KR20230091560A - Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test - Google Patents

Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test Download PDF

Info

Publication number
KR20230091560A
KR20230091560A KR1020210180777A KR20210180777A KR20230091560A KR 20230091560 A KR20230091560 A KR 20230091560A KR 1020210180777 A KR1020210180777 A KR 1020210180777A KR 20210180777 A KR20210180777 A KR 20210180777A KR 20230091560 A KR20230091560 A KR 20230091560A
Authority
KR
South Korea
Prior art keywords
test
pressurization
voltage
low
low voltage
Prior art date
Application number
KR1020210180777A
Other languages
Korean (ko)
Inventor
이희
김정운
강기삼
Original Assignee
한국전력공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전력공사 filed Critical 한국전력공사
Priority to KR1020210180777A priority Critical patent/KR20230091560A/en
Publication of KR20230091560A publication Critical patent/KR20230091560A/en

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/40Testing power supplies
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/165Indicating that current or voltage is either above or below a predetermined value or within or outside a predetermined range of values
    • G01R19/16566Circuits and arrangements for comparing voltage or current with one or several thresholds and for indicating the result not covered by subgroups G01R19/16504, G01R19/16528, G01R19/16533
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/25Arrangements for measuring currents or voltages or for indicating presence or sign thereof using digital measurement techniques
    • G01R19/2506Arrangements for conditioning or analysing measured signals, e.g. for indicating peak values ; Details concerning sampling, digitizing or waveform capturing

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A method of performing a low-voltage primary injection test according to the present invention may include the steps of: checking a primary injection test condition for a test target site; checking low-voltage injection node connection; performing primary injection with low voltage; collecting the operating states and measurement values of major facilities of the target site; and analyzing the collected operating states and measurement values. Therefore, accidents can be prevented.

Description

저전압 사전 가압 시험 수행 방법 및 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템{PERORMING METHOD OF LOW-VOLTAGE PRIMARY INJECTION TEST AND VERIFCIATION SYSTEM OF POWER FACILITY RELIABILITY FOR LOW-VOLTAGE PRIMARY INJECTION TEST}Method for performing low-voltage pre-energization test and test management system of power equipment for low-voltage pre-energization test

본 발명은 변전소나 발전소에서 변압기 등 설치된 전력 설비에 대하여 실전압으로 가압 시험전에 저전압으로 사전 가압 시험을 수행하는 전력 설비의 시험 관리 시스템에 관한 것이다.The present invention relates to a power facility test management system that performs a pre-pressurization test at a low voltage prior to a live voltage energization test for power facilities such as transformers installed in a substation or power plant.

일반적으로, 전력은 가정, 사무실, 공장 등의 최종 수용가측으로 송전하는데 있어 중간 단계로 변전소와 변압기를 거쳐서 최종 수용가측에 이르고 있다.BACKGROUND ART In general, electric power reaches a final consumer side via a substation and a transformer as an intermediate step in transmitting power to a final consumer side of a home, office, factory, or the like.

발전소에서 발전된 전력은 통상적으로 154kV 또는 345kV의 고압으로 변전소에 공급된다. 변전소에서는 154kV 또는 345kV의 고압을 통상적으로 22.9kV 의 고압으로 다운시켜 최종 수용가측에 이르는 바로 전단계인 변압기에 공급한다. 다음, 변압기에서는 최종 수용가측에서 사용하기에 적합한 전압에 해당하는 110V 또는 220V의 전압으로 변환시켜 최종 수용가측으로 공급하게 된다.Electric power generated in power plants is normally supplied to substations at high voltages of 154 kV or 345 kV. In the substation, the high voltage of 154kV or 345kV is usually reduced to a high voltage of 22.9kV and supplied to the transformer, which is the right step before reaching the final customer side. Next, the transformer converts the voltage into a voltage of 110V or 220V corresponding to a voltage suitable for use at the end consumer side and supplies it to the end consumer side.

변전소나 발전소 등에 설치된 변압기, GIS 등 전력 설비의 불량 등으로 인한 전력 공급 과정에서의 문제는 사회의 산업들이 지속되는 것을 방해할 뿐만 아니라, 관련 인원들에 대한 심각한 안전상의 위험을 야기시킬 수 있다.Problems in the power supply process due to defects in power facilities such as transformers and GIS installed in substations and power plants not only hinder the continuation of society's industries, but can also cause serious safety hazards to related personnel.

사고를 미연에 방지하기 위해, 새롭게 건설되거나 대규모 보수가 이루어진 변전소나 발전소 등 주요 사이트에서는, 건설 중, 또는 건설(개보수) 후 최초 운전전에 현장시험후 사이트(현장) 단위로 설치된 설비들에 대한 가압 시험을 수행한다. 크게 문제되지 않을 수준으로 평상시 보다 높은 전압을 인가하여, 그에 대한 주요 설비들의 동작이나 측정값들을 분석하여, 사고를 미리 방지하는 것이다.In order to prevent accidents in advance, at major sites such as substations or power plants that have been newly constructed or undergone large-scale repairs, pressurization is applied to facilities installed on a site (site) basis after a field test before the first operation during construction or after construction (repair). do the test It is to prevent accidents in advance by applying a higher voltage than usual to a level that is not a big problem, and analyzing the operation of major facilities or measured values therefor.

그런데, 154kV 또는 345kV, 765kV의 고압의 경우, 사용 전압 자체가 매우 높으며, 해당 변압기 2차측도 분전되기 전이라서 전류량이 매우 크기 때문에, 가압 시험 자체도 상당한 위험 부담을 가지고 있다. 또한, 상당히 넓은 공간에서 상당수의 인원들이 작업하여 가압 시험을 수행한다.However, in the case of high voltages of 154 kV, 345 kV, or 765 kV, the voltage used is very high, and the current amount is very large because the secondary side of the transformer is also discharged, so the pressurization test itself has a considerable risk. In addition, a large number of personnel work in a fairly large space to perform a pressure test.

만약, 건설 중 또는 현장시험의 오류사항이 완전하게 제거되지 않은 상태에서 가압된다면 가압과 동시에 설비가 소손되거나 계전기 오동작 등으로 계통에 고장이 파급되어 설비의 안정적 운영에 영향을 미칠 수 있다. If pressurization occurs during construction or in a state where errors in on-site testing are not completely removed, the equipment may be damaged at the same time as pressurization or malfunctions may spread to the system due to relay malfunction, which may affect the stable operation of the equipment.

이러한 방식의 종래의 일반적인 가압 시험은 인적실수에 의한 결선, 정정오류, 기기불량, 접지 등으로 가압 시험 자체에 휴먼에러형 사고의 발생 가능성이 매우 높기 때문이다.This is because the conventional general pressurization test of this type is very likely to cause human error type accidents in the pressurization test itself due to wiring, correction errors, equipment failure, grounding, etc. caused by human error.

대한민국 등록공보 10-1106724호Republic of Korea Registration No. 10-1106724

본 발명은 변전소나 발전소에서 가압 시험을 수행함에 있어서 사고 발생을 예방할 수 있는 저전압 사전 가압 시험을 수행하는 전력 설비의 시험 관리 시스템을 제공하고자 한다.An object of the present invention is to provide a test management system for power equipment that performs a low-voltage pre-pressurization test that can prevent accidents in performing a pressurization test at a substation or power plant.

본 발명의 일 측면에 따른 저전압 사전 가압 시험 수행 방법은, 시험 대상 사이트에 대한 가압 시험 조건을 확인하는 단계; 저전압 가압 노드 접속을 확인하는 단계; 저전압으로 사전 가압을 수행하는 단계; 상기 대상 사이트의 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계; 및 수집된 동작 상태 및 측정값들을 분석하는 단계를 포함할 수 있다.A method for performing a low-voltage pre-pressurization test according to an aspect of the present invention includes checking pressurization test conditions for a test target site; Checking low voltage pressurization node connection; performing prepressurization with low voltage; collecting operating states and measurement values of major facilities of the target site; and analyzing the collected operating states and measurement values.

여기서, 상기 동작 상태 및 측정값들을 분석하는 단계 이후, 수행된 사전 가압 시험의 분석 결과를 출력하는 단계를 더 포함할 수 있다.Here, the step of outputting an analysis result of the pre-pressurization test performed after the step of analyzing the operating state and the measured values may be further included.

여기서, 상기 동작 상태 및 측정값들을 분석에 따라 실 가압 시험에 위험 요인 존재 여부를 판단하는 단계; 및 실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하는 단계를 더 포함할 수 있다.Here, determining whether a risk factor exists in the actual pressurization test according to the analysis of the operating state and the measured values; and instructing a pressurization test with an actual voltage when it is determined that there is no risk factor in the actual pressurization test.

여기서, 상기 사전 가압 시험 조건을 확인하는 단계에서는, 상기 대상 사이트에서의 상기 저전압 가압 노드의 접지 해제 가능 여부, 주요 설비들의 상태 점검 가능 여부 및 주요 지점들의 각 측정기들의 성능을 확인할 수 있다.Here, in the step of checking the pre-pressurization test conditions, it is possible to check whether the grounding of the low-voltage pressurization node at the target site can be released, whether the status of main facilities can be checked, and the performance of each measuring device at the main points.

여기서, 상기 사전 가압 시험 조건을 확인하는 단계에서는, 상기 대상 사이트에 대한 사전 가압 시험 스케쥴 - 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정하는 단위 가압 시험들로 이루어짐 - 을 생성할 수 있다.Here, in the step of confirming the pre-pressurization test conditions, the pre-pressurization test schedule for the target site consists of unit pressurization tests defining the open/closed state of switches, facilities to be inspected, and items to collect measurement values - can create

여기서, 상기 저전압 가압을 수행하는 단계에서는, 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행할 수 있다.Here, in the step of applying the low voltage, the open/closed state of the switches for each unit pressurization test may be adjusted according to the pre-pressurization test schedule, and the low voltage pressurization for each unit pressurization test may be performed.

여기서, 상기 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계에서는, 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들을 취합할 수 있다.Here, in the step of collecting the operating states and measured values of the main facilities, the operating states of the facilities specified as items to be collected for each unit pressure test according to the pre-pressurization test schedule are checked, and the specified measured values are can be aggregated.

여기서, 상기 저전압 가압 노드 접속을 확인하는 단계에서는, 3상 380V의 소내전원의 개폐 스위치를 통한 상기 저전압 가압 노드로의 물리적 연결 상태를 확인할 수 있다.Here, in the step of confirming the connection to the low voltage pressurized node, it is possible to check the physical connection state to the low voltage pressurized node through the open/close switch of the three-phase 380V in-house power supply.

여기서, 상기 실 가압 시험에 위험 요인 존재 여부를 판단하는 단계에서는, 저전압 가압된 상태에서의 주요 설비의 on/off 상태가 규정과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정할 수 있다.Here, in the step of determining whether a risk factor exists in the actual pressurization test, if the on/off state of the main facility in the low voltage pressurized state is different from the regulation, or the current or voltage of a specific main point in the pressurized state If the measured value exceeds a predetermined reference value, it can be determined as dangerous.

본 발명의 다른 측면에 따른 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템은, 시험 대상 사이트의 소내전원으로 사전 가압용 전압을 생성하는 저전압 생성부; 상기 사전 가압용 전압을 상기 대상 사이트의 저전압 가입 노드로 인가하기 위한 사전 가압용 스위치; 상기 대상 사이트의 주요 설비들의 동작 상태 및 측정값들을 수집하는 시험 결과 수집부; 수집된 상기 주요 설비들의 동작 상태 및 측정값들을 분석하는 분석부; 및 사전 가입 시험 수행에 따라, 상기 사전 가압용 스위치를 닫음과 함께 상기 시험 결과 수집부에 상기 주요 설비들의 동작 상태 및 측정값들의 수집을 지시하는 사전 가압 및 측정 제어부를 포함할 수 있다.A test management system of a power facility for a low voltage pre-pressurization test according to another aspect of the present invention includes a low voltage generator for generating a pre-pressurization voltage with a power source of a test site; a pre-pressurization switch for applying the pre-pressurization voltage to a low voltage subscription node of the target site; a test result collection unit that collects operational states and measurement values of major facilities of the target site; an analysis unit that analyzes the collected operating conditions and measurement values of the major facilities; and a pre-pressurization and measurement control unit that closes the pre-pressurization switch and instructs the test result collection unit to collect operating states and measurement values of the main facilities according to the pre-subscription test.

여기서, 상기 분석부는, 상기 동작 상태 및 측정값들의 분석 결과 실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하고, 실 가압 시험에 위험 요인이 존재한다고 판단하면, 위험 요인 존재의 취지로 수행된 사전 가압 시험의 분석 결과를 출력할 수 있다.Here, the analyzer, as a result of the analysis of the operating conditions and measured values, determines that there is no risk factor in the actual pressurization test, instructs the pressurization test with an actual voltage, and if it is determined that a risk factor exists in the actual pressurization test, the analysis unit determines that a risk factor exists in the actual pressurization test. The analysis result of the pre-pressurization test performed to the effect of the presence of a factor can be output.

여기서, 상기 분석부는, 저전압 가압된 상태에서의 주요 설비의 on/off 상태가 규정과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정할 수 있다.Here, the analysis unit determines that it is dangerous if the on/off state of the main equipment in the low voltage pressurized state is different from the regulation, or if the current or voltage measured value of a specific main point in the pressurized state exceeds a predetermined reference value can do.

여기서, 상기 사전 가압 및 측정 제어부는, 상기 대상 사이트가 사전 가압 시험을 수행할 수 있는 조건을 충족하는지 확인할 수 있다.Here, the pre-pressurization and measurement control unit may check whether the target site satisfies the condition for performing the pre-pressurization test.

여기서, 상기 사전 가압 및 측정 제어부는, 상기 대상 사이트에 대한 사전 가압 시험 스케쥴 - 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정하는 단위 가압 시험들로 이루어짐 - 을 생성할 수 있다.Here, the pre-pressurization and measurement control unit generates a pre-pressurization test schedule for the target site - consisting of unit pressurization tests defining the opening and closing states of switches, facilities to be inspected, and items to collect measurement values. can

여기서, 상기 사전 가압 및 측정 제어부는, 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행할 수 있다.Here, the pre-pressurization and measurement control unit may adjust open/closed states of the switches for each unit pressurization test according to the pre-pressurization test schedule and perform low voltage pressurization for each unit pressurization test.

여기서, 상기 시험 결과 수집부는, 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들을 취합할 수 있다.Here, the test result collection unit may check operating states of equipment specified as items to be collected for each unit pressure test according to the prior pressure test schedule, and may collect prescribed measurement values.

본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법 및/또는 전력 설비의 시험 관리 시스템을 실시하면, 변전소나 발전소에서 실 사용 전압 수준에서 가압 시험을 수행함에 있어서 사고 발생을 예방할 수 있는 이점이 있다. 즉, 저전압으로 가압하여 실제 가압시의 고장리스크를 방지할 수 있다.When the method for performing a low voltage pre-pressurization test and/or the test management system for power facilities according to the spirit of the present invention is performed, there is an advantage in preventing accidents in performing a pressurization test at an actual voltage level at a substation or power plant. That is, it is possible to prevent a failure risk at the time of actual pressurization by pressurizing at a low voltage.

예컨대, 본 발명의 저전압 사전 가압 시험 수행 방법 및/또는 전력 설비의 시험 관리 시스템은, 최근 변압기 권선 변경제작(1,2,3차 임핀던스 상이) 변경에 의한 권선간 임피던스 변화에 의한 변압기 보호계전기 오동작 사례 등을 사전에 방지할 수 있다.For example, the method for performing a low voltage pre-pressurization test and/or the test management system of a power facility of the present invention is a transformer protection relay due to a change in impedance between windings due to a recent change in transformer winding (differential 1st, 2nd and 3rd impedance) Malfunction cases can be prevented in advance.

예컨대, 본 발명의 저전압 사전 가압 시험 수행 방법 및/또는 전력 설비의 시험 관리 시스템은, 154kV 변전소에 인출 월부싱 접지 미제거나, 345kV GIS 단락바 미제거등 단락, 접지상태에서 가압하는 고장 등을 사전에 예방할 수 있다.For example, the method for performing a low voltage pre-pressurization test and/or the test management system for power facilities of the present invention may prevent a 154kV substation from removing a wall bushing grounding, a short circuit of a 345kV GIS short-circuit bar, a failure of pressurization in the ground state, etc. can be prevented in

예컨대, 본 발명의 저전압 사전 가압 시험 수행 방법 및/또는 전력 설비의 시험 관리 시스템은, 765kV 3차측 케이블 결선오류, 변압기의 방향성보호계전기(67) 등의 결선, 정정오류를 실제 부하전류를 통하여 계전기, 결선상태를 파악하여 오동작을 예방할 수 있다.For example, the method for performing a low voltage pre-pressurization test and/or the test management system of a power facility according to the present invention detects a 765kV tertiary side cable connection error, a wiring error of a directional protection relay 67 of a transformer, and a correction error through an actual load current. , it is possible to prevent malfunction by identifying the wiring status.

예컨대, 본 발명의 저전압 사전 가압 시험 수행 방법 및/또는 전력 설비의 시험 관리 시스템은, 765, 345kV 변전소 준공시험시 최초가압 전에 저전압 가압시험법을 활용하여 주도체 상태, PT. CT 2차회로 결선, 계전기 상태, 정정오류 등을 검출하여 사고예방에 기여할 수 있다.For example, the low-voltage pre-pressurization test method and/or test management system for power facilities of the present invention utilizes the low-voltage pressurization test method prior to the first pressurization during the completion test of a 765, 345kV substation to perform a main conductor state, PT. It can contribute to accident prevention by detecting CT secondary circuit wiring, relay status, and correction errors.

도 1은 본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법의 일 실시예를 도시한 흐름도.
도 2는 저전압 사전 가압 시험의 개념을 도시한 개요도.
도 3은 765kV E/C 변전소의 표준 계통도.
도 4는 765kV 변전소에 대한 본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법을 도시한 절차도.
도 5는 변전소에 대한 전압 측정을 위해 765kV 변전소의 345KV #1 모선측에 3상 380V 인가하는 S134 단계의 수행 구조를 나타낸 계통도.
도 6은 765kV 변전소의 345kV #1BUS에 3상 380V 인가하고, 345kV #1BUS측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 7은 765kV 변전소의 CB(7271, 7200, 7272)를 Close하고, 선로 및 #2BUS측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 8은 765kV 변전소의 CB(7471, 7400, 7472)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 9는 765kV 변전소의 CB(7171, 7100, 7172)를 Close하고, 선로 및 #1M.Tr 1,2,3차측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 10은 765kV 변전소의 CB(7371, 7300, 7372)를 Close하고, 선로 및 #2M.Tr 1,2,3차측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 11은 765kV 변전소의 CB(8171, 8100, 8172) Close하고, #1, 2BUS 및 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 12는 765kV 변전소의 CB(8271, 8200)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 13은 765kV 변전소의 CB(8371, 8300, 8372)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 14는 765kV 변전소의 CB(8471, 8400)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도.
도 15는 변전소에 대한 전류 측정을 위해 765kV 변전소의 345KV #1 모선측에 3상 380V 인가하는 S134 단계의 수행 구조를 나타낸 계통도
도 16은 765kV 변전소의 CB(8171, 8100, 7171)를 Close하고, 관련 차단기 전류 측정, 전류 측정 후 CB(8100, 7171) 개방할 때의 활성화 영역을 나타낸 계통도.
도 17은 765kV 변전소의 CB(8271, 8200, 7100, 7172, 7271, 7200, 7272)를 Close하고, 관련 차단기 전류 측정할 때의 활성화 영역을 나타낸 계통도.
도 18은 765kV 변전소의 CB(8371, 8300, 7371)를 Close하고, 관련 차단기 전류 측정, 전류 측정 후 CB(8300, 7371) 개방할 때의 활성화 영역을 나타낸 계통도.
도 19는 765kV 변전소의 CB(8471, 8400, 7300, 7372, 7471, 7400, 7472)를 Close하고, 관련 차단기 전류 측정할 때의 활성화 영역을 나타낸 계통도.
도 20은 본 발명의 사상에 따른 저전압 사전 가압 시험을 수행하는 전력 설비의 시험 관리 시스템을 도시한 블록도.
1 is a flowchart illustrating an embodiment of a method for performing a low voltage pre-pressurization test according to the spirit of the present invention.
Figure 2 is a schematic diagram showing the concept of a low voltage pre-pressurization test.
3 is a standard system diagram of a 765kV E/C substation.
Figure 4 is a procedure diagram showing a method for performing a low voltage pre-energization test according to the spirit of the present invention for a 765kV substation.
Figure 5 is a schematic diagram showing the structure of performing step S134 of applying 3-phase 380V to the 345KV # 1 bus side of the 765kV substation for voltage measurement at the substation.
6 is a schematic diagram showing an activation region when a three-phase 380V is applied to a 345kV #1BUS of a 765kV substation and the voltage on the 345kV #1BUS is measured.
7 is a schematic diagram showing active areas when CBs (7271, 7200, 7272) of a 765kV substation are closed and voltages on the line and #2BUS are measured.
8 is a schematic diagram showing active areas when CBs (7471, 7400, and 7472) of a 765kV substation are closed and line-side voltage is measured.
9 is a schematic diagram showing activation areas when CBs (7171, 7100, and 7172) of a 765kV substation are closed and line and #1M.Tr 1, 2, and 3 voltages are measured.
10 is a schematic diagram showing activation areas when CBs (7371, 7300, and 7372) of a 765kV substation are closed and line and #2M.Tr 1, 2, and 3 voltages are measured.
11 is a system diagram showing activation areas when CBs (8171, 8100, 8172) of a 765kV substation are closed and #1, 2BUS and line-side voltages are measured.
12 is a system diagram showing an active region when CBs (8271, 8200) of a 765kV substation are closed and line-side voltage is measured.
13 is a system diagram showing an active area when CBs (8371, 8300, 8372) of a 765kV substation are closed and line-side voltage is measured.
14 is a system diagram showing an active region when CBs (8471, 8400) of a 765kV substation are closed and line-side voltage is measured.
15 is a schematic diagram showing the structure of performing step S134 of applying 3-phase 380V to the 345KV #1 bus side of the 765kV substation to measure current for the substation.
16 is a schematic diagram showing activation areas when CBs (8171, 8100, and 7171) of a 765kV substation are closed, currents of related breakers are measured, and CBs (8100, 7171) are opened after current measurement.
17 is a schematic diagram showing activation areas when CBs (8271, 8200, 7100, 7172, 7271, 7200, and 7272) of a 765kV substation are closed and the related breaker current is measured.
18 is a schematic diagram showing an activation area when CBs (8371, 8300, 7371) of a 765kV substation are closed, and CBs (8300, 7371) are opened after measuring the relevant breaker current and measuring the current.
19 is a schematic diagram showing activation areas when CBs (8471, 8400, 7300, 7372, 7471, 7400, and 7472) of a 765kV substation are closed and the related breaker current is measured.
20 is a block diagram showing a test management system of a power facility that performs a low voltage pre-pressurization test according to the spirit of the present invention.

본 발명을 설명함에 있어서 제 1, 제 2 등의 용어는 다양한 구성요소들을 설명하는데 사용될 수 있지만, 구성요소들은 용어들에 의해 한정되지 않을 수 있다. 용어들은 하나의 구성요소를 다른 구성요소로부터 구별하는 목적으로만 된다. 예를 들어, 본 발명의 권리 범위를 벗어나지 않으면서 제 1 구성요소는 제 2 구성요소로 명명될 수 있고, 유사하게 제 2 구성요소도 제 1 구성요소로 명명될 수 있다. In describing the present invention, terms such as first and second may be used to describe various components, but the components may not be limited by the terms. Terms are only for the purpose of distinguishing one element from another. For example, a first element may be termed a second element, and similarly, a second element may be termed a first element, without departing from the scope of the present invention.

어떤 구성요소가 다른 구성요소에 연결되어 있다거나 접속되어 있다고 언급되는 경우는, 그 다른 구성요소에 직접적으로 연결되어 있거나 또는 접속되어 있을 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해될 수 있다.When a component is referred to as being connected or connected to another component, it may be directly connected or connected to the other component, but it may be understood that another component may exist in the middle. .

본 명세서에서 사용한 용어는 단지 특정한 실시예를 설명하기 위해 사용된 것으로, 본 발명을 한정하려는 의도가 아니다. 단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함할 수 있다. Terms used in this specification are only used to describe specific embodiments, and are not intended to limit the present invention. Singular expressions may include plural expressions unless the context clearly dictates otherwise.

본 명세서에서, 포함하다 또는 구비하다 등의 용어는 명세서상에 기재된 특징, 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것이 존재함을 지정하려는 것으로서, 하나 또는 그 이상의 다른 특징들이나 숫자, 단계, 동작, 구성요소, 부품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해될 수 있다. In this specification, the terms include or include are intended to designate that there is a feature, number, step, operation, component, part, or combination thereof described in the specification, and one or more other features or numbers, It can be understood that the presence or addition of steps, operations, components, parts, or combinations thereof is not precluded.

또한, 도면에서의 요소들의 형상 및 크기 등은 보다 명확한 설명을 위해 과장될 수 있다.In addition, shapes and sizes of elements in the drawings may be exaggerated for clearer description.

본 발명은 변전소/발전소 건설 현장에서 설비가압 전에 저전압을 이용 사전 가압시험을 하여 설비소손을 방지하고 가압 시 고장을 방지할 수 있는 절차를 적용함으로서 설비의 건전성을 미리 확인할 수 있는 방법으로서 저전압 사전 가압 시험을 제안한다.The present invention is a method for confirming the soundness of facilities in advance by applying a procedure for preventing equipment burnout and preventing breakdowns during pressurization by performing a pre-pressurization test using low voltage before pressurization at a substation / power plant construction site. Low voltage pre-pressurization suggest a test

저전압 사전 가압 시험은 설비의 손상 없이 주도체의 단락, 지락, 상꼬임 등을 확인할 수 있으며 변성기를 통하여 공급되는 계측회로, 보호회로의 입, 출력상태를 확인하여 실제 전압을 통한 가압 때와 동일한 조건을 만들어 전력설비 및 보호, 계측회로 등의 건전성을 검증할 수 있는 시험이다. 저압 전원을 통한 가압으로 발전소의 접속설비, 변전소 설비 등 AC 계통의 주도체 및 변성기의 상태 값을 확인하여 신뢰성을 검증할 수 있다. The low-voltage pre-pressurization test can check the short circuit, ground fault, phase twist, etc. of the main conductor without damaging the equipment, and checks the input and output status of the instrumentation circuit and protection circuit supplied through the transformer, under the same conditions as when pressurization through the actual voltage. It is a test that can verify the soundness of power facilities, protection, and measurement circuits by making Reliability can be verified by checking the state values of main conductors and transformers of the AC system, such as power plant connection facilities and substation facilities, by pressurization through low voltage power.

사전가압 시험은 전압시험과 전류시험으로 구분하여 시행할 수 있다. 전압시험은 변전소의 개폐기를 이용하여 변전소의 1, 2차측에 적정전압을 가하여 주도체, 변성기를 통한 2차측 건전성을 확인할 수 있다. 전류시험은 변압기 1차 또는 2차측을 단락하고 상대단에 적정전압을 가해 단락전류를 흘려 주도체를 통한 CT 2차회로 및 보호계전기, 계측기 등의 상태 값을 확인하여 건전성을 확인할수 있다.The pre-pressurization test can be divided into a voltage test and a current test. The voltage test can check the soundness of the secondary side through the main conductor and transformer by applying an appropriate voltage to the primary and secondary sides of the substation using the switchgear of the substation. In the current test, the primary or secondary side of the transformer is short-circuited, an appropriate voltage is applied to the other end, and the short-circuit current is flowed to check the state values of the CT secondary circuit, protective relay, and measuring instrument through the main conductor to confirm soundness.

발전소나 변전소에는 변압기가 있으므로 변압기의 단락시험을 하는 방법으로 변압기의 1차 혹은 2차측을 단락한 후 시행한다. Since there are transformers in power plants and substations, the short-circuit test of the transformer is performed after short-circuiting the primary or secondary side of the transformer.

저전압 가압을 위한 전원은 소내전원(380V, 220V)을 이용 단락전류 크기를 고려하여 1차 혹은 2차측 단락하고 개폐기를 이용 폐로를 구성하여 가압하고 시험한다.For the power supply for low voltage pressurization, use the in-house power supply (380V, 220V) to short circuit the primary or secondary side considering the size of the short circuit current, construct a circuit using a switch, pressurize, and test.

도 1은 본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법의 일 실시예를 도시한 흐름도이다.1 is a flowchart illustrating an embodiment of a method for performing a low voltage pre-pressurization test according to the spirit of the present invention.

도시한 저전압 사전 가압 시험 수행 방법은, 실 가압 시험 조건을 확인하는 단계(S110); 저전압 가압 노드 접속을 확인하는 단계(S120); 저전압으로 사전 가압을 수행하는 단계(S130); 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계(S140); 및 수집된 동작 상태 및 측정값들을 분석하는 단계(S150)를 포함할 수 있다.The illustrated method for performing the low voltage pre-pressurization test includes the steps of confirming actual pressurization test conditions (S110); Checking the connection of the low voltage pressurized node (S120); Performing pre-pressurization with low voltage (S130); Collecting operating states and measurement values of major facilities (S140); and analyzing the collected operating states and measured values (S150).

상기 분석하는 단계(S150) 이후, 수행된 사전 가압 시험의 분석 결과를 출력(리포팅)하는 단계를 더 포함할 수 있다.After the analyzing step (S150), a step of outputting (reporting) the analysis result of the pre-pressurization test performed may be further included.

본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법은 실제 사용 전압으로 가압하기 전에 수행되므로, 이후, 실 가압 시험이 수행되며, 상기 실 가압 시험을 개시할 때까지로 규정할 수도 있다.Since the method for performing the low voltage pre-pressurization test according to the spirit of the present invention is performed before pressurization with an actual voltage, the actual pressurization test is performed thereafter, and may be defined as until the start of the actual pressurization test.

이 경우, 상기 저전압 사전 가압 시험 수행 방법은, 상기 동작 상태 및 측정값들을 분석에 따라 실 가압 시험에 위험 요인 존재 여부를 판단하는 단계(S160); 및 실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하는 단계(S170)를 더 포함할 수 있다. 한편, 실 가압 시험에 위험 요인이 존재한다고 판단한 경우(S160), 위험 요인 존재의 취지로 수행된 사전 가압 시험의 분석 결과를 출력(리포팅)하는 단계(S180)를 수행할 수 있다.In this case, the method for performing the low-voltage pre-pressurization test may include determining whether there is a risk factor in the actual pressurization test according to the analysis of the operating state and measured values (S160); and instructing a pressurization test with an actual voltage when it is determined that there is no risk factor in the actual pressurization test (S170). On the other hand, if it is determined that a risk factor exists in the actual pressurization test (S160), a step of outputting (reporting) the analysis result of the pre-pressurization test performed to the effect of the presence of the risk factor (S180) may be performed.

상기 사전 가압 시험 조건을 확인하는 단계(S110)에서는, 신규 건설된 변전소나 발전소 등 대상 사이트(현장)가 사전 가압 시험을 수행할 수 있는 조건을 충족하는지 확인하기 위한 것으로서, 예컨대, 대상 사이트에서의 상기 저전압 가압 노드의 접지 해제 가능 여부, 주요 설비들의 상태 점검 가능 여부 및 주요 지점들의 각 측정기들의 성능(분해능)을 확인할 수 있다.In the step of checking the pre-pressurization test conditions (S110), it is to check whether the target site (site), such as a newly constructed substation or power plant, meets the conditions for performing the pre-pressurization test, for example, at the target site It is possible to check whether the low-voltage power supply node can be grounded, whether the state of major facilities can be checked, and the performance (resolution) of each measuring device at the main points.

또한, 대상 사이트(현장)가 사전 가압 시험을 수행할 수 있는 조건을 충족하는 경우, 저전압 사전 가압을 가할 수 있는 상기 사이트의 선로상의 지점(저전압 가압 노드)의 위치를 확인할 수 있다. In addition, when the target site (site) satisfies the conditions for performing the pre-energization test, the location of a point (low-voltage power-on node) on the line of the site to which low-voltage pre-energization can be applied can be identified.

구현에 따라, 상기 S110 단계에서는 대상 사이트에 대한 사전 가압 시험 스케쥴을 생성할 수 있다. 예컨대, 사전 가압 시험은 대상 사이트의 다양한 항목들에 대하여 각각 수행하는 단위 가압 시험들로 이루어질 수 있으며, 사전 가압 시험 스케쥴은 스케쥴 상 각 단위 가압 시험들에서의 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정할 수 있다.Depending on implementation, in step S110, a pre-pressurization test schedule for a target site may be created. For example, the pre-pressurization test may consist of unit pressurization tests performed on various items of the target site. And items to collect measurement values can be specified.

상기 저전압 가압 노드 접속을 확인하는 단계(S120)는, 본 발명의 사상에 따른 저전압 사전 가압을 위한 저전압 가압을 수행하기 직전에, 상기 저전압 가압 노드로의 시험을 위한 저전압 인가를 위한 설비 상태를 확인하기 위한 것이다. 예컨대, 3상 380V의 소내전원의 개폐 스위치를 통한 상기 저전압 가압 노드로의 물리적 연결 상태를 자동 또는 수동(작업자 입력)으로 확인할 수 있다. In the step of confirming the connection to the low-voltage pressurization node (S120), right before performing the low-voltage pressurization for the low-voltage pre-pressurization according to the spirit of the present invention, the equipment state for applying the low voltage for the test to the low-voltage pressurization node is checked. It is to do. For example, it is possible to automatically or manually (operator input) check the physical connection state to the low voltage pressurized node through an on/off switch of a three-phase 380V on-site power source.

도 2는 저전압 사전 가압 시험의 개념을 도시한 개요도이다.2 is a schematic diagram illustrating the concept of a low voltage pre-pressurization test.

예컨대, 상기 저전압 가압을 수행하는 단계(S130)에서는 도 2의 개요도에 따를 방식으로 저전압을 인가할 수 있다.For example, in the step of applying the low voltage ( S130 ), the low voltage may be applied in a manner according to the schematic diagram of FIG. 2 .

도 2는 간단한 345/22kV 발전소 스위치 야드의 사전 가압시험을 위한 원리도 로서, 주도체에 일정 전압 및 전류를 인가해서 2차측에 나타날 전류를 계산하거나 혹은 EMTP를 이용하여 얻은 결과는 하기 표 1과 같으며, 현장 계전기 실측 데이터는 하기 표 2와 같다.Figure 2 is a principle diagram for a pre-pressurization test of a simple 345/22kV power plant switch yard, and the results obtained by applying a constant voltage and current to the main conductor to calculate the current to appear on the secondary side or using EMTP are shown in Table 1 below. The same, and the actual measurement data of the field relay are shown in Table 2 below.

Figure pat00001
Figure pat00001

Figure pat00002
Figure pat00002

상기 저전압 가압을 수행하는 단계(S130)에서는, 상기 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행할 수 있다.In the step of applying the low voltage (S130), the open/closed state of the switches may be adjusted for each unit pressurization test according to the schedule, and the low voltage pressurization may be performed for each unit pressurization test.

상기 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계(S140)에서는, 상기 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할(점검) 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들로서, 해당 센서로서 CT나 PT의 측정값들을 취합할 수 있다. In the step of collecting the operating state and measured values of the main facilities (S140), the operating state of the facilities specified as items to be collected (checked) for each unit pressure test according to the schedule is checked, and the specified measured values As a sensor, the measured values of CT or PT can be collected.

상기 수집된 동작 상태 및 측정값들을 분석하는 단계(S150)에서는, 사이트의 안전 확인을 위해 필요한 항목들을 계산할 수 있다. 예컨대, 변전소/발전소의 단락 전류를 다음과 같이 계산할 수 있다.In the step of analyzing the collected operational states and measured values (S150), items necessary for safety confirmation of the site may be calculated. For example, the short-circuit current of a substation/power plant can be calculated as:

단락 전류는,

Figure pat00003
로 구할 수 있으며, 3상 380V나 220V를 이용한 765kV 변전소, 345kV 변전소 또는 발전소 변압기의 단락전류를 계산하면 수십 암페어 이내로서 시험이 가능하다. 345kV 변전소는 154kV측 단락 후 345kV측에 380V 인가시 하기 수학식 1과 같은 값을 얻을 수 있다.The short-circuit current is
Figure pat00003
, and if the short-circuit current of a 765kV substation, 345kV substation or power plant transformer using three-phase 380V or 220V is calculated, the test is possible within several tens of amperes. The 345kV substation can obtain the same value as Equation 1 below when 380V is applied to the 345kV side after a short circuit on the 154kV side.

Figure pat00004
Figure pat00004

예컨대, 도 2에 도시한 간략한 사전 가압 시험의 경우, 상기 수행된 사전 가압 시험의 분석 결과를 출력(리포팅)하는 단계에서는, 상기 수학식 1에 따라 계산한 단락 전류를 출력할 수 있다.For example, in the case of the simple pre-pressurization test shown in FIG. 2 , in the step of outputting (reporting) the analysis result of the performed pre-pressurization test, the short-circuit current calculated according to Equation 1 may be output.

예컨대, 도 2에 도시한 간략한 사전 가압 시험의 경우, 도 1의 S160 단계에서는, 상기 수학식 1에 따라 계산한 단락 전류들 중 하나가 소정의 기준값을 넘으면 위험으로 판정할 수 있다. 보다 복잡하고 다수의 항목들을 점검하는 사전 가압 시험의 경우의 S160 단계에서도, 이와 유사하게 가압된 상태에서의 주요 설비의 on/off 상태가 규정(스케쥴)과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정할 수 있다. For example, in the case of the simple pre-pressurization test shown in FIG. 2, in step S160 of FIG. 1, if one of the short-circuit currents calculated according to Equation 1 exceeds a predetermined reference value, it may be determined as dangerous. Even at step S160 in the case of a pre-pressurization test that is more complicated and checks a number of items, similarly, if the on/off state of the main facility in the pressurized state is different from the regulation (schedule), or in the pressurized state, a specific If the measured value of the current or voltage at the main point exceeds a predetermined reference value, it can be determined as dangerous.

다음, 본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법을 765kV 변전소의 시험에 적용한 경우로 예시하여 구체적인 절차들을 살펴본다.Next, specific procedures will be described by exemplifying a case in which the low voltage pre-pressurization test method according to the spirit of the present invention is applied to a test of a 765kV substation.

도 3은 765kV E/C 변전소의 표준 계통도이다.3 is a standard system diagram of a 765kV E/C substation.

도 4는 765kV 변전소에 대한 본 발명의 사상에 따른 저전압 사전 가압 시험 수행 방법을 도시한 절차도이다.4 is a flowchart illustrating a method of performing a low voltage pre-energizing test according to the spirit of the present invention for a 765kV substation.

도 5는 변전소에 대한 전압 측정을 위해 765kV 변전소의 345KV #1 모선측에 3상 380V 인가하는 S134 단계의 수행 구조를 나타낸 계통도이다.5 is a schematic diagram showing the structure of performing step S134 of applying 3-phase 380V to the 345KV # 1 bus side of the 765kV substation for voltage measurement at the substation.

도 1의 S110 단계가 도 4에서는 S112 단계 및 S114 단계로 세분화되었다.Step S110 in FIG. 1 is subdivided into steps S112 and S114 in FIG. 4 .

765kV 변전소의 3상 380V 전원을 사용하여 전압, 전류를 얻기 위한 조건 계산 결과는 다음과 같으며, 대상 765kV 변전소에 설치된 PT 및 CT의 사양(예: 센싱 분해능)이 이를 만족하는지 확인할 수 있다(S112, S114).The result of calculating the conditions for obtaining the voltage and current using the 3-phase 380V power supply of the 765kV substation is as follows, and it can be confirmed whether the specifications (e.g., sensing resolution) of the PT and CT installed in the target 765kV substation satisfy it (S112 , S114).

PT 전압 계산(345kV 측 380V 인가 시)PT voltage calculation (when 380V is applied on the 345kV side)

- 765k측 2차 상전압 73.1㎷ (765kV/115V)- 765k side secondary phase voltage 73.1㎷ (765kV/115V)

- 345k측 2차 상전압 73.1㎷ (345kV/115V)- 345k side secondary phase voltage 73.1㎷ (345kV/115V)

- 23k측 2차 상전압 70.0㎷ (23kV/110V)- 23k side secondary phase voltage 70.0㎷ (23kV/110V)

CT 전류 계산(765kV측 단락 후 345kV측 380V 인가 시)CT current calculation (when 380V is applied on the 345kV side after a short circuit on the 765kV side)

- 변압기 정격 용량 : 2000[MVA]- Transformer rated capacity: 2000[MVA]

- 변압기 정격 전압 : 765/345/23kV- Transformer rated voltage: 765/345/23kV

- %Z=18.0%, 정격 전류 1차 1509.5A, 2차 3347.1A- %Z=18.0%, rated current 1st 1509.5A, 2nd 3347.1A

- 345kV측 3상 380V 인가 단락전류 1차 9.24A, 2차 20.48A- 345kV side 3-phase 380V applied short-circuit current 1st 9.24A, 2nd 20.48A

- 765kV 4000/1A 기준 2.31㎃, 6000/1A 기준 1.54㎃- 765kV 4000/1A standard 2.31mA, 6000/1A standard 1.54mA

- 345kV 6000/5A 기준 17.06㎃- 17.06mA based on 345kV 6000/5A

도 1의 S130 단계가 도 4에서는 765kV, 345kV 전 DS 투입하는 S132 단계 및 345kV #1 BUS측 ES측에 저전압을 인가하는 S134 단계로 세분화되었다.Step S130 of FIG. 1 is subdivided into step S132 of inputting all 765kV and 345kV DS in FIG. 4 and step S134 of applying low voltage to the ES side of 345kV #1 BUS side.

상기 S134 단계에서는, 도 5의 점선 박스 부분(R)과 같이, 345KV #1 모선측의 접지를 분리한 후, 380V를 인가할 수 있다.In step S134, 380V may be applied after disconnecting the ground of the 345KV #1 bus, as shown in the dotted line box R of FIG.

도 1의 S140 단계가 도 4에서는 S412 단계 내지 S146 단계로 세분화되었다.Step S140 in FIG. 1 is subdivided into steps S412 to S146 in FIG. 4 .

먼저, 변전소에 대한 전압 위상 측정 과정으로서 S412 단계 및 S414 단계에 대하여 설명한다. First, steps S412 and S414 will be described as a voltage phase measurement process for the substation.

상기 S142 단계에서 전압 측정은 345kV 가압과 같이 380V를 345kV측 모선의 접지 분리 후, 가압 절차서등으로 규정할 수 있는 스케쥴상의 단위 가압 시험들을 순차적으로 수행하되, 각 단위 가압 시험들에 따라 순차적으로 인가하여 주도체,계전기, 계측기의 전압 값을 확인하여 오류를 판별할 수 있다. 이때, 순서에 따라 PT 전압도 측정하되, 각 Bay 별로 순서에 맞게 시험을 요하나, 시험을 마친 Bay는 차단기를 개방할 필요가 없다.In the step S142, the voltage measurement is performed sequentially by unit pressurization tests on a schedule that can be specified in a pressurization procedure after disconnecting 380V from the ground of the 345kV side bus, such as 345kV pressurization, but sequentially applied according to each unit pressurization test You can determine the error by checking the voltage value of the main conductor, relay, and measuring instrument. At this time, the PT voltage is also measured according to the order, and the test is required according to the order for each bay, but there is no need to open the circuit breaker for the bay that has completed the test.

도 6은 765kV 변전소의 345kV #1BUS에 3상 380V 인가하고, 345kV #1BUS측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 6 is a schematic diagram showing an activation region when a three-phase 380V is applied to a 345kV #1BUS of a 765kV substation and the voltage on the 345kV #1BUS is measured.

도 7은 765kV 변전소의 CB(7271, 7200, 7272)를 Close하고, 선로 및 #2BUS측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 7 is a schematic diagram showing active areas when CBs 7271, 7200, and 7272 of a 765kV substation are closed and voltages on the line and #2BUS are measured.

도 8은 765kV 변전소의 CB(7471, 7400, 7472)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 8 is a schematic diagram showing an active region when CBs 7471, 7400, and 7472 of a 765kV substation are closed and line-side voltage is measured.

도 9는 765kV 변전소의 CB(7171, 7100, 7172)를 Close하고, 선로 및 #1M.Tr 1,2,3차측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 9 is a schematic diagram showing active areas when CBs (7171, 7100, and 7172) of a 765kV substation are closed and the line and #1M.Tr 1st, 2nd, and 3rd side voltages are measured.

도 10은 765kV 변전소의 CB(7371, 7300, 7372)를 Close하고, 선로 및 #2M.Tr 1,2,3차측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 10 is a schematic diagram showing activation areas when CBs (7371, 7300, and 7372) of a 765kV substation are closed and the line and #2M.Tr 1, 2, and 3 voltages are measured.

도 11은 765kV 변전소의 CB(8171, 8100, 8172) Close하고, #1, 2BUS 및 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 11 is a schematic diagram showing activation areas when CBs (8171, 8100, 8172) of a 765kV substation are closed and #1, 2BUS and line-side voltages are measured.

도 12는 765kV 변전소의 CB(8271, 8200)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 12 is a system diagram showing an active region when CBs (8271, 8200) of a 765kV substation are closed and line-side voltage is measured.

도 13은 765kV 변전소의 CB(8371, 8300, 8372)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 13 is a schematic diagram showing an active region when CBs (8371, 8300, 8372) of a 765kV substation are closed and line-side voltage is measured.

도 14는 765kV 변전소의 CB(8471, 8400)를 Close하고, 선로측 전압 측정할 때의 활성화 영역을 나타낸 계통도이다. 14 is a system diagram showing an active region when CBs (8471, 8400) of a 765kV substation are closed and line-side voltage is measured.

도 6 내지 도 14는 상기 S142 단계에서의 전압 위상 측정을 위한 단위 가압 시험들을 각각 수행하는 모습을 도시한 계통도들이다. 즉, 각 단위 가압 시험들은 해당 도면에 도시한 바와 같은 스위치 개폐 조건에서 가압이 수행되어, 붉은 색으로 표시한 가압으로 활성화된 영역에 대한 CT/PT 측정 및 해당 설비(소자)들의 상태를 수집한다.6 to 14 are schematic diagrams showing each of the unit pressure tests for voltage phase measurement in step S142. That is, in each unit pressurization test, pressurization is performed under the switch opening/closing condition as shown in the corresponding figure, and CT/PT measurement for the area activated by pressurization indicated in red is collected and the state of the corresponding equipment (elements) is collected. .

다음, 변전소에 대한 전류 위상 측정 과정으로서 S416 단계에 대하여 설명한다. Next, step S416 will be described as a current phase measurement process for the substation.

도 15는 변전소에 대한 전류 측정을 위해 765kV 변전소의 345KV #1 모선측의 R 영역에 3상 380V 인가하는 S134 단계의 수행 구조를 나타낸 계통도이다15 is a schematic diagram showing the structure for performing step S134 of applying 3-phase 380V to the R region of the 345KV #1 bus side of the 765kV substation to measure current for the substation.

상기 S416 단계에서 전류 측정은, 345kV #1모선측에 3상 380V 인가하고, 765kV #1모선측을 단락(모선 ES 투입, 접지 분리)한 상태에서 스케쥴상의 단위 가압 시험들을 순차적으로 수행할 수 있다. 이때, 각 Bay 별로 순서에 맞게 시험을 요하며, 시험을 마친 Bay는 차단기를 Bay별 한 대 개방한다.In the step S416, the current measurement is performed sequentially by applying a 3-phase 380V to the 345kV #1 bus and short-circuiting the 765kV #1 bus (bus ES input, ground disconnection) according to the schedule. . At this time, the test is required in order for each bay, and for the bays that have completed the test, one circuit breaker is opened for each bay.

도 16은 765kV 변전소의 CB(8171, 8100, 7171)를 Close하고, 관련 차단기 전류 측정, 전류 측정 후 CB(8100, 7171) 개방할 때의 활성화 영역을 나타낸 계통도이다. 16 is a schematic diagram showing an activation area when CBs (8171, 8100, 7171) of a 765kV substation are closed, current of the circuit breaker is measured, and CBs (8100, 7171) are opened after current measurement.

도 17은 765kV 변전소의 CB(8271, 8200, 7100, 7172, 7271, 7200, 7272)를 Close하고, 관련 차단기 전류 측정할 때의 활성화 영역을 나타낸 계통도이다. 17 is a schematic diagram showing activation areas when the CBs (8271, 8200, 7100, 7172, 7271, 7200, 7272) of the 765kV substation are closed and the related breaker current is measured.

도 18은 765kV 변전소의 CB(8371, 8300, 7371)를 Close하고, 관련 차단기 전류 측정, 전류 측정 후 CB(8300, 7371) 개방할 때의 활성화 영역을 나타낸 계통도이다. 18 is a schematic diagram showing an activation region when CBs (8371, 8300, 7371) of a 765kV substation are closed, current of the circuit breaker is measured, and CBs (8300, 7371) are opened after current measurement.

도 19는 765kV 변전소의 CB(8471, 8400, 7300, 7372, 7471, 7400, 7472)를 Close하고, 관련 차단기 전류 측정할 때의 활성화 영역을 나타낸 계통도이다. 19 is a schematic diagram showing activation areas when CBs (8471, 8400, 7300, 7372, 7471, 7400, and 7472) of a 765kV substation are closed and the related breaker current is measured.

도 16 내지 도 19는 상기 S146 단계에서의 전압 위상 측정을 위한 단위 가압 시험들을 각각 수행하는 모습을 도시한 계통도들이다. 즉, 각 단위 가압 시험들은 해당 도면에 도시한 바와 같은 스위치 개폐 조건에서 가압이 수행되어, 붉은 색으로 표시한 가압으로 활성화된 영역에 대한 CT/PT 측정 및 해당 설비(소자)들의 상태를 수집한다.16 to 19 are schematic diagrams showing the state of performing unit pressure tests for voltage phase measurement in step S146, respectively. That is, in each unit pressurization test, pressurization is performed under the switch opening/closing condition as shown in the corresponding figure, and CT/PT measurement for the area activated by pressurization indicated in red is collected and the state of the corresponding equipment (elements) is collected. .

345kV 변전소의 경우도,In the case of a 345kV substation,

214 345kV 변전소의 시험 방법 및 절차214 Test Methods and Procedures for 345kV Substations

345kV 변전소의 경우에도 유사한 방식으로, 3상 380V 전원을 사용하여 전압, 전류를 얻기 위한 계산 결과를 다음과 같이 얻을 수 있다.In the case of a 345kV substation, in a similar way, the calculation results for obtaining voltage and current using a three-phase 380V power source can be obtained as follows.

1. PT 전압 계산(345kV 측 380V 인가 시)1. Calculation of PT voltage (when applying 380V on the 345kV side)

- 345k측 2차 상전압 73.1㎷ (345kV/115V)- 345k side secondary phase voltage 73.1㎷ (345kV/115V)

- 154k측 2차 상전압 73.1㎷ (161kV/115V)- 154k side secondary phase voltage 73.1㎷ (161kV/115V)

- 23k측 2차 상전압 70.0㎷ (23kV/110V)- 23k side secondary phase voltage 70.0㎷ (23kV/110V)

2. CT전류 계산(154kV측 단락 후 345kV측 380V 인가 시)2. Calculation of CT current (when 380V on the 345kV side is applied after a short circuit on the 154kV side)

- 변압기 정격 용량 : 500[MVA]- Transformer rated capacity: 500[MVA]

- 변압기 정격 전압 : 345/161/23kV- Transformer rated voltage: 345/161/23kV

- %Z=10.0%, 정격 전류 1차 836.7A, 2차 1793.0A- %Z=10.0%, rated current 1st 836.7A, 2nd 1793.0A

- 345kV측 3상 380V 인가 단락전류 1차 9.22A, 2차 19.77A- 345kV side 3-phase 380V applied short-circuit current 1st 9.22A, 2nd 19.77A

- 345kV 4000/5A 기준 11.5㎃, 2000/5A 기준23.0㎃- 11.5mA based on 345kV 4000/5A, 23.0mA based on 2000/5A

- 154kV 2000/5A 기준 49.4㎃- 49.4mA based on 154kV 2000/5A

전압 측정은 380V를 실제가압과 같이 345kV측에 순차적으로 가압하여 주도체, 계전기, 계측기의 전압 값을 확인하여 오류를 판정한다. 전류 측정도 Bay별로 순차적으로 측정할 수 있다.For voltage measurement, 380V is sequentially applied to the 345kV side as in actual application, and errors are determined by checking the voltage values of the main conductor, relay, and measuring instrument. Current measurement can also be sequentially measured for each bay.

도 20은 본 발명의 사상에 따른 저전압 사전 가압 시험을 수행하는 전력 설비의 시험 관리 시스템을 도시한 블록도이다.20 is a block diagram illustrating a test management system of a power facility that performs a low voltage pre-pressurization test according to the spirit of the present invention.

도시한 저전압 사전 가압 시험을 수행하는 전력 설비의 시험 관리 시스템은, 시험 대상 사이트(10)의 소내전원으로 사전 가압용 전압을 생성하는 저전압 생성부(110); 상기 사전 가압용 전압을 상기 대상 사이트(10)의 저전압 가입 노드로 인가하기 위한 사전 가압용 스위치(120); 상기 대상 사이트의 주요 설비들의 동작 상태 및 측정값들을 수집하는 시험 결과 수집부(140); 수집된 상기 주요 설비들의 동작 상태 및 측정값들을 분석하는 분석부(150); 및 사전 가입 시험 수행에 따라, 상기 사전 가압용 스위치(120)를 닫음과 함께 상기 시험 결과 수집부(140)에 상기 주요 설비들의 동작 상태 및 측정값들의 수집을 지시하는 사전 가압 및 측정 제어부(170)를 포함할 수 있다.The test management system of the power facility performing the low-voltage pre-pressurization test shown includes a low-voltage generator 110 for generating a pre-pressurization voltage with the in-house power of the test target site 10; a pre-pressurization switch 120 for applying the pre-pressurization voltage to a low voltage subscription node of the target site 10; a test result collection unit 140 that collects operational states and measurement values of major facilities of the target site; Analysis unit 150 for analyzing the collected operating conditions and measured values of the main facilities; and a pre-pressurization and measurement control unit 170 that closes the pre-pressurization switch 120 and instructs the test result collection unit 140 to collect the operation status and measurement values of the main facilities according to the pre-subscription test being performed. ) may be included.

도시한 전력 설비의 시험 관리 시스템은 도 1에 도시한 흐름도의 저전압 사전 가압 시험 수행 방법을 수행할 수 있다.The test management system of the illustrated power facility may perform the low voltage pre-pressurization test method of the flowchart illustrated in FIG. 1 .

저전압 사전 가압 시험 수행 방법의 전반적인 과정을 상기 사전 가압 및 측정 제어부(170)가 수행하며, S140 단계는 상기 시험 결과 수집부(140)가 수행하며, S150 단계 내지 S180 단계는 상기 분석부(150)가 수행한다.The overall process of the method for performing the low voltage pre-pressurization test is performed by the pre-pressurization and measurement control unit 170, step S140 is performed by the test result collection unit 140, and steps S150 to S180 are performed by the analyzer 150. is carried out

이에 따라, 상기 분석부(150)는, 저전압 가압된 상태에서의 주요 설비의 on/off 상태가 규정과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정할 수 있다.Accordingly, the analyzer 150 determines whether the on/off state of a major facility in a low voltage pressurized state is different from the regulation, or a current or voltage measured value of a specific main point in a pressurized state is a predetermined reference value. If it exceeds , it can be judged as dangerous.

이에 후속하여 상기 분석부(150)는, 상기 동작 상태 및 측정값들의 분석 결과 실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하고, 실 가압 시험에 위험 요인이 존재한다고 판단하면, 위험 요인 존재의 취지로 수행된 사전 가압 시험의 분석 결과를 출력할 수 있다.Subsequently, if it is determined that there is no risk factor in the actual pressurization test as a result of the analysis of the operating state and the measured values, the analysis unit 150 instructs the pressurization test with an actual voltage, and the risk factor exists in the actual pressurization test. If it is determined that a risk factor exists, an analysis result of a prepressurization test performed to the effect of existence of a risk factor may be output.

예컨대, 상기 사전 가압 및 측정 제어부(170)는, 상기 대상 사이트가 사전 가압 시험을 수행할 수 있는 조건을 충족하는지 확인할 수 있다.For example, the pre-pressurization and measurement control unit 170 may check whether the target site satisfies the condition for performing the pre-pressurization test.

또한, 상기 사전 가압 및 측정 제어부는, 상기 대상 사이트에 대한 사전 가압 시험 스케쥴 - 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정하는 단위 가압 시험들로 이루어짐 - 을 생성할 수 있다.In addition, the pre-pressurization and measurement control unit generates a pre-pressurization test schedule for the target site - consisting of unit pressurization tests defining the opening and closing states of switches, facilities to be inspected, and items to collect measurement values. can

상기 사전 가압 시험 스케쥴을 따르는 경우, 상기 사전 가압 및 측정 제어부는(170), 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행하고, 상기 시험 결과 수집부(140)는, 상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들을 취합할 수 있다.When the pre-pressurization test schedule is followed, the pre-pressurization and measurement controller 170 adjusts the open/close state of the switches for each unit pressurization test according to the pre-pressurization test schedule, and applies low voltage for each unit pressurization test and the test result collection unit 140 checks the operating state of equipment specified as items to be collected for each unit pressure test according to the pre-pressure test schedule, and collects prescribed measurement values. .

이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형이 가능할 것이다. 따라서, 본 발명에 개시된 실시예들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 실시예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다. 본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.The above description is merely an example of the technical idea of the present invention, and various modifications and variations can be made to those skilled in the art without departing from the essential characteristics of the present invention. Therefore, the embodiments disclosed in the present invention are not intended to limit the technical idea of the present invention, but to explain, and the scope of the technical idea of the present invention is not limited by these embodiments. The protection scope of the present invention should be construed according to the claims below, and all technical ideas within the equivalent range should be construed as being included in the scope of the present invention.

10 : 시험 대상 사이트
110 : 저전압 생성부
120 : 사전 가압용 스위치
140 : 시험 결과 수집부
150 : 분석부
170 : 사전 가압 및 측정 제어부
10: test target site
110: low voltage generating unit
120: switch for pre-pressurization
140: test result collection unit
150: analysis unit
170: pre-pressurization and measurement control unit

Claims (16)

시험 대상 사이트에 대한 가압 시험 조건을 확인하는 단계;
저전압 가압 노드 접속을 확인하는 단계;
저전압으로 사전 가압을 수행하는 단계;
상기 대상 사이트의 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계; 및
수집된 동작 상태 및 측정값들을 분석하는 단계
를 포함하는 저전압 사전 가압 시험 수행 방법.
Checking pressurized test conditions for the test site;
Checking low voltage pressurization node connection;
performing prepressurization with low voltage;
collecting operating states and measurement values of major facilities of the target site; and
Analyzing the collected operating conditions and measured values
Method for performing a low-voltage pre-pressurization test comprising a.
제1항에 있어서,
상기 동작 상태 및 측정값들을 분석하는 단계 이후,
수행된 사전 가압 시험의 분석 결과를 출력하는 단계
를 더 포함하는 저전압 사전 가압 시험 수행 방법.
According to claim 1,
After analyzing the operating state and measured values,
Outputting the analysis result of the pre-pressurization test performed
Method for performing a low voltage pre-pressurization test further comprising a.
제1항에 있어서,
상기 동작 상태 및 측정값들을 분석에 따라 실 가압 시험에 위험 요인 존재 여부를 판단하는 단계; 및
실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하는 단계
를 더 포함하는 저전압 사전 가압 시험 수행 방법.
According to claim 1,
determining whether a risk factor exists in an actual pressurization test according to the analysis of the operating state and measured values; and
Instructing a pressurization test with an actual voltage if it is determined that there is no risk factor in the actual pressurization test
Method for performing a low voltage pre-pressurization test further comprising a.
제1항에 있어서,
상기 사전 가압 시험 조건을 확인하는 단계에서는,
상기 대상 사이트에서의 상기 저전압 가압 노드의 접지 해제 가능 여부, 주요 설비들의 상태 점검 가능 여부 및 주요 지점들의 각 측정기들의 성능을 확인하는 저전압 사전 가압 시험 수행 방법.
According to claim 1,
In the step of confirming the pre-pressurization test conditions,
A method for performing a low-voltage pre-energization test for checking whether the low-voltage power-on node at the target site can be grounded, whether the status of major facilities can be checked, and the performance of each measuring device at key points.
제1항에 있어서,
상기 사전 가압 시험 조건을 확인하는 단계에서는,
상기 대상 사이트에 대한 사전 가압 시험 스케쥴 - 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정하는 단위 가압 시험들로 이루어짐 - 을 생성하는 저전압 사전 가압 시험 수행 방법.
According to claim 1,
In the step of confirming the pre-pressurization test conditions,
A method for performing a low-voltage pre-pressurization test for generating a pre-pressurization test schedule for the target site - consisting of unit pressurization tests defining the opening and closing states of switches, facilities to be inspected, and items to collect measurement values.
제5항에 있어서,
상기 저전압 가압을 수행하는 단계에서는,
상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행하는 저전압 사전 가압 시험 수행 방법.
According to claim 5,
In the step of performing the low voltage pressurization,
A method for performing a low-voltage pre-pressurization test in which the opening and closing states of switches are adjusted for each unit pressurization test according to the pre-pressurization test schedule, and low-voltage pressurization is performed for each unit pressurization test.
제6항에 있어서,
상기 주요 설비들의 동작 상태 및 측정값들을 수집하는 단계에서는,
상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들을 취합하는 저전압 사전 가압 시험 수행 방법.
According to claim 6,
In the step of collecting the operating conditions and measured values of the main facilities,
A method for performing a low-voltage pre-pressurization test for checking the operating state of facilities specified as items to be collected for each unit pressurization test according to the pre-pressurization test schedule and collecting prescribed measured values.
제1항에 있어서,
상기 저전압 가압 노드 접속을 확인하는 단계에서는,
3상 380V의 소내전원의 개폐 스위치를 통한 상기 저전압 가압 노드로의 물리적 연결 상태를 확인하는 저전압 사전 가압 시험 수행 방법.
According to claim 1,
In the step of confirming the connection of the low voltage pressurization node,
A method for performing a low-voltage pre-pressurization test to check the physical connection state to the low-voltage pressurization node through an on-off switch of a three-phase 380V on-site power source.
제3항에 있어서,
상기 실 가압 시험에 위험 요인 존재 여부를 판단하는 단계에서는,
저전압 가압된 상태에서의 주요 설비의 on/off 상태가 규정과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정하는 저전압 사전 가압 시험 수행 방법.
According to claim 3,
In the step of determining whether a risk factor exists in the seal pressurization test,
Conducting a low voltage pre-energization test that is judged as dangerous when the on/off state of major facilities in a low voltage pressurized state is different from the regulations, or when the measured value of current or voltage at a specific key point in a pressurized state exceeds a predetermined standard value method.
시험 대상 사이트의 소내전원으로 사전 가압용 전압을 생성하는 저전압 생성부;
상기 사전 가압용 전압을 상기 대상 사이트의 저전압 가입 노드로 인가하기 위한 사전 가압용 스위치;
상기 대상 사이트의 주요 설비들의 동작 상태 및 측정값들을 수집하는 시험 결과 수집부;
수집된 상기 주요 설비들의 동작 상태 및 측정값들을 분석하는 분석부; 및
사전 가입 시험 수행에 따라, 상기 사전 가압용 스위치를 닫음과 함께 상기 시험 결과 수집부에 상기 주요 설비들의 동작 상태 및 측정값들의 수집을 지시하는 사전 가압 및 측정 제어부
를 포함하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
A low voltage generator for generating a voltage for prepressurization with the power source of the site to be tested;
a pre-pressurization switch for applying the pre-pressurization voltage to a low voltage subscription node of the target site;
a test result collection unit that collects operational states and measurement values of major facilities of the target site;
an analysis unit that analyzes the collected operating conditions and measurement values of the major facilities; and
Pre-pressurization and measurement control unit for instructing the test result collection unit to collect the operation status and measured values of the main facilities while closing the pre-pressurization switch according to the pre-subscription test
Test management system of power equipment for low voltage pre-pressurization test comprising a.
제10항에 있어서,
상기 분석부는,
상기 동작 상태 및 측정값들의 분석 결과 실 가압 시험에 위험 요인이 존재하지 않는다고 판단하면, 실제 전압으로 가압 시험을 지시하고,
실 가압 시험에 위험 요인이 존재한다고 판단하면, 위험 요인 존재의 취지로 수행된 사전 가압 시험의 분석 결과를 출력하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
According to claim 10,
The analysis unit,
As a result of the analysis of the operating conditions and measured values, if it is determined that there is no risk factor in the actual pressurization test, the pressurization test is instructed with an actual voltage,
A test management system of a power facility for a low-voltage pre-pressurization test that outputs an analysis result of a pre-pressurization test performed to the effect of the existence of a risk factor, if it is determined that a risk factor exists in the actual pressurization test.
제11항에 있어서,
상기 분석부는,
저전압 가압된 상태에서의 주요 설비의 on/off 상태가 규정과 달라진 경우, 또는, 가압된 상태에서 특정 주요 지점의 전류 또는 전압의 측정값이 소정의 기준값을 넘으면 위험으로 판정하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
According to claim 11,
The analysis unit,
If the on/off state of major facilities in the low voltage pressurized state is different from the regulations, or if the measured value of current or voltage at a specific main point in the pressurized state exceeds a predetermined standard, the low voltage pre-pressurization test is performed. test management system of power equipment for.
제10항에 있어서,
상기 사전 가압 및 측정 제어부는,
상기 대상 사이트가 사전 가압 시험을 수행할 수 있는 조건을 충족하는지 확인하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
According to claim 10,
The pre-pressurization and measurement control unit,
A test management system of a power facility for a low voltage pre-pressurization test that checks whether the target site meets the conditions for performing a pre-pressurization test.
제10항에 있어서,
상기 사전 가압 및 측정 제어부는,
상기 대상 사이트에 대한 사전 가압 시험 스케쥴 - 스위치들의 개폐 상태, 상태 점검할 설비들 및 측정값을 수집할 항목들을 규정하는 단위 가압 시험들로 이루어짐 - 을 생성하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
According to claim 10,
The pre-pressurization and measurement control unit,
Test of power equipment for low voltage pre-energization test to create a pre-energization test schedule for the target site - consisting of unit power-up tests that specify the open/close state of switches, facilities to be inspected, and items to collect measurement values management system.
제14항에 있어서,
상기 사전 가압 및 측정 제어부는,
상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험을 위해 스위치들의 개폐 상태를 조정하고, 각 단위 가압 시험을 위한 저전압 가압을 수행하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.
According to claim 14,
The pre-pressurization and measurement control unit,
A test management system of a power facility for a low voltage pre-pressurization test that adjusts the open/close state of switches for each unit pressurization test according to the pre-pressurization test schedule and performs low-voltage pressurization for each unit pressurization test.
제15항에 있어서,
상기 시험 결과 수집부는,
상기 사전 가압 시험 스케쥴에 따라 각 단위 가압 시험에 대하여 수집할 항목들로 규정된 설비들의 동작 상태를 확인하고, 규정된 측정값들을 취합하는 저전압 사전 가압 시험을 위한 전력 설비의 시험 관리 시스템.















According to claim 15,
The test result collection unit,
A test management system of power equipment for a low voltage pre-pressurization test that checks the operation status of facilities defined as items to be collected for each unit pressurization test according to the pre-pressurization test schedule and collects prescribed measured values.















KR1020210180777A 2021-12-16 2021-12-16 Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test KR20230091560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210180777A KR20230091560A (en) 2021-12-16 2021-12-16 Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210180777A KR20230091560A (en) 2021-12-16 2021-12-16 Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test

Publications (1)

Publication Number Publication Date
KR20230091560A true KR20230091560A (en) 2023-06-23

Family

ID=86993610

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210180777A KR20230091560A (en) 2021-12-16 2021-12-16 Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test

Country Status (1)

Country Link
KR (1) KR20230091560A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116990625A (en) * 2023-09-27 2023-11-03 国网江苏省电力有限公司电力科学研究院 Function switching system and method of intelligent quick-checking device of distribution transformer

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101106724B1 (en) 2011-07-19 2012-01-18 (주)파워버스 Smart pannel board with blackbox and emergency-battery

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101106724B1 (en) 2011-07-19 2012-01-18 (주)파워버스 Smart pannel board with blackbox and emergency-battery

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116990625A (en) * 2023-09-27 2023-11-03 国网江苏省电力有限公司电力科学研究院 Function switching system and method of intelligent quick-checking device of distribution transformer
CN116990625B (en) * 2023-09-27 2023-12-08 国网江苏省电力有限公司电力科学研究院 Function switching system and method of intelligent quick-checking device of distribution transformer

Similar Documents

Publication Publication Date Title
CN101563824B (en) System and method to determine the impedance of a disconnected electrical facility
AU2007324283C1 (en) Power supply monitoring system
KR101003814B1 (en) Switchgear for diagnosing electrical network disorder and method therefor
CN111007439B (en) Transformer substation bus protection secondary circuit commissioning on-load test method
KR102298314B1 (en) Test simulator of protective relay for AC electric railway system
CN108459230A (en) Electric high-voltage equipment fault detection method
CN112485717A (en) Power distribution true test load simulation device and method
KR100305921B1 (en) Test equipment for making of ground and short in a distribution system
CN115267640A (en) Current transformer abnormity checking method, system, equipment and medium
KR20230091560A (en) Perorming method of low-voltage primary injection test and verifciation system of power facility reliability for low-voltage primary injection test
CN107831378B (en) Device and method for detecting compensation effect of arc suppression coil
KR102262653B1 (en) System for circuit breaker simulation and analysis
CN102565614B (en) Alternating voltage loop test method
CN113156276B (en) Method for checking and debugging secondary voltage loop of bus alternating-current withstand voltage test of switching equipment
KR20170051984A (en) Before using electrical short circuit resistance measuring device for applying distribution board
CN111585265B (en) Secondary equipment test power supply safe starting protection device and application
JP2008263762A (en) Ground fault protective relay system
KR101971031B1 (en) Apparatus and method for dynamic performance test of digital protection relay
KR100637619B1 (en) Method and apparatus for protecting shunt capacitor banks based on voltage difference
CN111398857A (en) Single-phase earth fault detection system of line selection device for arc suppression coil grounding system
Bolotinha Substations equipment inspection and periodic maintenance
Kokor et al. Effects of neutral point grounding methods on single-phase short circuit fault characteristics
KR100927462B1 (en) The switchgear with diagnostic equipment for circuit breaker and method for diagnosing switchgear
KR102539224B1 (en) Integral Management System and Method for Intelligent Electronic Device
CN105116352B (en) The double set DC power system string electro-detection methods of substation

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E601 Decision to refuse application