Other languages
Russian (ru)
Other versions
RU98106852A (en
Inventor
Поль ЛАРОШ
Original Assignee
Потэн С.А.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Потэн С.А. filed Critical Потэн С.А.
Publication of RU98106852A publication Critical patent/RU98106852A/en
Application granted granted Critical
Publication of RU2189936C2 publication Critical patent/RU2189936C2/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/34Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes
    • B66C23/342Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes with telescopic elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

FIELD: mechanical engineering; tower cranes. SUBSTANCE: invention relates to automatically mountable tower lifting crane with foldable load-lifting boom formed by hinge-connected members. Proposed tower lifting crane has load- lifting boom 6 consisting of at least three members 7, 8, 9 and intermediate boom folding member 10 connecting base 7 of boom 6 with second member 8 of boom 6. Intermediate member consists of rear part 15 and front part 16 of pyramidal shape with rectangular base hinge-connected in points 20, 30 with base 7 of boom 6 and with second member 8 of boom 6 level of lower load- bearing beams 21, 31, hinge joint with vertical turning axis which connects said rear part 15 and front part 16 of intermediate member, this axis being displaced sidewise, and temporary coupling means. These means are designed for connecting rear part 15 of intermediate member 10 with front part 16 of intermediate member in working position of said tower lifting crane. EFFECT: facilitated transportation of crane along motor roads in folded position. 4 cl, 10 dwg

Description

Изобретение касается башенного подъемного крана с автоматизированным процессом монтажа и складной грузоподъемной стрелой, образованной несколькими элементами стрелы, шарнирно связанными между собой. В рамках приведенного ниже описания предлагаемого изобретения термин "монтаж" подъемного крана означает его раскладывание или разворачивание из сложенного транспортировочного положения в его рабочее положение, причем обратная операция перехода от рабочего положения этого подъемного крана к его транспортировочному положению будет называться складыванием. The invention relates to a tower crane with an automated installation process and a folding lifting boom formed by several boom elements articulated together. In the framework of the description of the invention below, the term “installation” of a crane means folding or unfolding from a folded transport position to its working position, the reverse operation of moving from the working position of this crane to its transport position will be called folding.

Говоря более конкретно, предлагаемое изобретение относится к устройству шарнирного соединения элементов складной грузоподъемной стрелы, вставленному между двумя различными элементами этой стрелы с целью обеспечения возможности ее бокового складывания для транспортировки по автодорогам. More specifically, the present invention relates to a device for articulating the elements of a folding boom inserted between two different elements of this boom in order to enable lateral folding for transportation on highways.

Итак, предлагаемое изобретение применяется к башенным подъемным кранам с автоматизированным процессом монтажа, которые должны быть сложенными для обеспечения возможности их транспортировки по автомобильным дорогам с одной строительной площадки на другую или с одного места установки на другое в наилучших возможных условиях быстроты складывания, безопасности и приемлемых габаритных размеров. В этом контексте предлагаемое изобретение, говоря более конкретно, ближе всего касается башенного подъемного крана, оборудованного складной грузоподъемной стрелой, образованной по меньшей мере тремя различными элементами этой стрелы, которые могут иметь различную длину и даже отличные друг от друга поперечные сечения, причем складывание этой грузоподъемной стрелы осуществляется в вертикальной плоскости по принципу складывания "гармошкой" или "спиралью" и одна часть сложенной таким образом стрелы занимает место сбоку от мачты данного подъемного крана с целью хранения и транспортировки этого подъемного крана в возможно более компактном виде. So, the present invention is applied to tower cranes with an automated installation process, which must be folded to enable transportation on roads from one construction site to another or from one installation site to another in the best possible conditions of folding speed, safety and acceptable overall sizes. In this context, the present invention, more specifically, relates most closely to a tower crane equipped with a folding boom formed by at least three different elements of this boom, which can have different lengths and even cross sections that are different from each other, and folding this load the boom is carried out in a vertical plane according to the principle of folding with an "accordion" or "spiral" and one part of the boom folded in this way takes place on the side of the mast of this crane to store and transport this crane in the most compact form possible.

Многочисленные технические решения уже были предложены для реализации возможности складывания грузоподъемных стрел башенных кранов, состоящих из нескольких элементов. Известное типовое техническое решение, с которым связано предлагаемое изобретение, состоит в размещении между двумя главными составляющими элементами данной стрелы, в частности, между первым ее элементом, называемым "основанием стрелы", и последующим элементом этой стрелы, короткого промежуточного элемента, реализующего шарнирную связь между двумя рассматриваемыми главными элементами данной стрелы. Такой промежуточный элемент, обеспечивающий возможность складывания грузоподъемной стрелы башенного подъемного крана, описан, например, в патенте Франции 2368430 и в заявке на европейский патент 0733584. Numerous technical solutions have already been proposed to realize the possibility of folding the lifting arrows of tower cranes, consisting of several elements. A well-known standard technical solution with which the invention is associated consists in placing between the two main constituent elements of this arrow, in particular between its first element, called the "base of the arrow", and the subsequent element of this arrow, a short intermediate element that implements an articulated connection between two considered main elements of this arrow. Such an intermediate element enabling folding of the lifting boom of a tower crane is described, for example, in French patent 2368430 and in European patent application 0733584.

Рассматривая более конкретно упомянутый выше патент Франции 2368430, можно отметить, что этот документ предлагает грузоподъемную стрелу башенного подъемного крана, состоящую из трех элементов и складываемую гармошкой в вертикальной плоскости, а также складываемую в горизонтальной плоскости для обеспечения возможности транспортировки. Один промежуточный элемент связывает основание этой грузоподъемной стрелы со следующим элементом этой стрелы или с ее вторым элементом. Considering more specifically the aforementioned French patent 2368430, it can be noted that this document offers a lifting boom of a tower crane, consisting of three elements and folded accordion in the vertical plane, and also folding in the horizontal plane to enable transport. One intermediate element connects the base of this lifting boom with the next element of this boom or with its second element.

Упомянутый промежуточный элемент, представляющий собой участок складывания данной грузоподъемной стрелы, образован двумя трехгранниками. Задний трехгранник связан своим основанием при помощи шарнирных соединений с основанием данной стрелы на уровне нижних силовых балок посредством двух противоположных друг другу осей. Этот задний трехгранник связан также на уровне своей вершины при помощи растяжек с некоторой промежуточной стойкой. Said intermediate element, which is a folding section of a load-lifting boom, is formed by two trihedra. The rear trihedron is connected by its base with the help of articulated joints to the base of the boom at the level of the lower power beams by means of two axes opposite each other. This rear trihedron is also connected at the level of its apex with the help of extensions with some intermediate stance.

Передний трехгранник шарнирно связан своим основанием с упомянутым вторым элементом данной грузоподъемной стрелы на уровне его опорных балок при помощи двух противоположных друг другу шарнирных осей. Этот передний трехгранник связан также на уровне своей вершины при помощи растяжки со вторым элементом данной стрелы. The front trihedron is pivotally connected with its base to the second element of this lifting boom at the level of its support beams with the help of two articulated axes opposite each other. This front trihedron is also connected at the level of its apex by means of a stretch with the second element of this arrow.

Оба эти трехгранника связаны между собой шарниром, располагающимся в средней вертикальной плоскости грузоподъемной стрелы, на уровне наклонного ребра каждого трехгранника. Два съемных стержня объединяют в единое целое нижние балки двух элементов стрелы в ее рабочем положении для того, чтобы обеспечить непрерывность пути качения грузоподъемной тележки данной стрелы. Both of these trihedrons are interconnected by a hinge located in the middle vertical plane of the lifting boom, at the level of the inclined edge of each trihedron. Two removable rods combine the lower beams of two boom elements in a single position in its working position in order to ensure continuity of the rolling path of the load-lifting trolley of this boom.

Это известное устройство не позволяет обеспечить раскладывание и складывание в вертикальной плоскости грузоподъемной стрелы, состоящей из трех элементов, уложенных друг на друга. Кроме того, это устройство не позволяет обеспечить складывание стрелы в горизонтальной плоскости на угол 180o вследствие того, что упомянутый шарнир располагается в средней плоскости элементов стрелы. В то же время, необходимость установки и снятия двух съемных стержней создает дополнительные сложности.This known device does not allow for the folding and folding in the vertical plane of the lifting boom, consisting of three elements stacked on top of each other. In addition, this device does not allow folding of the boom in the horizontal plane at an angle of 180 o due to the fact that the hinge is located in the middle plane of the boom elements. At the same time, the need to install and remove two removable rods creates additional difficulties.

Задача данного изобретения состоит в том, чтобы устранить отмеченные выше недостатки и предложить конструкцию башенного подъемного крана с автоматизированным процессом монтажа и складываемой стрелой, оборудованного промежуточным элементом складывания, разработанным таким образом, чтобы обеспечить возможность раскладывания и складывания грузоподъемной стрелы в вертикальной плоскости, а также обеспечить возможность раскладывания и складывания передней части этой стрелы в горизонтальной плоскости, предусмотрев при этом возможность хранения тележки. The objective of the invention is to eliminate the above-mentioned disadvantages and to propose the design of a tower crane with an automated installation process and a folding boom equipped with an intermediate folding element, designed in such a way as to enable the folding boom to be folded out and folded in a vertical plane, and also to provide the possibility of folding and folding the front of this boom in a horizontal plane, while providing for Storage carts.

Поставленная задача решается посредством того, что в башенном подъемном кране с автоматизированным процессом монтажа и со складываемой грузоподъемной стрелой, состоящей из, по меньшей мере, трех элементов стрелы и промежуточного элемента складывания стрелы, содержащего заднюю часть, шарнирно связанную с основанием стрелы на уровне нижних силовых балок, переднюю часть, шарнирно связанную со вторым элементом стрелы, шарнир, соединяющий заднюю часть промежуточного элемента складывания стрелы с передней частью этого промежуточного элемента, а также средства временной связи, предусмотренные для соединения задней части промежуточного элемента складывания стрелы с передней частью этого промежуточного элемента в рабочем положении данного башенного крана, причем упомянутый промежуточный элемент связывает основание этой стрелы со вторым элементом этой стрелы, а часть сложенной стрелы занимает место сбоку от мачты данного подъемного крана в его сложенном транспортировочном положении, согласно изобретению, задняя часть промежуточного элемента выполнена пирамидальной формы с прямоугольным основанием и связана своей верхней деталью при помощи домкрата с верхней силовой балкой основания стрелы, передняя часть также выполнена пирамидальной формы с прямоугольным основанием и связана своей верхней деталью при помощи домкрата с верхней силовой балкой второго элемента стрелы, при этом шарнир смещен в боковом направлении с размещением его вертикальной оси на одной из сторон упомянутого промежуточного элемента. The problem is solved by the fact that in a tower crane with an automated installation process and with a folding lifting boom, consisting of at least three boom elements and an intermediate boom folding element containing a rear part pivotally connected to the base of the boom at the lower power level beams, a front part pivotally connected to the second boom element, a hinge connecting the rear part of the intermediate boom folding element with the front part of this intermediate element nta, as well as temporary communication means, provided for connecting the rear part of the intermediate boom folding element with the front part of this intermediate element in the working position of this tower crane, said intermediate element connecting the base of this boom to the second element of this boom, and part of the folded boom takes place on the side of the mast of this crane in its folded transport position, according to the invention, the rear of the intermediate element is made of a pyramidal shape we are with a rectangular base and connected by its upper part with a jack to the upper power beam of the boom base, the front part is also made in a pyramidal shape with a rectangular base and connected by its upper part by means of a jack with the upper power beam of the second boom element, while the hinge is laterally shifted direction with the placement of its vertical axis on one side of the said intermediate element.

Боковое смещение шарнира, связывающего шарнирным образом две части промежуточного элемента складывания грузоподъемной стрелы, позволяет обеспечить возможность поворота передней части этого промежуточного элемента относительно его задней части на угол 180o. Целесообразным является то, что упомянутый шарнир, связывающий две части промежуточного элемента складывания стрелы, выполнен из двух частей, а именно, нижней части шарнира, располагающейся над прямоугольными основаниями задней и передней частей пирамидальной формы промежуточного элемента и верхней части шарнира.The lateral displacement of the hinge, which pivots the two parts of the intermediate folding element of the lifting boom in a hinged manner, makes it possible to rotate the front of this intermediate element relative to its rear part by an angle of 180 o . It is advisable that said hinge connecting two parts of the intermediate boom folding element is made of two parts, namely, the lower part of the hinge located above the rectangular bases of the rear and front parts of the pyramidal shape of the intermediate element and the upper part of the hinge.

Предпочтительным является то, что временные средства соединения между задней и передней частями промежуточного элемента складывания стрелы выполнены в виде верхней вилки и нижних вилок, а также поперечной перемычки и шипа, размещенных соответственно на уровне прямоугольных оснований и верхних деталей, двух упомянутых выше частей и съемных осей, предусмотренных для соединения двух нижних вилок с поперечной перемычкой и верхней вилки с шипом. It is preferable that temporary means of connection between the rear and front parts of the intermediate boom folding element are made in the form of an upper fork and lower forks, as well as a transverse bridge and a spike located respectively at the level of rectangular bases and upper parts, the two parts mentioned above and the removable axes provided for connecting the two lower forks with a transverse jumper and the upper forks with a spike.

Благодаря этим средствам в развернутом рабочем положении данной грузоподъемной стрелы, обеспечивается жесткое соединение между основанием стрелы и вторым элементом этой стрелы, причем нижние силовые балки задней и передней частей упомянутого промежуточного элемента обеспечивают непрерывность пути качения грузовой тележки данной стрелы. Thanks to these means, in the unfolded operating position of this load-lifting boom, a rigid connection is provided between the base of the boom and the second element of this boom, the lower power beams of the rear and front parts of the said intermediate element ensuring the continuity of the rolling path of the cargo truck of this boom.

Нижние силовые балки одной из двух частей промежуточного элемента складывания стрелы, в частности, нижние силовые балки задней части этого промежуточного элемента, выполнены с возможностью размещения на них грузовой тележки стрелы в ее сложенном транспортировочном положении. The lower power beams of one of the two parts of the intermediate boom folding element, in particular, the lower power beams of the rear of this intermediate element, are arranged to accommodate the boom of the boom in its folded transport position.

В своей совокупности конструкция, являющаяся объектом предлагаемого изобретения, позволяет обеспечить соответствие условиям допустимых дорожных габаритов и даже получить габаритные размеры подъемного крана в сложенном состоянии менее максимально допустимых, укладывая второй и третий элементы грузоподъемной стрелы сбоку от основного пакета в вертикальной плоскости, параллельной этому пакету, содержащему сложенную мачту данного подъемного крана и основание его стрелы, тогда как грузовая тележка стрелы размещается позади сложенного подъемного крана. Together, the design, which is the object of the present invention, can ensure compliance with the conditions of permissible road dimensions and even get the overall dimensions of the crane when folded is less than the maximum allowable, laying the second and third elements of the lifting boom on the side of the main package in a vertical plane parallel to this package, containing the folded mast of the crane and the base of its boom, while the cargo boom of the boom is located behind the folded a crane.

Кроме того, предложенная конфигурация подъемного крана позволяет осуществлять операцию складывания и раскладывания грузоподъемной стрелы этого крана в горизонтальной плоскости, то есть реализовать движение поворота на угол 180o, допускаемое шарниром с вертикальной поворотной осью, на уровне земли или на высоте меньше человеческого роста вручную, с использованием только мускульной силы и без приложения особенных усилий.In addition, the proposed configuration of the crane allows the operation of folding and unfolding the lifting boom of this crane in a horizontal plane, that is, realize a rotation movement of 180 ° , allowed by a hinge with a vertical rotary axis, at ground level or at a height less than human height manually, with using only muscular strength and without special effort.

И наконец, техническое решение в соответствии с предлагаемым изобретением устраняет всякие ограничения размерного характера в том, что касается высоты конструкции элементов грузоподъемной стрелы, в отличие от специфической конфигурации, описанной в заявке на Европейский патент 0733584. And finally, the technical solution in accordance with the invention eliminates any dimensional limitations with regard to the height of the structural elements of the lifting boom, in contrast to the specific configuration described in European patent application 0733584.

В любом случае предлагаемое изобретение будет лучше понято из приведенного ниже описания двух примеров практической реализации подъемного крана с автоматизированным процессом монтажа и складываемой грузоподъемной стрелой в соответствии с этим изобретением, где даются ссылки на приведенные в приложении фигуры, среди которых:
- фиг.1 представляет собой схематический вид сбоку бешенного подъемного крана в соответствии с предлагаемым изобретением, имеющего складываемую "спиралью" стрелу, представленную здесь в своем рабочем положении;
- фиг. 2 представляет собой схематический вид сбоку подъемного крана, показанного на фиг.1, в его сложенном транспортировочном положении;
- фиг. 3 представляет собой схематический вид сзади того же подъемного крана, показанного на фиг.1, в его сложенном транспортировочном положении;
- фиг.4 представляет собой схематический вид сбоку одной грузоподъемной стрелы этого подъемного крана, сложенной в вертикальной плоскости, но разложенной в горизонтальной плоскости;
- фиг. 5 представляет собой схематический перспективный вид промежуточного элемента складывания грузоподъемной стрелы в его сложенном положении;
- фиг. 6 представляет собой схематический перспективный вид промежуточного элемента складывания грузоподъемной стрелы в его разложенном положении;
- фиг. 7 представляет собой схематический вид сбоку другого башенного подъемного крана в соответствии с предлагаемым изобретением, имеющего стрелу, складываемую "гармошкой" и представленную в ее рабочем положении;
- фиг.8 представляет собой схематический вид сбоку подъемного крана, показанного на фиг.7, в его сложенном транспортировочном положении;
- фиг. 9 представляет собой схематический вид сзади того же подъемного крана, показанного на фиг.7, в его сложенном транспортировочном положении;
- фиг.10 представляет собой схематический вид сбоку одной грузоподъемной стрелы этого подъемного крана, сложенной в вертикальной плоскости, но разложенной в горизонтальной плоскости.
In any case, the invention will be better understood from the following description of two examples of the practical implementation of a crane with an automated installation process and a folding boom in accordance with this invention, where reference is made to the figures given in the appendix, including:
- figure 1 is a schematic side view of a rabid crane in accordance with the invention, having a folding "spiral" boom, presented here in its working position;
- FIG. 2 is a schematic side view of the crane shown in FIG. 1 in its folded transport position;
- FIG. 3 is a schematic rear view of the same crane shown in FIG. 1 in its folded transport position;
- figure 4 is a schematic side view of one lifting boom of this crane, folded in a vertical plane, but laid out in a horizontal plane;
- FIG. 5 is a schematic perspective view of an intermediate folding member of a load-lifting boom in its folded position;
- FIG. 6 is a schematic perspective view of an intermediate folding member of the lifting boom in its unfolded position;
- FIG. 7 is a schematic side view of another tower crane in accordance with the invention, having an arrow foldable by an "accordion" and presented in its working position;
- Fig. 8 is a schematic side view of the crane shown in Fig. 7 in its folded transport position;
- FIG. 9 is a schematic rear view of the same crane shown in FIG. 7 in its folded transport position;
- figure 10 is a schematic side view of one lifting boom of this crane, folded in a vertical plane, but laid out in a horizontal plane.

Башенный подъемный кран в соответствии с предлагаемым изобретением, схематически представленный сбоку на фиг.1, содержит базовое шасси 1, на котором смонтировано поворотное шасси 2, ориентируемое в пространстве вокруг вертикальной оси 3. В задней части этого поворотного шасси 2 установлен противовес 4, а в передней части этого поворотного шасси закреплена телескопическая раздвижная мачта 5. Этот подъемный кран снабжен грузоподъемной стрелой 6. A tower crane in accordance with the invention, shown schematically on the side of FIG. 1, comprises a base chassis 1 on which a swing chassis 2 is mounted, oriented in space around a vertical axis 3. A counterweight 4 is mounted at the rear of this swing chassis 2, and in a telescopic sliding mast 5 is fixed to the front of this rotary chassis. This crane is equipped with a load-lifting boom 6.

Стрела 6 данного подъемного крана может быть сложена и разложена и реализована из трех главных последовательно расположенных элементов относительно большой длины, обозначаемых соответственно как основание стрелы 7, второй элемент стрелы 8 и вершина стрелы 9. Два промежуточных элемента складывания этой стрелы 10 и 11, имеющие относительно малую длину, вставляются здесь соответственно между двумя упомянутыми главными элементами стрелы 7 и 8 и между двумя главными элементами стрелы 8 и 9. В рабочем положении данного подъемного крана его мачта 5 установлена в вертикальное положение и все элементы грузоподъемной стрелы 7, 8, 9, 10 и 11 располагаются на одной линии в горизонтальном положении. Грузовая тележка стрелы 12 имеет возможность перемещаться вдоль протяженности этой стрелы 6. The boom 6 of this crane can be folded and unfolded and realized of three main successively arranged elements of relatively large length, respectively designated as the base of the boom 7, the second element of the boom 8 and the top of the boom 9. Two intermediate folding elements of this boom 10 and 11, having relatively short lengths are inserted here respectively between the two mentioned main elements of the boom 7 and 8 and between the two main elements of the boom 8 and 9. In the working position of the crane, its mast 5 getting a vertical position and all the elements of the lifting boom 7, 8, 9, 10 and 11 are aligned horizontally. The cargo truck of the boom 12 has the ability to move along the length of this boom 6.

Данный подъемный кран содержит также заднее устройство удержания 13, связывающее грузоподъемную стрелу 6 с поворотным шасси 2, а также устройство подъема мачты этого крана. This crane also contains a rear holding device 13, connecting the lifting boom 6 with the swinging chassis 2, as well as a mast lifting device of this crane.

Благодаря шарнирному соединению основания стрелы 7 относительно горизонтальной оси поворота 14 с вершиной мачты 5 данного подъемного крана и благодаря двум промежуточным элементам 10 и 11 складывания данная грузоподъемная стрела 6 является складываемой "спиралью" сама на себя, а также складываемой по отношению к мачте 5, с целью обеспечения возможности беспрепятственной транспортировки данного подъемного крана, как это схематически показано на фиг.2 и 3. Due to the articulated connection of the base of the boom 7 relative to the horizontal axis of rotation 14 with the top of the mast 5 of this crane and thanks to two intermediate folding elements 10 and 11, this load-bearing boom 6 is a folding “spiral” on itself, as well as folding relative to the mast 5, s the purpose of providing the possibility of unimpeded transportation of the crane, as schematically shown in figure 2 and 3.

В рассматриваемом здесь примере практической реализации предлагаемого изобретения конструкция второго промежуточного элемента 11 складывания стрелы, вставленного между вторым элементом стрелы 8 и вершиной этой стрелы 9, может быть аналогичной той конструкции, которая описана в заявке на Европейский патент за номером 0733584 на имя Заявителя. In the example of practical implementation of the invention considered here, the construction of the second intermediate boom folding element 11 inserted between the second boom element 8 and the top of this boom 9 can be similar to that described in European patent application number 0733584 addressed to the Applicant.

Конструкция первого промежуточного элемента 10 складывания стрелы, говоря более конкретно, представляющая собой объект предлагаемого изобретения, подробно схематически представлена на фиг.5 и 6. Этот промежуточный элемент 10 сам состоит из двух частей, а именно, задней части 15 и передней части 16, каждая из которых в целом имеет форму пирамиды с прямоугольным несущим основанием. The construction of the first intermediate boom folding element 10, more specifically representing an object of the present invention, is shown in detail schematically in FIGS. 5 and 6. This intermediate element 10 itself consists of two parts, namely, the rear part 15 and the front part 16, each of which, in general, has the shape of a pyramid with a rectangular bearing base.

Задняя часть 15 промежуточного элемента 10 складывания стрелы имеет две нижние параллельные силовые балки 17, соединяемые на своих концах поперечными перемычками 18, формируя таким образом упомянутое прямоугольное основание пирамидальной задней части промежуточного элемента. Задние концы двух нижних силовых балок 17 продолжаются соответствующими шипами 19, при помощи которых эта задняя часть 15 промежуточного элемента шарнирно соединяется вдоль поперечной горизонтальной оси 20 с передним концом основания стрелы 7 на уровне нижних силовых балок 21 этого основания стрелы. The rear part 15 of the intermediate boom folding element 10 has two lower parallel power beams 17 connected at their ends by transverse bridges 18, thereby forming the rectangular base of the pyramidal rear part of the intermediate element. The rear ends of the two lower power beams 17 are continued by respective studs 19, by means of which this rear part 15 of the intermediate element is pivotally connected along the transverse horizontal axis 20 to the front end of the base of the boom 7 at the level of the lower power beams 21 of this base of the boom.

Из четырех углов прямоугольного основания задней части 15 промежуточного элемента проходят в направлении вверх четыре сходящихся наклонных стержня 22 (один из которых не показан), соединенных между собой верхней деталью 23, которая соединена при помощи домкрата 24 с верхней силовой балкой 25 основания стрелы 7. Of the four corners of the rectangular base of the rear part 15 of the intermediate element, four converging inclined rods 22 (one of which is not shown) are connected in an upward direction, interconnected by an upper part 23, which is connected by a jack 24 to the upper power beam 25 of the base of the boom 7.

Практически аналогичным образом передняя часть 16 промежуточного элемента 10 имеет две нижние параллельные силовые балки 26, соединенные на своих концах между собой поперечными перемычками 27, а также диагональной перемычкой 28, формируя таким образом прямоугольное основание этой передней части промежуточного элемента. Передние концы двух нижних силовых балок 26 продолжаются соответствующими шипами 29, при помощи которых передняя часть 16 промежуточного элемента 10 шарнирно соединена вдоль поперечной горизонтальной поворотной оси 30 с задним концом второго элемента стрелы 8 на уровне нижних силовых балок 31 этого второго элемента 8. In almost the same way, the front part 16 of the intermediate element 10 has two lower parallel power beams 26 connected at their ends by transverse jumpers 27, as well as a diagonal bridge 28, thereby forming a rectangular base of this front part of the intermediate element. The front ends of the two lower power beams 26 are continued by corresponding spikes 29, by means of which the front part 16 of the intermediate element 10 is pivotally connected along the transverse horizontal pivot axis 30 with the rear end of the second boom element 8 at the level of the lower power beams 31 of this second element 8.

Из четырех углов этого прямоугольного основания передней части 16 промежуточного элемента 10 проходят в направлении вверх четыре наклонных сходящихся стержня 32 (два из которых не показаны), соединенных между собой верхней деталью 33 удлиненной формы, поддерживаемой сзади также двумя другими наклонными стержнями 34. Эта верхняя деталь 33 соединена при помощи домкрата 35 с верхней силовой балкой 36 второго элемента 8 стрелы. From the four corners of this rectangular base of the front part 16 of the intermediate element 10, four inclined converging rods 32 (two of which are not shown) extend in an upward direction, interconnected by an elongated upper part 33, also supported by two other inclined rods 34 at the back. This upper part 33 is connected by a jack 35 to the upper power beam 36 of the second boom element 8.

Задняя часть 15 и передняя часть 16 промежуточного элемента 10 шарнирно соединены друг с другом вдоль вертикальной поворотной оси 37, располагающейся на одной стороне этого промежуточного элемента 10. Для этого предусмотрен шарнир 38, соединяющий переднюю боковую стойку 39 задней части 15 с задней боковой стойкой 40 передней части 16. Сам упомянутый шарнир 38 состоит из следующих элементов:
- нижней части шарнира, располагающейся над прямоугольными основаниями задней 15 и передней 16 частей данного промежуточного элемента и образованной соединением шарнира 41, жестко связанного с боковой стойкой 39, и шипа 42, жестко связанного с боковой стойкой 40;
- верхней части шарнира, образованной соединением другого шарнира 43, закрепленного на вершине боковой стойки 39, и шипа 44, закрепленного на вершине боковой стойки 40.
The rear part 15 and the front part 16 of the intermediate element 10 are pivotally connected to each other along a vertical pivot axis 37 located on one side of this intermediate element 10. A hinge 38 is provided for this purpose, connecting the front side strut 39 of the rear part 15 with the rear side strut 40 of the front parts 16. The mentioned joint 38 itself consists of the following elements:
- the lower part of the hinge located above the rectangular bases of the rear 15 and front 16 parts of this intermediate element and formed by the connection of the hinge 41, rigidly connected to the side strut 39, and the spike 42, rigidly connected to the side strut 40;
- the upper part of the hinge formed by connecting another hinge 43, mounted on the top of the side strut 39, and a spike 44, mounted on the top of the side strut 40.

Благодаря этому шарниру 38 две части 15 и 16 промежуточного элемента 10 имеют возможность поворачиваться друг относительно друга вокруг вертикальной оси 37 на угол 180o между так называемым "сложенным" положением (см. фиг.5), в котором две эти части 15 и 16 примыкают друг к другу своими боковыми сторонами, и так называемым "разложенным" положением (см. фиг.6), в котором две эти части 15 и 16 располагаются, последовательно продолжая друг друга.Due to this hinge 38, the two parts 15 and 16 of the intermediate element 10 are able to rotate relative to each other around the vertical axis 37 through an angle of 180 o between the so-called "folded" position (see figure 5), in which these two parts 15 and 16 are adjacent to each other with their lateral sides, and the so-called "unfolded" position (see Fig.6), in which these two parts 15 and 16 are located, sequentially continuing each other.

Для соединения между собой задней 15 и передней 16 частей промежуточного элемента 10 в "замкнутом" или "разложенном" положении, определенном выше, дополнительно предусмотрены:
- на основании и в передней части упомянутой задней части 15 промежуточного элемента 10 на поперечной перемычке 18 специальные отверстия 45, и на верхней детали 23 этой задней части 15 верхняя вилка 46;
- на основании и в задней части упомянутой передней части 16 промежуточного элемента 10 на поперечной перемычке 27 две вилки 47, расположение которых соответствует положению упомянутых отверстий 45 и на верхней детали 33 этой передней части 16 перфорированный шип 48, соответствующий упомянутой верхней вилке 46;
- съемные соединительные оси 49 и 50, которые обеспечивают возможность соединения двух нижних вилок 47 с поперечной перемычкой 18, на уровне отверстий 45, а также возможность соединения верхней вилки 46 с шипом 48.
To connect the rear 15 and front 16 parts of the intermediate element 10 in a "closed" or "unfolded" position, as defined above, are additionally provided:
- on the base and in the front of said rear part 15 of the intermediate element 10 on the transverse jumper 18, special openings 45, and on the upper part 23 of this rear part 15, the upper fork 46;
- on the base and in the rear part of said front part 16 of the intermediate element 10 on the transverse jumper 27, two forks 47, the arrangement of which corresponds to the position of the said holes 45 and on the upper part 33 of this front part 16, a perforated spike 48 corresponding to the said upper fork 46;
- removable connecting axes 49 and 50, which provide the ability to connect the two lower forks 47 with the transverse jumper 18, at the level of the holes 45, as well as the ability to connect the upper forks 46 with a spike 48.

В сложенном положении данного подъемного крана, предназначенном для его транспортировки по автомобильным дорогам, как это схематически представлено сплошными линиями на фиг. 2 и 3, телескопическая мачта 5 этого подъемного крана сложена путем вдвигания ее элементов друг в друга и опущена в горизонтальное положение, основание грузоподъемной стрелы 7 опущено сверху на мачту 5 и лежит на специальных опорах (не показанных на приведенных в приложении фигурах), располагающихся вдоль этой мачты. Второй элемент стрелы 8 и вершина стрелы 9 располагаются одна поверх другой сбоку от системы, образованной мачтой 5 и основанием стрелы 7. Это боковое складывание части грузоподъемной стрелы 6 обеспечивается при помощи специальной конструкции первого промежуточного элемента складывания стрелы 10, переведенного в "сложенное" положение (так, как было определено выше) таким образом, чтобы разместить систему, сформированную вторым элементом стрелы 8 и вершиной стрелы 9, сбоку от основания этой стрелы 7. Ось связи (не показанная на приведенных в приложении фигурах) соединяет два элемента стрелы 8 и 9 с мачтой 5. In the folded position of this crane, intended for transportation by road, as schematically represented by solid lines in FIG. 2 and 3, the telescopic mast 5 of this crane is folded by pushing its elements into each other and lowered to a horizontal position, the base of the lifting boom 7 is lowered onto the mast 5 from above and lies on special supports (not shown in the figures given in the appendix) located along this mast. The second element of the boom 8 and the top of the boom 9 are located one on top of the other side of the system formed by the mast 5 and the base of the boom 7. This lateral folding of part of the lifting boom 6 is provided by the special design of the first intermediate folding element of the boom 10, translated into the "folded" position ( as defined above) in such a way as to place the system formed by the second element of the boom 8 and the top of the boom 9, on the side of the base of this boom 7. The axis of communication (not shown in the decomposition figures) connects the two jib elements 8 and 9 to the mast 5.

Здесь следует также отметить, что в сложенном транспортировочном положении данного подъемного крана грузовая тележка стрелы 12 располагается на задней части 15 промежуточного элемента складывания стрелы 10. Сложенный таким образом подъемный кран в соответствии с предлагаемым изобретением имеет минимальные габаритные размеры и может транспортироваться по автомобильным дорогам при помощи седельного тягача 51 наподобие прицепа или полуприцепа, причем автомобильный тягач 51 прицепляется с конца, противоположного тому концу сложенного подъемного крана, где располагается грузовая тележка стрелы 12. It should also be noted that in the folded transport position of this crane, the boom trolley 12 is located on the rear part 15 of the intermediate boom folding element 10. The crane thus folded in accordance with the present invention has minimum overall dimensions and can be transported by road using a tractor unit 51, like a trailer or a semi-trailer, the vehicle tractor 51 being attached from the end opposite that end of the folded lift crane, where the boom 12 is located.

Раскладывание грузоподъемной стрелы 6 из ее сложенного транспортировочного положения, схематически представленного на фиг.2 и 3, осуществляется описанным ниже образом. Unfolding the lifting boom 6 from its folded transport position, schematically shown in figure 2 and 3, is carried out as described below.

После доставки данного подъемного крана в сложенном транспортировочном положении на предполагаемое место его установки и подъема системы, образованной мачтой 5 и стрелой 6, отсоединяют от этой мечты 5 два элемента стрелы 8 и 9, удаляя для этого соответствующую соединительную ось. After the delivery of this crane in the folded transport position to its intended installation location and lifting of the system formed by the mast 5 and boom 6, two elements of the boom 8 and 9 are disconnected from this dream 5, removing the corresponding connecting axis.

Затем "раскладывают" стрелу 6, то есть поворачивают на угол 180o вокруг вертикальной оси 37 шарнира 38 систему, образованную вторым элементом стрелы 8 и вершиной стрелы 9, а также передней частью 16 промежуточного элемента 10 складывания стрелы, для ее перевода в ту же вертикальную плоскость, в которой располагается остальная часть этой стрелы 6, то есть ее основание 7 и задняя часть 15 промежуточного элемента 10, как это схематически показано на фиг.4.Then the arrow 6 is “laid out”, that is, the system formed by the second element of the arrow 8 and the top of the arrow 9, as well as the front part 16 of the intermediate element 10 of folding the arrow, is rotated 180 ° around the vertical axis 37 of the hinge 38 to translate it into the same vertical the plane in which the rest of this boom 6 is located, that is, its base 7 and the rear part 15 of the intermediate element 10, as shown schematically in FIG. 4.

После достижений этого положения соединяют между собой заднюю и переднюю части 15 и 16 промежуточного элемента 10, теперь уже располагающиеся по одной линии, путем введения соединительных осей 49 и 50 в вилки 47 и 46. Грузовая тележка стрелы 12 также разблокируется от задней части 15 промежуточного элемента 10. After reaching this position, the rear and front parts 15 and 16 of the intermediate element 10, now already located in one line, are connected by introducing the connecting axles 49 and 50 into the forks 47 and 46. The boom 12 also unlocks from the rear part 15 of the intermediate element 10.

Все эти операции легко осуществляются вручную с земли, учитывая то обстоятельство, что промежуточный элемент 10 в данном случае располагается в достаточно низком по отношению к земле положении, вполне доступном для обычного человека. All these operations are easily carried out manually from the ground, taking into account the fact that the intermediate element 10 in this case is located in a position quite low relative to the ground, quite accessible to the average person.

Затем можно приступить к разворачиванию стрелы 6 в ее вертикальной плоскости вплоть до достижения этой стрелой ее рабочего линейного и горизонтального положения путем приведения в действие двух домкратов 24 и 35, обеспечивающих выравнивание промежуточного элемента 10 с основанием стрелы 1 и с вторым элементом 8 этой стрелы. Then you can begin to deploy the boom 6 in its vertical plane until this boom reaches its working linear and horizontal position by actuating two jacks 24 and 35, ensuring alignment of the intermediate element 10 with the base of the boom 1 and the second element 8 of this arrow.

Само собой разумеется, что складывание грузоподъемной стрелы 6 осуществляется в результате выполнения обратного процесса, который, в частности, содержит:
- разъединение задней 15 и передней 16 частей промежуточного элемента 10 складывания стрелы;
- складывание этого промежуточного элемента 10, переводящее его переднюю часть 16 к боковой стороне его задней части 15.
It goes without saying that the folding of the lifting boom 6 is carried out as a result of the reverse process, which, in particular, contains:
- separation of the rear 15 and front 16 parts of the intermediate element 10 of the folding boom;
- folding this intermediate element 10, translating its front part 16 to the side of its rear part 15.

Как показано штрих-пунктирными линиями на фиг.2 и 3, подъемный кран в соответствии с предлагаемым изобретением может также транспортироваться на строительную площадку или с одного места установки в другое в таком положении, когда его грузоподъемная стрела 6 не уложена сбоку от его мачты. As shown by dashed-dotted lines in FIGS. 2 and 3, the crane in accordance with the invention can also be transported to the construction site or from one installation site to another in such a position that its load-bearing boom 6 is not laid to the side of its mast.

В этом случае второй элемент стрелы 8 и вершина стрелы 9 располагаются над пакетом, образованным сложенной мачтой 5 и основанием стрелы 7. При таком расположении сложенного подъемного крана в соответствии с предлагаемым изобретением задняя 15 и передняя 16 части промежуточного элемента 10 остаются соединенными между собой. In this case, the second boom element 8 and the top of the boom 9 are located above the package formed by the folded mast 5 and the base of the boom 7. With this arrangement of the folded crane in accordance with the invention, the rear 15 and front 16 parts of the intermediate element 10 remain interconnected.

В примере реализации предлагаемого изобретения, подробно описанном выше со ссылками на фиг.1-6, шла речь о грузоподъемной стреле подъемного крана, складываемой, как говорят, "спиралью", причем вершина стрелы 9 занимает место между основанием стрелы 7 и вторым элементом этой стрелы 8, как это схематически показано, в частности, на фиг.2 и 4. In the example implementation of the invention, described in detail above with reference to figures 1-6, we were talking about a lifting boom of a crane, folding, as they say, "spiral", and the top of the boom 9 takes place between the base of the boom 7 and the second element of this boom 8, as shown schematically, in particular in FIGS. 2 and 4.

На фиг. 7-10, в принципе соответствующих фиг.1-4, схематически представлен подъемный кран в соответствии с предлагаемым изобретением, оборудованный грузоподъемной стрелой 6, складываемой "гармошкой". В конструкции этой грузоподъемной стрелы промежуточный элемент 10 складывания стрелы вставляется между основанием стрелы 7 и вторым элементом 8 этой стрелы, тогда как второй промежуточный элемент складывания стрелы исключается, причем вершина стрелы 9 непосредственно присоединяется шарнирным образом к второму элементу этой стрелы 8 на уровне нижних силовых балок вдоль горизонтальной поворотной оси 52. In FIG. 7-10, in principle, corresponding to figures 1-4, a crane in accordance with the invention is schematically represented, equipped with a load-lifting boom 6, folding "accordion". In the construction of this lifting boom, an intermediate boom folding element 10 is inserted between the base of the boom 7 and the second boom element 8 thereof, while the second intermediate boom folding element is eliminated, and the top of the boom 9 is directly articulated to the second element of this boom 8 at the level of the lower power beams along the horizontal rotary axis 52.

Таким образом, в этом варианте реализации предлагаемого изобретения промежуточный элемент 10 складывания стрелы оказывается более коротким, в частности, в своей передней части 16, но в основном конструкция этого промежуточного элемента идентична конструкции этого элемента, описанной выше. Благодаря своему поворотному шарниру этот промежуточный элемент 10 позволяет установить в транспортировочном положении (схематически показанном сплошными линиями на фиг. 8 и 9) второй элемент стрелы 8 и вершину стрелы 9 сбоку от сложенной мачты 5 и основания этой грузоподъемной стрелы 7. Thus, in this embodiment of the invention, the intermediate boom folding element 10 is shorter, in particular in its front part 16, but basically the construction of this intermediate element is identical to the construction of this element described above. Due to its swivel joint, this intermediate element 10 allows you to set the second element of the boom 8 and the top of the boom 9 to the side of the folded mast 5 and the base of this load-lifting boom 7 in the transport position (schematically shown by solid lines in Figs. 8 and 9).

Разумеется, предлагаемое изобретение не ограничивается теми формами реализации этого подъемного крана с автоматизированным процессом монтажа и со складываемой грузоподъемной стрелой, которые были описаны выше в качестве иллюстративных примеров. На самом деле данное изобретение охватывает все возможные варианты его реализации и практического применения, соответствующие заявленному принципу. В частности, не будут выходить за рамки предлагаемого изобретения:
- различные модификации деталей конструкции двух частей 15 и 16 промежуточного элемента 10 складывания стрелы, а также модификации шарнира 38, связывающего две эти части 15 и 16 промежуточного элемента между собой;
- адаптация предложенного устройства для подъемного крана, грузоподъемная стрела которого будет состоять из более чем трех различных элементов, в частности, для грузоподъемной стрелы, образованной четырьмя элементами, независимо от того, будет ли эта стрела складываться "спиралью" или "гармошкой".
Of course, the present invention is not limited to those forms of implementation of this crane with an automated installation process and with a folding lifting boom, which were described above as illustrative examples. In fact, this invention covers all possible options for its implementation and practical application, consistent with the stated principle. In particular, they will not go beyond the scope of the invention:
- various modifications of the structural parts of the two parts 15 and 16 of the intermediate element 10 of folding the boom, as well as modifications of the hinge 38 connecting these two parts 15 and 16 of the intermediate element to each other;
- adaptation of the proposed device for a crane, the lifting boom of which will consist of more than three different elements, in particular, for the lifting boom formed by four elements, regardless of whether this boom is folded by a “spiral” or “accordion”.

Claims (4)

1. Башенный подъемный кран с автоматизированным процессом монтажа и со складываемой грузоподъемной стрелой (6), состоящей из по меньшей мере трех элементов (7, 8, 9) стрелы и промежуточного элемента (10) складывания стрелы, содержащего заднюю часть (15), шарнирно связанную с основанием (7) стрелы на уровне нижних силовых балок (17, 21), переднюю часть (16), шарнирно связанную со вторым элементом (8) стрелы, шарнир (38), соединяющий заднюю часть (15) промежуточного элемента (10) складывания стрелы с передней частью (16) этого промежуточного элемента, а также средства временной связи (45-50), предусмотренные для соединения задней части (15) промежуточного элемента (10) складывания стрелы с передней частью (16) этого промежуточного элемента (10) в рабочем положении данного башенного подъемного крана, причем упомянутый промежуточный элемент связывает основание (7) стрелы со вторым элементом (8) этой стрелы, а часть (8, 9) сложенной стрелы занимает место сбоку от мачты (5) данного подъемного крана в его сложенном транспортировочном положении, отличающийся тем, что задняя часть (15) промежуточного элемента (10) выполнена пирамидальной формы с прямоугольным основанием и связана своей верхней деталью (23) при помощи домкрата (24) с верхней силовой балкой (25) основания (7) стрелы, передняя часть (16) также выполнена пирамидальной формы с прямоугольным основанием и связана своей верхней деталью (33) при помощи домкрата (35) с верхней силовой балкой (36) второго элемента (8) стрелы, при этом шарнир (38) смещен в боковом направлении с размещением его вертикальной оси (37) на одной из сторон упомянутого промежуточного элемента". 1. A tower crane with an automated installation process and with a folding boom (6), consisting of at least three boom elements (7, 8, 9) and an intermediate boom folding element (10) containing the rear part (15), articulated connected to the base (7) of the boom at the level of the lower power beams (17, 21), the front part (16), pivotally connected to the second element (8) of the boom, the hinge (38) connecting the rear part (15) of the intermediate element (10) folding the boom with the front part (16) of this intermediate element, as well as the medium temporary connections (45-50) provided for connecting the rear part (15) of the intermediate element (10) for folding the boom with the front part (16) of this intermediate element (10) in the operating position of this tower crane, said intermediate element connecting the base (7) arrows with the second element (8) of this arrow, and part (8, 9) of the folded arrow takes place on the side of the mast (5) of this crane in its folded transport position, characterized in that the rear part (15) of the intermediate element (10) completed and a pyramidal shape with a rectangular base and connected with its upper part (23) with a jack (24) with the upper power beam (25) of the base (7) of the arrow, the front part (16) is also made of a pyramidal shape with a rectangular base and connected with its upper part (33) by means of a jack (35) with the upper power beam (36) of the second boom element (8), wherein the hinge (38) is laterally displaced by placing its vertical axis (37) on one side of the said intermediate element. " 2. Башенный подъемный кран по п. 1, отличающийся тем, что шарнир (38), связывающий две части (15, 16) промежуточного элемента (10) складывания стрелы, выполнен из двух частей, а именно: нижней части шарнира (41, 42), располагающейся над прямоугольными основаниями задней (15) и передней (16) частей пирамидальной формы промежуточного элемента, и верхней части шарнира (43, 44). 2. A tower crane according to claim 1, characterized in that the hinge (38) connecting the two parts (15, 16) of the intermediate boom folding element (10) is made of two parts, namely: the lower part of the hinge (41, 42 ) located above the rectangular bases of the rear (15) and front (16) parts of the pyramidal shape of the intermediate element, and the upper part of the hinge (43, 44). 3. Башенный подъемный кран по п. 1 или 2, отличающийся тем, что временные средства соединения между задней (15) и передней (16) частями промежуточного элемента (10) складывания стрелы выполнены в виде верхней вилки (46) и нижних вилок (47), а также поперечной перемычки (18) и шипа (48), размещенных соответственно на уровне прямоугольного основания и верхних деталей (23, 33), двух частей (15, 16) и съемных осей (49, 50), предусмотренных для соединения двух нижних вилок (47) с поперечной перемычкой (18) и верхней вилки (46) с шипом (48). 3. A tower crane according to claim 1 or 2, characterized in that the temporary means of connection between the rear (15) and front (16) parts of the intermediate boom folding element (10) are made in the form of an upper fork (46) and lower forks (47 ), as well as a transverse jumper (18) and a spike (48), located respectively at the level of a rectangular base and upper parts (23, 33), two parts (15, 16) and removable axes (49, 50), designed to connect two lower forks (47) with a transverse jumper (18) and upper forks (46) with a spike (48). 4. Башенный подъемный кран по любому из пп. 1-3, отличающийся тем, что нижние силовые балки (17) одной из частей (15, 16) промежуточного элемента (10) складывания стрелы, в частности нижние силовые балки задней части (15) этого промежуточного элемента (10), выполнены с возможностью размещения на них грузовой тележки (12) стрелы (6) в ее сложенном транспортировочном положении. 4. Tower crane according to any one of paragraphs. 1-3, characterized in that the lower power beams (17) of one of the parts (15, 16) of the intermediate element (10) folding arrows, in particular the lower power beams of the rear part (15) of this intermediate element (10), are made with the possibility placing on them a cargo trolley (12) boom (6) in its folded transport position.
RU98106852A 1997-04-11 1998-04-10 Automatically mountable tower lifting crane with boom sidewise folded for transportation RU2189936C2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR9704719A FR2761971B1 (en) 1997-04-11 1997-04-11 AUTOMATED CRANE WITH FOLDABLE BOOM, WITH LATERAL FOLDING FOR TRANSPORT
FR9704719 1997-04-11

Publications (2)

Publication Number Publication Date
RU98106852A RU98106852A (en) 2000-02-10
RU2189936C2 true RU2189936C2 (en) 2002-09-27

Family

ID=9506010

Family Applications (1)

Application Number Title Priority Date Filing Date
RU98106852A RU2189936C2 (en) 1997-04-11 1998-04-10 Automatically mountable tower lifting crane with boom sidewise folded for transportation

Country Status (5)

Country Link
EP (1) EP0870726B1 (en)
DE (1) DE69806991T2 (en)
ES (1) ES2180131T3 (en)
FR (1) FR2761971B1 (en)
RU (1) RU2189936C2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0999171A1 (en) * 1998-11-05 2000-05-10 Gru Dalbe S.r.l. A foldable jib of a tower crane
ITMI20010116A1 (en) 2001-01-23 2002-07-23 San Marco Internat S R L TOWER CRANE WITH SELF-ASSEMBLING STRUCTURE WITH FOLDABLE AND REMOVABLE TOWER AND ARM WITH MULTIPLE PORTIONS
DE102012018111A1 (en) * 2012-09-13 2014-03-13 Liebherr-Werk Biberach Gmbh Tower Crane
EP2708488B1 (en) 2012-09-14 2014-11-05 Gru Comedil s.r.l. Foldable jib for a crane and such crane
DE102018114832A1 (en) * 2018-06-20 2019-12-24 Liebherr-Werk Ehingen Gmbh Large crane with jib
ES2910102A1 (en) 2020-11-09 2022-05-11 Saez Machinery S L Automated folding and deployed tower crane (Machine-translation by Google Translate, not legally binding)
WO2022104030A1 (en) * 2020-11-13 2022-05-19 Anders Ragnarsson Boom vehicle with vertically and laterally foldable boom assembly

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2368430A1 (en) * 1976-10-22 1978-05-19 Pingon Manubat Sa Folding crane jib - has main and second struts with tie ropes to inner and outer sections
DE3032823A1 (en) * 1980-08-30 1982-04-15 Wilhelm 5020 Frechen König Joint structure for folding tower crane - includes joint in horizontal jib with vertical hinge to reduce length for transport
DE8234374U1 (en) * 1982-12-07 1986-04-03 KOTAX GmbH, 8000 München Tower crane
DE3303524A1 (en) * 1983-02-03 1984-08-09 Wilhelm 5020 Frechen König Revolving tower crane
IT1182698B (en) * 1985-11-22 1987-10-05 Andrea Ferreri ARM FOR CRANE
DE9316113U1 (en) * 1993-10-21 1995-02-16 Liebherr-Werk Biberach GmbH, 88400 Biberach Tower crane
FR2732000B1 (en) * 1995-03-22 1997-05-30 Potain Sa AUTOMATED MOUNT CRANE WITH FOLDABLE BOOM ON ITSELF

Also Published As

Publication number Publication date
DE69806991D1 (en) 2002-09-12
EP0870726B1 (en) 2002-08-07
ES2180131T3 (en) 2003-02-01
DE69806991T2 (en) 2003-04-30
FR2761971A1 (en) 1998-10-16
EP0870726A1 (en) 1998-10-14
FR2761971B1 (en) 1999-05-28

Similar Documents

Publication Publication Date Title
US3939988A (en) Tower crane
US4920595A (en) Solid bridge kit
JP2793932B2 (en) Automatic folding boom for cranes
US3944081A (en) Tower crane
WO2013026279A1 (en) Concrete pump truck and arm stand device thereof
EP1735233A1 (en) Mobile crane system comprising a mobile crane and an auxiliary device for assembly of a bracing device
RU2189936C2 (en) Automatically mountable tower lifting crane with boom sidewise folded for transportation
US4150754A (en) Utility crane
EP2055362B1 (en) Upright support structure for a fairground attraction, in particular a ferris wheel
RU2193007C2 (en) Tower crane three-member mast with folding and unfolding device
US5276930A (en) Folding transportable bridge
PL182893B1 (en) Apparatus for loading and unloading containers onto and from motor vehicles
US3934729A (en) Tower crane
US20040000531A1 (en) Vehicle crane with a telescopic boom, as well as process for assembling and disassembling the anchor supports of the telescopic boom
US5318149A (en) Apparatus for inspecting the underside of bridges
US6872144B2 (en) Amusement device
EP0653529A1 (en) Folding scaffold for construction work
RU2249561C2 (en) Device for folding crane boom with members placed one into the other
EP0165712B1 (en) Bridge construction
RU2065397C1 (en) Tower crane
CN111119028A (en) Movable folding overbridge
KR0181569B1 (en) Outer-boom crane
CN211645931U (en) Movable folding overbridge
RU2191156C2 (en) Mast-lifting device for tower crane with telescopic mast
RU2169695C2 (en) Lift crane

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20140411